Risk Assessment – Rev.

0 – 25 Sep 2021

RISK ASSESSMENT

Project / Contract Activity Assessment By: Reviewed By: Assessment No:


Multi Storey Car Park Building Name KAMRAN Name JAH-S-EL-RA-001
Excavation &backfill for U/G Cable
at BWTC Complex Date 25/9/21 Date

Potential Hazards / Conditions to be Considered


1 Use of Hand Tools 6 Fall from Height 11 Work on or Over Water 16 Fire Risk 21 High Winds 26 Young Persons
2 Use of Power tools 7 Working Platforms / Ladders 12 Lifting Operations 17 Noise /Dust/Vibration 22 Adverse Weather 27 Loading / Unloading
3 Use of Plant Equipment 8 Slips /Tripping 13 Confined Spaces 18 Fumes 23 Environmental Risk 28 Other Workers
4 Excavations 9 Manual Handling 14 Fuel Storage Demolition 19 Traffic 24 Training Required 29 General Public
5 Buried / Overhead Services 10 COSHH 15 Storage /Lay Down Area 20 Ground Conditions 25 Health Surveillance 30 Lack of supervision

Likelihood

Likelihood

Residual
Severity

Severity
Risk

Risk
No Task Hazard Who may be harmed Control Measures

 Pinch points, trap hand, fingers  Equipment’s and machineries should be used by competent
and feet. operators
 Improper lifting/rigging.  Must be supervised by competent and trained supervisor
Loading /  Line of fire.  Equipment’s must be inspected prior use.
Unloading of  Moving equipment.  Tool box talk prior work activity
Operators
Materials,  Damaged and substandard lifting  Use double taglines while lifting the materials to control the load.
Helpers
1 Mobilization of gears. 2 3 6  Ensure availability of proper hoisting and rigging 1 3 3
equipment  Failure of equipment. Supervisor
equipment’s for lifting.
(Crane operation,).  Uncertified operators and rigger. Surrounded employees
 Area must be provided with barricades and signs to restrict
 Swinging of load. unauthorized access
 Overloading.
 All lifting operations must be pre-planned. Correct lifting equipment
 High wind must be provided compatible with the loads in consideration.
 Falling of lifting loads
 All employees shall be fully aware of emergency procedure.
 Falling into excavation  Site emergency plan shall be prepared by supervisor/ safety
officer.
Manual Excavation  Collapse of sides of excavation Supervisor
 Proper means of access and egress to the trench shall be
2 & backfill (using  People and vehicles falling Helpers 2 2 4 1 2 2
hand tools) provided.
into excavation Surrounded employees
 Trench either sides to be fully barricaded or safety warning
lights to be in place and safety sign boards in different
languages.
Risk Assessment – Rev. 0 – 25 Sep 2021

RISK ASSESSMENT

 Tool box Talk and supervision.


 Competent persons must carry out the task
 Procedure limit shall be followed strictly.
 A sufficient numbers of trial pits shall be excavated to ensure the
 Fire clearance of the line’s path (trial pits shall be excavated by using
Mechanical  Explosion hand tools only).
Excavation &  Cutting Operators  A banks man must be available at all time during excavation with
3 Backfill (using  Moving equipment. Helpers 2 3 6 excavator (JCB). 1 3 3
excavator,  Pinch points, trap hand, fingers Surrounded employees  A competent backhoe shall be in good operation condition, free
compactors etc). and feet. from any defect.
 Hand excavation only while working close to underground services
as per approved condition.
 Tool box Talk
 Job watcher and continuous supervisor.
 Ensure that sufficient water is made available at
work location.
 Take rest as per work/rest cycle.
Working in  Ensure rest shelters are available for each work
adverse weather.  Heat Stress stations.
Engineers
HOT, SUMMER  Heat exhaustion  Ensure that clothing is suitable for the climate.
Operators
Working in a  Confusion/drowsiness  All working in hot weather must have undergone
4 Helpers 2 2 4 1 1 1
Dusty  Heat stroke heat stress prevention training program.
Supervisor
environment.  Poor visibility  Comply with the local law & summer timing.
Surrounded employees
Working in a Noisy  Equipment movement nearby  Noise assessment shall be carried out on each project and for
environment specific tasks known to have high dB output sound level below
85db shall be maintained
 Dust masks shall be issued if activities such as sweeping up
generate excessive dust.
 Proper physical barricading and warning sign boards should
be erected at excavation area and edge.
 Site area not fully  Walkways with standard guardrails are required when
Falling of secured. employees cross over the excavation.
Helpers
Workers / tools  Inadequate site access control.
5 Supervisor 2 2 4  Enable proper Lifting Techniques. 1 2 2
or materials in to  No or inadequate sign boards Surrounded employees  PPE's must be worn like Hard Hats, Safety Shoes, High
the excavation  Insufficient PPE
visibility clothing, Reflective jacket etc.
 All materials and equipment’s should be placed at a distance
of 1 m from the edge of the excavation.
Risk Assessment – Rev. 0 – 25 Sep 2021

RISK ASSESSMENT

 Daily Based site inspections.

 Warning vests or other suitable garments made of reflector zed or


 Vehicle accident Operators high-visibility material and ensure that they wear them.
Working on the  Fall in the excavation Helpers  Proper barricading and traffic signs should be provided.
6 2 3 6 1 3 3
road  Unprotected excavation Supervisor  Diversion should be done as per the diversion plan approved by
 Obstructed road/walkways Surrounded employees concerned authority.
 Appoint a Flagman to control or to divert the traffic as necessary

Risk Likelihood Risk Rating


Rating 3 2 1
Severity
3 9 6 3 3 Major Injury/ Pollution/ Damage
Severity

2 6 4 2 2 Minor / Pollution/ Damage/ Loss


1 3 2 1 1 Injury / Low Damage / Loss
Likelihood
3 Likely
4 or more = Unacceptable Risk 2 Possible
Risk Rating = S x L = R 1 Never / Very Unlikely

Recommendation Actions

Risk level
1-2 Low Risk Acceptable - No additional risk control measures may be needed, need review to ensure risk level accurate.
3-4 Medium Risk Carryout careful hazard evaluation to ensure risk level reduced. Interim risk control measures, management attention required.
6-9 High Risk Reduction of high risk to medium risk before work starts, there should be interim risk control measures, hazard should be
Eliminated before work commences, management attention required before work starts.

Noted By:________________________________ Designation:___________________________________ Date:__________________________________