Professional Documents
Culture Documents
Authorized licensed use limited to: Centro Universitário Fei. Downloaded on March 08,2022 at 19:53:52 UTC from IEEE Xplore. Restrictions apply.
POWERENG 2009 Lisbon, Portugal, March 18-20, 2009
entire facility load and the excess is delivered to the public aim a number of simulations were carried out. The system
grid. behavior for the critical conditions is the main subject of this
--A portion of the facility load is supplied by the local work.
generation and the remainder is imported from the utility.
A. Industrial Plants Delivering Power to the Public
II. SYSTEM DESCRIPTION Grid
A . One line Diagram of the Study System For this generic scenario, the critical operating condition
results when the three generators of each industrial plant are in
A simplified one line diagram of the industrial power service supplying the entire demand of each system and
system is shown in figure 1. To prevent releasing any delivering 45 MW to the public grid, 20 MW from plant C and
proprietary information of the study system, both the industrial 25 from plant NP. In this case, after the loss of the
plants and their buses have been renamed. interconnection to the public grid the following two post-
disturbance conditions were considered:
A.1 Both industrial plants remain connected.
A.2 Industrial plants are separated immediately after the
loss of interconnection with the public grid.
The above post-contingency conditions were considered to
assess the benefits of the interconnection between the
electrical power systems of the industrial plants. Since the
interconnection of the power systems of the two industrial
plants is rather new and the interconnected system
performance was still under evaluation, post-contingency
condition A.2 reproduces the way in which these industrial
systems were formerly operated.
B. Industrial Plants Importing Power from the Public
Grid
For this generic scenario, a critical operating condition
results for the following operating conditions:
Fig.1 Simplified one line diagram of the Industrial Power B.1 Demand of industrial plant C is 36 MW, two of its
System. generators are out of service, the one in service is at full load
and supplies 18 MW, the other 18 MW are imported from the
public grid. The demand of industrial plant NP is 40 MW, it is
A.2 System Component and Loading Conditions entirely supplied by its three generators.
The study system is composed by two industrial plants,
initially designed to be operated as isolated systems. Each
industrial plant contains three generators. The three generators IV. DYNAMIC SIMULATION RESULTS
of Plant C are gas-turbine type and their governor systems Due to space constraints, only the behavior of the
operate in isochronous mode. On the other hand, in Plant NP generators rotor angle, terminal voltages and system frequency
one is gas-turbine type and the other two are steam-turbine, variables is shown.
the governor systems of the generators operate in droop mode.
For the two general operating conditions described in the
previous section of the paper the loading conditions of Plant C IV.1 Simulation results for Generic Scenario A
were 33 MW and 36 MW, while the loading conditions of The dynamical performance of the generators rotor angle,
Plant NP were 47.7 MW and 40 MW, when delivering power figures 2 (both industrial plants remain connected after de
to and importing power from the public grid respectively. disturbance condition A.1) and 3 (the electrical systems of the
industrial plants are separated immediately after the
III. STUDY OBJECTIVES disturbance condition A.2), indicate that the generators of both
Each of the industrial plants shown in de one line diagram industrial plants remain in synchronism after the sudden loss
operated for several years as isolated systems. Since the two of the industrial-utility tie. At first glance, figure 3 suggests
systems are physically close and the amount of on-site that the system is unstable, since the magnitude of the rotor
generation in each one is approximately twice the amount of angle of some generators exhibits a monotonically grown. The
the maximum load level, it was decided to interconnect them rotor angles with this trend are associated with the three
as shown in figure 1. The main goal of the studies on the generators of industrial plant NP. However, the transient
interconnected system was to assess its performance, after the stability condition of a power system is determined by the
interconnection with the public grid is suddenly lost. With this difference between the rotor angles of the system generators.
It is, if the angular difference between any two generators in
480
Authorized licensed use limited to: Centro Universitário Fei. Downloaded on March 08,2022 at 19:53:52 UTC from IEEE Xplore. Restrictions apply.
POWERENG 2009 Lisbon, Portugal, March 18-20, 2009
481
Authorized licensed use limited to: Centro Universitário Fei. Downloaded on March 08,2022 at 19:53:52 UTC from IEEE Xplore. Restrictions apply.
POWERENG 2009 Lisbon, Portugal, March 18-20, 2009
482
Authorized licensed use limited to: Centro Universitário Fei. Downloaded on March 08,2022 at 19:53:52 UTC from IEEE Xplore. Restrictions apply.
POWERENG 2009 Lisbon, Portugal, March 18-20, 2009
V. CONCLUSIONS
The results presented in the paper highlights the importance
of dynamical studies on industrial power systems if they
become interconnected with the public grid or to assess the
benefits of interconnecting two isolated industrial power
systems.
For the study system considered in the paper, it was found
that the negative effects on the system frequency of the NP
industrial plant, following the sudden loss of the industrial-
utility tie when the industrial plants supply electrical power to
the power grid are greatly attenuated if the electrical systems
of the industrial plants remain connected after the disturbance.
For an acceptable system operation after the loss of the
industrial-utility tie when one of the industrial plants import
electrical power from the public grid a load shedding scheme
is needed. The design of any load shedding scheme should be
evaluated using transient stability simulations for a number of
operating conditions.
REFERENCES
[1] Paine David M., “Increasing the Electrical Output of a Cogeneration
Plant”, IEEE Trans. On Industry Applications, vol. 38, no. 3, pp. 726-
735, May/Jun 2002.
[2] Shilling Stanley R., “Electrical Transient Stability and Underfrequency
Load Shedding Analysis for a Large Pump Station”, IEEE Trans. On
Industry Applications, vol. 33, no. 1, pp. 194-201, Jan/Feb 1997.
[3] Smith Thomas P., “Power System Studies for Cement plants”, IEEE
Industry Applications magazine, pp. 56-65, July/August 2007
[4] Dommen Mathew P. and Kohler Jeffery L., “An Improved Model for
Analyzing Industrial Power Systems”, IEEE Trans. On Industry
Applications, Vol. 31, No. 5, pp. 1140-1146, September/October 1995
[5] Dunki-Jacobs J. R. and Davis Chet E., “An Argument and Procedure for
Conceptual Power System Design Studies”, IEEE Trans. On Industry
Applications, Vol. 30, No. 2, pp. 253-261, March/April, 1994
[6] Rosales S. I., López V. J. J., García P. J., Robles P. E., García A. D. Y
Guzmán C. B., “Interconexión de centros industriales con la red eléctrica
del servicio público”, Boletín IIE, pp. 42-48, enero-febrero 2000.
[7] Clark H. K. and Feltes J. M., “Industrial and Cogeneration Protection
Problems Requiring Simulation”, IEEE Trans. On Industry Applications,
Vol. 25, No. 4, pp. 766-775, July/August, 1989
[8] IEEE Recommended Practice for Industrial and Commercial Power
Systems Analysis (IEEE Brown Book), IEEE Std 399-1997.
[9] Kundur P., “Power System Stability and Control”, Mc Graw Hill, 1994.
483
Authorized licensed use limited to: Centro Universitário Fei. Downloaded on March 08,2022 at 19:53:52 UTC from IEEE Xplore. Restrictions apply.