You are on page 1of 27

LARANA, INC.

MOTERA STADIUM
AHEMDABAD

CMT MAJOR PROJET

PRESENTED BY

AVINASH KUNAL NANDAN ANIRUDDHA RAVINDRA SHOHAN


PROJECT BRIEF
The Narendra Modi Stadium (formerly Motera Stadium) is in
Sardar Vallabhbhai Patel Sports Complex, Ahmedabad, India.
Constructed in 1983. It was renovated in 2006, and in 2015, the
stadium was demolished and completely rebuilt by February
2020.

Features
It is the largest stadium in the world, with a seating capacity of
110,000 spectators.
Heaviest column in the World installed of 280 MT( Metric
Tonnes)
30,000 sq.m. PTFE ( poly-tetra-fluoro-ethylene) membrane for
the roof was installed in one go
PROJECT INFORMATION
Client : Gujarat Cricket Association
Contractor: Larsen and Toubro
PMC Consultant : STUP Consultant
Overall cost of project: Rs 662.62 Crores
Type of contract: EPC contract with turnkey lump sum basis offer
Total area of land: 63 Acres
Design Life : 100 years
Project start date: 7 th December 2016
Contractual end date: 8 th December 2018
Contract duration: 24 months
PROJECT IMFORMATION KEY FEATURES
SR No. MAJOR SCOPE OF WORK QUANTITY UNIT The complex has an Olympic-size swimming
pool, 4 dressing rooms, and 76 corporate
1 Earthwork 295000 m3
boxes.The stadium houses a cricket academy
2 Concreting 103000 m3 indoors and a 40-person athlete hostel.
The stadium utilises top-notch "Sub Surface
3 Reinforcement 12600 MT
Drainage System". Using this , rain affected
4 Shuttering 536000 m2 match play can start in 30 minutes after the
5 Block work 75000 m3 rain stops .
The new stadium has 1,10,000 seats, which is
6 Plastering 140000 m2
twice as many as the old one. It will surpass
7 Flooring 55000 m2 Australia's Melbourne Cricket Ground (MCG),
8 Structural steel work 2700 MT
as the greatest stadium in terms of seating
capacity.
9 Tensile cable 300 MT
The newly built stadium hosted the first pink-
10 Pipe Roof membrane 28000 m2 ball Test between India and England in 2020.
BIDDING PROCESS

The association formed a Tender Committee of nine experts to evaluate the


proposals based on efficiency, resources, time frame, and ease of
implementation.
Three companies, Shapoorji Pallonji Group, Nagarjuna Construction
Company, and Larsen & Toubro, submitted their proposals to rebuild the
stadium.
Larsen & Toubro won the bid with the lowest bid of ₹677.19 crores and built
and designed the stadium.
MAIN STADIUM-KEY
PLAN

The entire Main Stadium is divided


into 8 Zones:
ZONE-I: VIP Pavilion (complete in-
situ)
ZONE-4: Media centre (Precast+ cast
in-situ)
ZONE-2, 3, 5. and 6: Typical bay
construction (Precast) KEY PLAN
ZONE- 7. 8: Ramp (cast in-situ)

OVERALL CONSTRUCTION METHODOLOGY


:
PLANT AND
EQUIPMENT
Key equipment used included excavators, backhoes,
cranes, concrete mixers and pumps, bulldozers, dump
trucks, and pavers with vibratory rollers.
This equipment was crucial in digging, lifting heavy
materials, pouring and placing concrete, clearing and
leveling the site, transporting materials, and paving.
Careful planning and coordination were required to select
and use the equipment effectively.
The successful implementation of the equipment was a
testament to the project team's experience and expertise.
QUANTIFICATION OF MATERIALS AND
LABOUR PRODUCTIVITY
MACHINERY
Excavators and Backhoes: Used for digging, earthmoving, and
demolition to create space for the stadium's seating, field, and
infrastructure.
Cranes: Various cranes were used, including tower and mobile cranes,
to lift heavy materials and equipment into place.
Concrete Mixers and Pumps: Used to pour and place large volumes of
concrete quickly to ensure the stadium's structure was strong and
durable.
Bulldozers: Used to clear the site, level the ground, and create a stable
foundation for the stadium. They were also used to move large amounts
of earth and soil around the site.
Dump Trucks: Used to transport materials and debris around the site,
keeping the site clean and organized and ensuring timely delivery of
materials.
Pavers and Vibratory Rollers: Used to lay asphalt and pave the parking
lots around the stadium. Vibratory rollers were used to compact the soil
and asphalt, ensuring a smooth and even surface.
ICT AND AUTOMATION
ICT refers to the use of technology to
communicate, manage information, and
automate processes in construction.

Examples of ICT used in Motera


Stadium construction: Building
Information Modeling (BIM), 3D
modeling software, drones for
surveying and monitoring construction
progress.
ICT AND AUTOMATION
Automation refers to the use of technology to perform tasks that would
otherwise require human intervention.

Examples of Automation used in Motera Stadium construction:


Prefabrication of precast concrete panels, use of robotic equipment for
welding and cutting steel.

The use of information and communication technology (ICT) and


automation in construction can help improve efficiency, reduce costs,
and enhance safety. In the case of Motera Stadium, the use of ICT and
automation played a crucial role in completing the project on time and
within budget.
BIM
BIM is a digital representation of a building's physical
and functional characteristics
Construction team used BIM software to create a
detailed model of Motera Stadium
Model included information about materials,
equipment, systems, design, and layout
BIM was used to plan and coordinate various stages of
construction
It was also used to simulate the construction process
and identify potential issues beforehand.
STRATEGIES

Contour crafting was used to create Construction team used automated


concrete molds using 3D printing. It manufacturing processes to prefabricate
involved using a robotic arm to layer many stadium components, including
concrete in a pre-determined pattern to seating sections and steel structures
create a 3D object.

3D PRINTING DRONES
STRATEGIES

Construction team used automated A robot was used to cut and shape steel
manufacturing processes to prefabricate components for the stadium. The robot was
many stadium components, including seating equipped with a plasma cutter and a
sections and steel structures computer-controlled arm for high-accuracy
steel cutting.

PREFABRICATION ROBOTICS
The implementation of ICT and automation played a critical role in the construction of
Motera Stadium.

The use of ICT and Automation in the construction of Motera Stadium


enabled faster construction
reduced costs
increased precision
improved safety
TIME OF COMPLETION:

The project was initiated in November 2015 and was completed in February
2020, with a total construction time of around 4 years.
The stadium was completed within the stipulated deadline of 36 months,
despite
facing some delays due to issues related to land acquisition and
environmental clearances.
The precast construction technique helped to reduce the construction time
by almost 2 years compared to traditional construction methods.
SAFETY PERFORMANCE
ANALYSIS :
The stadium's architecture incorporates safety features
such as the ability to evacuate up to 50,000 people in
less than 7 minutes in the case of an emergency.

The stadium's design also includes measures to prevent


stampedes, such as multiple entry and exit points and
clear signage.

The stadium has been built to withstand natural


disasters such as earthquakes.

Overall, safety was given due consideration during the


construction of the Motera Stadium, with measures taken
to ensure the safety of workers, visitors, and nearby
residents.
CHALLENGES FACED AND STRATEGIES USED :

The stadium was built To increase seating To be completed The total cost of
on a 63-acre plot of capacity from 49,000 within 3 years owning reconstruction was
land . The land was to 110,000 on the to upcoming estimated to be ₹700
owned by multiple same site as the old international crores. However, the
parties, including stadium. The design matches final cost was
farmers and the state also had to ensure a reported at ₹800
government. 360-degree view of crores

the cricket field

LAND DESIGN TIME COST


ACQUISITION CHALLENGES CONSTRAITS : CONSTRAITS :



LAND ACQUISITION :
The process of acquiring the land was
complicated due to negotiations with each
landowner and in some cases, government
intervention was required.
The civic body ADU planned to merge two
town planning (TP) schemes and procure
land through an exchange.
More than 21 private and public plots
around the Narendra Modi Cricket Stadium
were identified for this purpose.
The necessary changes in the TP schemes
were initiated to enable this acquisition
process.
DESIGN CHALLENGES :
The city of Ahmedabad is located in seismic
zone 3, the roof needed to be lightweight to
reduce seismic demand and develop an
economical roof system.
It was decided that the best option would
be to incorporate a lightweight cable-
supported tensile membrane roof
supported by steel columns.
The radial cables are aligned in such a way
that rainwater flows over the membrane
and drains into the gutter positioned along
the lower chord of the compression ring
PLACING OF PRECAST MEMBERS
STADIUM BEFORE COMPLETION
STADIUM AFTER COMPLETION
FINANCIAL DETAILS:
Debt- Equity Ratio : Debt equity ratio is 25:75 for the project
Debt cost has been taken at 14%
GST of 18% has been considered for taxation
Debt repayment considered as 7 years
Parking and clubhouse will be constructed in the first year. Parking will be given on lease till the
commissioning of the project and during the non-match days. Also, membership of clubhouse has been
started.
Also some number of corporate boxes are pre-sold.
It is important to note, however, that cost overruns are not uncommon in large construction projects, and
may be due to a variety of factors such as changes in design, unexpected delays, or unforeseen construction
challenges. A detailed cost performance analysis would be needed to determine the specific reasons for the
cost overruns in this case.
COST ANALYSIS :

• The stadium cost roughly 800 crore rupees to construct. (around 110 million
USD).
• Larsen & Toubro (L&T) and its joint venture partner, Populous, a US-based
architecture firm, completed the project.
• Based on the given cost statistics, it appears that the Motera Stadium project
may have encountered cost overruns. The stadium's initial budget was at 7 billion
INR (approximately $95 million USD), although the final cost is said to be closer to
8 billion INR (approximately $110 million USD).
COST ANALYSIS :
Top Down Approach is used for cost estimation.
Total cost of the project, 800 Cr (execution cost -
662.62 Cr+ consultancy Fees ,overheads) , is
further broken down into work package cost and
further upto activity level
For the activity cost breakdown, BOQ of Etawah
Stadium is used for comparison (project cost :
222.2 Cr)

METHOD : The activity cost of a work package was divided by the total work package cost for getting a
ration, which was then multiplied with Motera stadium cost breakdown to reach to an activity level cost
breakdown.
Cost breakdown was done considering locational index.

You might also like