You are on page 1of 9

Electrical Power & Energy Srstems Vol. 18, No. 3, pp.

143 151, 1996


Copyright ! i 1996 Elsevier Science Ltd
Printed in Great Britain. All rights reserved
0142-0615(94)00016-6 0142-0615/96/$15.00 + 0.00

ELSEVIER

Impact of power wheeling on


composite system adequacy
evaluation
R Billinton and F Gbeddy
Power Systems Research Group, University of
Saskatchewan, Saskatoon, Saskatchewan,
Canada S7N 0W0

has also encouraged the wheeling of power in the case of


One of the many possible uses and benefits of interconnec-
joint ownership by several utilities of large, high capital
tion between neighbouring electric power systems is the
plants where the wheeling technique is used to transport
opportunity to wheel energy through the transmission
power/energy back to the plant's owners for marketing.
facilities of one system in order to serve another system.
Wheeling of energy/power is not limited to intercon-
Wheeling of energy can also occur within a system when an
nected systems, it can also be practised in stand-alone
independent power producer serves a load located at some
utility systems having independent power production
other point in the system. Power wheeling transactions are
facilities in the form of Non-Utility Generators (NUGs)
recognized to have a definite impact on the utility's system
or cogeneration facilities. The local utility, for one reason
losses depending upon the system topology, the amount of
or the other, may not be the actual recipient of the energy
power~energy wheeled and the wheeling distance involved.
produced from the NUGs and this energy is therefore not
These factors currently form the basis for determining
used directly to supplement system supplies from con-
service charges associated with power wheeling. Quantifi-
ventional generating locations'. It is possible, however,
cation of the reliability impacts of power wheeling is also
for the energy produced by the NUG to be sold directly to
important in order to understand fully the impacts of
another customer located at a different point in the
wheeling options. This paper discusses the effects of power
system. It therefore becomes necessary to wheel the
wheeling on the composite power system adequacy indices
power/energy from the independent power production
of two test systems. The impacts associated with both
facility to the prospective customer over the transmission
intra-system and inter-system power wheeling are illu-
facilities of the local utility. The term 'wheeling' in this
strated. The results presented were obtained using a
paper is used to denote the transmission of electrical
basic" computational tool for composite power system
energy/power from one producer to a second party over
adequacy assessment.
the transmission facilities of a third party. Wheeling in
interconnected systems is denoted as inter-system power
Keywords." interconnections, power wheeling, composite
wheeling. Intra-system power wheeling is used to denote
system adequacy
wheeling of energy/power from NUGs at one part of a
utility system to a customer at another part of the same
system.
I. Introduction Power wheeling transactions are recognized to have a
One of the many possible uses and benefits of inter- definite impact on the utility system losses 2 '3 depending
connection between neighbouring electric power systems upon the system topology, the amount of power/energy
is the opportunity to wheel energy through the transmis- wheeled and the wheeling distance involved. These
sion facilities of one system in order to serve another factors currently form the basis for determining service
system. The most common application of the wheeling charges associated with power wheeling3. Quantification
technique involves the distribution of power from gen- of the reliability impacts of power wheeling is also
erating companies to rel~Ltivelysmall private, municipal important in order to understand fully the impacts of
or public etc. utilities which then market the power. The wheeling options. The effects of power wheeling on
development of large generation facilities in recent years composite generation and transmission system adequacy
is illustrated in this paper. These effects are examined in
Received 14 January 1993; accepted subject to revisions 28 July regard to the individual load point and overall system
1994; accepted 4 October 1994 adequacy indices of two test systems. The single line

143
144 Impact of power wheefing on composite system adequacy. R. Billinton and F. Gbeddy

2 x 40MW ( ~ ) ~) I x 40 MW
1 x 20 MW
1 xlOMW
BUS 1 [ 3 I I
4x 20MW
2x5MW
BUS 2
BUS I~0- 33 " ~ BUS 21 22

I
20 MW
1 6

BUS 3 I I ' I" BUS4

85 MW 40 MW

BUS 6 91 2°~Mw

20 MW
Figure 1. Single line diagram of the RBTS
diagrams of the Roy Billinton Test System (RBTS) 4 and
the IEEE-Reliability Test System (IEEE-RTS) 5 used in
these studies are shown respectively in Figures 1 and 2.

II. Composite system analysis


The modelling techniques used to represent intra-system Figure 2. Single line diagram of the IEEE-RTS
and inter-system wheeling situations have been developed
to suit the structure of the COMREL program 6-9 used
the NUG and the customer other than the transmission
for the analyses discussed in this paper. The COMREL
facilities of the utility, an agreement with the utility is
program is a basic computational tool developed by the
required to use its transmission facilities in order to
Power Systems Research Group at the University of
transport the power from the NUG to the prospective
Saskatchewan for composite power system reliability
customer. When an agreement is reached, the required
analysis. The program is based on the contingency
power to be wheeled will be injected into the utility's
enumeration approach and proceeds by a systematic
power system at the NUG location and then passed on to
selection, evaluation and classification of outage contin-
the customer's load in accordance with the terms of the
gencies according to predetermined failure criteria. The
contract. Apart from a few instances, such as those
level of outage contingency to be considered is pre-
involving small hydro sources which are site specific in
specified in order to minimize the computational require-
nature, NUGs are usually located close to system load
ments. The program is equipped to take corrective or
points. For the purposes of this study, the NUG is
remedial actions, such as generation rescheduling, in
assumed to be introduced at a utility system load point
order to alleviate capacity deficiencies or line overload
which is designated as the 'wheeling source'. The load to
conditions that may be associated with certain outage
be served by the NUG is considered to be located at
contingencies. If a problem persists, load curtailment is
another load point somewhere in the same system. This
effected at appropriate load points as dictated by a load
load point is designated as the 'wheeling sink' in this
curtailment philosophy.
discussion. No additional buses are therefore introduced
The load curtailment philosophy used in the
COMREL program is based on the classification of Intermediate
toad at every system load point as either firm load or Tapped power system Injected
curtailable load. Based on individual load point require- wheeling power wheeling power
ments, curtailable load may represent some percentage of
total load at the bus. In these studies 20% of the load at
I
each system load point is considered to be curtailable
load. If load curtailment is required, curtailable load is
interrupted first, followed by firm load if necessary.

I1.1 Intra-system power wheeling


Load
A NUG facility located in the supply jurisdiction of a
power utility may be required to supply a prospective
customer with electrical energy at another part of the Figure 3. Illustration of power wheeling in inter-
utility system. As there is no direct connection between connected systems
Impact of power wheeling on composite system adequacy. R. Billinton and F. Gbeddy 145

Wheeling Buffer Intermediate equivalent increase in load at the designated wheeling


sink BUS p o w e r system sink. The incremental component of load at the wheel-
ing sink is regarded as firm load representing the
wheeling load to be served. This leads to a reduction in
|
the proportion of curtailable load at that load point, thus
providing appropriate signals that indicate an increase in
the firm component of load at the load point. The
Wheeling Tie Load incremental component of firm load is expected to be
load lines served by the dedicated NUG at the wheeling source.

Figure 4. Interconnection configuration of the wheel- 11.2 Inter-system power wheeling


ing sink Figure 3 illustrates the concept of power wheeling in
interconnected systems.
into the utility system when modelling an intra-system The wheeling source in Figure 3 represents the system
power wheeling situation. Existing system load points are providing the energy to be wheeled whilst the wheeling
modified to accommodate the wheeling transactions. sink represents the system receiving the energy. These two
When a PQ-bus is selected to serve as a wheeling systems are not directly interconnected, but are both
source, its characteristic,; are redefined as a P V-bus connected to a third system situated between them
with scheduled power generation appropriately assigned. which is denoted as the Intermediate Power System
The introduction of a certain wheeling power capacity at (IPS). An agreement with the IPS is required in order
the wheeling source is matched simultaneously with an for its transmission facilities to be utilized to transport the

I n t r a - w h e e l i n g from BUS I lntra-wheeling from BUS1


160
140 ~
-Z~- ~--¢~-- ~ - - Z ~ - - ~ - - - z ~ - - ~ - - ~ 160 _~_.~...~._.Z~_..~.4~/..~_.~._,~
140'
13
120 120 z
= 100 100 #
80 DIEGO
r"

8o ~ H
z 60
/ /
/ u3 60 /
40 -0-0-[3-[]-0-[3-0 Z
W 401 ~-O~E3~D
W
20
,..;~....~---.,~....&-.-~-..& -.-~.-.,~-.-&--.& 20 --.~---.~---X---.~---~---)~---,---X.---.3.--~
OC v . . . . . . . ~ 0' v~ m = ~ t~ i == == v == == ==
0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
Wheeling p o w e r (MW) Wheeling p o w e r {MW)
Intra-wheelincl from BUS 3 n t r a - w h e e l i n g from B U S 2
160 160 ~--~- - -L~--~ - -~--¢~- -~---~ --Z~-~- ~
~r-~- - ~ - ~ - - -Z~--~-." -Z~--~--~--~- --Z~
140 ~ Legend
140
Legend
• BUS 2
120 L
>.
12o ff • BUS2
I00 13 BUS 3
t- 100 // 13 BUS 3
x BUS 4
80
o _Bp_S.S_ 80 ~.12k~E]~'O x BUS 4
60
z
uJ A BUS 6
U3
z
uJ
60 .cro~o~° O BUS 5
uJ 401 -13"13-13-13--13--O--E3-O-E3-13 LU 401 y A BUS 6
20 ~..-,~...~--.~-..~---~..-x-.- ~.-.,~--.x---x zo-_~...~...~...~_..~.._x...x..-x--~ .
0 ~ ~ C ~ {~ ~ - - C" - - j ' - ' ~ ' ' ' ~ - ' ' ~
0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
Wheeling p o w e r (MW) Wheeling p o w e r (MW)
160 Intra-wheeling from BUS 6 160j~ I n t r a - w h e e l i n g from B U S 6
R~
1404
140~
120 12o
>. \
c- I00 ~

80 '\ 80 ',,

z
60 "k 60 ~ \,
uJ ,,=,
w 40t -D- ~ _ n _ r - l _ ~ _ D_ D_O_13 40 +-O-~,, D - D - D - D - D - D - D - °
20 i.~...~.., ...~i..~...x...~...~_._~...x
" 20
~---x.- -x---~-- -x- --x ---x--- x- --x---x.-- -x"
0~, ,., v ,., v w v v ~, ~ ~ 0=
0 5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
Wheeling p o w e r (MW) Wheeling p o w e r (MW)

Figure 5, Variation in EENS with intra-system wheeling Figure 6. Variation in EENS with intra-system wheeling
power to supply wheeling load at bus 2 of the RBTS power to supply wheeling load at bus 3 of the RBTS
146 Impact of power wheeling on composite system adequacy. R. Billinton and F. Gbeddy

wheeling power from the wheeling source to the sink. lines with adequate transmission capacity to transport the
Once an agreement is reached, wheeling power can be entire range of wheeling power considered are assumed to
injected into the IPS and passed on to the wheeling sink at exist for interconnecting the wheeling source and the sink
the respective interconnection points in accordance with with the IPS. The failure rates of these tie lines are
the terms of the contract. The wheeling source is modelled assumed to be zero thus implying 100% availability.
as an imaginary generating bus, which is directly con- Wheeling load is considered to be external to the utility
nected to the IPS. The energy/power to be provided (i.e. system demand in both the intra-system and inter-system
the wheeling power) is assumed to originate from this power wheeling analyses. The wheeling load (or the
imaginary bus which is external to the IPS. The wheeling wheeling component of load) at the sink is therefore not
power is modelled as a 100% available generating unit utilized when computing the system peak load.
located at the wheeling source. The rated capacity of the
unit is assumed to be equal to the contracted wheeling III. S y s t e m s t u d i e s
power. The wheeling sink is also assumed to be an The objective of the analyses in this paper is to examine
imaginary load bus which is connected to the IPS through the impact of wheeling operations on the composite
a buffer bus with tie lines as shown in Figure 4. In an ideal system indices of the power system which renders the
wheeling situation, the wheeling sink should be able to wheeling service. In the intra-system wheeling analysis,
receive all the energy/power contracted for wheeling; this refers to the local utility's power system whilst in the
hence curtailment effects occurring in the IPS should inter-system wheeling analysis this refers to the inter-
not affect the sink. However, this condition is difficult mediate power system. The DC load flow feature of the
to satisfy in all situations. The configuration shown in COMREL program was used as the network solution
Figure 4 is used to connect the wheeling sink to the IPS as technique during the power wheeling studies in order to
it minimizes the load curtailment impacts experienced at avoid the problem of accounting for system losses arising
the wheeling sink resulting from outage events occurring from power wheeling operations. Outage contingency
in the IPS. The entire wheeling load at the sink is enumeration was limited to independent overlapping
considered to be firm load and it is assumed to be outages up to the 4th level for generating units and up
always equal to the input power from the wheeling to the 3rd level for transmission lines (or transformers).
source. The percentage of curtailable load at the wheeling Combined generator-line outages involving up to two
sink is therefore specified to be zero and load curtailment generating units and one line, and one generating unit
actions are confined as much as possible to the IPS. Tie and two lines were also considered.

Load points
I n t r a - w h e e l i n g from BUS 8=>16
I n t r a - w h e e l i n g from BUS 16 =>8 in the Load points.
800 n o r t h region 8OO in the
--~- --ZX--6-- - ~ - - ~ " .Z~--~- - -Z~--~-- -~ Legend .._~...~._~.. _~._..~. _.&.--~ - - ~ - "-6 n o r t h region
7O0 700,
• BUS 13 Legend
600 600
>- [ ] BUS 14 • BUS 13
"- 500 -- 500
• BUS 15 ...0..0_-0__0.--0---0--0--0--0--0 r l BUS 14
..-•- - • . - -•-- -•----•- - 0 - - • - - • " - • - " • .~ 4004
400 l O BUS 16 • BUS 15
Ch
z 300 A BUS 18 300 O BUS 16
UJ m I I m mm m m I I |
x BUS 19 200, L A BUS 18
200~._.;_..v_v.__v..-n-v.-~.-.~:::y:~
_ . . ~ . . . . X . - - - K - - -" X " " ~2 BUS 20 x BUS 19
I00
~ _..~.._Q-
~ - ~ = -O-.-O-.-O---O-.O---O-'-O
~=~-_=~-_.-~_.-~.-.~..m v BUS 20
01
0 10 20 30 40 50 60 70 80 90 100 10 20 30 40 50 60 70 80 90 100
Wheeling power (MW) Wheeling power (MW)
Load points
Load points
in the
in the
south region
south region
60 r • Legend
Legend
A BUS1
50 x--x A US.____1
B
+ BUS 2 II~IL~_~:~:_~__ ~_~=u__._ + BUS 2
40~--+--*=
i~_m...m.--m...m.-.m---m---m-m----
- - ~m x BUS 3 4o~..i...m--m..m'-71zT..l.-.l~l=lz: x BUS 3
o Bu;- 30 .................. 0 BUS 4
V BUS 5
~7 BUS 5
• BUS 6
,,,,,, 20 • BUS 6

• BUS 8
• BUS 8
O BUS 9
O BUS 9
0 10 20 30 40 50 60 70 80 90 100 [] BUS I0 0 10 20 30 40 50 60 70 80 90 100
Wheeling power (MW) [3 BUS I0
Wheeling power {MW}

Figure 7. Variation in EENS with intra-system wheeling F i g u r e 8. V a r i a t i o n in EENS w i t h i n t r a - s y s t e m w h e e l i n g


power f r o m b u s 16 t o b u s 8 o f t h e I E E E - R T S power f r o m bus 8 t o b u s 1 6 o f t h e I E E E - R T S
Impact of power wheeling on composite system adequacy."R. Billinton and F. Gbeddy 147

Results of the analyses utilizing the RBTS and the considered to be continuously available in the same
IEEE-RTS respectively as the study systems are pre- amount throughout the study period.
sented and illustrated. In the studies performed, up to
50 MW and 100 MW of power was wheeled through the IV. Discussion of results
RBTS and the IEEE-RTS respectively• This produces
different impacts on the load point and the overall IV.1 Load point indices
power system adequacy indices ~. The impacts on the
Expected Energy Not Supplied (FENS) indices at the IV.1.1. Intra-system wheeling results
various load points of the test systems are discussed Figure 5 shows variations in the FENS indices at various
below. Additional indices such as the probability and load points when up to 50 MW of power is wheeled from
frequency of load point failure were also determined in different parts of the RBTS to supply wheeling loads
these studies• The effects on the severity index of both located at bus 2 in the system.
test systems are also considered to illustrate the impacts It can be observed from Figure 5 that the inadequacy
on overall power system adequacy. All the results indices for most of the RBTS load points remained
shown are annual indices which reflect the variations virtually unaffected throughout the power wheeling
in load level over a year. A 4-step (10% load step) load scenario in most cases studied• This shows that the
model was used for the RBTS analysis and a 7-step (5% RBTS is able to accommodate the range of wheeling
load step) load model was used for the analysis of the power to bus 2 without causing any significant adverse
IEEE-RTS. The wheeling load was, however, kept impacts on adequacy at the system load points. Wheeling
constant at all load levels as its dedicated supply was from load points in the southern section of the RBTS to

I n t e r - w h e e l i n g from BUS I I n t e r - w h e e l i n g from BUS 1


160 160 _z~..Zy_~ . 4 ~ _ ~ . . . Z ~ . ~ _ ~ . . ~
140' 140 ~ /
t. 120
lOO (- 100 ,,E]/
,£3
~ so 3; 80 /D~
ffl
z 6O / t/3
z 60 .d
.~3. ~_.o__~_ 4:~-o-a3' "' j 3 ~ j 3-
w 40( LU
401
20 --~--x---~---~---~---~---~---x--~---x 20 _.X.. -X- --X-- -X- - -X- - -X--'X- - "X" - -X- - -X

0 5 I0 15 20 25 30 35 40 45 50 L0 5 10 15 20 25 30 35 40 45 50
Wheeling power (MW) Wheeling power (MW)
I n t e r - w h e e l i n g from BUS 3 i n t e r - w h e e l i n g from BUS 2
160 . 160 ~.~.
~-~ - ~X---~---£~-~- - -~---~- -~--~- -~
140 ~ Legend 140 ' -~.--Z~,--~.--ZX---~---~--~-- .A
Legend
~. 120 • BU.S 2 120 I~
>.
• BUS 2
100 o B_U__S_~ 100 P"
o B_U_S_~
80 x BUS 4 80
¢n 60 O ~ rl~D~13" ,~ x _B_US_~_
u~ 60 O BUS 5
Z . . . . .
W
O _B.U_S.5_
w 401 " "O-d3._D._E3__D..O_.O_.O_D A BUS 6 w 401 /
X..-X A BUS 6
20 i--x---x--.~_._~...~...~...~...~...~..x 20 .x._.x_..x..-x---x- --x-- - x " ,3:)
Op_i.~--r-'--.---#r~r-~...- .~ . . 1,, .
0 .5 10 15 20 25 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
Wheeling power (MW) Wheeling power (MW)
160 I n t e r - w h e e l i n g from BUS 6 160 I n t e r - w h e e l i n g from BUS 6
140 ~ 140 z
~. 120 ~ 120
-- 100 ", 100 "

60 ', tn 60 •
Z
w 40 " "O-43-43- -O--O- -O--C]--(3 Zww 401 -t-I-~q-o-E] ---E]-O-O-E]'-E]-O
20 -....
; ¢- ' " x:"\ "'~'-- ~-'-':~'-)1----~''~'-"x-'-~. 20 i..~..-~--~- -~---x---x---x --x---x- --x
0 ~- . . . . . . . . . . . . . 0
0 5 10 15 20 ;!5 30 35 40 45 50 0 5 10 15 20 25 30 35 40 45 50
Wheeling power (MW) Wheeling power (MW)

Figure 9. V a r i a t i o n in EENS w i t h i n t e r - s y s t e m w h e e l i n g Figure 10. V a r i a t i o n in EENS w i t h the i n t e r - s y s t e m


p o w e r for w h e e l i n g o p e r a t i o n s w i t h the sink c o n n e c t e d w h e e l i n g o p e r a t i o n s w i t h the sink c o n n e c t e d to b u s
to bus 2 of t h e R B T S 3 of the R BTS
148 Impact of power wheeling on composite system adequacy. R. Billinton and F. Gbeddy

the northern parts of the system generally assures a more considerable increase in both the number of load curtail-
effective redistribution of power flow in the RBTS net- ment events and the amount of load curtailed at bus 3.
work. This accounts for the system's ability to cope with Similar observations can be made from Figure 6 which
the entire range of wheeling power capacity considered. shows the impacts on EENS indices at the load points
Approximately 90% of the RBTS load is located in the when intra-system power wheeling operations are carried
southern section of the system. Wheeling power imports out to supply wheeling loads located at bus 3 of the
in the south can therefore be used effectively to supply the RBTS.
loads in that part of the system with minimum transmis- The impact on the indices when the wheeling opera-
sion requirements. This reduces, to some extent, the tions involve only buses within the heavily loaded section
dependence of the southern section of the system on of the RBTS are observed to be relatively minimal
conventional generation supplies which have to be trans- compared with when the wheeling loads are supplied
ported from the north (i.e. from buses 1 and 2) over directly from bus 2, a conventional generation supply
transmission facilities which are exposed to the risk of location in the north. Wheeling from the north section of
failure. Meanwhile the wheeling load located in the the RBTS is generally not suitable, because the extra
northern section of the RBTS is also supplied effectively transmission capacity available in that part of the system
from the conventional generation sources located in that is not adequate to transport the increased supply require-
part of the system. Wheeling from bus 6 produces sig- ments of the south region effectively (created by the
nificant drops in the value of the indices at that load added wheeling load) from the generating facilities in
point, because the wheeling supply made available at the the north. In all the cases shown, the load point indices
bus is used to supplement utility supply both during at bus 6 remained virtually unaffected throughout the
normal system operation and when the load point is entire wheeling scenario except when the wheeling power
isolated from the conventional generation sources. Sup- is from that bus. This is expected because wheeling
plying a wheeling load located at bus 2 from additional operations beyond the radial link do not address the
generation supplies provided at the swing bus (i.e. bus 1) isolation problems basically responsible for inadequacy
results in a deterioration in adequacy at bus 3 where at the bus.
about 46% of the RBTS load is located. This effect Variations in the EENS indices at the load points of the
becomes most significant when the wheeling load intro- IEEE-RTS when up to 100 MW of power is wheeled from
duced exceeds 35MW, at which stage more frequent bus 16 (in the north region) to bus 8 (in the south region)
swing bus overload conditions experienced cause a are shown in Figure 7. Similar results obtained for

I n t e r - w h e e l i n g from BUS 17=>8 I n t e r - w h e e l i n g from BUS 8=>17


Load points Load points
800 in the 8OO in the
_ . ~ . ~__~__ _z~__~. _z~--~- - ~ - - ~ - - ~ north region north region
700~ 7OO __~.. _~r_~__~__~_..~5..-~- - - ~ "~z~'-'~
Legend Legend
600 600
• BUS 13 • BUS 13
r-I BUS 14 500
- ~ ~ ~ ~ n BUS 14
• BUS 15 400 • BUS 15
U3 u3
z 300 O BUS 16 z 300 O BUS 16
I.U i i m m lm mm mm llm
LU A BUS 18
_..~....s~-.-~....J~--'>-l~ A BUS 18
• m -- I -- I mm iN --
200 200 r.__K3....~_-~.._~
- .... .-- x BUS 19 x BUS 19
100 100
~7 BUS 20 BUS 20
0 0
0 102030405060708090100 I020304050607080901Q0
Wheel!ng power (MW) Wheeling power (MW]
Load points
in the Load p o i n t s
south region in t h e
south region
60501 AqL-, Legend Legend
~0~0~ A BUS____Z
A BUS 1
+ BUS 2
~---~'~--$~ ÷. . . . -- l .l.-l-I I.. + BUS 2
4omlm...m..m.l...m....im...m..m . . . . x BUS 3 >. 40 . Ii_.m...i..a.-a.--m--- m --m-'m'a
x _B_US_]
.c O BUS 4
30 : ~ A~...~...~...4j~_~ v BUS S O BUS 4
v _Bp..S__S
u~
Z 20
• BUS
-...........6 Z 20
UJ LU • .B...U...S...)
'" @ _B_U_.S...7 LU

10
¢' _BUS.._7
IO • BUS 8
• BUS 8
° ) ,T q 3i ~ , O . , I- o - ,I 4 3 1I - - oI - - oI = ' OI - ~I i
o BUS 9
o o BUS 9
0 102030405060708090100 D BUS 10 0 10 20 30 40 50 60 70 80 90 100
Wheeling power (MW) D BUS I0
Wheeling power (MW,I

Figure 1 I . V a r i a t i o n in EENS w i t h i n t e r - s y s t e m w h e e l - Figure 1 2. V a r i a t i o n in EENS w i t h i n t e r - s y s t e m w h e e l -


ing p o w e r f r o m bus 17 to bus 8 of the IEEE-RTS ing p o w e r f r o m bus 8 to bus 17 of I E E E - R T S
Impact of power wheeling on composite system adequacy. R. Billinton and F. Gbeddy 1 49

wheeling in the opposite', direction are also shown in IV.1.2. Inter-system wheeling results
Figure 8. Figures 9 and 10 show variations in the EENS indices at
It can be observed from Figure 7 that wheeling from the load points when up to 50 MW of power is wheeled
bus 16 in the north to bus 8 in the south region of the through the interconnected RBTS with the wheeling sink
IEEE-RTS causes a considerable deterioration in ade- connected to bus 2 and to bus 3 respectively. Similar
quacy at several load peints, particularly in the south results for the IEEE-RTS are shown in Figures 11 and 12
region. This is expected, because as noted in Reference 1, when up to 100 MW of power is wheeled through the
the south region is a net generation-importing area and is system with buses 8 and 17 serving as the interconnection
highly dependent on sul~plies from the north-eastern points of the wheeling source and the sink.
parts of the IEEE-RTS. ]Introducing a wheeling load in It can be observed that the results shown by these
the south region therefore increases that region's depen- figures are fairly similar to those obtained in the case of
dency on supplies from the north and consequently intra-system wheeling. The worst impacts in the case
increases the pressure on transmission facilities respon- of the RBTS are obtained when the wheeling source is
sible for transporting the increased supplies to the (sOuth) connected to any of the two generation buses in the
region. On the other hand, the effects of wheeling in the northern part of the system. In the case of the IEEE-
opposite direction from bus 8 to bus 16 as shown in RTS, the worst wheeling impacts result when the wheeling
Figure 8 are observed to be generally minimal and power has to be tapped from the net generation-importing
virtually negligible at a number of load points• This (south) region. It can therefore be concluded that the
occurs because introduction of a wheeling source in the provision of additional generation supplies to satisfy
south region makes generation supplies more readily effectively the increased demand resulting from an intro-
available to the region a:ad reduces the region's depen- duced wheeling load is significantly influenced by the
dence on supplies from the north. Generally, adequacy availability of sufficient composite generation and trans-
at load points directly bavolved in the wheeling oper- mission capacity in the system, and this is reflected in the
ation are the ones most affected, although the effects calculated reliability indices.
can spread to immediate neighbouring load points as
well. Whilst an improvement in adequacy is noticed at IV.2 System indices
the wheeling source, the wheeling sink and the load
points surrounding it generally experience a deterio- IV.2.1. Intra-system wheeling results
ration in adequacy. Figure 13 shows variations in the overall system severity

(a) I n t r a - w h e e l i n g to BUS2 (a) l n t r a - w h e e l i n g to BUS8

52
•~ 9Ol- . _ _ - ~ "~ sl From
E° 8o":, ....... ~,--~-..l..~.mm-m-.ll ~o so 17 BUS 16
70 " ~ 49 • BUS 19
• ~_V.s.~g
x 50 " x 47

45 I p ~ ' - m - - i - ml" ~ _ _ i - - 0 " ~ " -


"E 20 ~I...t..41I~t_H_.I__ 1 Wheeling
I0 , I , , , , ' ' ' I ~ 4 3 ~
u~ 5 I0 15 20 ;!5 30 35 40 45 50
From ~ 0 10 20 30 40 50 60 70 80 90 100
A BUS 1
Wheeling power (MW) Wheeling power (MW)
x BUS 2
[] _B_U__S__3
(b) Intra-wheeling to BUS3 (b) I n t r a - w h e e l i n g from BUS 8
• BUS 5
~" 210 I ~"
o 53
• BUS 6
52
• 170 "T= 51
150 50 To
130 1 ~ . x i x 49 [ ] BUS 16
110 ~ ~ 48 • BUS 19
_~.ICI
41,
+ ".-..e
x 901 ~ - l l - -•- -•- -I I - - - ~ - ~ "~ 46 • .B..U_.S..2.0_
"~ 70 -'.
s0 ~'. ~ 4s n

I I I I I I I I I I
>o io , , ",~-~~P-i~~F-+,e-9, ~ 43
cy~ 5 10 15 20 25 30 35 40 45 50 10 20 30 40 50 60 70 80 90 100
Wheeling p o w e r MW) Wheeling power CMW)
Figure 1 3. Variation in severity index w i t h intra-system Figure 1 4. Variation in severity index w i t h intra-system
w h e e l i n g p o w e r within the RBTS w h e e l i n g p o w e r within the IEEE-RTS
1 50 Impact of power wheeling on composite system adequacy. R. Billinton and F. Gbeddy

index when up to 50MW of power is wheeled from tions considered are observed to be sensitive to the
different locations to supply wheeling loads located at proximity of the wheeling source and sink locations to
buses 2 and 3 of the RBTS respectively. the swing bus (i.e., bus 23). Capacity deficiencies are
It can be observed that wheeling from and to different noted to be accountable for the bulk of inadequacy in
parts of the RBTS produced different and varying degrees the IEEE-RTS TM and these frequently lead to swing bus
of impact on overall system adequacy. A slight drop in overload conditions mainly affecting load points,
the value of the severity index is noticed when wheeling is particularly in the north region ~. Hence introduction
done from most parts of the system to supply a wheeling of a wheeling source close to the swing bus tends to
load at bus 2. This indicates slight improvements in suppress the occurrence of swing bus overload condi-
overall system adequacy compared with the level of tions, thus prOducing a considerable improvement in
system adequacy that existed prior to the start of the overall system adequacy. When the wheeling source is
wheeling operations. Wheeling operations involving only located farther away from the swing bus or the wheeling
buses located in the heavily loaded southern section also load is introduced close to the swing bus, reduced levels
produce similar or no effects on the severity index. of improvement in overall system adequacy are obtained.
Wheeling from either bus 1 or bus 2 in the north is Referring to the single-line diagram of the IEEE-RTS
generally undesirable as this results in a deterioration in shown in Figure 2, bus 20 is directly connected through
the level of overall system adequacy. As noted earlier, this a double circuit to bus 23 which served as the swing
condition is due to capacity limitation problems experi- bus in these analyses. Bus 19 is farther away from the
enced by the lines responsible for bulk power movement swing bus than bus 20, and bus 16 is still farther
from the north to the south. The lines are therefore away from it than the previous two buses. It can there-
unable to accommodate effectively the entire range of fore be seen from Figure 14a that relatively lower severity
wheeling power imposed on the RBTS. index values are obtained as the wheeling source is
The variations in overall system severity index when up introduced nearer to the swing bus. Introduction of
to 100MW of power is wheeled from and to different wheeling loads farther away from the swing bus also
parts of the IEEE-RTS are shown in Figure 14. produces similar effects on the system severity index as
The impacts obtained for the various wheeling opera- shown in Figure 14b.

(a) Sink connected to BUS 2 (b) Source connected to BUS2


i) System load up by 10% i) System load up by 5%
170I 215 / ii

•-.E 160
\ ~.-- ; ¢" 17s
.>-IF= 15s ~'~
,,'/ E ~

>~ ~,
> ~
~ 13s
I~].,,B~"
.,~"
~ 115
j •
1451
o l'S ;o ~s ~o ~s ~0 ~s ~o
i'o 9s- ~ io 1's 2'0 2's 3o ~s 40 .s 5o
Wheeling power (MW) Wheeling power (MW)

ii) System load up by 5% ii) Normal system load


11o 200 Legend
Legend
"o~ 180 / !
~".i.-, lOS~ • Stand-alone • Stand-alone
RBTS
t-- G
•~.F= 160 i
! / RBTS
.~ .E IOO [] Wheeling [] Wheeling
•~ E 140 to BUS 3
from BUS 3
E

>~ 9o
95
x Wheeling
from BUS 5
>~. 120
~ 100
...~.~_.~_~..~.~r x Wheeling
t_o_B_US__S_
85 ., ,,,,, ,.,~, 80, | i i

s 1o is 2% ~s ~o ~s ~o is •50
5 10 15 0 5 30 35 40 5 0
Wheeling power (MW) Wheeling power (MW)

iii) Normal system load iii) System load down by 5%


100 19° F II
x~'~ 1701 /1
-o ~ 150[_ 71
•- ¢ 91
~'F= 13o t / i
"i~
m ~ ~
80
75 70 ~ • I , , , , • • • J-
5, ~
10 i~5 2 ~0 25
~ 30
~ , 40
35 I 45
~ 50 0 5 10 15 20 25 30 35 40 45 50
Wheeling power (MW) Wheeling power (MW)

Figure 1 5. Comparison of severity index variations w i t h inter-system w h e e l i n g p o w e r t h r o u g h the RBTS operating


at different system peak load levels
Impact of power wheeling on composite system adequacy: R. Billinton and F. Gbeddy 1 51

IV.2.2. Inter-system w h e e l i n g results system adequacy and in some cases may have relatively
Severity-index variations,; for wheeling operations in little effect on the indices of the system rendering the
interconnected systems ;ire generally similar to those wheeling service. The impact on the indices due to a
obtained for intra-system wheeling. Figure 15 shows the specific wheeling operation depends largely on the exist-
effects on the system severity index when wheeling opera- ing composite generation and transmission system con-
tions involving bus 2 are undertaken by the RBTS when figuration of the utility system.
operating at three different peak load levels. The different The studies clearly illustrate that it is extremely impor-
peak load levels were obEained by varying load propor- tant to assess quantitatively the reliability implications
tionally at all the system load points. Similar results were of wheeling operations prior to establishing formal
obtained for the analysis utilizing the IEEE-RTS as contracts. The investigations should cover detailed
the IPS. These analyses were performed to determine the examination of load point and overall system adequacy
relative magnitude of the effects associated with different prior to wheeling in order to provide a datum against
wheeling options at different IPS peak load levels. The which to assess the implications of possible wheeling
severity index value for the stand-alone system at each options.
load level served as the datum for these comparisons.
It can be observed from Figure 15a that the severity Vl. References
index values obtained beyond 15 MW of power wheeling
through the RBTS are lower than the corresponding 1 Billinton, R and Gbeddy, F 'Effects of non-utility generators
values for the stand-alone system when the RBTS is on composite system adequacy evaluation' IEEE/PES
Summer Meeting Seattle, WA, July 1992, Paper 92 SM
operating at any of the peak load levels considered. 442 4 PWRS
This is an indication that wheeling beyond 15 MW of
power for this (wheeling) option is favourable to the 2 Mukerji, R, Neugebauer, W, Ludorf, R P and Catelli, A
RBTS. A comparison of the adequacy gains resulting 'Evaluation of wheeling and non-utility generation (NUG)
from the wheeling transactions shows an increase in the options using optimal power flows' IEEE Power Eng. Rev.
Vol 12 No 2 (1992)
adequacy gains at higher peak load levels. It can therefore
be concluded that wheeling options that are favourable to 3 Noyes, RGenerationofsteamandelectricpowerNoyesData
the IPS generally tend to be more attractive and beneficial Corporation, Park Ridge, New Jersey (1978)
when the IPS is subjected to a higher system load stress. 4 Billinton, R, Kumar, S, Chowdhury, K, Chu, K, Debnath, K,
On the other hand, Figure 15b shows typical results of Goel, L, Khan, E, Kos, P, Nourbakhsh, G and Oteng-Adjei, J
wheeling transactions whose impacts adversely affect the 'A reliability test system for educational purposes--Basic
level of adequacy in the IPS throughout the wheeling data' IEEE Trans. Power Syst. Vol 4 No 3 (1989) pp 1238
scenario studied for the interconnected RBTS. These 1244
wheeling operations are considered to be unfavourable 5 IEEE Committee Report 'IEEE reliabilitytest system' IEEE
wheeling options for the IPS. It can be observed that the Trans. Power Appar. Syst. Vol PAS-98 (1979) pp 2047-2054
severity index values shown in these figures increase 6 Billinton,R 'Composite systemadequacy assessment--The
steadily with wheeling power, and that they consistently contingency enumeration approach' IEEE (Power
remain above the corre,,~ponding values for the stand- Engineering Society) Tutorial Course, Course Text 90EH
alone system. The rate,, at which the severity index 311-1-PWR: Reliability assessment of composite generation
increases is generally not uniform, but can be observed and transmission systems (1989) pp 29-35
to be higher at higher peak load levels. This is expected 7 Medieherla, T K P 'Reliability evaluation of composite
because when the IPS system demand is increased, the generation and transmission systems' Master's thesis,
effect of transmission capacity constraints on wheeling University of Saskatchewan, Saskatoon (1982)
operations become more intensified and this produces
higher severity index values. 8 Kumar, S 'Adequacy evaluation of composite power
system' Master's thesis, University of Saskatchewan,
Saskatoon (1984)
V. Conclusions 9 Khan, E 'Fast adequacy assessment of composite power
The concept of quantitatively assessing the impact of systems' Master's thesis, University of Saskatchewan, Sas-
katoon (1988)
wheeling on composite power system adequacy is dis-
cussed in this paper. It has been shown by utilizing the 10 BiUinton,R and Allan, R N Reliability evaluation of power
COMREL program that a wide range of impacts on load systems Plenum Press, New York & London (1984)
point and overall system indices is produced by different 11 Billinton, R and Li, W 'Hybrid approach for reliability
wheeling options. The reliability impacts associated with evaluation of composite generation and transmission sys-
wheeling options can eit]her lead to an improvement or a tems using Monte-Carlo and enumeration technique' lEE
deterioration in the load point adequacy and overall Proc. C, Vol 138 No 3 (1991) pp 233-241

You might also like