Upgradation
Project
RAMS & Lifting Plan for Date: 2-10-2022
Equipment’s Installation
PREPARED BY: ENGR SABIR SHAH Issued For Approval Rev: R00
Employee Representative: SAJJAD Document Reference:
FAIZ SE/RAMS/Canning-03
Document Number:
Revision: R00
Status: ISSUED FOR APPROVAL
Revision Date: 02-Oct-2022
1 of 9
Canning Line
Upgradation
Project
RAMS & Lifting Plan for Date: 2-10-2022
Equipment’s Installation
PREPARED BY: ENGR SABIR SHAH Issued For Approval Rev: R00
Employee Representative: SAJJAD Document Reference:
FAIZ SE/RAMS/Canning-03
Installation of Chiller:
Fix the crane close to the chiller foundation and park the trailer inside main entrance
close to the crane.
Mark and make holes for spring isolators in concrete foundation and use anchor for
nut bolting.
Install the spring isolators on the chiller foundation as per approved construction
drawing.
Tight the spring isolator with nut bolts so that no movement will take place at time
of chiller installation.
Unload the chiller from trailer by 100 Ton of crane and install on the allocated
foundation on the installed spring isolators and tight it by nut bolts with the spring
isolators.
The weights of different equipment’s are as under.
Fix the crane in front of link corridor at a distance of 16 meters from the wall of
corridor.
Bleed Fan with Inertia filter will also be lift and installed with the FAHU
Foundation.
Place the rubber pads as per approved drawing of FAHU on foundation on link
corridor.
2 of 9
Canning Line
Upgradation
Project
RAMS & Lifting Plan for Date: 2-10-2022
Equipment’s Installation
PREPARED BY: ENGR SABIR SHAH Issued For Approval Rev: R00
Employee Representative: SAJJAD Document Reference:
FAIZ SE/RAMS/Canning-03
Unload & Lift the FAHU on link corridor by the allocated foundation for the
Fresh Air Handling Unit.
The distance (radius) between FAHU foundation and crane where fixed is 21
meter.
Dry cooler & Dry Adiabatic cooler will be installed on link corridor and radius is
21 meter where it is installed.
Glycol booster pump will be installed on link corridor and radius of crane is 21
meter.
Exhaust Fan will be lifted on the canning line roof and installed on roof top.
Radius of crane will be 10 meter during installation of exhaust fan.
Weight of Exhaust fan is 0.15 Ton.
3 of 9
Canning Line
Upgradation
Project
RAMS & Lifting Plan for Date: 2-10-2022
Equipment’s Installation
PREPARED BY: ENGR SABIR SHAH Issued For Approval Rev: R00
Employee Representative: SAJJAD Document Reference:
FAIZ SE/RAMS/Canning-03
4 of 9
Canning Line
Upgradation
Project
RAMS & Lifting Plan for Date: 2-10-2022
Equipment’s Installation
PREPARED BY: ENGR SABIR SHAH Issued For Approval Rev: R00
Employee Representative: SAJJAD Document Reference:
FAIZ SE/RAMS/Canning-03
5 of 9
Canning Line
Upgradation
Project
RAMS & Lifting Plan for Date: 2-10-2022
Equipment’s Installation
PREPARED BY: ENGR SABIR SHAH Issued For Approval Rev: R00
Employee Representative: SAJJAD Document Reference:
FAIZ SE/RAMS/Canning-03
6 of 9
Canning Line
Upgradation
Project
RAMS & Lifting Plan for Date: 2-10-2022
Equipment’s Installation
PREPARED BY: ENGR SABIR SHAH Issued For Approval Rev: R00
Employee Representative: SAJJAD Document Reference:
FAIZ SE/RAMS/Canning-03
Risk Assessment
Step 1: Hazard-Activity/Workplace/Equipment/Event
3 4 12
Overall assessment
7 of 9
Canning Line
Upgradation
Project
RAMS & Lifting Plan for Date: 2-10-2022
Equipment’s Installation
PREPARED BY: ENGR SABIR SHAH Issued For Approval Rev: R00
Employee Representative: SAJJAD Document Reference:
FAIZ SE/RAMS/Canning-03
Step 5: Further recommended control measures (Medium to very high risks must be
reduced to lowest level so far as is reasonably practicable).
Safety Precaution for Lifting Operation
Cranes must have valid party inspection and certification.
Permit to Work shall be obtained prior to start the work.
Crane operators and riggers must have a valid 3rd party certification
Only trained and currently 3rd party approved certified riggers must assist and
give signal to the operator.
Operator must follow the manufacturer’s safe operating procedures & best
practices.
No lifting work in adverse weather condition (wind @ 32 KPH wind /20Mph,
sandstorm, foggy, immediately after rainfall)
During blind lift, two riggers must assist the operator and only one rigger must
give signal to the operator at a time.
Crane lifting equipment and tackles must be inspected by the rigger prior to use
Use adequate length and number of taglines.
Proper set-up of cranes / outrigger fully extended (watch out for out rigger pad
settlement
Crane outrigger must be position at least 1 meter away from the edge of
excavation
Exclusion zone / working radius must be barricaded and warning signs to be in
place before/during lifting activities.
Correct size of outrigger crane mats to be used.
Hitching and slinging must be done by certified rigger.
Rigger to sound whistle and crane operator the horn to warn people to clear the
lifting area.
Only authorized licensed & certified personnel to be deployed as operators.
Reversing / maneuvering equipment shall be assisted by banks man/flagman.
Basic safety warning devices (i.e. reverse alarm & beacon light) shall be in good
working condition prior to each operation.
8 of 9
Canning Line
Upgradation
Project
RAMS & Lifting Plan for Date: 2-10-2022
Equipment’s Installation
PREPARED BY: ENGR SABIR SHAH Issued For Approval Rev: R00
Employee Representative: SAJJAD Document Reference:
FAIZ SE/RAMS/Canning-03
There are no obstruction such as building or overhead lines in the vicinity of the
lift.
Use of Proper PPE.
Priority Status:
High: Risk being addressed is serious; action / control required urgently/ immediately
Medium: Potentially serious, remedial action should be taken within agreed timetable
Low: Minor risk Implement if /when resources allow
Step:7 Forecast Residual Risk rating - after additional controls applied
Likelihood 2 × Severity 3 = 6
Notes; Including names and contact number of risk assessment participant
Name: Sajjad Faiz (Safety Officer), Mob# 059-1305167
Name: Muhammad Sabir Shah (Project Engineer), Mob# 054-5736923
Name: Umer Farooq (Supervisor), Mob# 050-0179465
9 of 9