Professional Documents
Culture Documents
Abstract—Compared with conventional synchronous is proposed [7]. Variable droop control method is studied [8].
generators, wind turbines are connected to power grid through Aiming at the problem of frequency disturbance caused by
converters. Active power response and grid frequency are rotor inertia control, improved strategies of additional power
decoupled. Wind turbines do not have the ability of active is proposed [9]. VSG technology applied to wind turbines
frequency support. With the rapid development of new energy grid-connected control is mainly in the aspects of normal
power in China, wind power penetration continues to increase. operation state and control strategies under grid fault [10-11].
New challenges of gird frequency stability occur. Virtual Field test and analysis is not carried out.
synchronous generator (VSG) Demonstration Project is built VSG Demonstration Project is built in Zhangbei Wind,
in Zhangbei Wind, Photovoltaic and Energy Storage Station by
Photovoltaic and Energy Storage Station by State Grid in
State Grid. Through the VSG technology reform of wind
turbines, active frequency regulation ability is possessed.
2016. WPVSG engineering reform has completed. Due to
Reserve capacity and rotor inertia control technical routes of the lack of measured data, wind turbines frequency
wind power virtual synchronous generator (WPVSG) are regulation characteristics is not clear.
introduced. A field test method is presented. The method is Aimed at WPVSG of Demonstration Project, reserve
based on analog frequency disturbance applied to the capacity and rotor inertia control are presented in this paper.
secondary side. Field test is conducted. The results show that According to control structure of WPVSG, a field test
WPVSG has ability of active frequency regulation support. method based on analog frequency disturbance applied to the
Two kinds of control methods have their own characteristics. secondary side of WPVSG is presented. Various test
conditions are designed. Field test is conducted and test data
Keywords-wind power virtual synchronous generator; is analyzed.
frequency regulation; field test
II. WPVSG CONTROL METHOD
I. INTRODUCTION WPVSG of Demonstration Project control structure is
China's new energy power generation is developing shown in figure 1.
rapidly. China's wind power installed capacity has reached
168.7GW in 2016. New installed capacity is 23.4GW. The
total installed capacity is expected to reach 210GW by 2020 &RQYHUWHU
[1]. A high percentage of new energy access has become a
major feature of future power systems. Compared with
conventional synchronous generators, wind turbines are
connected to the grid via converters. The output of active
Kf*PN/fN
power is completely decoupled from grid frequency [2].
When system frequency changes as a result of DC blocking
or load sudden change [3], wind turbines do not have the d/dt TJ*PN/fN
initiative to respond. The rotational inertia of wind turbines
is zero. Therefore, power grid frequency regulation Figure 1. WPVSG control structure.
capability is weaken after large-scale wind power access.
Risk to frequency stability of power system increases [4-5]. As shown in figure 1, fN is rated frequency; fpll is the
Domestic and foreign scholars and research institutes frequency collected by converter PLL; Δf is the amount of
have carried out a great deal of research on wind power frequency change; df/dt is the rate of frequency change; TJ
frequency regulation technology [6]. A strategy of wind and Kf are inertia time constant and active frequency
power frequency regulation based on maximum torque limit
Active power/pu
reserve capacity control, pitch angel is always greater than 0°. 0.3 A
E 7m/s
Wind turbines operate on deloading state [8]. When WPVSG
detects system frequency change, reserve capacity can be
released (or stored) by adjusting pitch angle. Thus, active 0.2
power support are provided. Reserve capacity control D
operation curves are shown in figure 2 which wind speed is 0.1
between 7m/s~8.5m/s. 0.4 0.6 0.8 1 1.2
1000 Generator speed/pu
8m/s
Figure 3. Rotor inertia control operation curves.
Active power/kW
800
7m/s
Rotor inertia control in constant speed interval is similar
to MPPT interval. The difference is that the generator speed
600 10%PN at point A is rated speed.
β=0
400
III. FIELD TEST METHOD
β>0 Normal operation curves Based on the control structure of Demonstration Project
Deloading curves WPVSG, a field test method of unit frequency regulation
200
0.9 1 1.1 1.2 1.3 performance is presented in this paper. Power grid frequency
Generator speed/pu disturbance is simulated by applying a disturbance signal on
Figure 2. Reserve capacity control operation curves. the secondary side of wind turbines. Compared with the
method of applying frequency disturbance directly on grid
Wind turbines reserve 10%PN capacity according to wind side, this method has the advantages of low cost, high testing
conditions to respond to frequency change in figure 2. Pitch efficiency and safety. The method test principle diagram is
angels are 1.8° and 1.4° respectively under 7m/s and 8m/s. shown in figure 4.
690V/35kV
B. Rotor Inertia Control Grid
WPVSG does not need reserve capacity under rotor Gearbox
DFIG
inertia control. When system frequency changes, generator Convertors Voltage and current
speed decreases (or increases) to releasing (or storing)
rotational inertia to provide active power support [9]. When Data Acquisition
wind turbines operate at maximum power point tracker AC voltage signals
(MPPT) interval, rotor inertia control operation curves are Convertor control
shown in figure 3. Pitch angel control
Signal Generator
As shown in figure 3, wind turbines mechanical power Master control
Wind speed etc.
varying with generator speed is blue curve in 7m/s. The red
curve is the active power curve corresponding to each
Figure 4. Frequency regulation test principle diagram.
generator speed during normal operation of wind turbines.
When system frequency is rated and wind speed is 7m/s,
As shown in figure 4, the signal generator outputs 3 AC
wind turbines run at point A. Electromagnetic power of wind
voltage signals to wind turbines converters. Power grid
turbines rises from point A to B when frequency drops.
frequency disturbance is simulated by adjusting AC voltage
Electromagnetic power maintains B→C under frequency
frequency. Analog frequency signal is collected by
regulation process. Mechanical power changes from A to E.
converters and feeds back to master control system. Master
As the electromagnetic power is always greater than
control system adjusts the active power of wind turbines to
mechanical power, generator speed is declining. Wind
actively participate in frequency regulation according
turbines provide active power support by releasing rotational
frequency changes. Test data is collected and recorded by
inertia. When generator speed drops to the lower limit and
194
Authorized licensed use limited to: UNIVERSIDAD POLITECNICA SALESIANA. Downloaded on May 02,2023 at 02:15:38 UTC from IEEE Xplore. Restrictions apply.
data acquisition equipment, including wind speed, pitch
angel, generator speed, active power, electromagnetic torque,
three-phase voltage and current of unit, AC voltage signals
and so on.
According to the control method of WPVSG, wind
turbines operation intervals and frequency disturbance, 16
kinds of test conditions are set as shown in Table 1.
TABLE I. TEST CONDITIONS
Reserve capacity
Rotor inertia control
control
Test conditions Frequency Frequency Frequency Frequency
step slope step slope
disturbance disturbance disturbance disturbance
MPPT interval Condition1 Condition5 Condition9 Condition13
Constant speed Figure 5. Reserve capacity control measured curves.
Condition2 Condition6 Condition10 Condition14
interval
Rated power interval Condition3 Condition7 Condition11 Condition15 TABLE II. FREQUENCY REGULATION PERFORMANCE INDEXES UNDER
RESERVE CAPACITY CONTROL
Limited power
Condition4 Condition8 Condition12 Condition16
interval Active power Active power Active power Response
initial value (kW) increment (kW) error (kW) time (s)
IV. RESULTS AND ANALYSIS 521 (26.1%PN) 209 (10.5%PN) 9 (0.5%PN) 0.6
195
Authorized licensed use limited to: UNIVERSIDAD POLITECNICA SALESIANA. Downloaded on May 02,2023 at 02:15:38 UTC from IEEE Xplore. Restrictions apply.
process after generator speed dropping to lower limit. Wind V. CONCLUSIONS
turbines turn to normal control and gradually resume The main conclusion or summary from the present study
generator speed and active power. Active power support time is as follows:
is 20.7s and recovery time is 29.0s in the process. 1) A field test method based on analog frequency
disturbance applied to the secondary side of WPVSG is
presented. The method has the advantages of low cost, high
testing efficiency and safety.
2) WPVSG of Demonstration Project has frequency
regulation capability, which can take the initiative to
participate in power grid frequency regulation process.
3) Continuous active power support are provided by
reserve capacity control, which results in additional loss of
power generation. Short-term support is supplied by rotor
inertial control, but there is a risk of second drop in system
frequency due to generator speed recovery.
ACKNOWLEDGMENT
This paper is supported by the National Science &
Figure 6. Rotor inertia control measured curves. Technology Pillar Program of China (No. 2015BAA06B03)
and the National Power Grid Corp Science and Technology
TABLE IV. FREQUENCY REGULATION PERFORMANCE INDEXES Project “Key Operation and Maintenance Technology
UNDER ROTOR INERTIA CONTROL Research on Major Science and Technology Demonstration
Active power Active power Active power Response Project of Zhangjiakou Renewable Energy Demonstration
initial value (kW) increment (kW) error (kW) time (s) Area”.
768 (38.4%PN) 206 (10.3%PN) 6 (0.3%PN) 0.5
REFERENCES
[1] Sawyer S, Dyrholm M, et al. "Global wind report: annual market
The advantage of rotor inertia control is economic update 2016." (2017)
operation due to no reserve capacity by theoretical analysis [2] Ghosh S, Kamalasadan S, Senroy N, et al. "Doubly fed induction
and engineering test. The disadvantage is unable to provide generator (DFIG)-based wind farm control framework for primary
active power support for a long time. When generator speed frequency and inertial response application." IEEE Transactions on
is restored, the instantaneous drop of electromagnetic power Power Systems 31.3(2016):1861-1871.
is larger. As shown in figure 6, electromagnetic power drops [3] Zhaowei L I, Xuelian W U, Zhuang K, et al. "Analysis and reflection
rapidly from 974kW (48.7%PN) to 316kW (15.8%PN). A on frequency characteristics of East China Grid after bipolar locking
of “9•19” Jinping-Sunan DC transmission line." Automation of
large power shortage results in system frequency "second Electric Power Systems 41.7(2017):149-155.
drop" phenomenon. The above frequency regulation process [4] Lee J, Jang G, Muljadi E, et al. "Stable short-term frequency support
is simulated in MATLAB/Simulink model. New energy using adaptive gains for a DFIG-based wind power plant." IEEE
accounts for 20% in simulation system. 5% of installed Transactions on Energy Conversion 31.3(2016):1068-1079.
capacity power shortage happens in 20s. Wind power [5] Arani M F M, Mohamed A R I. "Analysis and mitigation of
absence of frequency regulation and active frequency undesirable impacts of implementing frequency support controllers in
regulation simulation results are shown in figure 7. wind power generation." IEEE Transactions on Energy Conversion
50 31.1(2016):174-186.
[6] Dreidy M, Mokhlis H, Mekhilef S. "Inertia response and frequency
49.8 control techniques for renewable energy sources: A review."
Renewable and Sustainable Energy Reviews 69 (2017): 144-155.
49.6
f/Hz
196
Authorized licensed use limited to: UNIVERSIDAD POLITECNICA SALESIANA. Downloaded on May 02,2023 at 02:15:38 UTC from IEEE Xplore. Restrictions apply.