Professional Documents
Culture Documents
Methodology For PCC Laying: Table of
Methodology For PCC Laying: Table of
Project Incharge
FABS
Issued by
SRI HITECH INFRA PROJECTS
AND SOLUTIONS
*TABLE OF
CONTENTS
1.PURPOSE
2.SCOPE
3.REFERENCES
4.RESPONSIBILTIES
5.METHODOLOGY
6.HEALTH, SAFETY&ENVIRONMENT
7.QUALITY ASSURANCE & QUALITY CONTROL
SECTION-02: SCOPE
Execution of footing PCC laying according to the approved drawings line and level
in site.
SECTION-03: REFERENCE
1.Contractor documents/Technical specification.
2.GFC drawings of grid lines and footings drawings.
3.Quality assurance manual
4.Quality system manual
5.Health,Safety Environment plan
SECTION-04: RESPONSIBILTIES
Site Incharge:
- Shall be report to project manager
-Shall be responsible for supervision, control, Implementation and execution of
plans
-Shall also be responsible for supervision of construction activities and preparation
of construction records Develop construction schedules, procedures and prepare
progress and accomplishment reports.
Site Engineers:
-Shall report to Site in charge.
-Shall be responsible for day to day planning of site, Construction activities and
preparation of construction records.
Survey Engineer/Surveyor:
-Shall report to Project Manager
QA/QC Engineer:
-Shall report to Project Manager
-Shall be responsible for overall control of QC
-Supervision of activities and sub-contractors QC activities, implementation of
Quality plan.
Safety Engineer:
-Shall report to Project Manager
-Shall be responsible for overall control of safety system.
-Supervision of activities and sub contractors
-Safety activities, implementation of safety plan.
METHOD STATEMENT FOR PCC LAYING
INTRODUCTION:
Plain cement concrete is the mixture of cement, fine aggregate(sand) and coarse aggregate without
steel. PCC is an important component of a building which is laid on the soil surface to avoid direct
contact of reinforcement of concrete with soil and water.
1. Coarse Aggregate
Coarse aggregate used in the PCC must be of hard broken stone of granite or
similar stone, free from dust, dirt and other foreign matter. The stone ballast shall
be 20 mm in size and smaller. All the coarse material should be retained in a 5mm
square mesh and should be well graded so that the voids do not exceed 42%.
2. Fine Aggregate
Fine aggregate shall be of coarse sand consisting of hard, sharp and angular grains
and shall pass through a screen of 5 mm square mesh. Sand shall be of standard
specifications, clean and free from dust, dirt and organic matter. Sea sand shall not
be used.
3. Cement
Portland Pozzolana cement (P.P.C) is normally used for plain cement concrete. It
should conform to the specifications and shall have the required tensile and
4. Water
Water used shall be clean and reasonably free from injurious quantities of
deleterious materials such as oils, acids, alkalis, salts and vegetable growth.
Generally, potable water shall be used having a pH value not less than 6. The
maximum permissible limits for solids shall be as per IS 456:2000 Clause 5.4, Page
No 15.
Proportioning of Plain Cement Concrete
Hand Mixing
Machine Mixing
1. The PCC is laid in the layers of not more than 150mm thick and
thoroughly vibrated by the means of mechanical vibrators till a dense
concrete is obtained.
2. Wherever needed, hand compaction shall be done with the help of wooden
tamping rods so that concrete is thoroughly compacted and completely
walked into the corners of the formwork.
3. Compaction shall be completed before the initial setting starts that is within
thirty minutes of addition of water to the dry mixture.
Dos
Don’ts
All site personnel shall follow the health and safety policy of the company and
environment policy and plan of SIL.
*While pouring concrete manpower should have follow the minimum required PPE.
*No greenery near the work area to be disturbed and should follow the safety
guidelines.
Quality control and assurance shall be strictly followed as per the approved quality
assurance plan and work method statement.
*Marking to be done and side shuttering to be done before pouring the concrete.
*Levels to be fixed before pouring the concrete and take approval from PMC.
*Dedicated team to be deployed for carrying out the works in near the work area.