You are on page 1of 18

Elimination of Prestressed

Concrete Compression Limits


at Service Load
Panya Noppakunwijai, Ph.D. This paper addresses the justification for removal
Research Assistant Professor
Department of Civil Engineering of two compressive stress limits, called hereafter
University of Nebraska-Lincoln Limits 1 and 2, which are currently used in both
Omaha, Nebraska
the ACI 318 Building Code and AASHTO Bridge
Specifications to limit concrete stresses due to
effective prestress combined with applied loads.
Removal of these limits provides relief in sizing of
members that have small compression zones that
are subjected to large bending moments, such as
inverted tee bridge members in the positive
Nabil Al-Omaishi, Ph.D., P.E. moment zones and I-girder bridges made
Research Assistant Professor
Department of Civil Engineering continuous for superimposed loads in the negative
University of Nebraska-Lincoln moment zone. Limit 1 is 0.6f c′, where f c′ is the
Omaha, Nebraska
specified compressive strength at service. It is
imposed on concrete stresses due to the effective
prestress combined with full dead plus live loads.
Maher K. Tadros, Ph.D., P.E.
Cheryl Prewett Professor
Limit 2 is 0.45f c′. It is imposed on stresses due to
Department of Civil Engineering the effective prestress combined with dead loads.
University of Nebraska-Lincoln It is proposed that strength be used as the primary
Omaha, Nebraska
design criterion to determine member capacity in
compression at various loading stages, including
prestress transfer, lifting, erection, deck weight,
superimposed dead load and live load. Various
serviceability checks can additionally be used as
needed to control camber, deflection, vibration,
and cracking. Design steps and numerical
Gary L. Krause Ph.D., P.E.
Associate Professor examples are given. Also, proposed changes to the
Department of Civil Engineering ACI 318 Building Code and to the AASHTO-LRFD
University of Nebraska-Lincoln
Omaha, Nebraska
Bridge Design Specifications are given.

2 PCI JOURNAL
he restrictions on concrete com-

T pressive stress at service limit


state in the design of prestressed
concrete flexural members in the
Limit 1: fd + fl ≤ 0.6f c′

American Concrete Institute Building Limit 2: fd ≤ 0.45f c′


Code (ACI 318-02), 1 and American Limit 3: fd + 2fl ≤ 0.8f c′
Association of State Highway and
Transportation Officials (AASHTO)
Load and Resistance Factor Design
(LRFD) Bridge Design Specifications2
appear to be based on historical justifi-
cation. They neither directly address
serviceability conditions, such as cam-
ber and deflection limits, nor ensure
adequate strength under factored
loads.
When an inverted tee bridge super-
structure is designed and the working
stress design compressive stress limits
are checked, its capacity is often con- Fig. 1. Concrete compression stress limits according to AASHTO Specifications.
trolled by the limit imposed by the ef-
fective prestress plus dead load, as cal-
culated by the standard elasticity both “working stress design,” which stress plus dead load. Limits 1 and 2
theory without regard to stress-strain was the prevalent design method, and in the AASHTO-LRFD Specifications
nonlinearity or creep redistribution of “strength design,” which was getting are identical to those in the ACI 318
stresses between the precast beam and introduced at that time. Convention- Building Code.
the cast-in-place topping. ally reinforced concrete, on the other A third limit, unique to bridge de-
The same problem sometimes arises hand, was allowed to be designed sign, is 0.40f c′. It is required to be ap-
in bridge I-girders in integral bridge starting with the 1963 edition of the plied in AASHTO-LRFD to concrete
systems, i.e., when the girders are ACI 318 Code by either the working stresses due to 50 percent of effective
made continuous with cast-in-place stress design method or the strength prestress plus 50 percent of dead load
concrete diaphragms and continuity design method, but not both methods. plus 100 percent of live load. It is in-
negative moment reinforcement in the The overly conservative compressive tended to control fatigue due to live
deck. Bottom fiber stresses can exceed stress limits in current working stress load, which is a repeated cyclic load
the allowable limits, even though the design practice of prestressed concrete caused by moving vehicles during the
strength of the negative moment sec- control the design in a number of ap- life of a bridge. However, the provi-
tion meets all code requirements. This plications and thus limit the utilization sions for that limit should be moved
situation forces designers to either ig- of the full potential of prestressed con- from their current location to the sec-
nore the code requirements or unnec- crete. tion that deals with design for fatigue
essarily select a larger member size. In an earlier paper,3 a strength-based effects. In that section, the fatigue
Removal of the unnecessary com- design method for prestressed con- truck loading model, rather than the
pression limits could result in creation crete flexural members at transfer of standard truck loading model used for
of a series of more efficient precast, prestress was presented as a replace- strength calculations, should be used
prestressed concrete products. This, ment of working stress design and the to determine the live load stresses.
coupled with increasing acceptance of compressive stress limit of 0.60f ci′ , With these two suggested modifica-
self-compacting concrete, would make where f ci′ is the specified compressive tions, this limit should not be re-
producers and their engineers develop, strength of concrete at initial prestress moved, and thus the topic is not dis-
for example, efficient inverted double transfer. cussed further in this paper.
tee members that would be connected This paper presents a historical The AASHTO Standard Specifica-
in the field with a thin topping, creat- background of compressive stress lim- tions for Highway Bridges
ing a very efficient building floor with its at service load conditions, and pro- (AASHTO-STD) 4 are being phased
a shallow depth and a smooth soffit. vides a justification for total removal out. They have similar limits to those
Many existing products could be opti- of these limits. The two limits being in AASHTO-LRFD, except that Limit
mized, reducing their weights and in- imposed on concrete in compression 2 in AASHTO-STD is 0.40f c′ rather
creasing their capacities. are Limit 1, 0.60f c′, on concrete stress than 0.45f c′. Both values were intro-
As prestressed concrete was being due to effective prestress, after al- duced in the 1994 editions of the two
introduced in North America, about 50 lowance for long-term losses, com- sets of AASHTO Specifications. The
years ago, it was believed to be impor- bined with full loads, and Limit 2, difference is believed to have occurred
tant to double-check its adequacy with 0.45f c′, on stress due to effective pre- by an arbitrary decision by the com-

November-December 2002 3
Fig. 2. Cross section of axially prestressed
member example.

mittee in charge of maintaining these


specifications. For clarity, only the
0.45f c′ value is used in further discus- Fig. 3. Comparison between results of linear and nonlinear analyses.
sion in this paper.
The three limits of allowable com-
pressive stresses in AASHTO-LRFD
by a discussion justification for re- proposed different limits ranging from
can be written as follows:
moval of Limits 1 and 2. An alternate 0.33f c′ to 0.5f c′ as reported in Refer-
Limit 1: fd + fl ≤ 0.6f c′ (1) strength-based design procedure is ence 6. According to Article 3.4.11 of
presented and illustrated with numeri- the 1953 “AASHO Standard Specifi-
Limit 2: fd ≤ 0.45f c′ (2) cal examples. Changes to the affected cations for Highway Bridges,” an al-
Limit 3: fd + 2fl ≤ 0.8f c′ (3) sections in the ACI 318 Code and in lowable compressive stress limit of
the AASHTO-LRFD Specifications 0.4f c′ was given for conventional con-
where are proposed. crete subjected to dead, live, or impact
fd = compressive stresses due to loads. The Bureau of Public Roads
the sum of effective prestress conservatively adopted the same stress
HISTORICAL
and permanent loads after al- limit for prestressed concrete struc-
lowance for time-dependent BACKGROUND tures.
losses The Prestressed Concrete Institute The allowable compression stress
fl = compressive stresses due to (PCI) issued the first specifications5 limit of 0.45f c′ appeared in the first
live load for bonded pretensioned prestressed published draft of the ACI-ASCE
Fig. 1 shows the domain of limits on concrete on October 7, 1954. In those Joint Committee 323 Report “Recom-
fd and fl to satisfy each of Limits 1, 2 specifications, the maximum allow- mended Practice for Prestressed Con-
and 3. For example, when the live load able compressive stresses under final crete”7 in 1958. The early code writers
stress, fl, is equal to 0.2f c′ or higher, dead and live loads was 0.40f c′ for felt that this limit was conservatively
the maximum dead load plus effective bridge members and 0.44f c′ for build- established to decrease the probability
prestress, fd, is controlled by Limit 3 ing members. of failure of prestressed concrete
which controls concrete fatigue. When In 1954, the Bureau of Public Roads members due to repeated loads and to
fl is less than 0.15, Limit 2 controls (BPR) published the first edition of preclude excessive creep deforma-
the maximum allowed fd. Thus, Limit Criteria for Prestressed Concrete tions. In the 1958 report, “Tentative
1 has practically no impact on design Bridges, by E. L. Erickson,6 who at Recommendations for Prestressed
by the current LRFD provisions, as the time was chief of the Bridge Divi- Concrete” and 1959 report “PCI Stan-
seen in Fig. 1. sion, Bureau of Public Roads (BPR). dard Building Code for Prestressed
It can be shown, using a similar That bureau was later renamed the Concrete (Tentative),” the 0.45f c′ limit
graph as in Fig. 1, that Limit 1 never Federal Highway Administration was retained, but there was no clear
controls design according to the (FHWA). commentary as to why this was done.
AASHTO-STD Specifications. There- At that time, there was a consider- Although the 0.45f c′ limit was totally
fore, removal of Limit 1 saves an un- able difference of opinion among the removed for non-prestressed concrete
necessary design check since either various authorities as to how much at the time of the introduction of
Limit 2 or Limit 3 supersedes it. The compression to allow in the extreme strength design, this limit was kept un-
proposal in this paper, however, is to concrete fiber under dead, live, and changed until 1995 for prestressed
remove both Limits 1 and 2. impact load. Several authorities (for concrete. The ACI 318-95, the 1994
In the following sections, a histori- example, Hajnal-Konyi, Dobell, Leon- AASHTO-LRFD and the 1996
cal overview is given. It is followed hardt, Muller, Billig) at that time had AASHTO-STD Specifications adopted

4 PCI JOURNAL
changes based on the work by Huo et Table 1. Inverted tee section properties.
al.8 That reference gave justification Area Total depth yb I Sb St (beam) St (deck)
for a 33 percent increase in the limit to Section Ed /Eb (sq in.) (in.) (in.) (in.4) (in.3) (in.3) (in.3)
0.60f c′, and for the introduction of Beam – 252.0 24.00 8.14 12,235 1503 771 –
Limit 2, due to the effective prestress Deck – 144.0 6.00 27.00 432 – – –
plus dead load. It was believed, by Composite 1.00 396.0 30.0 15.00 45,252 3017 5028 3017
Age-adjusted
some code committee members, that 0.66 347.0 30.0 13.31 37,053 2784 3466 2220
composite
the 0.45f c′ limit should not be ex-
Note: 1 in. = 25.4 mm; 1 sq in. = 645 mm2; 1 in.3 =16,387 mm3; 1 in.4 = 416,231 mm4.
ceeded to avoid dealing with the non-
linear creep of concrete at higher
stress levels.
Since live load is considered tran-
sient, it was indicated that a 33 percent
additional stress would not be detri-
mental. Huo et al.8 indicated that the
changes were intended to be transi-
tional, with the eventual goal of total
elimination of compressive stress lim-
its. It was further demonstrated that, if
working stress had to be performed on
a conventionally reinforced rectangu-
lar section example that was already Fig. 4. Cross-
designed with strength design, the ex- sectional
treme fiber compressive stress could dimensions of
be as high 0.83f c′. inverted tee, 82 ft
span bridge girder.

FLEXURAL BEHAVIOR OF
PRESTRESSED MEMBERS will be summarized below, that allow when 44 strands are used. However,
designers to directly check for mem- nonlinear analysis more correctly indi-
Two sources of nonlinearity exist in ber strength against concrete crushing, cates that concrete continues to resist
the flexural behavior of prestressed or for member serviceability against placement of more prestressing up to
concrete, namely, nonlinearity due to excessive deflections. 62 strands when the strain reaches the
increasing load and nonlinearity due to assumed ultimate strain of 0.003.
time-dependent volume change effects. This figure confirms three facts:
The first part of this section deals with Analysis at Transfer due to
Increasing Prestress Level 1. Concrete crushes when its strain
the nonlinearity of the concrete stress- reaches ultimate strain, not when the
strain relationship and its effect on Huo et al.9 considered an example stress reaches its peak elastic analysis
member condition at time of prestress of an axially prestressed concrete value.
transfer. It will be shown that the linear member, summarized below. The 2. As prestressing increases, so does
elastic calculation of compressive cross section is shown in Fig. 2. Con- concrete strain and prestress losses.
stress is not compatible with the 0.6f c′ crete and steel stresses and strains due Thus, unlike externally induced com-
limit which falls outside of the linear to a progressively increased number of pression, prestressing has a self-reliev-
range of the stress-strain diagram, nor prestressing strands up to the failure ing mechanism.
is it representative of a constant safety load, are shown in Fig. 3. The strands 3. Member failure cannot be accu-
index against concrete crushing. are assumed to be arranged to produce rately predicted without utilization of
The second part of this section a concentric load as their number in- the entire stress-strain diagram
demonstrates that continuous stress re- creases. through nonlinear analysis and
distribution occurs due to creep and Two methods of analysis, namely, strength based design.
shrinkage of concrete in a composite standard linear analysis and nonlinear
member, consisting of two concrete analysis, are considered. As shown in
components. When that effect is taken Fig. 3, both standard linear analysis Analysis of Composite Members
into account, the top fiber stresses of and the more accurate nonlinear anal- After Prestress Transfer
the precast concrete component of the ysis produce about the same results, a In standard practice in current use,
member undergo considerable relief. maximum of 26 strands, when the linear elastic behavior is employed to
Therefore, a linear elastic analysis for concrete stress is at the 0.6f ci′ code check tension and compression limits
compressive stress, and limiting it to limit. The strains are not as close as in concrete and to calculate camber
0.6f c′, does not correspond to the ac- the stresses between the two models. and deflection. Concrete, as well as
tual member behavior. On the other Linear analysis appears to indicate steel, is assumed to follow Hooke’s
hand, methods are available, which that concrete reaches the strength f ci′ Law, i.e., stress equals the product of

November-December 2002 5
1.755 ksi

-0.536 ksi

-0.286 ksi

Fig. 5. Concrete
stresses in an
inverted tee
bridge girder at
various loading
stages.

strain and modulus of elasticity. Pre- ber and deflection calculations. Concrete strength of the precast sec-
stress losses due to creep and shrink- • The fourth example shows how tion at transfer, f ci′ = 6 ksi (41.37 MPa)
age of concrete and relaxation of pre- safety can be directly satisfied and at service, f c′ = 8 ksi (55.16 MPa).
stressing steel are calculated against failure by conducting a The deck concrete strength is 6 ksi
separately and assumed to be exter- strength analysis of the member. (41.37 MPa).
nally introduced as “negative pre- Due to space limitations, only seg- Moments at midspan: M g = 2648
stress” in the linear elastic analysis. ments of the full example will be kip-in. (299 kN-m), Md = 1513 kip-in.
When these assumptions are made, given. A more detailed treatment of (171 kN-m), Ml = 5295 kip-in. (598
true time-dependent stress redistribu- the topic is given in Reference 10. kN-m) due to self-weight, deck
tion cannot be determined and design- weight, and live load, respectively.
ers are left with, at best, nominal stress The stress in the prestressing steel
values that may be highly exagger- Example 1: Elastic Analysis of an has been determined through time-de-
ated. The following four numerical ex- Inverted Tee Bridge Beam pendent analysis to be 184.21 ksi
amples relate to the same bridge A precast concrete bridge super- (1270 MPa), 173.49 ksi (1196 MPa)
beam: structure consists of an inverted tee and 160.28 ksi (1105 MPa) immedi-
• The first example illustrates the con- beam, with a span of 82 ft (24.99 m), ately after transfer, at time of deck
ventional elastic stress analysis for and a spacing of 2 ft (0.61 m). The placement and at time infinity, respec-
stresses at various stages of loading. beam is made composite with a 6 in. tively. The corresponding prestress
• The second example shows how (152 mm) thick cast-in-place slab. Fig. force values are: 620.1, 584.0 and
time-dependent analysis can be con- 4 shows the concrete dimensions and 539.5 kips (2758, 2598 and 2400 kN).
ducted and how much the results dif- steel arrangement. Table 1 gives the The precast concrete top fiber stress,
fer from those of the elastic analysis. section properties of the precast beam f t, is calculated using the following
• The third example deals with cam- and composite section. elastic stress analysis formula:

6 PCI JOURNAL
Table 2. Summary of stresses at various loading stages.
Linear elastic analysis
Transfer Erection Final
Top beam Bottom beam Top beam Bottom beam Top deck Bottom deck Top beam Bottom beam
Loads (ksi) (ksi) (ksi) (ksi) (ksi) (ksi) (ksi) (ksi)
P/A 2.461 2.461 2.317 2.317 – – 2.141 2.141
Pe/S -4.133 2.122 -3.892 1.999 – – -3.596 1.847
Mg/S 3.431 -1.762 3.431 -1.762 – – 3.431 -1.762
Md/S – – 1.961 -1.007 – – 1.961 -1.007
Ml/S – – – – 1.755 1.053 1.053 -1.755
Total 1.759 2.821 3.817 1.547 1.755 1.053 4.990 -0.536
Limiting 0.6f ci′ 0.6f ci′ 0.45f c′ 0.45f c′ 0.6f c′ 0.6f c′ 0.6f c′ 6 fc′
stresses 3.600 3.600 3.600 3.600 3.600 3.600 4.800 -0.537
OK OK High OK OK OK High OK
Time-dependent analysis
At erection 3.817 1.547 – – 3.817 1.547
Differential
creep and – – 0.198 0.209 -0.830 0.251
shrinkage
Prestress loss – – – – 0.120 -0.329
Live load 1.755 1.053 1.053 -1.755
Total 3.817 1.547 1.953 1.262 4.160 -0.286
High OK OK OK OK OK
Note: 1 ksi = 6.895 MPa.

P Pe M section are calculated in a similar way. results in significant reduction in the


ft = + + (4) The results are shown in Fig. 5 and elastic compressive stress at the top
A St St
Table 2. fiber of the precast component. Such
where Both the ACI 318 Code and the redistribution cannot be determined
P = prestress force AASHTO LRFD Specifications re- through elastic analysis (see, for ex-
e = eccentricity of the prestressing quire that the stress due to permanent ample, Kamel11). Thus, the standard
force loads not exceed 0.45f c′ = 3.6 ksi practice of elastic analysis, which is
M = external load moment (24.82 MPa). The stress at erection of based on limiting the top fiber com-
A = section area 3.817 ksi (26.32 MPa) exceeds that pressive stress, is misleading.
St = section modulus limit. Both codes require that the The theory that Kamel used in-
stress due to full load not exceed volved an elaborate analysis of time-
At transfer: 0.60f c′ = 4.8 ksi (33.09 MPa). The dependent effects, based on earlier
stress of 4.990 ksi (34.41 MPa) ex- work by Tadros et al.12 The time his-
620.05 620.5(5.14) 2648
ft = − + ceeds that limit. Thus, according to tory, in that analysis, is divided into
252 771 771 elastic analysis, the beam fails to meet many small steps. As the size of the
= 1.759 ksi (12.13 MPa) the code requirements due to both time-step decreases, the accuracy of
loading combinations. the analysis increases. However, that
At erection: method is suited for commercial soft-
ware solutions.
583.97 583.97(5.14) Time-Dependent Stress
ft = − A slightly less accurate, but greatly
252 771 Redistribution in simplified, method presented by Dil-
2648 1513 Composite Member ger13 is suitable for hand-calculation
+ +
771 771 The purpose of this section is to and designer-developed spreadsheet
= 3.817 ksi (26.32 MPa) demonstrate two points: solutions. Dilger’s “age-adjusted ef-
1. If there is a need for serviceabil- fective modulus” method is the one
At final time: ity checks, means already exist to cal- adopted in this paper for further dis-
culate the design parameters and to cussion.
539.50 539.50(5.14)
ft = − + check against required limits. This ap- The age-adjusted effective modulus
252 771 plies to deflection, camber, cracking, method is similar to conventional elas-
2648 1513 5295 and other parameters. tic analysis. Instead of using the con-
+ +
771 771 5028 2. Composite members consisting of ventional modulus of elasticity to de-
= 4.990 ksi (34.41 MPa) precast, prestressed concrete and cast- termine transformed section
in-place concrete components undergo properties, the age-adjusted effective
The stresses at other locations in the continuous stress redistribution that modulus is used. In addition, deforma-

November-December 2002 7
tion due to shrinkage and creep of The corresponding modulus of elastic- Step 2
concrete, and relaxation of prestress- ity, Ed = 4696 ksi (32.38 GPa). Calculate the forces and the corre-
ing steel, are considered during a time Creep and shrinkage of precast con- sponding stresses in each component
interval as “initial” strains, much like crete between erection and time infin- that cancel the deformations in Step 1.
pseudo-elastic analysis for effects of ity, ψbdf = 0.65, and εbsh = 150 × 10-6. For this analysis, the age-adjusted ef-
temperature change. Creep and shrinkage of deck con- fective modulus for each material is
To incorporate initial strains into the crete ψddf = 1.3, and εdsh = 300 × 10-6. used.
stress analysis, three steps are fol- The aging coefficient is taken con- Age-adjusted effective modulus for
lowed: stant for both materials, χb = χd = 0.7. precast beam:
1. Separate various concrete and For clarity of presentation, the age-ad-
steel components of the cross section justed transformed section properties Eb
and allow them to deform freely. are calculated assuming an area of Eb* =
1 + χ bψ bdf
2. Restrain the components of the steel equal to zero.
section and calculate the restraining Note that a more detailed set of cal- 5422
=
forces to bring the initial strains calcu- culations of the same example, includ- 1 + (0.7)(0.65)
lated in Step 1 to zero. ing the interaction of the prestressing = 3727 ksi (25.70 GPa)
3. Reattach the various components steel may be found in Reference 10.
to each other and restore equilibrium Using the actual area of steel in calcu- Age-adjusted effective modulus for
by applying equal and opposite forces lation would automatically account for deck:
to those calculated in Step 2. time-dependent prestress losses. In
The sum of stresses in Steps 2 and 3 this example, the prestress losses esti- Ed
Ed* =
is the net stress, and the deformation mated for Example 1 will be assumed. 1 + χ bψ bdf
in Step 3 is the net deformation. In Because of the simplified assump-
4696
Steps 2 and 3, the modulus of elastic- tions used in this example, the con- =
ity of concrete is adjusted by dividing crete stress increments due to various 1 + (0.7)(1.3)
Ec by (1 + χψ), where χ is the aging actions are identical to those in Exam- = 2459 ksi (16.95 GPa)
coefficient to allow for gradual intro- ple 1, with one exception. Once the
duction of time-dependent stress in- deck becomes composite with the Axial restraining force in precast
crements, and ψ is the creep coeffi- girder, differential creep and shrinkage beam:
cient. To illustrate this procedure, the between the two concretes cause con-
following example provides a detailed tinuous redistribution in the concrete = –(free axial strain)Eb* Ab
calculation of stress, strain and defor- stresses. The calculations will, thus, = –4.278(3727)(252)(10-4)
mation due to time-dependent effects focus on the time interval between = –401.75 kips (–1787.08 kN)
in a composite section. erection and time infinity.
The analysis steps explained earlier Corresponding stress in precast
will be followed. beam:
Example 2: Time-Dependent
Analysis of the Beam of Example 1
= –401.75/252
This example shows the difference Step 1
= –1.594 ksi (–10.99 MPa)
in results with the elastic analysis Separate the two section compo-
when time-dependent stress redistribu- nents and allow each to deform freely. The bending restraint force in the
tion is accounted for. The input data is beam and the axial restraining force in
Axial strain in precast beam:
the same as in Example 1. Addition- the deck can be calculated similarly to
ally, the following time-dependent P
ψ bdf + ε bsh be –516.97 kips-in. (–2300 kN) and
properties have been estimated using AE –106.21 kips (–472.46 kN).
the formulas in Reference 14 assum- 583.97 The corresponding stresses in the
ing the member is subject to ambient = (0.65) + 0.00015
252(5422) beam are:
relative humidity of 70 percent. Other Top fibers, –2.264 ksi (–15.61
sources of prediction of material prop- = 4.278 × 10 −4
MPa);
erties are AASHTO LRFD Specifica- Bottom fibers, –1.250 ksi (–8.62
tions, and the PCI Bridge Design Curvature in precast beam:
MPa); and in the deck are: top fibers =
Manual (PCI-BMD).15 M bottom fibers = –0.738 ksi (–5.09
The modulus of elasticity of the pre- ψ bdf
EI MPa).
cast concrete at service, Eb = 5422 ksi
(37.39 GPa). An average compressive =
[2648 + 1513 – 583.97(5.14)] (0.65)
strength of the deck of 6 ksi (41.37 5422(12, 235) Step 3
MPa) is assumed for the period be- = 1.134 × 10 in. (4.464 × 10 mm )
-5 -1 -7 -1
Now that the compatibility of the
tween the time it starts to act compos- two components has been restored in
itely with the girder and time infinity. Axial strain in deck = 0.0003 Step 2, the two components can be

8 PCI JOURNAL
“reattached” and equilibrium restored
by applying equal and opposite forces
to the forces obtained in Step 2. To
undertake the analysis in this step, the
age-adjusted composite section prop-
erties must be calculated and used.
These can be found using a deck-to-
beam modular ratio = E d* /E b* =
2459/3727 = 0.66. The section proper-
ties are shown in Table 1.
All the component forces in this
step are then combined into an axial
force at the centroid of the age-ad-
justed composite section.

Axial force:
= 401.75 + 106.21
= 507.96 kips (2259.53 kN)

Bending moment:
= –102.58 kip-in. (–11.59 kN-m)

The corresponding top fiber stress in


the beam is:

507.96 102.58(24 − 13.31)


ft = −
347 37, 053 Fig. 6. Comparison of stress diagrams between working stress design and strength design.
= 1.434 ksi (9.89 MPa)

The stresses at the extreme fibers of dependent stress increments. For the cracking, and not to check against
the deck and at the bottom fibers of beam top fibers, that net stress is: concrete crushing which is the func-
the beam are calculated similarly. tion of strength design.
3.817 – 0.830 + 0.12
= 3.107 ksi (21.42 MPa) Example 3: Camber and Deflection
Step 4 Calculations of the Beam of
The summation of all stresses and This stress is below the code limit Examples 1 and 2
deformations in Steps 1 through 3 pro- of 0.45f c′ = 3.6 ksi (24.82 MPa).
This example illustrates the calcula-
duce the net incremental values due to Adding live load stresses as shown
tion of the camber and deflection at
creep and shrinkage between at time in Example 1, the beam top fiber
the midspan of the beam of Examples
of erection and time infinity. The stress equals:
1 and 2. Numerical integration of the
time-dependent top fiber stress in the curvature may be used to obtain the
beam, for example, equals –2.264 + 3.107 + 1.053
deflection.
1.434 = –0.830 ksi (–5.72 MPa). Other = 4.160 ksi (28.68 MPa).
For this example, the deflection-cur-
values are given in Table 2. vature relationships δ = φc l2/8 due to
The additional prestress losses in This again is less than the code limit prestressing and δ = 5φc l2/48 due to
steel between erection and final time of 0.6f c′ = 4.8 ksi (33.09 MPa). gravity load, given in Reference 16, are
were assumed to be the same as in Ex- A comparison of the results of Ex- used. The symbols δ, φc , and l repre-
ample 1. Thus, a concrete stress amples 1 and 2 leads to the conclusion sent midspan deflection, midspan cur-
change due to a steel stress loss of: that a linear elastic analysis does not vature, and span length, respectively.
account for the generally significant
= 160.28 – 173.49 stress relief of the compressive stress
= –13.21 ksi (–91.08 MPa) in the top fibers of the precast compo- (1) Instantaneous camber at initial
nent of a composite section, and leads prestress transfer
needs to be included. As shown in to the false impression that these Design for prestress transfer, using
Table 2, the stress change at the top fibers are overstressed. the strength design method proposed
fibers is 0.12 ksi (0.83 MPa). It should be emphasized that the in Reference 3, indicates that no drap-
The net stresses, including time-de- value of service load analysis is to ing or debonding of the strands is
pendent effects, are equal to the check member serviceability, i.e., to needed if the concrete strength at pre-
stresses at the erection plus the time- check for excessive deformation and stress transfer, f ci′ , is set at 5.74 ksi

November-December 2002 9
Net camber before deck placement:

= –2.07 – 0.74 + 0.34


= –2.47 in. (–63 mm)

(4) Instantaneous deflection due to


deck weight

Md
φc =
EI
1513
=
5422(12, 235)
= 2.281 × 10-5 in.-1 (8.980 × 10-7 mm-1)

5φ c l 2
Fig. 7. Time-dependent deflection. δ =
48
5(2.281 × 10 −5 )(82 × 12) 2
(39.58 MPa) and if two No. 4 Grade (2) Camber increment between =
48
60 bonded crack control mild steel re- transfer and erection due to initial = 2.30 in. (58 mm)
inforcing bars are placed at the top of loads
the member in the end zone. Thus, it To account for concrete creep and Net camber immediately after deck
can be assumed for curvature and shrinkage, the age-adjusted modulus placement
camber calculations that the prestress of elasticity calculated in Example 3,
imposes a constant bending moment is used in this step to determine the in- = –2.47 + 2.30
over the full span length. cremental curvature. = –0.17 in. (–4 mm)
(a) Due to prestress force
Mψ bid
Pe φc = An accurate estimate of camber just
φc = EI before deck placement allows for a
EI
(2648 − 620.05 × 5.14)(0.65) correct prediction of concrete deck
–620.05 (5.14) =
= 4696 × 12, 235 thickness directly over the girder
4696 × 12, 235 (haunch thickness), that would accom-
= –6.124 × 10-6 in.-1 (–2.411 × 10-7 mm-1)
= –5.550 × 10-5 in.-1 (–2.185 × 10-6 mm-1) modate member camber and produce a
φc l 2 smooth roadway profile. An accurate
φc l 2 δ=
δ= 8 prediction of camber is also an indica-
8 –6.124 × 10 −6 (82 × 12) 2 tion of good correlation between the
–5.550 × 10 −5 (82 × 12)
2 = design calculations and actual behav-
= 8
ior. There is no code limit on camber
8 = – 0.74 in. (–19 mm) at erection. Some designers prefer to
= – 6.72 in. (–171 mm)
have a positive, i.e., upward, camber
(3) Deflection increment due to just after deck placement, for aesthetic
(b) Due to self-weight moment prestress loss between release and purposes.
Mg erection
φc =
EI ∆P = (173.49 – 184.21)3.366 (5) Time-dependent camber after
2648 = –36.08 kips (–160.51 kN)
= deck placement to final load
4696 × 12, 235
∆Pe The curvature change due to time-
= 4.608 × 10-5 in.-1 (1.814 × 10-6 mm-1) φc =
EI dependent effects can be calculated
5φ c l 2 36.08(5.14) based on a bending moment obtained
δ= = from Step 3 of the Example 2:
48 5422(12, 235)
5(4.608 × 10 −5 )(82 × 12) 2 = 2.797 × 10-6 in.-1 (1.101 × 10-7 mm-1) M
= ∆φ c =
48 Eb* I
φc l2
= 4.65 in. (118 mm) δ=
8 102.58
=
Net initial camber at transfer: 2.797 × 10 −6 (82 × 12) 2 3727 × 37, 053
=
= –6.72 + 4.65 8 = –7.429 × 10-7 in.-1
= –2.07 in. (–53 mm) = 0.34 in. (9 mm) (–2.925 × 10-8 mm-1)

10 PCI JOURNAL
φc l 2
δ=
8
–7.429 × 10 −7 (82 × 12) 2
=
8
= – 0.09 in. (–2 mm)

(6) Deflection due to prestress loss


after deck placement
∆Pe
φc =
EI
(160.38 − 173.49)(3.366)(5.14)
=–
5422(12, 235)
= 3.447 × 10-6 in.-1 (1.357 × 10-7 mm-1)
Fig. 8. Beam specimen under loading.
φ l2
δ= c
8
should be noted. They create end rota- stress-strain power formula given in
3.447 × 10 −6 (82 × 12) 2
= tional restraints which can reduce de- the PCI Bridge Design Manual:
8 flection by up to 80 percent.
= 0.42 in. (11 mm) f ps =

Net deflection before live load ap- Example 4: Strength Analysis of the  
27, 613
ε ps 887 + 
{ }
plication: Beam of Examples 1 to 3  
1/ 7.36
= –0.17 – 0.09 + 0.42  1 + (112.4ε ps ) 7.36 
In addition to limiting service load
= 0.16 in. (4 mm) (5)
compressive concrete stresses, the
ACI 318 Code and AASHTO Specifi- where fps is the stress in seven-wire,
(7) Deflection due to live load cations require that the strength of pre- 270 ksi (1860 MPa) low relaxation
Ml stressed concrete members due to ef- strands, corresponding to a total strain
φc = fective prestress plus full loads be εps, which is the strain in the concrete
EI
checked. For composite members, the at the same level as the steel row being
5295
= strength of the precast concrete mem- considered plus decompression strain
5422( 45, 252) ber due to all loads applied to it before (which is approximately taken as the
= 2.158 × 10-5 in.-1 (8.496 × 10-7 mm-1) it becomes composite with the deck, is ratio of effective prestress to modulus
not required to be checked. of elasticity).
5φ c l 2 In both ACI 318 and AASHTO,
δ= The results of the strain compatibil-
48 non-prestressed reinforced concrete is ity analysis produce a neutral axis
5(2.158 × 10 −5 )(82 × 12) 2 required to be designed for strength depth, c = 21.57 in. (548 mm), com-
= only. In this example, strength design pression block depth a = β 1 c =
48
will be performed to check the flexu- 0.65(21.57) = 14.02 in. (356 mm),
= 2.18 in. (55 mm)
ral capacity of the precast member strain at the centroid of the tension re-
The recommended live load deflec- alone and the capacity of the compos- inforcement = 0.006, and average
tion limit for bridge superstructures is: ite member. The load and resistance stress in the prestressing steel:
factors of the AASHTO LRFD Speci-
f ps =
l (82 × 12) fications are applied.
=
800 800 (a) Strength of the precast mem-  
27, 613
= 1.23 (31 mm) ber. Loads applied are the member ε ps 887 + 
 { } 
1/ 7.36
weight and the deck weight. The re-  1 + (112.4ε ps ) 7.36 
The calculated live load deflection, quired moment is:
using a simple span assumption, indi- 
cates that the member is too shallow Mu = 1.25(Mg + Md) = 0.006007887 +

or the span is too long. A simple span = 1.25(2648 + 1513) 
length of 69 ft (21 m) would corre- = 5201 kip-in. (587.59 kN-m)
27, 613 
spond to an acceptable live load de- 
flection. However, the importance of The steel stress at flexural strength {1 + (112.4 × 0.006007) }
7.36 1/ 7.36 

integral abutment diaphragms, which may be obtained using the strain com-
are standard practice in Nebraska, patibility analysis procedure and the = 170.0 ksi (1172 ksi)

November-December 2002 11
Mu = 1.25(Mg + Md) + 1.75(Ml)
= 1.25(2648 + 1513) + 1.75(5295)
= 12,467 kip-in. (1409 kN-m)

Using the strain compatibility


method, c = 8.07 in. (205 mm), a =
5.25 in. (133 mm), εps = 0.0126, fps =
254.50 ksi (1755 MPa), φ = 1.0, and
φMn = 20,881 kip-in. (2359 kN-m) >
Mu.
The strength analysis of the com-
posite section in this example indi-
Fig. 9. Cross section of bridge. cates that the deck slab provides the
compression resistance of the flexure
couple and that the top of the beam
Table 3. NU 900 precast beam and composite section properties. has no impact on the capacity as the
compression block depth is within the
Total depth Cross-sectional Moment of Distance between Weight of
h area A inertia I centroid and bottom section flange. The compressive stress distri-
Section (in.) (sq in.) (in.4) fibers yb (in.) (lb/ft) bution near member failure is consis-
Precast Beam
35.4 648.1 110,262 16.1 675.1
tent with experimental observations
NU 900 and is quite different from that ob-
Composite 43.4 1237.9 282,790 27.27 1544 served in the working stress analysis
2 4 4
Note: 1 in. = 25.4 mm; 1 sq in. = 645 mm ; 1 in. = 416,231 mm ; 1 lb/ft = 0.0146 kN/m. of Examples 1 and 2, in which the top
fibers of the beam appear to be the
most stressed fibers and the slab ap-
pears to be lightly stressed (see Fig.
5). Thus, working stress analysis
should only be used for serviceability
checks under unfactored loads and
strength analysis should be used to
check strength against overload, using
load magnification factors.

Discussion of Examples 1 to 4
The solution of Examples 1 to 4 has
demonstrated the following:
1. Working stress design using the
Fig. 10. Strand pattern at midspan and end of girder. customary linear elastic analysis as-
sumptions may grossly overestimate
compressive stresses at the extreme
For equilibrium, the tension force Bridge Design Manual: fibers of the precast concrete compo-
must equal the compression force (T = nent of a composite section.
C). 0.7 ≤ φ = 0.2 + 0.3(dext/c) ≤ 1.0 (6) 2. Time-dependent analysis for dif-
ferential creep and shrinkage between
fps Ap = 170.0(3.366) = 0.85f c′ba φ = 0.2 + 0.3(22/21.57) the precast concrete beam and the
= 572 kips (2544 kN) OK = 0.51 ≤ 0.7 cast-in-place composite topping is
Therefore, use φ = 0.7 available to designers using existing
The stress level in the prestressing software and spreadsheets, such as
steel is significantly lower than the φMn = φ fps Ap(dp – a/2) Excel spreadsheet calculations. The
yield strength of the strand of 0.9(270) = 0.7(170.00×3.366)(21 – 14.02/2) analysis shows that the top fiber stress
= 243 ksi (1675 MPa). Thus, this pre- = 5603 kip-in. (633 kN-m) > in the precast section is well below the
cast-only section should be considered Mu = 5201 kip-in. (587.59 kN-m) code limits, even though linear elastic
over-reinforced for this analysis. This analysis would show an unacceptable
is not a surprising outcome as the deck Thus, the section is adequate. design.
has not yet hardened at this loading 3. Spreadsheet time-dependent anal-
stage. (b) Strength of the composite ysis can be effectively used to calcu-
Using Mast’s resistance factor inter- member due to full dead plus live late member camber at various stages
polation function given in the PCI load: of construction and service life of the

12 PCI JOURNAL
member. This approach, rather than Table 4. Results of proposed versus conventional design of member in
artificial concrete stress limits, should Example 5.
be the procedure for deflection con- Conventional Proposed
trol. Number of strands and Design Controlling Design Controlling
4. Working stress analysis is only concrete strength parameter criterion parameter criterion
needed for satisfaction of the bottom Number of strands Bottom stress Bottom stress
36 36
fiber tensile stress limit. It may also be at midspan at service at service
Number of draped strands Compression limit Strength at
needed in the rare occasions of fatigue at ends
4
(0.6f ci′ )
4
transfer
analysis of the compression zone due Precast concrete strength Compression limit Strength at
7.06 6.0
to live loads. Even in these cases, a re- at transfer (ksi) (0.6f ci′ ) transfer
alistic time-dependent analysis, rather Precast concrete strength
7.11
Compression limit
6.57
Strength at
than the traditional linear elastic anal- at service (ksi) (0.45f c′) deck placement
Cast-in-place deck Strength under Strength under
ysis, should be used. 4.0 4.0
concrete strength (ksi) full load full load
Concrete capacity to resist the ap-
Note: 1 ksi = 6.895 MPa.
plied loads with adequate safety
against crushing is best handled
through strength analysis of both the
precast component of the member for A 50 ft (15.24 m) long, 15.75 in. men shimmed several times before it
loads introduced before the composite (400 mm) deep IT-400 was preten- finally collapsed.
topping is hardened, and again for the sioned with 18 0.5 in. (12.7 mm) diam- The maximum measured deflection
total section due to full loads. The lat- eter bottom strands and two 0.5 in. and load just before failure were 14.7
ter check is a current code require- (12.7 mm) diameter top strands, at the in. (373 mm) and 54 kips (240 kN).
ment. Rinker Materials, Inc. plant in Obviously, the large deflection shows
Fig. 6 shows a comparison between LaPlatte, Nebraska. The beam was a tremendous amount of ductility in
a typical stress diagram based on shipped to the Structures Laboratory of the beam and no signs of compres-
working stress design and strength de- the University of Nebraska, and placed sion-controlled brittle failure. The
sign along the beam depth of the non- on supports for a period of 52 days be- measured load was close to that pre-
composite and composite sections. A fore a 6 in. (150 mm) thick by 48 in. dicted by theory, 51.9 kips (231 kN).
strength analysis of a composite sec- (1220 mm) wide composite topping
tion indicates that the depth of the was placed. The composite beam was
PROPOSED FLEXURAL
equivalent rectangular compression tested 20 days after the slab was cast.
The maximum compressive concrete DESIGN CRITERIA
stress block is likely within the thick-
ness of the topping deck. Thus, the im- stress at transfer was 4.062 ksi (28 The following design modifications
pact of high compression in the top MPa) which was 0.74 of the specified are proposed for the flexural design of
fiber of the precast component on concrete strength of 5.5 ksi (38 MPa) prestressed concrete members:
member strength is virtually nonexis- and 0.60 of the actual strength of 6.82 • Eliminate the requirements for con-
tent. A check of the strength of the ksi (47 MPa). In both cases, the allow- crete compression limits at prestress
precast-only section for applicable able limit of 0.6f c′ was exceeded. The transfer, 0.6f ci′ , due to effective pre-
loads should be added as a code re- maximum compressive stress at the stress combined with dead loads,
quirement and the compression limits top fiber of the precast member at the 0.45f c′, and due to effective prestress
should be removed as proposed in this time of deck placement, using linear combined with full loads, 0.6f c′.
paper. elastic analysis was 0.66 of the speci- • Retain the requirement for concrete
fied concrete strength of 8 ksi (55 compression limit due to fatigue
MPa) and 0.65 of the actual concrete loading, 0.4f c′, for bridge members
EXPERIMENTAL PROGRAM strength of 8.14 ksi (56 MPa). and other relevant applications.
Several full-scale specimens have This was the primary criterion being • Retain service load checks for con-
been tested in this research program. tested and the calculated stress was crete tensile stresses at transfer and
One objective of the experiments was much higher than the code limit of at service. If stress exceeds the
to determine whether camber and de- 0.45f c′. Fig. 7 shows the predicted de- modulus of rupture of concrete,
flection can be accurately estimated flection-time diagram, and the mea- generally limited to 6 fc′ (in
when the code compression limits are sured values at key events. The agree- pounds per square inch), bonded re-
exceeded. A second objective is to ment between experimental and inforcement is to be added as per
verify that no strength or ductility dis- predicted values is excellent. current practice to control flexural
advantages result from waiving the The beam was then tested to failure. cracking.
code required compression limits. A Two hydraulic jacks with a 10 in. (250 • Retain all other serviceability crite-
full description of the experimental mm) stroke were not adequate to ac- ria such as deflection control, cam-
program is given in Reference 10. commodate the large deflection of the ber control, vibrations, and other pa-
Here, only the results of one inverted beam before it failed (see Fig. 8). The rameters. With increasing use of
tee specimen will be shown. load had to be removed and the speci- high strength concrete, such criteria

November-December 2002 13
become increasingly important. span bridge. The span lengths are 80 - section for AASHTO LRFD Service
• Add the requirement of strength de- 100 - 80 ft (24.4 - 30.5 - 24.4 m). The Level III loading combination:
sign for prestress transfer to ensure superstructure consists of five NU-900
member capacity against concrete I-beams spaced at 9 ft (2.74 m) on Pe Pe ( Mg + Md )
fb = + e −
crushing. center, as shown in Fig. 9. The beams A Sb Sb
• Retain the strength design of full are designed to act compositely with a ( Mb + Mws ) ( M LL+ I )
section due to total loads, and use 7.5 in. (191 mm) cast-in-place con- − − 0.8 ×
Sbc Sbc
this criterion as the primary design crete deck slab.
criterion. A 0.5 in. (12.7 mm) wearing surface
• Add the requirement that precast- is considered to be an integral part of 1210.86 1210.86 × 13.1
= +
only sections have adequate flexural the slab. Thus, the slab is considered 648.1 6, 849
strength due to loads applied before to be 7.5 in. (191 mm) thick for resis- (810.5 + 1110.3) × 12
the sections become composite with tance calculations. The design loads −
6, 849
cast-in-place topping. and resistance factors of AASHTO
The steps to be used in design may LRFD Bridge Design Specifications (52.0 + 95.3) × 12
− −
vary according to designer preference. will be used. 10, 370
The following steps may be used for Midspan moment due to weight of 1184.8 × 12
0.8 ×
standard precast concrete bridge and the precast member, Mg = 810.5 kip-ft 10, 370
building members: (1099 kN-m); due to deck weight, Md
Step 1: Select section shape and = 1110.3 kip-ft (1505 kN-m); due to = –0.448 ksi (–3.09 MPa)
size based on prior experience. barrier weight, Mb = 52.0 kip-ft (70.5
Step 2: Determine area of prestress- kN-m); due to future wearing surface, This stress is within the corresponding
ing steel required for acceptable ca- Mws = 95.3 kip-ft (129.2 kN-m); and tensile stress limit of –6 fc′ = –0.537
pacity of the member at final condi- due to live load-plus-impact, MLL+I = ksi (–3.70 MPa).
tions due to full loads. There are two 1184.8 kip-ft (1606.37 kN-m).
criteria for this step: (a) strength of Seven-wire, 0.6 in. (15.4 mm) diam- Required strength of composite sec-
composite section must be not less eter, Grade 270, low-relaxation tion:
than the factored total load moment, strands at 2 in. (50.8 mm) spacing are
and (b) concrete tensile stress due to used. The steel stress is assumed to be Mu = 1.25(Mg + Md + Mb) + 1.5(Mws)
unfactored service loads must be 202.5 ksi (1396 MPa), just before + 1.75 (MLL + I)
smaller than the code limit. In this transfer, 180 ksi (1241 MPa) just after = [1.25(810.5 + 1110.3 + 52.0)
step, the specified compressive transfer, and 155 ksi (1069 MPa) after + 1.5(95.3) + 1.75(1186.6)](12)
strength of the deck concrete can be allowance for all time-dependent = 56,226 kip-in. (6353 kN-m)
determined such that the compression losses.
block is confined within the deck slab. The following concrete strengths are Strength analysis indicates that the
Step 3: Determine the concrete initially assumed, based on current design strength, φMn = 77,589 kip-in.
strength of the precast component of standard practice in Nebraska: precast (8766 kN-m), which is significantly
the section, based on strength analysis concrete strength at prestress transfer larger than the required strength, Mu,
of the section for the loads applied be- = 6.5 ksi (45 MPa), and at service = 8 indicating that the strength at service
fore it becomes composite with the ksi (55 MPa); cast-in-place deck con- is not a critical design criterion. The
deck concrete. crete = 4 ksi (28 MPa). Table 3 shows depth of the equivalent rectangular
Step 4: Using strength design, de- the properties of the non-composite stress block, a = 5.62 in. (143 mm)
termine the concrete strength at trans- and composite cross sections. which is less than the 7.5 in. (191 mm)
fer, and debonding and/or draping re- slab thickness, indicating that a 4 ksi
quirements at the end section. Also, (28 MPa) deck concrete is adequate.
Step 1: Section shape and size
determine if top bonded reinforcement
at member end is required to control A limited superstructure depth is as-
sumed to be a constraint for this Step 3: Required strength of
cracking at transfer. precast section at time of
Step 5: Check remaining service- bridge. A relatively shallow, 900 mm
deck placement
ability criteria, such as deflection and (35.4 in.) NU I-girder size is selected.
fatigue. Mu = 1.25(Mg + Md)
The following example illustrates = 28,812 kip-in. (3255.3 kN-m)
Step 2: Required area of
the proposed design steps. reinforcement based on flexural The analysis for this loading case is
design at midspan done using the strain compatibility
Example 5: Flexural Design of a Initially, select 36 - 0.6 in. (15.24 method of the PCI Bridge Design
NU-900 I-Beam mm) diameter strands, arranged as Manual which incorporates Mast’s
It is required to design an interior shown in Fig. 10. Check the tensile variable strength reduction formula, as
beam of the center span of a three- stresses at midspan of the composite described in Example 4. A minimum

14 PCI JOURNAL
precast concrete strength of 6.57 ksi For comparison purposes, an analy- loads introduced just before the mem-
(45.23 MPa) is needed to satisfy the sis of the same example using the cur- ber becomes composite with the top-
strength requirements for this loading rent conventional criteria was under- ping.
case. The corresponding nominal taken. The results are given in Table 4. 7. Mast’s unified strength design
strength, Mn is 41,179 kip-in. (4653 method which provides an interpola-
kN-m). tion function for transition of the resis-
The analysis indicates that the sec- CONCLUSIONS tance factor from tension-controlled to
tion is compression-controlled and 1. The present restrictions on con- compression-controlled behavior is the
that the resistance factor should be crete compressive stress at service most appropriate for analysis of bridge
taken = 0.7. Thus, φMn = 0.7 × 41,179 limit state in the design of prestressed beams, especially when considering
= 28,825 kip-in. (3257 kN-m) > concrete flexural members neither di- the precast component before compos-
28,812 kip-in. (3255.3 kN-m) rectly address serviceability condi- ite action takes effect. The method has
tions, nor ensure adequate strength un- been adopted as the standard method
Step 4: Required strength of derfactored loads. in ACI 318-02. It is the recommended
precast section at transfer 2. In composite members, the cur- method in the PCI Bridge Design
rent allowable compressive stress of Manual. The AASHTO LRFD Speci-
Using the strength design method of
0.6f c′, due to effective prestress plus fications should be revised to allow
Reference 3 for design at time of pre- for use of this method in bridge de-
full loads, gives the false impression
stress transfer, it can be established sign.
that the highest compressed fibers, and
that the required concrete strength at
most likely to “crush” under factored 8. Strength design should be used
transfer satisfies the midspan section
load, are the extreme precast concrete for conditions at prestress transfer, and
conditions. For this case, the analysis
fibers. This is in conflict with the at lifting out of the casting bed, as rec-
is done for a section subjected to a
strength design method and experi- ommended by Noppakunwijai et al.3
factored moment = 0.85M g = 8267
mental evidence which indicates that 9. Service load limits should remain
kip-in. (934 MPa) combined with a
the highest stressed fibers are those in imposed on such serviceability crite-
factored pretensioning force = 1.15
the composite topping. ria as camber, deflection, crack con-
(36)(0.217)(202.5) = 1819.22 kips
(205.54 kN). The corresponding mini- 3. Both the ACI 318 Code and trol and fatigue as appropriate for the
mum concrete strength is 4.73 ksi AASHTO Specifications already re- structure being designed. For exam-
(31.61 MPa). quire that the flexural strength of a ple, if bridges and some building
The analysis is repeated at the lift- member be checked. This applies structures are not desired to be
ing point, which is assumed to be 5 ft equally to prestressed and non-pre- cracked due to effective prestress plus
(1.52 m) away from the member end, stressed conventionally reinforced full loads, the tensile stress due to
to determine if any strand draping is members. The compressive stress lim- these effects should be limited to
its of 0.6f c′, due to full loads, and 6 fc′ as currently required in both
required. For that section, the factored
0.45f c′ due to sustained (dead) loads, ACI and AASHTO.
moment due to self weight =
are imposed on prestressed concrete 10. Limiting the compressive stress
(1.15)(0.675)(5)2(12)/2 = 116 kip-in.
members only. Conventionally rein- due to half of the effective prestress
(13.11 kN-m). With the full preten-
forced members have not been sub- and half of the dead loads combined
sioning force used, i.e., no strands
jected to these limits since the strength with the full live load is a fatigue
draped, the required concrete strength
design approach was introduced in the check for bridge members. It should
is 9.8 ksi (67.57 MPa) which is obvi-
codes about 50 years ago, without any be retained. However, it is inconsistent
ously too high.
related reported deficiencies. to use a standard truck load. Rather,
Now, if four strands are draped, the
corresponding strength at release is 4. Imposing unnecessary compres- the “Fatigue Truck,” and other rele-
6.0 ksi (41 MPa). Because of the re- sive stress limits on prestressed con- vant provisions to the fatigue limit
quirement of draping, the 0.4l section crete members inhibits development state in the AASHTO Specifications
would need to be checked. For that and use of efficient sections such us should be used.
section, the required concrete strength inverted tees and U-shaped precast 11. Time-dependent analysis, using
is 4.8 ksi (33.09 MPa) which is below sections with composite cast-in-place the age-adjusted effective modulus
that required for the section at the lift- topping slabs. method, as described by Dilger, and in
ing point. 5. It is proposed that the compres- the PCI Bridge Design Manual only
sive stress limits of 0.6f c′ and 0.45f c′ require modest programming with a
imposed on concrete stresses due to standard Excel or similar spreadsheet.
Step 5: Check deflection full loads and due to dead loads, re- It should be used for all serviceability
and fatigue spectively, be deleted as design re- checks, including tensile stress and
An analysis for these design criteria quirements. camber control. Computer software,
indicates that fatigue stress and deflec- 6. It is proposed that composite such as CREEP III17 and CONSPLICE
tion are below the recommended members be checked for strength at all PT,18 can also be used to design for
AASHTO LRFD limits. critical loading stages, particularly service limit states.

November-December 2002 15
ACKNOWLEDGMENT
This research was funded by the Nebraska Department of not have been possible. Mr. Sam Fallaha, Assistant Bridge
Roads, Project No. SPR-PL-1 (037) P527. Additional support Engineer, NDOR, and Dr. Sherif Yehia, Research Assistant
was provided by the Center for Infrastructure Research of the Professor, UNL, and Mr. Chuanbing Sun, Ph.D. student,
University of Nebraska-Lincoln (UNL), Omaha, Nebraska. provided significant assistance throughout this project.
The authors especially thank Mr. Lyman Freemon, Bridge The authors also want to thank several PCI JOURNAL re-
Engineer, Nebraska Department of Roads (NDOR) without viewers for their thoughtful and constructive comments.
whose vision, leadership and encouragement much of the They include Henry Bollman, Leslie Martin, Robert Mast,
prestressed concrete bridge advancement in Nebraska would George Nasser and Stephen Seguirant.

REFERENCES
1. ACI Committee 318, “Building Code Requirements for Struc- NAL, V. 42, No. 1, January-February 1997, pp. 95-99.
tural Concrete (ACI 318-02),” American Concrete Institute, 10. NDOR, “Allowable Compression Limits in Prestressed Con-
Farmington Hills, MI, 2002. crete Members,” NDOR Report, Nebraska Department of
2. AASHTO, AASHTO LRFD Bridges Design Specifications, Roads, Lincoln, NE, 2002.
Second Edition, American Association of State Highway and 11. Kamel, M., “Innovative Precast Concrete Composite Bridge
Transportation Officials, Washington DC, 1998. System,” Ph.D. Dissertation, Department of Civil Engineering,
3. Noppakunwijai, P., Tadros, M. K., Zhongguo (John) M., and University of Nebraska-Lincoln, Lincoln, NE, 1996.
Mast, R.F., “Strength Design of Pretensioned Flexural Con- 12. Tadros, M. K., Ghali, A., and Dilger, W. H., “Time-Dependent
crete Members at Prestress Transfer,” PCI JOURNAL, V. 46, Analysis of Composite Frames,” ASCE Journal of Structural
No. 1, January-February 2001, pp.34-52. Engineering, V. 103, No. 4, 1977-B, pp. 871-884.
4. AASHTO, AASHTO Standard Specifications for Highway 13. Dilger, W. H., “Creep Analysis of Prestressed Concrete Struc-
Bridges, 16th Edition, American Association of State Highway tures Using Creep Transformed Section Properties,” PCI
and Transportation Officials, Washington, DC, 1996. JOURNAL, V. 27, No. 1, January-February 1982, pp. 89-117.
5. PCI’s First Specifications for Pretensioned Bonded Pre- 14. NCHRP, “Prestress Losses in Prestentioned High-Strength
stressed Concrete Products, First Edition, Prestressed Con- Concrete Bridge Girders,” National Cooperative Highway Re-
crete Institute, Lakeland, FL, 1954. search Program, Washington, DC, 2002.
6. Erickson, E. L., Criteria for Prestressed Concrete Bridges, 15. PCI Bridge Design Manual, First Edition, Precast/Prestressed
Bureau of Public Roads, U.S. Department of Commerce, U.S. Concrete Institute, Chicago, IL, 1997.
Government Printing Office, Washington, DC, 1954. 16. Tadros, M. K., Ghali, A., and Meyer, A. W., “Prestress Loss
7. ACI-ASCE Joint Committee 323, “Tentative Recommenda- and Deflection of Precast Concrete Members,” PCI JOUR-
tions for Prestressed Concrete,” Title No. 54-30, ACI Journal, NAL, V. 30, No. 1, January-February 1985, pp. 114-141.
V. 29, No. 7, January 1958, pp. 545-578. 17. Karim A., Ahmad M., and Tadros, M. K., “Computer Analysis
8. Huo, X., Savage, J. M., and Tadros, M. K., “Reexamination of of Spliced Girder Bridges,” ACI Structural Journal, V. 90, No.
Service Load Limit Compressive Stress in Prestressed Con- 1, January-February 1993, pp. 21-31.
crete Members,” ACI Structural Journal, V. 92, No. 2, March- 18. CONSPLICE PT, Design and Analysis of Spliced Pre-
April 1995, pp. 199-210. stressed/Precast Bridge Girders and CIP Slabs, “Computer
9. Huo, X., and Tadros, M. K., “Allowable Compressive Strength Software Version 1,” Developed by LEAP Software Inc.,
of Concrete at Prestress Release,” Open Forum, PCI JOUR- Tampa, FL, 2001.

16 PCI JOURNAL
APPENDIX A — NOTATION
a = depth of equivalent rectangular stress block Md = unfactored bending moment due to deck weight
A = cross-sectional area Ml = unfactored bending moment due to live load
Ab = area of precast concrete beam MLL+I = unfactored bending moment due to live load and
Ap = area of pretensioning steel impact
b = width of compression face of member MWS = unfactored bending moment due future wearing
c = distance from extreme compression fiber to neu- surface
tral axis Mn = nominal flexural resistance
C = compression force Mu = factored bending moment at a section
dext = depth of extreme steel layer from extreme com- P = prestress force
pression fiber ∆P = change of prestress force
dp = distance from extreme compression fiber to cen- Pe = effective prestress force after allowing for all
troid of pretensioning tendons losses
e = eccentricity of prestressing strands Sb = section modulus for extreme bottom fiber of non-
E = modulus of elasticity composite precast beam
Ec = modulus of elasticity of concrete Sbc = composite section modulus for extreme bottom
Eb = modulus of elasticity of beam concrete fiber of precast beam
Ed = modulus of elasticity of deck St = section modulus for extreme top fiber
Eb* = age-adjusted, effective modulus of elasticity of T = tension force
precast concrete beam for a gradually applied yb = distance between section centroid and extreme
load at time of deck placement bottom fiber
Ed* = age-adjusted, effective modulus of elasticity of β1 = ratio of depth of equivalent uniformly stressed
concrete deck for a gradually applied load at time compression zone assumed in strength limit state
of deck placement to depth of actual compression zone
f c′ = specified compressive strength of concrete at 28 εps = strain in a given layer of reinforcement
days εbsh = shrinkage strain of precast beam
f ci′ = compressive strength of concrete at time of initial εdsh = shrinkage strain of deck
prestress φ = strength reduction factor
fd = compressive stresses due to effective prestress φ = curvature
plus dead load φc = curvature at midspan
fl = compressive stresses due to live load ∆φ = change of curvature
fps = stress in a given layer of prestressed reinforce- χ = aging coefficient
ment whose strain is εps χb = aging coefficient for precast beam
ft = concrete stress at top fiber of precast beam χd = aging coefficient for concrete deck
h = overall depth of member ψ = creep coefficient
I = moment of inertia ψbid = creep coefficient of precast beam at time of deck
l = span length placement
M = moment ψbdf = creep coefficient of precast beam at final place-
Mb = unfactored bending moment due to barrier weight ment
Mg = unfactored bending moment due to beam self- ψddf = creep coefficient of cast-in-place slab at final
weight placement

November-December 2002 17
APPENDIX B —
PROPOSED CHANGES TO AASHTO LRFD SPECIFICATIONS
ITEM #1: Add the following paragraph at the begin- and transient loads and during shipping and handling.
ning of Article 5.5.3.1: This limit may be waived if strength design is performed.
Fatigue of concrete in compression shall be checked using 0.60ϕw f c′
the fatigue load factor specified in Table 3.4.1-1 in combi-
nation with truck loading configuration specified in Article Other Affected Articles:
3.6.1.4. Live load stresses shall be computed in accordance None
with Table 3.3.1-1 and Article 3.6.1.4. The total concrete
compressive stress due to live load plus one-half the sum of Background:
effective prestress and permanent loads shall not exceed The provisions for fatigue should be moved from their
0.4f c′ (ksi). current location of Article 5.9.4.2.1, Service Limit State, to
Fatigue of reinforcement need not be investigated for Article 5.5.3, Fatigue Limit State. In Article 5.5.3.1, the fa-
…….(Remainder of Article remains unchanged) tigue truck configuration of Article 3.6.1.4 rather than the
standard truck loading used for strength design calculations
ITEM#2: Revise the first paragraph of Article 5.5.4.1 should be used to determine the live load stresses.
as follows: Relative to Item # 4, the stress limit for segmentally con-
The strength limit state issues to be considered shall be structed bridges and “other than segmentally constructed
those of strength and stability. For pretensioned concrete bridges” is the same and the two bullets should be combined
members, this method shall be considered as the primary de- into one bullet. The provisions for fatigue limit should be
sign method for satisfaction of member capacity in com- moved from their current location of Article 5.9.4.2.1, Ser-
pression at various loading stages, including prestress trans- vice Limit State, to Article 5.5.3, Fatigue Limit State.
fer, lifting, erection, deck placement, superimposed dead Working stress design should be replaced with the
loads and live loads. strength design method, consistently with the design of non-
prestressed concrete members. Study in 1993, Reference
ITEM #3: Add the following paragraph at the end of X1, showed that non-prestressed concrete members that are
Article 5.9.4.2.1: heavily reinforced could experience extreme compressive
Compressive stress limits specified in Table 5.9.4.2.1-1 stress significantly greater than 0.6f c′ if the unfactored load
may be waived for flexural member if the strength limit and linear stress-strain theory were employed, with no re-
state provisions according to Article 5.7.3.2. are satisfied at ported negative effects. Additionally, a study in 1997, Ref-
prestress transfer, at time of cast-in-place deck placement, erence X2, showed that the stress-strain relationship for con-
and at final loading. Further, the deflection and camber at crete deviates considerably from a linear relationship as the
various loading stages must be checked, using conventional stress in concrete exceeds about 0.5f c′. Therefore the appar-
analysis methods, for satisfaction of various design and con- ent compressive stress using the inaccurate linear analysis is
struction limitations. exaggerated. References X3 and X4 shows that strength de-
sign is adequate in satisfying the concrete capacity require-
ITEM #4: In Table 5.9.4.2.1-1, revise the 1st, 2nd, 3rd ments. It shall be noted that members made composite with
and 4th bullets, and “Stress Limit” as follows: multistage concrete placement shall be checked using
• In other than segmentally constructed due to the sum of strength design at each stage of concrete placement and the
effective prestress and permanent loads factored loads that exist at each of these stages.
• In segmentally constructed bridges dDue to the sum of ef-
fective prestress and permanent loads. This limit may be Anticipated Effect on Bridges:
waived if strength design is performed. • Consistent design for fatigue for all structural materials
0.45f c′ and systems.
• In other than segmentally constructed bridges due to live • Consistent design for conventionally reinforced and pre-
load and one-half the sum of effective prestress and per- stressed concrete flexural members.
manent loads. • Improved account for the influence of concrete strength
• Due to the sum of effective prestress, permanent loads, on design.

REFERENCES
X1. Huo, X., Savage, J. M., and Tadros, M. K., “Reexamination of X3. Noppakunwijai, P., Al-Omaishi, N., Tadros, M. K., and
Service Load Limit Compressive Stress in Prestressed Con- Krause, G. L., “Elimination of Prestressed Concrete Compres-
crete Members,” ACI Structural Journal, V. 92, No. 2, March- sion Limits at Service Load,” PCI JOURNAL, V. 47, No. 6,
April 1995, pp.199-210. November-December 2002, pp. 00-00.
X2. Huo, X., and Tadros, M. K., “Allowable Compressive X4. Noppakunwijai, P., “Allowable Compression Limits in Pre-
Strength of Concrete at Prestress Release,” PCI JOURNAL, stressed Concrete Members,” Ph.D. Dissertation, University of
Open Forum, V. 42, No. 1, January-February 1997, pp. 95-99. Nebraska-Lincoln, Lincoln, NE, 2001.

18 PCI JOURNAL
APPENDIX C —
PROPOSED CHANGES IN ACI CODE
Change Submittal: CG XYZ 1. Redistribution of stress, due to creep between precast
Subject: Modifications of ACI 318 Code wording that and cast-in-place components of the member, cause gradual
permit the strength design theory to be the primary method reduction of compression in the top fiber of the precast com-
of design of flexural member. ponent and a corresponding increase in compression in the
cast-in-place component. Therefore, calculated high stress at
Current Sections Affected: 18.4.3, 18.4.4, R18.4.3, the time of topping placement is only temporary and gradu-
R18.4.4 ally decreases upon hardening of topping concrete.
2. Strength analysis of the composite section often indi-
Reason: Permit the strength design theory to be the pri- cates that the equivalent rectangular compression stress
mary method of design of flexural members at various load- block is limited within the thickness of the topping and the
ing stages during construction and at service loads after ap- impact of the high compression in the top fibers of the pre-
plication of full external loads. cast component on member strength is virtually nonexistent.
The 0.6f c′ limit due to full loads plus effective prestress is
Proposed Code Change: only imposed on prestressed members. Study in 1993, Ref-
Add a new Section 18.4.3 erence 18.X1, showed that non-prestressed concrete mem-
18.4.3 — Compressive stress limits specified in Section bers that are heavily reinforced could experience extreme
18.4.2 (a) and (b) may be waived for flexural members if the compressive stress significantly greater than 0.6f c′ if the un-
strength limit state provisions according to Section 18.7 are factored load and linear stress-strain theory were employed,
satisfied at time of cast-in-place deck placement, and at final with no reported negative effects. Additionally, a study in
loading. Further, the deflection and camber at various load- 1997, Reference 18.X2, showed that the stress-strain rela-
ing stages must be checked, using conventional analysis tionship for concrete deviates considerably from a linear re-
methods, for satisfaction of various design and construction lationship as the stress in concrete exceeds about 0.5f c′.
limitations. Therefore, the apparent compressive stress using the inaccu-
rate linear analysis is exaggerated. References 18.X3 and
Renumber Section 18.4.3 to Section 18.4.4 18.X4 show that strength design is adequate to satisfy the
18.4.34 concrete capacity requirements. It shall be noted that mem-
Proposed Commentary Change: bers made composite with multistage concrete placement
Add Commentary R18.4.3 to read: shall be checked using strength design at each stage of con-
R18.4.3 –If creep deformation due to dead load is a con- crete placement and the factored loads that exist at each of
cern, it could be evaluated and a satisfactory limit on dead these stages.
load deflection imposed. For precast members made com-
posite with cast in place topping, the 0.45f c′ limit is some- Renumber Commentary Section 18.4.3 to Commentary
times reached at the top fiber of the precast component of Section 18.4.4
the section immediately after the topping concrete is placed. R18.4.34
However, the following two points provide justification for
removal of this requirement: Add new References 18.X1, 18.X2, 18.X3 and 18.X4:

REFERENCES
18.X1. Huo, X., Savage, J. M. and Tadros, M. K., “ Reexamina- 18.X3. Noppakunwijai, P., Al-Omaishi, N., Tadros, M. K., and
tion of Service Load Limit Compressive Stress in Pre- Krause, G. L., “Elimination of Prestressed Concrete Com-
stressed Concrete Members,” ACI Structural Journal, V. pression Limits at Service Load,” PCI JOURNAL, V. 47,
92, No. 2, March-April 1995, pp. 199-210. No. 6, November-December 2002, pp. 00-00.
18.X2. Huo, X., and Tadros, M. K., “Allowable Compressive 18.X4. Noppakunwijai, P., “Allowable Compression Limits in
Strength of Concrete at Prestress Release,” PCI Journal, Prestressed Concrete Members,” Ph.D. Dissertation, Uni-
Open Forum Section, V. 42, No. 1, January-February 1997, versity of Nebraska-Lincoln, Lincoln, NE, 2001.
pp. 95-99.

November-December 2002 19

You might also like