These specifications shall form part of the revised edition of the DPWH
Standard Specifications (Volume 11- Highways, Bridges and Airports).
HERMOGEN~k'ir..t •.•
~, JR.
Acting s~rd~c
11l1l1~mll1llll1
WIN6U00109
DEPARTMENT ORDER
No. K I Series of 2006
ANNEX Page 1 of 16
513.1 Description
3. The grout mix design and procedures for placing the grout.
1
DEPARTMENT ORDER
No. fLSeries of 2006
ANNEX Page 2 of 16
513.3.2 Grout
Water for mixing grout shall be potable, clean and free of injurious
quantities of substances known to be harmful to Portland cement or
prestressing steel.
2
DEPARTMENT ORDER
No. ~, Series of 2006
ANNEX Page 3 of 16
513.3.3 Centralizers
Encapsulation for the tendon bond length shall consist of one of the
following:
3
DEPARTMENT ORDER
No. 5/ Series of 2006
ANNEX Page 4 of 16
513.4.1 Fabrication
513.4.1.1. General
4
DEPARTMENT ORDER
No. -E1 Series of 2006
ANNEX Page 5 of 16
b. The maximum test load does not exceed 80% of the minimum
guaranteed ultimate tensile strength of the tendon.
5
DEPARTMENT ORDER
No. C1 Series of 2006
ANNEX Page 6 of 16
the encapsulation to the drill hole, or vice versa, will not be permitted.
The tendon shall be centralized within the encapsulation and the tube
sized .to provide a minimum 5mm of grout cover for the prestressing
steel. Spacers and centralizers shall be used to satisfy the same
requirements for grout protected ground anchor tendons. The anchorage
device of tendons protected with fusion-bonded epoxy shall be
electrically isolated from the structure.
The trumpet shall be welded to the bearing plate. The trumpet shall
have an inside diameter at least 6mmgreater than the diameter of the
tendon at the anchorage. The trumpet shall be long enough to
accommodate movements of the structure during testing and stressing.
For strand tendons with encapsulation over the unbonded length, the
trumpet shall be long enough to enable the tendon to make a transition
6
DEPARTMENT ORDER
No• ..t I Series of 2006
ANNEX Page 7 of 16
from the diameter of the tendon in the unbonded length to the diameter
of the tendon at the anchorhead without damaging the encapsulation.
513.4.2 Installation
513.4.2.1 Drilling
7
DEPARTMENT ORDER
No.~Serles of 2006
ANNEX. Page 8 of 16
The tendon shall be inserted into the drilled hole to the desired
depth without difficulty. When the tendon cannot be completely inserted
it shall be removed and the drill hole cleaned or redrilled to permit
insertion. Partially inserted tendons shall not be driven or forced into the
hole. Do not extend ground anchors beyond the right-of-way or
easement limits.
513.4.2.3 Grouting
The grout shall be injected from the lowest point of the drill hole.
The grout may be placed either before or after insertion of the tendon.
The grout may be pumped through grout tubes, casing, hollow-stem
augers or drill rods. The quantity of the grout and the grout pressures for
each ground anchor shall be recorded. The grout pressures and grout
takes shall be controlled to prevent excessive heaving of the ground or
fracturing of rock formations.
Except as indicated below, the grout above the top of the bond
length may be placed at the same time as the bond length grout, but it
shall not be placed under pressure. The grout at the top of the drill hole
shall stop 150mm from the back of the structure or from the bottom of
the trumpet, whichever is lowest.
8
DEPARTMENT ORDER
No. ~, Series of 2006
ANNEX Page 9 of 16
significant portion of its load resistance from the soil above the bond
length portion of the ground anchor.
Upon completion of grouting, the grout tube may remain in the drill
hole provided it is filled with grout.
9
DEPARTMENT ORDER
No. J1 Series of 2006
ANNEX Page 10 of 16
the tendon. No load greater than 10% of the design load may be applied
to the ground anchor prior to load testing. The test load shall be
simultaneously applied to the entire tendon
A hydraulic jack and pump shall be used to apply the test load. The
jack and a calibrated pressure gauge shall be used to measure the
applied load. The pressure gauge shall be graduated in 1MPa
increments or less. When the theoretical elastic elongation of the total
anchor length at the maximum test load exceeds the ram travel of the
jack, the procedure for recycling the jack ram shall be included in the
working drawings..Each increment of test load shall be applied as rapidly
as possible.
10
DEPARTMENT ORDER
No. -t I Series of 2006
ANNEX Page 11 of 16
Load Load
(START) (CONIlNUATION)
AL AL
0.25DL· O.25DL
AL O.50DL
0.25DL 0.75DL
0.50DL '" 1.00DL
AL 1.20DL •
0.25DL AL
0.50DL 0.25DL
O.75DL '" 0.50DL
AL 0.75DL
0.25DL . 1.00DL
O.50DL 1.20DL
0.75DL 1.33DL'"
(Malcimum test load)
1.OODL*
Reducetolock-offload
11
DEPARTMENT ORDER
No. --rl Series of 2006
ANNEX Page 12 of 16
Load Load
(START) (CONTINUATION)
AL
0.25DL 1.20DL
0.50DL 1.33DL (maxtest load)
0.75DL Reduce to lock-off load
1.00DL
The maximum test load in a proof test shall be held for 10 minutes.
The jack shall be repumped as necessary in order to maintain a constant
load. The load-hold period shall start as soon as the maximum test load
12
DEPARTMENT ORDER
No.~I Series of 2006
ANNEX Page 13 of 16
AL
0.25DL 10
0.500L 30
0.75DL 30
1.000L 45
1.20DL 60
1.33DL 300
13
DEPARTMENT ORDER
No. RSeries of 2006
ANNEX Page 14 of 16
14
DEPARTMENT ORDER
No• ..(""f Series of 2006
ANNEX Page 15 of 16
A ground anchor which has a creep rate greater than 2mm per log
cycle of time can be incorporated into the structure at a design load
equal to one-half of its failure load. The failure load is the load resisted
by the ground anchor after the load has been allowed to stabilize for 10
minutes.
When·a ground anchor fails, .the Contractor shall modify the design
and/or the installation procedures. These modifications may include, but
are not limited to, installing a replacement ground anchor, reducing the
design load by increasing the number of ground anchors, modifying the
installation methods, increasing the bond length or changing the ground
anchor type. Any modification which requires changes to the structure
shall be approved by the Engineer. Any modifications of design or
construction procedures shall be without additional cost to the
Department and without extension of contract time.
15
DEPARTMENT ORDER
No• ..s-I Series of 2006
ANNEX Page 16 of 16
completely unloaded prior to lock-off. After transferring the load and prior
to removing the jack, a lift-off load reading shall be made. The lift-off load
shall be within 10% of the specified lock-off load. If the load is not within
10% of the specified lock-off load, the anchorage shall be reset and
another lift-off load reading shall be made. This process shall be
repeated until the desired lock-off load is obtained..
Ground anchors will be measured and paid for by the sum of the
bonded and unbonded length of anchor bars installed and accepted as
shown on the plans or ordered by the Engineer. No change in the
number of ground anchors to be paid for will be made because of the
use by the Contractor of an alternative number of ground anchors.
Pay Item
Description Unit of Measurement
Number
513 Permanent Ground Anchor Linear meter