10DJL19F1036
INTERNSHIP IN MALAYSIAN SHEET GLASS
Introduction to the industry
◦ Malaysian Sheet Glass is a Japanese-owned company.
◦ This compony was established on 18 November 1971.
◦ Another name is Nippon Sheet Glass.
◦ The factory is in Sungai Buluh, Selangor.
◦ This company manufactures various car mirrors.
Among the types of car mirrors that are made are:
Week 2
◦ Learn about assembly line process
◦ Learn about trimming film pvb properly
Week 3
◦ Sick leave ( covid )
Weekly activities
Week 4
◦ Learn about machine in assembly. Like conveyor
◦ Learn about component at washer machine
◦ Learn about how to switch on or off washer machine
Week 5
◦ Learn about how to clean conveyor
◦ Learn about function of De-aring oven machine
◦ Learn about operator working in assembly line
Weekly activities
Week 6
◦ Learning about how to starting stretching machine
◦ Learning about the technical problem in machine caused the film Pvb to be rejected
Week 7
◦ Learning about the emergency action
Week 8
Weekly activities
Week 9
◦ Aidilfitri holidays for 1 week
Week 10
◦ Learn about final inspection process in final line 2
◦ Learn about operator working in the final line 2
◦ Working in the final line 2
Week 11
◦ Working in the assembly line
Weekly activities
Week 12
◦ Working in the assembly line
Week 13
◦ Working in the assembly line
◦ Learning about the effects of reject problem in the glass
Week 14
◦ Changing the new telfon in De-airing
◦ Changing the new air filter on the de-airing
Weekly activities
Week 15
◦ Self-reporting in maintenance room
◦ Changing the new sponge roll in washer
◦ Refuel the grease on the pillow block in the nipple grease
◦ Service Multistage Coolant Pump
Week 16
◦ Services vertical water pump and suction valve
◦ Welding in iron plate
◦ Service Multistage Coolant Pump
◦ Cleaning outside maintenance room
◦ Loosen the screw on the demaged gate valve
Weekly activities
Week 17
◦ Cleaning in the compressor room
◦ Cutting iron with grinder
Machine trouble in CP2 machine
◦ Changing cylinder
Week 18
◦ Cleaning on the Furnace
◦ Cleaning Vacuum pump from powder
Shutdown in CP2 machine
◦ Repairing glass cutting machine
◦ Refuel the grease on the pillow block in the nipple grease
WEEKLY ACTIVITIES
Week 19
◦ Changing new sponge roll in washer machine
◦ Repairing control valve
◦ Test run control valve
◦ Eid hajj holiday for 4 day
Week 20
◦ Repairing fan
◦ Repairing a clogged pillow block
TECHNICAL REPORT
De-airing Oven Vertical Washer Machine