0 - SCHEDULE TRACKING

Project Identification
Project Name:
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX Comments:
Project Manager: XXXXX Project Sponsor: XXXXX
Document Date: 20/11/2016 Document Version: Rev 0

Project Schedule Information

Time (days)

Actual Start
Percentage
Description

Dependent
Estimated

Resource

Complete
Start Day
Planned

Planned
Task ID

Actual
Finish

Finish
Upon
Task

1 Brainstorm 5 - All 06/10/2016 12/10/2016 100 06/10/2016 12/10/2016


2 Initiation Documentation 10 1 All 13/10/2016 27/10/2016 100 17/10/2016 31/10/2016
3 Project Scope 5 2 All 14/11/2016 20/11/2016 80 17/11/2016
4 Estimation 5 3 All 21/11/2016 25/11/2016 20 20/11/2016
Develop Project Management
5 5 3 All 05/12/2016 09/12/2016 20 20/11/2016
Plans
6 Scope Analysis 5 5 All 09/01/2017 13/01/2017
7 PDMS Software 20 6 All 14/04/2017 12/05/2017
8 Reporting 15 6 All 28/04/2017 02/06/2017
9 Project Management 15 6 All 28/04/2017 16/06/2017
10 Final Project Reporting 5 9 All 17/06/2017 22/06/2017
11 Archiving 5 10 All 23/06/2017 30/06/2017

|