i. Refer to ISM 4, describe “Designated Person(s)”. ii. Refer to ISM 5.2,describe circumstances where the master to exercise his “overriding authority”.
iii. As a senior engineer on the ship, describe
your duty & responsibility in compliance with ISM clause 10.
2. a) Explain the following heat treatment
process & how steel’s grain structure changes in relation to the heat treatment? i. Annealing ii. Normalising iii. Quenching iv. Tempering
b) Describe following process:
i. Case Hardening ii. Flame hardening iii. Carburizing iv. Nitriding v. Cyaniding.
3. Refer to MARPOL,
a) List the title of each Annex below: i. Annex I ii. Annex II iii. Annex III iv. Annex IV v. Annex V vi. Annex VI b) State current maximum allowable limit of sulphur content for ship’s fuel, i. Outside Emission Control Area, before 1 January 2020. ii. Outside Emission Control Area, after 1 January 2020. iii. Within Emission Control Area.
c) List Emission Control Area, as per
MARPOL Annex VI.
Part C:
12. As senior engineer of the ship, describe
preparation work to be done on the day before dry-docking the ship.
13. Why main engine crankshaft deflection to
be measured before docking, after docking and after sea trial. As senior engineer of the ship, describe your subsequent action if the crankshaft deflection before docking is within maker allowable limit, however after docking it is out of maker allowable limit. 14. Refer to welding, i) What is “Pre-weld Heat treatment”.
ii) What is “Post-weld heat treatment”
iii) What is “Hydrogen cracking”
iv) What is “Heat Affected Zone”
v) Why visual inspection and non-destructive test
on completed weld to be done 8 hours after work completion.