LSIS Co., Ltd.

LS Tower, LS-ro 127, Dongan-gu, Anyan-si,Gyeonggi-do, South Korea

No. : LS DCC –200212–IBT – 004 February 12, 2020


Eng. Rahman, J. Askar
DCC Project Manager, Technical Office, MoE, IRAQ
--------------------------------------------------------------------------------------------------------------------------------------

Subject: Provisional Acceptance Certificate Document


_DCC Project Contract Appendix No.(2) dated Jul 23, 2019

Dear Mr. Rahman,

With the subject above, We, LSIS hereby submits Handover Certificate for Babil,
Wasit and Najaf. You are kindly requested to officially distribute the Hand-Over
Certificate in each Gov.

In addition to this, Provisional Acceptance Certificate which shall be signed by you


is attached. Your kind attention in this regard would be appreciated.

Encls.
1. Hand-Over Certificate for Babil, Wasit and Najaf
2. Provisional Acceptance Certificate for MoE HQ

Yours faithfully,
CHO, Nam Hyuk

General Manager / Representative Iraq branch office


LSIS Co., Ltd. Korea

LHY
Republic of Iraq
Ministry of Electricity
DCC Project

Hand-Over Certificate
No:
Date: / /2020

Contract Name: Distribution Control Center Contract – IRAQ

Dear Sir,
Pursuant to Definition 1. Provisional Acceptance Certificate of Distributing Control
Center in Babil, Wasit and Najaf entered into between LSIS and the Employer No.
[6/2012] dated [17/12/2012], we hereby notify you that the Functional Guaranties
of the following part(s); SCADA, RTU and Communication System were satisfactorily
attained on the date specified below and Completion Report of Availability Test
approved by MoE.

Date of Operational Acceptance: / / 2020 in Babil Governorate

This letter does not relieve you of your obligation to complete the execution of
SCADA, RTU and Communication system in accordance with the Contract nor of
your obligation during Warranty Period for one year with the attached punch list as
soon as practicable.

Attachments: Punch List dated Jun 17 and Sep 2, 2019

Truly yours,

Name
Position
Signature

--------------------------------------------------------------------------------------------------------------
Received by (if necessary)
Name
Position
Signature
Republic of Iraq
Ministry of Electricity
DCC Project

Hand-Over Certificate
No:
Date: / /2020

Contract Name: Distribution Control Center Contract – IRAQ

Dear Sir,
Pursuant to Definition 1. Provisional Acceptance Certificate of Distributing Control
Center in Babil, Wasit and Najaf entered into between LSIS and the Employer No.
[6/2012] dated [17/12/2012], we hereby notify you that the Functional Guaranties
of the following part(s); SCADA, RTU and Communication System were satisfactorily
attained on the date specified below and Completion Report of Availability Test
approved by MoE.

Date of Operational Acceptance: / / 2020 in Wasit Governorate

This letter does not relieve you of your obligation to complete the execution of
SCADA, RTU and Communication system in accordance with the Contract nor of
your obligation during Warranty Period for one year with the attached punch list as
soon as practicable.

Attachments: Punch List dated Jun 17 and Sep 2, 2019

Truly yours,

Name
Position
Signature

--------------------------------------------------------------------------------------------------------------
Received by (if necessary)
Name
Position
Signature
Republic of Iraq
Ministry of Electricity
DCC Project

Hand-Over Certificate
No:
Date: / /2020

Contract Name: Distribution Control Center Contract – IRAQ

Dear Sir,
Pursuant to Definition 1. Provisional Acceptance Certificate of Distributing Control
Center in Babil, Wasit and Najaf entered into between LSIS and the Employer No.
[6/2012] dated [17/12/2012], we hereby notify you that the Functional Guaranties
of the following part(s); SCADA, RTU and Communication System were satisfactorily
attained on the date specified below and Completion Report of Availability Test
approved by MoE.

Date of Operational Acceptance: / / 2020 in Najaf Governorate

This letter does not relieve you of your obligation to complete the execution of
SCADA, RTU and Communication system in accordance with the Contract nor of
your obligation during Warranty Period for one year with the attached punch list as
soon as practicable.

Attachments: Punch List dated Jun 17 and Sep 2, 2019

Truly yours,

Name
Position
Signature

--------------------------------------------------------------------------------------------------------------
Received by (if necessary)
Name
Position
Signature
Republic of Iraq
Ministry of Electricity
DCC Project

Provisional Acceptance Certificate

According to the contract No. 06/2012 dated Dec 17, 2012 and
Article 1.Definitions “PAC shall mean the ‘Certificate’ to be issued
by the Employer on or about the Completion Date accepting the
completion of Availability Test and it shall be issued 15 days after
the availability test”, MoE confirms to issue the PAC to the
contractor (LSIS) for 3 DCCs (Babil, Wasit and Najaf Governorate)
with the attached Handover Certificate for each DCC and the
punch list signed between two parties dated / / 2020.

Date of Issuance of Provisional Acceptance Certificate:


/ / 2020 for Babil, Wasit and Najaf Governorate

Attachments
1. Hand-Over Certificate in Babil, Wasit and Najaf
2. Punch List dated Jun 17 and Sep 2, 2019

Applicant at Ministry of Electricity, IRAQ


Name: Eng. Rahman J. Askar
Position: DCC Project Manager
Signature: