Project Title Nomor Dokumen

Heater

Validation
Author’s Organization -
PT SK Metalindo Expired Date
PT. SK METALINDO -

METODE KERJA
INSTALATION NEW HEATER

Lembar Persetujuan
Nama Pemilik Tanggal Tanda Tangan

Revision Status

Tanda
Tanggal
Rev Oleh Check Setujui Tujuan Masalah Tangan
dikeluarkan
Pemilik
A Issue for Review
0 Issue for Approval
1 Issue for Approval
Lifting Operation Calculation Crane 250 Ton For Erection Of New Heater

A. EQUIPMENT DATA (Tailing Crane)


Type/Model
Crane Manufacture Mobile Crane 250T
Boom Length 50 M
Max Radius of Pick Up 28 M
Crane Capacity (SWL) 19 Ton
Crane Condition (CC) 80%
Load boom angle (degree) 50 – 7 0 Degree
Lifting Capacity (Load chart)(CC X LC) 80% X (19 Ton) 15.2 Ton

Lifting Object Heater


Max material weight 10 Ton
Lifting Gear Weight 0.3 Ton
Total Weight 10.3 Ton

LOAD CALCULATION

Safety Facrtor = Lifting Capacity X Crane Condition


Total Load X Dynamic Factor
= 19 Ton X 80%
10.3 Ton X 1.0
= 15.2
10.3
= 1.47
Crane Capacity Radius 28 Mtr (load chart) & 50 mtr boom 19 Ton
Safety Factor 1.47%
Share Load
Total Weight Weight Capacity x Safety Factor 15.14 Ton
= 10.3 T x 1.47
Result Total Weight < Lifting Capacity SAFE
15.14 Ton < 19 Ton

Crane Capacity Usage Total Weight/SWL X 100 54.2 %


(10.3 T/19 T) X 100

Lifting Gear yang digunakan


Webbing Sling Cap 5 Ton
Shackle ¾” x 4 EA

Sukarto Taufik H Pandapotan Michael


SKM SKM AUX IBR SHE IBR
Load Chart Crane 250T
Load Chart crane 250 T