Professional Documents
Culture Documents
ELSEVIER
143
144 Impact of power wheefing on composite system adequacy. R. Billinton and F. Gbeddy
2 x 40MW ( ~ ) ~) I x 40 MW
1 x 20 MW
1 xlOMW
BUS 1 [ 3 I I
4x 20MW
2x5MW
BUS 2
BUS I~0- 33 " ~ BUS 21 22
I
20 MW
1 6
85 MW 40 MW
BUS 6 91 2°~Mw
20 MW
Figure 1. Single line diagram of the RBTS
diagrams of the Roy Billinton Test System (RBTS) 4 and
the IEEE-Reliability Test System (IEEE-RTS) 5 used in
these studies are shown respectively in Figures 1 and 2.
8o ~ H
z 60
/ /
/ u3 60 /
40 -0-0-[3-[]-0-[3-0 Z
W 401 ~-O~E3~D
W
20
,..;~....~---.,~....&-.-~-..& -.-~.-.,~-.-&--.& 20 --.~---.~---X---.~---~---)~---,---X.---.3.--~
OC v . . . . . . . ~ 0' v~ m = ~ t~ i == == v == == ==
0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
Wheeling p o w e r (MW) Wheeling p o w e r {MW)
Intra-wheelincl from BUS 3 n t r a - w h e e l i n g from B U S 2
160 160 ~--~- - -L~--~ - -~--¢~- -~---~ --Z~-~- ~
~r-~- - ~ - ~ - - -Z~--~-." -Z~--~--~--~- --Z~
140 ~ Legend
140
Legend
• BUS 2
120 L
>.
12o ff • BUS2
I00 13 BUS 3
t- 100 // 13 BUS 3
x BUS 4
80
o _Bp_S.S_ 80 ~.12k~E]~'O x BUS 4
60
z
uJ A BUS 6
U3
z
uJ
60 .cro~o~° O BUS 5
uJ 401 -13"13-13-13--13--O--E3-O-E3-13 LU 401 y A BUS 6
20 ~..-,~...~--.~-..~---~..-x-.- ~.-.,~--.x---x zo-_~...~...~...~_..~.._x...x..-x--~ .
0 ~ ~ C ~ {~ ~ - - C" - - j ' - ' ~ ' ' ' ~ - ' ' ~
0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
Wheeling p o w e r (MW) Wheeling p o w e r (MW)
160 Intra-wheeling from BUS 6 160j~ I n t r a - w h e e l i n g from B U S 6
R~
1404
140~
120 12o
>. \
c- I00 ~
80 '\ 80 ',,
z
60 "k 60 ~ \,
uJ ,,=,
w 40t -D- ~ _ n _ r - l _ ~ _ D_ D_O_13 40 +-O-~,, D - D - D - D - D - D - D - °
20 i.~...~.., ...~i..~...x...~...~_._~...x
" 20
~---x.- -x---~-- -x- --x ---x--- x- --x---x.-- -x"
0~, ,., v ,., v w v v ~, ~ ~ 0=
0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
Wheeling p o w e r (MW) Wheeling p o w e r (MW)
Figure 5, Variation in EENS with intra-system wheeling Figure 6. Variation in EENS with intra-system wheeling
power to supply wheeling load at bus 2 of the RBTS power to supply wheeling load at bus 3 of the RBTS
146 Impact of power wheeling on composite system adequacy. R. Billinton and F. Gbeddy
wheeling power from the wheeling source to the sink. lines with adequate transmission capacity to transport the
Once an agreement is reached, wheeling power can be entire range of wheeling power considered are assumed to
injected into the IPS and passed on to the wheeling sink at exist for interconnecting the wheeling source and the sink
the respective interconnection points in accordance with with the IPS. The failure rates of these tie lines are
the terms of the contract. The wheeling source is modelled assumed to be zero thus implying 100% availability.
as an imaginary generating bus, which is directly con- Wheeling load is considered to be external to the utility
nected to the IPS. The energy/power to be provided (i.e. system demand in both the intra-system and inter-system
the wheeling power) is assumed to originate from this power wheeling analyses. The wheeling load (or the
imaginary bus which is external to the IPS. The wheeling wheeling component of load) at the sink is therefore not
power is modelled as a 100% available generating unit utilized when computing the system peak load.
located at the wheeling source. The rated capacity of the
unit is assumed to be equal to the contracted wheeling III. S y s t e m s t u d i e s
power. The wheeling sink is also assumed to be an The objective of the analyses in this paper is to examine
imaginary load bus which is connected to the IPS through the impact of wheeling operations on the composite
a buffer bus with tie lines as shown in Figure 4. In an ideal system indices of the power system which renders the
wheeling situation, the wheeling sink should be able to wheeling service. In the intra-system wheeling analysis,
receive all the energy/power contracted for wheeling; this refers to the local utility's power system whilst in the
hence curtailment effects occurring in the IPS should inter-system wheeling analysis this refers to the inter-
not affect the sink. However, this condition is difficult mediate power system. The DC load flow feature of the
to satisfy in all situations. The configuration shown in COMREL program was used as the network solution
Figure 4 is used to connect the wheeling sink to the IPS as technique during the power wheeling studies in order to
it minimizes the load curtailment impacts experienced at avoid the problem of accounting for system losses arising
the wheeling sink resulting from outage events occurring from power wheeling operations. Outage contingency
in the IPS. The entire wheeling load at the sink is enumeration was limited to independent overlapping
considered to be firm load and it is assumed to be outages up to the 4th level for generating units and up
always equal to the input power from the wheeling to the 3rd level for transmission lines (or transformers).
source. The percentage of curtailable load at the wheeling Combined generator-line outages involving up to two
sink is therefore specified to be zero and load curtailment generating units and one line, and one generating unit
actions are confined as much as possible to the IPS. Tie and two lines were also considered.
Load points
I n t r a - w h e e l i n g from BUS 8=>16
I n t r a - w h e e l i n g from BUS 16 =>8 in the Load points.
800 n o r t h region 8OO in the
--~- --ZX--6-- - ~ - - ~ " .Z~--~- - -Z~--~-- -~ Legend .._~...~._~.. _~._..~. _.&.--~ - - ~ - "-6 n o r t h region
7O0 700,
• BUS 13 Legend
600 600
>- [ ] BUS 14 • BUS 13
"- 500 -- 500
• BUS 15 ...0..0_-0__0.--0---0--0--0--0--0 r l BUS 14
..-•- - • . - -•-- -•----•- - 0 - - • - - • " - • - " • .~ 4004
400 l O BUS 16 • BUS 15
Ch
z 300 A BUS 18 300 O BUS 16
UJ m I I m mm m m I I |
x BUS 19 200, L A BUS 18
200~._.;_..v_v.__v..-n-v.-~.-.~:::y:~
_ . . ~ . . . . X . - - - K - - -" X " " ~2 BUS 20 x BUS 19
I00
~ _..~.._Q-
~ - ~ = -O-.-O-.-O---O-.O---O-'-O
~=~-_=~-_.-~_.-~.-.~..m v BUS 20
01
0 10 20 30 40 50 60 70 80 90 100 10 20 30 40 50 60 70 80 90 100
Wheeling power (MW) Wheeling power (MW)
Load points
Load points
in the
in the
south region
south region
60 r • Legend
Legend
A BUS1
50 x--x A US.____1
B
+ BUS 2 II~IL~_~:~:_~__ ~_~=u__._ + BUS 2
40~--+--*=
i~_m...m.--m...m.-.m---m---m-m----
- - ~m x BUS 3 4o~..i...m--m..m'-71zT..l.-.l~l=lz: x BUS 3
o Bu;- 30 .................. 0 BUS 4
V BUS 5
~7 BUS 5
• BUS 6
,,,,,, 20 • BUS 6
• BUS 8
• BUS 8
O BUS 9
O BUS 9
0 10 20 30 40 50 60 70 80 90 100 [] BUS I0 0 10 20 30 40 50 60 70 80 90 100
Wheeling power (MW) [3 BUS I0
Wheeling power {MW}
Results of the analyses utilizing the RBTS and the considered to be continuously available in the same
IEEE-RTS respectively as the study systems are pre- amount throughout the study period.
sented and illustrated. In the studies performed, up to
50 MW and 100 MW of power was wheeled through the IV. Discussion of results
RBTS and the IEEE-RTS respectively• This produces
different impacts on the load point and the overall IV.1 Load point indices
power system adequacy indices ~. The impacts on the
Expected Energy Not Supplied (FENS) indices at the IV.1.1. Intra-system wheeling results
various load points of the test systems are discussed Figure 5 shows variations in the FENS indices at various
below. Additional indices such as the probability and load points when up to 50 MW of power is wheeled from
frequency of load point failure were also determined in different parts of the RBTS to supply wheeling loads
these studies• The effects on the severity index of both located at bus 2 in the system.
test systems are also considered to illustrate the impacts It can be observed from Figure 5 that the inadequacy
on overall power system adequacy. All the results indices for most of the RBTS load points remained
shown are annual indices which reflect the variations virtually unaffected throughout the power wheeling
in load level over a year. A 4-step (10% load step) load scenario in most cases studied• This shows that the
model was used for the RBTS analysis and a 7-step (5% RBTS is able to accommodate the range of wheeling
load step) load model was used for the analysis of the power to bus 2 without causing any significant adverse
IEEE-RTS. The wheeling load was, however, kept impacts on adequacy at the system load points. Wheeling
constant at all load levels as its dedicated supply was from load points in the southern section of the RBTS to
0 5 I0 15 20 25 30 35 40 45 50 L0 5 10 15 20 25 30 35 40 45 50
Wheeling power (MW) Wheeling power (MW)
I n t e r - w h e e l i n g from BUS 3 i n t e r - w h e e l i n g from BUS 2
160 . 160 ~.~.
~-~ - ~X---~---£~-~- - -~---~- -~--~- -~
140 ~ Legend 140 ' -~.--Z~,--~.--ZX---~---~--~-- .A
Legend
~. 120 • BU.S 2 120 I~
>.
• BUS 2
100 o B_U__S_~ 100 P"
o B_U_S_~
80 x BUS 4 80
¢n 60 O ~ rl~D~13" ,~ x _B_US_~_
u~ 60 O BUS 5
Z . . . . .
W
O _B.U_S.5_
w 401 " "O-d3._D._E3__D..O_.O_.O_D A BUS 6 w 401 /
X..-X A BUS 6
20 i--x---x--.~_._~...~...~...~...~...~..x 20 .x._.x_..x..-x---x- --x-- - x " ,3:)
Op_i.~--r-'--.---#r~r-~...- .~ . . 1,, .
0 .5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
Wheeling power (MW) Wheeling power (MW)
160 I n t e r - w h e e l i n g from BUS 6 160 I n t e r - w h e e l i n g from BUS 6
140 ~ 140 z
~. 120 ~ 120
-- 100 ", 100 "
60 ', tn 60 •
Z
w 40 " "O-43-43- -O--O- -O--C]--(3 Zww 401 -t-I-~q-o-E] ---E]-O-O-E]'-E]-O
20 -....
; ¢- ' " x:"\ "'~'-- ~-'-':~'-)1----~''~'-"x-'-~. 20 i..~..-~--~- -~---x---x---x --x---x- --x
0 ~- . . . . . . . . . . . . . 0
0 5 10 15 20 ;!5 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
Wheeling power (MW) Wheeling power (MW)
the northern parts of the system generally assures a more considerable increase in both the number of load curtail-
effective redistribution of power flow in the RBTS net- ment events and the amount of load curtailed at bus 3.
work. This accounts for the system's ability to cope with Similar observations can be made from Figure 6 which
the entire range of wheeling power capacity considered. shows the impacts on EENS indices at the load points
Approximately 90% of the RBTS load is located in the when intra-system power wheeling operations are carried
southern section of the system. Wheeling power imports out to supply wheeling loads located at bus 3 of the
in the south can therefore be used effectively to supply the RBTS.
loads in that part of the system with minimum transmis- The impact on the indices when the wheeling opera-
sion requirements. This reduces, to some extent, the tions involve only buses within the heavily loaded section
dependence of the southern section of the system on of the RBTS are observed to be relatively minimal
conventional generation supplies which have to be trans- compared with when the wheeling loads are supplied
ported from the north (i.e. from buses 1 and 2) over directly from bus 2, a conventional generation supply
transmission facilities which are exposed to the risk of location in the north. Wheeling from the north section of
failure. Meanwhile the wheeling load located in the the RBTS is generally not suitable, because the extra
northern section of the RBTS is also supplied effectively transmission capacity available in that part of the system
from the conventional generation sources located in that is not adequate to transport the increased supply require-
part of the system. Wheeling from bus 6 produces sig- ments of the south region effectively (created by the
nificant drops in the value of the indices at that load added wheeling load) from the generating facilities in
point, because the wheeling supply made available at the the north. In all the cases shown, the load point indices
bus is used to supplement utility supply both during at bus 6 remained virtually unaffected throughout the
normal system operation and when the load point is entire wheeling scenario except when the wheeling power
isolated from the conventional generation sources. Sup- is from that bus. This is expected because wheeling
plying a wheeling load located at bus 2 from additional operations beyond the radial link do not address the
generation supplies provided at the swing bus (i.e. bus 1) isolation problems basically responsible for inadequacy
results in a deterioration in adequacy at bus 3 where at the bus.
about 46% of the RBTS load is located. This effect Variations in the EENS indices at the load points of the
becomes most significant when the wheeling load intro- IEEE-RTS when up to 100 MW of power is wheeled from
duced exceeds 35MW, at which stage more frequent bus 16 (in the north region) to bus 8 (in the south region)
swing bus overload conditions experienced cause a are shown in Figure 7. Similar results obtained for
10
¢' _BUS.._7
IO • BUS 8
• BUS 8
° ) ,T q 3i ~ , O . , I- o - ,I 4 3 1I - - oI - - oI = ' OI - ~I i
o BUS 9
o o BUS 9
0 102030405060708090100 D BUS 10 0 10 20 30 40 50 60 70 80 90 100
Wheeling power (MW) D BUS I0
Wheeling power (MW,I
wheeling in the opposite', direction are also shown in IV.1.2. Inter-system wheeling results
Figure 8. Figures 9 and 10 show variations in the EENS indices at
It can be observed from Figure 7 that wheeling from the load points when up to 50 MW of power is wheeled
bus 16 in the north to bus 8 in the south region of the through the interconnected RBTS with the wheeling sink
IEEE-RTS causes a considerable deterioration in ade- connected to bus 2 and to bus 3 respectively. Similar
quacy at several load peints, particularly in the south results for the IEEE-RTS are shown in Figures 11 and 12
region. This is expected, because as noted in Reference 1, when up to 100 MW of power is wheeled through the
the south region is a net generation-importing area and is system with buses 8 and 17 serving as the interconnection
highly dependent on sul~plies from the north-eastern points of the wheeling source and the sink.
parts of the IEEE-RTS. ]Introducing a wheeling load in It can be observed that the results shown by these
the south region therefore increases that region's depen- figures are fairly similar to those obtained in the case of
dency on supplies from the north and consequently intra-system wheeling. The worst impacts in the case
increases the pressure on transmission facilities respon- of the RBTS are obtained when the wheeling source is
sible for transporting the increased supplies to the (sOuth) connected to any of the two generation buses in the
region. On the other hand, the effects of wheeling in the northern part of the system. In the case of the IEEE-
opposite direction from bus 8 to bus 16 as shown in RTS, the worst wheeling impacts result when the wheeling
Figure 8 are observed to be generally minimal and power has to be tapped from the net generation-importing
virtually negligible at a number of load points• This (south) region. It can therefore be concluded that the
occurs because introduction of a wheeling source in the provision of additional generation supplies to satisfy
south region makes generation supplies more readily effectively the increased demand resulting from an intro-
available to the region a:ad reduces the region's depen- duced wheeling load is significantly influenced by the
dence on supplies from the north. Generally, adequacy availability of sufficient composite generation and trans-
at load points directly bavolved in the wheeling oper- mission capacity in the system, and this is reflected in the
ation are the ones most affected, although the effects calculated reliability indices.
can spread to immediate neighbouring load points as
well. Whilst an improvement in adequacy is noticed at IV.2 System indices
the wheeling source, the wheeling sink and the load
points surrounding it generally experience a deterio- IV.2.1. Intra-system wheeling results
ration in adequacy. Figure 13 shows variations in the overall system severity
52
•~ 9Ol- . _ _ - ~ "~ sl From
E° 8o":, ....... ~,--~-..l..~.mm-m-.ll ~o so 17 BUS 16
70 " ~ 49 • BUS 19
• ~_V.s.~g
x 50 " x 47
I I I I I I I I I I
>o io , , ",~-~~P-i~~F-+,e-9, ~ 43
cy~ 5 10 15 20 25 30 35 40 45 50 10 20 30 40 50 60 70 80 90 100
Wheeling p o w e r MW) Wheeling power CMW)
Figure 1 3. Variation in severity index w i t h intra-system Figure 1 4. Variation in severity index w i t h intra-system
w h e e l i n g p o w e r within the RBTS w h e e l i n g p o w e r within the IEEE-RTS
1 50 Impact of power wheeling on composite system adequacy. R. Billinton and F. Gbeddy
index when up to 50MW of power is wheeled from tions considered are observed to be sensitive to the
different locations to supply wheeling loads located at proximity of the wheeling source and sink locations to
buses 2 and 3 of the RBTS respectively. the swing bus (i.e., bus 23). Capacity deficiencies are
It can be observed that wheeling from and to different noted to be accountable for the bulk of inadequacy in
parts of the RBTS produced different and varying degrees the IEEE-RTS TM and these frequently lead to swing bus
of impact on overall system adequacy. A slight drop in overload conditions mainly affecting load points,
the value of the severity index is noticed when wheeling is particularly in the north region ~. Hence introduction
done from most parts of the system to supply a wheeling of a wheeling source close to the swing bus tends to
load at bus 2. This indicates slight improvements in suppress the occurrence of swing bus overload condi-
overall system adequacy compared with the level of tions, thus prOducing a considerable improvement in
system adequacy that existed prior to the start of the overall system adequacy. When the wheeling source is
wheeling operations. Wheeling operations involving only located farther away from the swing bus or the wheeling
buses located in the heavily loaded southern section also load is introduced close to the swing bus, reduced levels
produce similar or no effects on the severity index. of improvement in overall system adequacy are obtained.
Wheeling from either bus 1 or bus 2 in the north is Referring to the single-line diagram of the IEEE-RTS
generally undesirable as this results in a deterioration in shown in Figure 2, bus 20 is directly connected through
the level of overall system adequacy. As noted earlier, this a double circuit to bus 23 which served as the swing
condition is due to capacity limitation problems experi- bus in these analyses. Bus 19 is farther away from the
enced by the lines responsible for bulk power movement swing bus than bus 20, and bus 16 is still farther
from the north to the south. The lines are therefore away from it than the previous two buses. It can there-
unable to accommodate effectively the entire range of fore be seen from Figure 14a that relatively lower severity
wheeling power imposed on the RBTS. index values are obtained as the wheeling source is
The variations in overall system severity index when up introduced nearer to the swing bus. Introduction of
to 100MW of power is wheeled from and to different wheeling loads farther away from the swing bus also
parts of the IEEE-RTS are shown in Figure 14. produces similar effects on the system severity index as
The impacts obtained for the various wheeling opera- shown in Figure 14b.
•-.E 160
\ ~.-- ; ¢" 17s
.>-IF= 15s ~'~
,,'/ E ~
>~ ~,
> ~
~ 13s
I~].,,B~"
.,~"
~ 115
j •
1451
o l'S ;o ~s ~o ~s ~0 ~s ~o
i'o 9s- ~ io 1's 2'0 2's 3o ~s 40 .s 5o
Wheeling power (MW) Wheeling power (MW)
>~ 9o
95
x Wheeling
from BUS 5
>~. 120
~ 100
...~.~_.~_~..~.~r x Wheeling
t_o_B_US__S_
85 ., ,,,,, ,.,~, 80, | i i
s 1o is 2% ~s ~o ~s ~o is •50
5 10 15 0 5 30 35 40 5 0
Wheeling power (MW) Wheeling power (MW)
IV.2.2. Inter-system w h e e l i n g results system adequacy and in some cases may have relatively
Severity-index variations,; for wheeling operations in little effect on the indices of the system rendering the
interconnected systems ;ire generally similar to those wheeling service. The impact on the indices due to a
obtained for intra-system wheeling. Figure 15 shows the specific wheeling operation depends largely on the exist-
effects on the system severity index when wheeling opera- ing composite generation and transmission system con-
tions involving bus 2 are undertaken by the RBTS when figuration of the utility system.
operating at three different peak load levels. The different The studies clearly illustrate that it is extremely impor-
peak load levels were obEained by varying load propor- tant to assess quantitatively the reliability implications
tionally at all the system load points. Similar results were of wheeling operations prior to establishing formal
obtained for the analysis utilizing the IEEE-RTS as contracts. The investigations should cover detailed
the IPS. These analyses were performed to determine the examination of load point and overall system adequacy
relative magnitude of the effects associated with different prior to wheeling in order to provide a datum against
wheeling options at different IPS peak load levels. The which to assess the implications of possible wheeling
severity index value for the stand-alone system at each options.
load level served as the datum for these comparisons.
It can be observed from Figure 15a that the severity Vl. References
index values obtained beyond 15 MW of power wheeling
through the RBTS are lower than the corresponding 1 Billinton, R and Gbeddy, F 'Effects of non-utility generators
values for the stand-alone system when the RBTS is on composite system adequacy evaluation' IEEE/PES
Summer Meeting Seattle, WA, July 1992, Paper 92 SM
operating at any of the peak load levels considered. 442 4 PWRS
This is an indication that wheeling beyond 15 MW of
power for this (wheeling) option is favourable to the 2 Mukerji, R, Neugebauer, W, Ludorf, R P and Catelli, A
RBTS. A comparison of the adequacy gains resulting 'Evaluation of wheeling and non-utility generation (NUG)
from the wheeling transactions shows an increase in the options using optimal power flows' IEEE Power Eng. Rev.
Vol 12 No 2 (1992)
adequacy gains at higher peak load levels. It can therefore
be concluded that wheeling options that are favourable to 3 Noyes, RGenerationofsteamandelectricpowerNoyesData
the IPS generally tend to be more attractive and beneficial Corporation, Park Ridge, New Jersey (1978)
when the IPS is subjected to a higher system load stress. 4 Billinton, R, Kumar, S, Chowdhury, K, Chu, K, Debnath, K,
On the other hand, Figure 15b shows typical results of Goel, L, Khan, E, Kos, P, Nourbakhsh, G and Oteng-Adjei, J
wheeling transactions whose impacts adversely affect the 'A reliability test system for educational purposes--Basic
level of adequacy in the IPS throughout the wheeling data' IEEE Trans. Power Syst. Vol 4 No 3 (1989) pp 1238
scenario studied for the interconnected RBTS. These 1244
wheeling operations are considered to be unfavourable 5 IEEE Committee Report 'IEEE reliabilitytest system' IEEE
wheeling options for the IPS. It can be observed that the Trans. Power Appar. Syst. Vol PAS-98 (1979) pp 2047-2054
severity index values shown in these figures increase 6 Billinton,R 'Composite systemadequacy assessment--The
steadily with wheeling power, and that they consistently contingency enumeration approach' IEEE (Power
remain above the corre,,~ponding values for the stand- Engineering Society) Tutorial Course, Course Text 90EH
alone system. The rate,, at which the severity index 311-1-PWR: Reliability assessment of composite generation
increases is generally not uniform, but can be observed and transmission systems (1989) pp 29-35
to be higher at higher peak load levels. This is expected 7 Medieherla, T K P 'Reliability evaluation of composite
because when the IPS system demand is increased, the generation and transmission systems' Master's thesis,
effect of transmission capacity constraints on wheeling University of Saskatchewan, Saskatoon (1982)
operations become more intensified and this produces
higher severity index values. 8 Kumar, S 'Adequacy evaluation of composite power
system' Master's thesis, University of Saskatchewan,
Saskatoon (1984)
V. Conclusions 9 Khan, E 'Fast adequacy assessment of composite power
The concept of quantitatively assessing the impact of systems' Master's thesis, University of Saskatchewan, Sas-
katoon (1988)
wheeling on composite power system adequacy is dis-
cussed in this paper. It has been shown by utilizing the 10 BiUinton,R and Allan, R N Reliability evaluation of power
COMREL program that a wide range of impacts on load systems Plenum Press, New York & London (1984)
point and overall system indices is produced by different 11 Billinton, R and Li, W 'Hybrid approach for reliability
wheeling options. The reliability impacts associated with evaluation of composite generation and transmission sys-
wheeling options can eit]her lead to an improvement or a tems using Monte-Carlo and enumeration technique' lEE
deterioration in the load point adequacy and overall Proc. C, Vol 138 No 3 (1991) pp 233-241