HARADH AND HAWIYAH FIELD GAS COMPRESSION PROJECT

IK Contract No.: (6600040668 ,6600040670&66000672


JO. / PROJECT NO(10-130)
SAOC BI NO:BI-10-02029-0002,10-01996-0003&10-01966-0004

JSA No 0013 Date Created Nov 19, 2018 Revision No. 0001

JOB SAFETY ANALYSIS SHEET

Company: KAMCO CONTRACTING DIVISION


Project/Site HARADH AND HAWIYAH FIELD GAS COMPRESSION PROJECT Main Contractor TR
Copper pipes installation and Brazing with Oxygen and
Job Task Work Area Package 3 Areas under KAMCO’s Scope of Work
Acetylene.

Material Safety Data Sheets Required YES

Plant & Equipment Required YES


Licenses / Competencies Required YES

Work Permit System: Cold Work Permit Hot Work Permit Excavation Work Permit
Scaffolding Permit Electrical Work Permit Radiography Work Permit Crane Lifting Permit Other Work Permit

PPE Required:

High Risk Work: Structural Collapse Demolition of Structures Confined Spaces


Work in Tunnel Fall from Heights> 2m Explosives Excavation>1.5m Mobile Plant
Drowning Asbestos Pressurised Gas Pipes/Mains Electrical Traffic
Tilt-up/Precast Concrete Chemical/Fuel/Refrigerant Lines Contaminated/Flammable Atmosphere

Task/Location Specific Risks:: Ground Conditions Noise Weather


Access & Egress Obstacles/Buildings Overhead Obstructions Soil Pollution Water Pollution
Compressed Air Rotating Machinery Quick Cut Saw Angle Grinder Hot Work / Burns
Ignitions Sources Dust Fatigue Pedestrians / Workers Unauthorised Persons
Underground Services Poor Lighting Snakes / Vermin Exposure to UV

Emergency Contact Number: Construction Supervisor: Abdul Rehman Contact No: 0559329971

TR Hotline Number : +966 (0) 533992200


Emergency Contact Number: Rescue: 997 Traffic: 993 Fire Fighting: 998

KAMCO Hotline Number : +966 (0) 598072643


1/6
JOB SAFETY ANALYSIS SHEET

Risk Residual
Job Step Potential Hazard Control Method
Rating Risk

2/6
SITE PERSONNEL CONTACT NUMBERS

NAME DESIGNATION CONTACT NUMBER

ENGR. ABDEL AZIZ PROJECT MANAGER 056-892-9967

050-864-7091
ENGR. MAHMOUD ZAKI PROJECT MANAGER

KALEEM SARWAR SAFETY MANAGER 059-807-2643

CIVIL GROUP

MAHMOUD NOUR EL-DINE CIVIL SUPERVISOR 055-406-0614

ABDULRAHMAN ALI CIVIL SUPERVISOR 055-932-9971

3/6
ELECTRICAL GROUP

SATHEESH ELECTRICAL SUPERVISOR 053-194-2438

SAJI BABY ELECTRICAL SUPERVISOR 050-241-7667

MECHANICAL GROUP

EMAD MECHANICAL ENGINEER 054-347-7202

SAJI GEORGE MECHANICAL SUPERVISOR 050-791-2082

4/6
Supervisor Name: Supervisor Signature: Date: .

Prepared by: KALEEM SARWAR Reviewed by: ABDUL AZIZ Reviewed by : Approved by:

Position: HSEM Position : Project Manager Position : Position :

Date : Date : Date : Date :

Signature: Signature : Signature: Signature :

PREPARED BY REVIEWED BY REVIEWED BY APPROVED BY

JOB SAFETY ANALYSIS SHEET

Step 1
Consequences
5 – Severe Potential to be fatal. Permanent disability. Destruction of property or plant.
4 – Major Serious injury. Long term disability. Major damage to plant, property or environment.
3 – Moderate Potential for injury resulting in medical attention. Damage to plant, property or environment.
2 – Minor Injury requiring First Aid treatment and / or short term discomfort.
1 – Negligible Cause a near miss, needs to be reported

Step 2
Potential (Likelihood)
A – Almost Certain The event is expected to occur in most circumstances
B – Likely The event will probably occur in most circumstances
C – Possible The event might occur at some time
D – Unlikely The event could occur at some time
E– Rare The event may occur only in exceptional circumstances

5/6
Step 3
Matrix Consequences
Potential 1 – Negligible 2 – Minor 3 – Moderate 4 – Major 5 – Severe
A – Almost Certain M (9) S (15) S (19) H (24) H (25)
B – Likely L (7) M (11) S (18) S (21) H (23)
C – Possible L (5) L (6) M (13) S (17) H (22)
D – Unlikely L (3) L (4) M (10) M (14) S (20)
E– Rare VL (1) L (2) M (8) M (12) S (16)

Legend
Risk Rating
Activity to be re-planned and/or re-designed. If this is not possible, an independent Hazard Assessment of the activity is to be completed by the Project Manager prior
High
to completing the SWMS

Significant Activity Must be reviewed by Senior Site Management Representative and have identified risk controls built into the SWMS and work procedure

Medium Site Supervisor must review method of task.


Low Some action may be required, Supervisor to determine and monitor
Very Low Minimal risk, monitor where work changes