You are on page 1of 6

Issued To Project

In charge FABS

Issued by
SRI HITECH INFRA

0 14-04-23 ISSUED FOR (PLANNING) (QA/QC) PROJECT


APPROVAL MANAGER
BHARATHKHANN APPROVED
REV DATE DESCRIPTION PREPARED BY CHECKED BY
A BY
SRI HITECH
OF REVISION SRI HITECH INFRA (FABS)
INFRA

*TABLE OF
CONTENTS

1.PURPOSE
2.SCOPE
3.REFERENCES
4.RESPONSIBILTIES
5.METHODOLOGY
6.HEALTH, SAFETY&ENVIRONMENT
7.QUALITY ASSURANCE & QUALITY CONTROL

METHODOLOGY FOR COMPOUND WALL


DISMANTLING & HUME PIPE LAYING
Submitted by Received and Approved by

SECTION-01: PURPOSE
The purpose of the document is to describe the work procedure to be adopted for fencing work.

SECTION-02: SCOPE
The purpose of this method the statement is to lay down the systematic procedures for the various
activities required for fencing work to ensure that all works are carried out in accordance with the
approved drawings and project specifications. This method statement covers the general
procedures to be followed for old fencing removing, cutting, angle fixing, panting and new
fencing fixing.

SECTION-03: REFERENCE
1.Contractor documents/Technical specification.
2. DRAWING
3.Quality assurance manual
4.Quality system manual
5.Health, Safety Environment plan

SECTION-04: RESPONSIBILTIES

Following are the responsibilities and reporting structure of personnel involved in the scope of the
procedure.

Project Manager: - In charge of all activities at site.

Site In charge:
- Shall be report to project manager
-Shall be responsible for supervision, control, Implementation and execution of plans
-Shall also be responsible for supervision of construction activities and preparation of construction
records Develop construction schedules, procedures and prepare progress and accomplishment
reports.

Site Engineers:
-Shall report to Site in charge.
-Shall be responsible for day to day planning of site, Construction activities and preparation of
construction records.

Survey Engineer/Surveyor:
-Shall report to Project Manager

QA/QC Engineer:
-Shall report to Project Manager
-Shall be responsible for overall control of QC
-Supervision of activities and sub-contractor’s QC activities, implementation of Quality plan.

Safety Engineer:
-Shall report to Project Manager
-Shall be responsible for overall control of safety system.
-Supervision of activities and sub contractors
-Safety activities, implementation of safety plan.

SECTION:05 METHODOLOGY FOR WALL DISMANTLING


& HUME PIPE LAYING WORK
TITLE: WALL DISMANTLING & EXCAVATION WORK & HUME PIPE LAYING& GATE FIXING

TOOLS&EQUIPMENT REQUIRED:

 POWER TOOLS
 PORTABLE TOOLS
 EXCAVATORE
 TRACTORE
 FARHANA

WALL DISMANTLING

 Dismantling of RCC structures and brick work and carting away to outside plant.
 After the carting and disposal of debris good housekeeping to be done

METHOD STATEMENT FOR EXCAVATION WORK


INTRODUCTION:
Work procedure for excavation at construction site involves understanding of center line and
excavation drawings, setting out of plan on ground, excavation of soil and removal of excess soil.
Quality checks such as recording ground level and marking of reference points should be done.
Excavation is the process of moving earth, rock or other materials with tools, equipment or
explosives. It also includes trenching, wall shafts, tunnelling and underground. It is the preliminary
activity of the construction project.

Drawings Required for Excavation

1. Centerline Drawing or Gridline Drawing


Gridline drawings represents the grids marked in numbers and alphabets whose measurements are
shown for site marking out reference. These grid lines are so aligned that the line falls on the
excavation and footing.

2. Excavation Drawing
Excavation drawing represents the length, width and depth of the excavation. Excavation line is
marked in dotted line.

Scope of the work for Excavation


The major works done before, while and after excavation are as follows,

1. Setting out of corner benchmarks.


2. Survey for ground levels.
3. Survey for top levels
4. Excavation to approved depth.
5. Dressing of loose soil.
6. Making up to cut off level
7. Marking boundaries of the building.

Working Procedure of Excavation

1. The first and primary step involved in the excavation is to find out the extent of soil and
Clearing of construction site is of unwanted bushes, weeds and plants.
2. Setting out or ground tracing is the process of laying down the excavation lines and centre
lines etc. on the ground before the excavation is started.
3. Maximum of 4 and minimum of 2 benchmarks are marked in the corner for the measurement
of level. These benchmarks are marked on permanent structures like, plinth, road or tree.
4. The tracing is marked by lime powder or red oxide.
5. With the reference of drawing and benchmarks the depth of the excavation is fixed.
6. Excavation is done by manual or machine means depending on the availability.
7. The excavated soil is to either removed out the site or stocked around the excavation pit.
Minimum of 1m distance must be maintained between the stocking of excess soil and pit, so
that due to rain or other forces the soil should not sweep into the pits.
8. Dressing of excavated pits is to be done as specified in the drawings.
9. If the site is located in loose soil area, proper shoring must be done to hold the loose soil.
10. Construction of dewatering Drain and interconnecting drains are to provided if needed.
11. All the sides of the building must be sealed for the safety propose.

Removal of Excess Soil


Estimate the excavated stuff to be re-utilized in filling, gardening, preparing roads, etc. As far as
possible try to carry excavation and filling simultaneously to avoid double handling. Select and stack
the required material in such a place that it should not obstruct other construction activities. The
excess or unwanted material should immediately be carried away and disposed
Off.

Quality Checks for Excavation

1. Recording initial ground level and check size of bottom.


2. Disposal of unsuitable material for filling.
3. Stacking suitable material for backfilling to avoid double handling.
4. Strata classification approval by competent authority.
5. Dressing bottom and sides of pits as per drawing with respect to centerline.
6. Necessary safety measures observed.

Quality Checks for Filling

1. Recording initial ground level


2. Sample is approved for back filling.
3. Necessary marking/ reference points are established for final level of backfilling.
4. Back filling is being carried out in layers (30cm to 50cm).
5. Required watering, compaction is done.
6. Required density is achieved.

HUME PIPE LAYING


 We are fixing the new Hume Pipe.
 Using the Farhana for Lifting.
 Proper inspected the all tools & Vehicle before start the work.
 Follow the Safety rules according to HCCB Guideline.
 Authorized persons only doing the work.
GATE WELDING AND FIXINNG
 We are doing Gate welding and fixing work: -
 We are ensuring power tools like- Grinding machine,
welding machine etc.
 Fire extinguisher and fire watcher provided in this work
location.
 Ensure the minimum work location 30 min after start the
work.

SECTION: - 6 HEALTH, SAFETY AND ENVIRONMENT

The safety of the personnel and properties is to be given prime importance and all the works
to be carried out without causing any accidents or property damages. Fencing fixing work
involves the following activities.
 Daily tool box talks meeting conducted
 Daily follow the checklist of the equipment’s.
 Ensuring the hot and height work.
 Ensuring the PPE’s
 Proper providing Safety Training of the workers
 Daily work site visited.
 Ensuring and providing Safety Signage boards
 Proper lighting arrangements to be done at the excavated areas and in overall work area.
 Flag Man Provided for Vehicle Movement

SECTION-7 : QUALITY ASSURANCE AND QUALITY CONTROL

Quality control and assurance shall be strictly followed as per the approved quality
assurance plan and work method statement.
*Drawings to be studied earlier while starting the excavation process.
*Marking to be done by the surveyor and marked as visible to the excavator
operator.
*NGL’S to be noted down as per site and take approval from the PMC.
*Before starting the excavation take the approval for the soil type.
*Safety measures to be followed as mentioned in the construction safety guidelines
book.
*Excavation to be done up to required level from existing Road and hard strata to
be obtained.
*Dedicated team to be deployed for carrying out the works in near the work area.

You might also like