Professional Documents
Culture Documents
Please note that this is not intended to show or to include every type of hazard. Each of the
Almarai premises is different and the individual circumstances at each location must be
taken into account.
Fall of person and materials from height during scaffold during erection and dismantling and pipelines
installation work
Damage to existing facilities (cable tray, pipes, ducts etc.) during work
Overreaching from work platform during work
Uneven surface
Outriggers placed on ground without pad
Hit the Pre cast wall and damage of structure
Crane movement without escort
Access block due to parking of crane
Hit by material delivery trailer
Crane parked without barricade
Lifting Of Pipes, Material and Curbstone, Weight = 45 to 65 KG (CPP1 Roof Top Near New Canning Line
Building) By using Crane (Work Procedure)
Fall of material, crane collapse, and tip or roll over, uneven ground, out riggers not fully extended etc.
Placement and stacking of material near roof edges
Material /load may hit (struck) the adjacent structure (precast wall)
Mechanical failure of equipment during lifting
Workers passing/standing under the suspended load
Incompetent operator and Rigger
Adverse weather condition such as high wind speed, sand storm
Substandard of damaged rigging tools being used for lifting and transfer of material
Working without lifting plan
Activity starts without isolating the area to prevent un authorized access
Installation Of Curbstone for Utility Pipe Support (Size=500 X 400 X 150 X 80 MM) (Approximately
Weight = 45 to 65 KG) & Installation of Pipe Support and Utilities Lines (Steam,4inch) (Condensate,1-1/2)
(Glycol Supply&Return,3inch) (First and Reuse Water,2inch&3inch) (Hot Water,2inch) (Compressed
Air,3inch) & Insulation cladding work
Tapping for New Utilities Lines (Steam,4inch) (Condensate,1-1/2) (Glycol Supply&Return,3inch) (First and
Reuse Water,3inch&3inch) (Hot Water,2-1/2inch) (Compressed Air,3inch) From Existing Main Lines
High noise
Excessive Temperature
Damage to the existing nearby facilities such AHU, electrical panels and other facilities during work.
Line not properly isolated and drained /de pressurized
Sharp edges of cladding
Improper access/egress and work place
Health hazard (skin irritation) while removing insulation
Congested workplace
Presence of residuals inside tapping lines
Hot and cold surfaces
Accidental start-up of existing lines being taped
Manual Handling:
Repeated, sustained or high force during handling of material
Repetitive movements of task
Exposure to sustained vibration
Loads that are unstable, unbalanced or hard to hold
Heavy load
Other Hazards
Location / Circumstances where hazard could arise
Step 3: Possible consequences - What harm might occur where hazard could arise
Serious injury like death due to falling from height onto existing facilities or ground during scaffolding
erection, dismantling and lines during work.
Fire and explosion
Minor injuries, cut injuries during removing of cladding from existing line for tapping work and
installation of new line cladding work
Damage of property such as existing utilities lines, AHU, electrical panels
High radiation exposure can result in the following symptoms: Hair/skin loss, Vomiting
Multiple injuries
Step 4: Existing control measures in place
Overall assessment
LOW (1-8) MEDIUM (9-12) HIGH (15+) ✔
Step 6: Further recommended control measures (Medium to very high risks must be reduced to lowest level so far
as is reasonably practicable).
Description
Edge protection (parapet very low in height):
Will ensure all work area near the edge are protected by barricade with MS pipe
All employee briefed daily not to go near to the edge area.
All work will commence on completion of edge protection of edge protection and inspection of contractor
safety staff.
H
No materials stored near to edge.
Overreaching from working platform is strictly prohibited.
While working at height, always remain within the confine of the platform.
Never sit, stand or climb on the guard rail
Erection And Dismantling of Scaffolding for Utilities line installation and Tapping work H
Scaffolding components shall be inspected by competent scaffolding personnel prior to scaffold erection to
ensure their quality
Temporary covering of hot and cold line must be made before start the work.
Make sure existing facilities should not damage during erection and distancing work
By provide the safe work techqines to carry out work through TBT
Scaffold of different types such as cup coupler and tube coupler shall not be intermixed unless they are
compatible.
Scaffold components shall be properly stored to prevent damage.
Scaffold tubing shall be 48.3 mm (1.9 in) nominal outside diameter and other material must be checked by
scaffold inspector before start the erection.
Scaffolding should be built by certified scaffold erector.
Scaffold erector shall continuously wear a full-body harness with shock absorbing double lanyard while
erecting, altering or dismantling a scaffold.
Scaffold erector shall properly anchor their lanyard whenever they are not protected by a guardrail system and
could fall more than 1.8 m (6 ft).
Must be built on firm, level ground, base plate must be used and standards must be upright position
Scaffold must be equipped with a guardrail system including top rails, mid rails, and toe boards
Guardrail systems (consisting of top rails, mid rails and support uprights) shall be installed on all open sides
and ends of scaffold platforms
The top edge height of top rails shall not be less than 0.95 m (38 in) and not more than 1.15 m (45 in) above
the walking/working surface of a platform or per site condition.
Guardrail systems shall be completely installed before a scaffold platform or stair/ladder landing is used by
personnel other than the scaffold craftsmen.
Planks shall not be placed on top rails or mid rail. Toe boards shall be installed along all edges of scaffold
platforms and Minimum 6” Toe Board must be installed. Scaffold platforms must be tightly planked with
scaffold plank grade material or equivalent
Platforms shall be kept free of obstructions, unnecessary materials, projecting nails and other unnecessary
tripping hazards (including uneven decking).
Adequate space for workers to safely pass shall be provided and maintained wherever materials are placed on
platforms.
Platform units that have become slippery with oil, sand or any other substance shall be cleaned, or otherwise
removed and replaced, prior to continuing use.
Ladders shall be installed in a safe and accessible location. Only one person shall climb the ladder at a time
and Three-point contacts shall be maintained while climbing ladders
Scaffold materials must be place in a rack when transporting. Personnel must stay away and clear the area
prior for lifting of materials and working area must be covered with hard barricade.
Damage materials must not be used and must be removed from site and Scaffold materials must not be
painted
Only authorized personnel are allowed in the work area.
Barricades with signage’s (Danger: Scaffolding Works in Progress) must be provided and posted to warn
other personnel of the ongoing activity.
Sufficient clearness should be provided if any electrical cables there
End caps should be provided in all exposed scaffold tubes in order to prevent from damage and injury caused
by exposed tubing.
Tags should be displayed on scaffold with all necessary remarks for identify a safe use.
Workers should be aware of heat, pneumatic, electrical and other sources that are existing in place where the
scaffold being erect nearby with, that awareness must be given by HSE officer of site.
All involvers should have a clear idea of emergency evacuation route and signage’s and that should not be
obstructed
Lifting Of Pipes, Material and Curbstone, Weight = 45 to 65 KG (CPP1 Roof Top Near New Canning Line H
Building) By using Crane (Work Procedure)
Installation Of Curbstone for Utility Pipe Support (Size=500 X 400 X 150 X 80 MM) (Approximately Weight H
= 45 to 65 KG) & Installation of Pipe Support and Utilities Lines (Steam,4inch) (Condensate,1-1/2) (Glycol
Supply&Return,3inch) (First and Reuse Water,2inch&3inch) (Hot Water,2inch) (Compressed Air,3inch) &
Insulation cladding work
Combustible materials (if present there) must be removed before start the work during installation of pipes and
support work and hot work area must be covered with fire blankets.
Place welding machine on level ground, ensure all equipment is correctly tagged, inspect all power tools prior
to use, ensure all power leads are hanging from insulated hooks and are not lying on the ground, do not run
leads through scaffolds
Ensure safe manual handling techniques are adopted by the workers
Follow Watch Your Step technique and work area must be clear to avoid slip trip and fall before start the work
Ensure right tool is used for the right job
Provision of personal protective equipment during cladding and insulation work.
Information, instruction and training regarding manual handling is given to employees
Availability of fire extinguishers (CO2 and DCP) and trained fire watch
Tapping of New Utilities Lines (Steam,4inch) (Condensate,1-1/2) (Glycol Supply&Return,3inch) (First and
Reuse Water,3inch&3inch) (Hot Water,2inch) (Compressed Air,3inch) From Existing Main Lines
Ensure must lines are isolated, lockout and tagged and properly drained before start cutting the lines and make
sure lines are isolated and drained to check through isolation valves and drain point and lockout must be done
by contractor along with tagged in which clearly identifies the location and purpose of tagged and clearly
mentioned the date and time and signed by the contractor responsible person.
In case any leakage during work. immediately stop the work and informed related department and not resume
the work until line is clear.
Job rotation procedure must be adopted to minimize the hot environment exposure and cold drinking water
must be available there all time.
Ear muffs must be used by all team during work and other PPES must be used all time.
Ensure proper work plat form is erected by competent personal and inspected for its safe use
All work force will be informed and advised to never use (Existing facilities as work platform)
H
Ensuring that overreaching and working /standing on guardrail is strictly prohibited
Ensure cladding is removed carefully after the pipe is isolated, drained and de pressurized and is cool
Ensure compliance with PPEs (mask and gloves and full sleeves shirt while removing insulation from pipes.
All affected personal in area will be informed.
Area barricaded and signage installed
Ensure that all employees will be well aware of emergency response procedure and assembly point
Ensure that tools and equipment used during tapping activity are pre inspected, safe
Ensure compliance with mandatory PPEs (safety helmet, safety shoes, vest, glasses, mask) and secondary
PPEs (earplugs, earmuffs, face shield)
Ensure close safety monitoring during tapping activity
Provision of close supervision will be made sure
Availability of sufficient numbers of fire extinguishers is ensured at workplace
Pre-Operational Check:
Ensure task (e.g., Drawings, instructions, specifications etc.) is clearly understood.
Check that the accessories and attachments are properly fitted and that all guards and other safety devices are
in place and working properly.
Before you inspect any parts, make sure the power is turned off and the lead unplugged from the power source.
Check workspace and walkways to ensure no slip/trip hazards are present. Remove any flammable liquids or
combustible materials from the near proximity if present there.
Identify ON/OFF switch and emergency stop button.
Ensure all other employees are clear of the immediate work area.
Safe Operation:
Use of power tools (angle grinder, drilling machine, cable drum, welding machine, etc...) H
Appropriate personal protective equipment (PPE) shall be worn at all times when using hand tools and power
tools (e.g., hard hat, safety glasses/ goggles, hearing protection, safety shoes, gloves, face shield).
Personnel shall not operate any tools unless they are appropriately trained in their selection, use, inspection and
storage. Training records shall be made available upon request.
Tools constructed of good quality materials shall be used. Use of “homemade” tools is prohibited.
Tools shall be kept clean at all times.
Tools shall be inspected before and after use, as well as before storage
Only properly insulated or nonconductive tools shall be used when work is performed on or near electrical
equipment. Insulation integrity shall be regularly inspected by an authorized/certified electrician.
A record of tools issued, repaired or withdrawn from use shall be maintained
Cords, cables, etc., shall be positioned where they are not likely to be damaged (e.g., run overhead) or shall be
otherwise protected from damage (e.g., running them inside impact resistant conduit or using abrasion resistant
supply leads)
Residual current devices (RCDs), shall be used for all 110/220 V portable electric power tools
Three pin plugs will be used for electrical equipment.
Manual Handling:
Plan the move and measure access of the path.
Ensure clear passage.
Bring in professionals for large jobs.
Use pallets and forklift where possible.
Aim for a minimal distance carry and lift.
2 persons lift where required. Avoid The Need for Manual Handling. ...
Reduce The Load Risk by Using Lighter Weights or More Stable Containers. ...
Reorganize The Activity or Environment to Further Reduce the Impact on The Individual. ... H
Utilize Mechanical Lifting Aids or Equipment. Ensure Appropriate Rest Breaks, Job Rotation & Training Is
Involved.
Hand-held Tools: M
First Aid facility will be made available on site to take care of unexpected first aid cases.
Adequate supervision provided and emergency contacts will be provided with the workers in case any
incidents/Accidents.
Routine clean – up during the execution of the works. L
Clean up / dispose unused or excess materials.
Area left in safe condition and returned to normal operating stage
Priority Status:
High : Risk being addressed is serious; action/control required urgently/immediately
Medium : Potentially serious, remedial action should be taken within agreed timetable
Low : Minor risk, implement if/when resources allow
✔
LOW (1-8) MEDIUM (9-12) HIGH (15+)