Professional Documents
Culture Documents
Methodology For Reinforcement Work: Table of
Methodology For Reinforcement Work: Table of
Issued To
Project Incharge
FABS
Issued by
SPC INFRA PROJECTS
*TABLE OF
CONTENTS
1.PURPOSE
2.SCOPE
3.REFERENCES
4.RESPONSIBILTIES
5.METHODOLOGY
6.HEALTH, SAFETY&ENVIRONMENT
7.QUALITY ASSURANCE & QUALITY CONTROL
SECTION-02: SCOPE
The purpose of this method the statement is to lay down the systematic
procedures for the various activities required for reinforcement bars to ensure
that all works are carried out in accordance with the approved drawings and
project specifications. This method statement covers the general procedures to
be followed for installation of reinforcement bar for footing, strap beam, raft,
and slab.
SECTION-03: REFERENCE
1.Contractor documents/Technical specification.
2.GFC drawings of grid lines and footings drawings.
3.Quality assurance manual
4.Quality system manual
5.Health,Safety Environment plan
SECTION-04: RESPONSIBILTIES
Site In charge:
- Shall be report to project manager
-Shall be responsible for supervision, control, Implementation and execution of
plans
-Shall also be responsible for supervision of construction activities and preparation
of construction records Develop construction schedules, procedures and prepare
progress and accomplishment reports.
Site Engineers:
-Shall report to Site in charge.
-Shall be responsible for day to day planning of site, Construction activities and
preparation of construction records.
Survey Engineer/Surveyor:
-Shall report to Project Manager
QA/QC Engineer:
-Shall report to Project Manager
-Shall be responsible for overall control of QC
-Supervision of activities and sub-contractors QC activities, implementation of
Quality plan.
Safety Engineer:
-Shall report to Project Manager
-Shall be responsible for overall control of safety system.
-Supervision of activities and sub contractors
-Safety activities, implementation of safety plan.
TOOLS&EQUIPMENT REQUIRED:
PROCUREMENT,STORAGE&HANDLING:
a) The reinforcement shall be ordered & procured from the approved cut &
bend sub-contractor / supplier with all necessary documentation as
required.
b) On receipt of the material on-site, the reinforcement shall be checked against
the documentation to ensure compliance. Once the delivery order and mill
certificate have been stamped Approved and accepted the material shall be
stacked in the storage yards/ lay down area.
c) The storage yards shall be set up to ensure that the quality of the
reinforcement does not fall below acceptable limits before it’s placement at
the site. To ensure this:
d) Keep material off the ground by supporting by timber / concrete pad at all
times.
e) Keep the material covered whenever possible.
f) Handle and stack material to prevent deformation.
SITE INSTALLATION:
Quality control and assurance shall be strictly followed as per the approved quality
assurance plan and work method statement.