Method Statement Document

Method Statement
for
HV Cables Relocation at
Multi Storey Car Park Building at BWTC
Complex

Multi Storey Car Park Building at


Project Title:
BWTC Complex
Contractor: Dadabhai Construction
Document Title: Method Statement
Document Reference: JAH-S-EL-MS-005/Revision 00
Date: 10 October 2021

JAH-S-EL-MS-005 Revision 00 P a g e 1|5


Method Statement Document

TABLE OF CONTENTS

SECTION TITLE PAGE

1 INRODUCTION 3

2 SCOPE OF WORK 3

3 LOCATION 3

4 REFERENCES 3

5 RESOURCES 6

5.1 MANPOWER 6

5.2 MATERIALS 6

5.3 TOOLS & EQUIPMENTS 6

6 SEQUENCES/STAGE OF WORK 7

JAH-S-EL-MS-005 Revision 00 P a g e 2|5


Method Statement Document

1) INTRODUCTION

The purpose of this Method Statement is to provide methodology for 11kV cables relocation at
‘Multi Storey Car Park Building at BWTC Complex’ in compliance with Standard Specifications EDD
– MTC August 2015 and specification for the project.

2) SCOPE OF WORK

This Method Statement will define the scope of works for 11kV cables relocation, which
describes details of activities & execution involve in procedure under project specifications &
approved drawings.

3) LOCATION

As shown in the latest shop drawings.

- JAH-SI-INFRA-HV-101 Rev. 2, Existing Cable Rerouting Layout Ground Floor

4) REFERENCE

 EDD MTC – August 2015


 IFC Drawings, Shop Drawings, RFI’s (if any), STQ’s (if any), ESI’s (if any).

5) RESOURCES

5.1 Manpower

 Project Manager
 Project Engineer
 Site Supervisor
 Safety Officer
 Forman
 Cable Jointers
 Electricians
 Helpers

JAH-S-EL-MS-005 Revision 00 P a g e 3|5


Method Statement Document

5.2 Materials

 Cable Tray and accessories – Approved by GEMAC


 Solid concrete support blocks – Approved by Engineers

5.3 Tools & Equipment

 Portable generator
 General tools
 Drill machine
 Metal cutting machine
 PPE
 Barricades
 Safety sign boards & warning lights

6) SEQUENCE/STAGE OF WORKS

 Arrange cable trays, tray accessories & concrete support blocks at site prior to shutdown
date.
 Shutdown will be agreed and work permit shall be issued by MODA team.
 Mark the roof demolishing line
 Provide new route marking (2 mtr away from demolishing line)
 Request for Permit to work to be submitted to Moda Mall facility Team.
 After approval of work permit arrange to dismantle existing unused cable tray and pipes
and make the route for cable tray clear.
 Co-ordinate with Moda Mall Facility for disconnection of power to Feeder Pillar cables and
disconnection.
 Install the new cable trays and make ready the cable tray needed for the tie in with existing
cable tray
 Obtain final approval from consultant and Moda Mall Facility Team.
 Request for another work permit to work on the existing 11KV cable at roof.
 Make loose the existing cable tray covers by removing the screws
 Request for shutdown. Duration – 6Hrs.

JAH-S-EL-MS-005 Revision 00 P a g e 4|5


Method Statement Document

 Organize manpower/ material/machines etc. on the day of approved shutdown.


 Co-ordinate with Moda Mall HV Engineer for switching activities.

The above activities need to be completed prior to the shutdown


 Provide shutdown and issue “Permit To Work”
 Once it’s done immediately lift the cable from existing tray and move to new tray
 Install the covers
 Re-energize the cable
 House keeping