Logical Framework Analysis

Plan 205 - Project Planning and Development (c.diaz)

1
The Logical Framework Approach

Analytical, presentational and management tool which can help


planners and managers:
Analyze the existing situation
Establish a logical hierarchy of means by which objectives will
be reached
Establish how outputs and outcomes might best be monitored
and evaluated
Present a summary in a standard format

2
The Logical Framework Approach
The approach involves problem analysis, stakeholder analysis,
developing a hierarchy of objectives and selecting a preferred
implementation strategy

Problem Analysis Stakeholder Analysis

Developing a Hierarchy of
Objectives

Selecting a Preferred
Implementation Strategy
3
What is a “Logical Framework
Matrix”?
The product of logical framework analysis

A summary of:
what are intended to be done and how,
what the assumptions are, and
how outputs will be monitored and evaluated

4
The Logical Framework Matrix

Description Indicators Means of Assumptions


Verification

Goal
Purpose
Component
Objective
Outputs
Activities
5
The Vertical Logic
Identifies what the intentions are, clarifies the causal relationships,
and specifies the important assumptions and uncertainties beyond
the manager’s control

6
The Vertical Logic
Goal National and sectoral objectives
Purpose What the program is expected to achieve in terms of
development outcome
Component Objective statement per component
Objectives
Outputs Specific results and tangible products (goods and
services) produced by undertaking a series of activities
Activities Specific tasks undertaken to achieve required outputs

7
Horizontal Logic
Defines how objectives specified in description will be measured,
and the means by which the measurement will be verified

Provides the framework for monitoring and evaluation

8
The Horizontal Logic

Indicators Means of Verification Assumptions


Information needed to Specify expected source of Conditions which could affect
determine progress towards information needed to collect progress of success of project
meeting project objectives data
Should have a clearly defined Positive statement of a condition
unit of measurement and a that must be met to achieve
target detailing quantity, project activities
quality, and timing of
expected results

9
The Logical Framework Matrix Structure and
Sequence for Completion

Description Indicators Means of Verification (MOVs) Assumptions

Goal Indicators MOVs


Purpose Indicators MOVs Assumptions
Component Indicators MOVs Assumptions
Objectives
Outputs Indicators MOVs Assumptions

Activities Milestones Management Reports on Assumptions


specified in Physical & Financial Progress
activity schedules

1
0
CLARIFYING the CONCEPTS

Input - resources and other required interventions (i.e.


inputs to the project)
Output - government interventions designed to
effectively and significantly affect the target
beneficiaries (i.e. the project)
Impacts or Outcome - level and changes in the
welfare status of target beneficiaries (i.e. the
measurable changes on indices as a result of the
project)
1
2
Source: http://www.worldbank.org/html/opr/pmi/maintx10.html#IMPORT
Objectives Tree
Reading down
•Prepared answers the questions
“why and how?” - what
after do we need to do to
achieve this result?
Problem
Trees Reading across
answers the question
“what else?” – what
additional things do we
need to do to achieve
the next objective?

Reading up answers the


question “so what?” –
what is the significance of
our accomplishments?

1
3 Source: http://www.worldbank.org/html/opr/pmi/maintx10.html#IMPORT
Problem Trees
Help in the analysis of the existing situation:
Major problems and their main causal relationships are
identified and discussed.
The output is a graphical arrangement of problems
differentiated according to :
‘causes’
‘effects,’
joined by a core, or focal, problem.
Problems trees as a technique help facilitate the
understanding of:
the context and interrelationship of problems, and
potential impacts when targeting projects and programs
toward specific issues.

14
15 Source: http://www.seafdec.org.ph/DREAM_MINI_WEB/images/problem_tree.gif
16
Source: www.fao.org/docrep/008/y5793e/y5793e02.jpg
TRAFFIC
CONGESTION

AIR &
Manifestation NOISE
POLLUTION
Problems INCREASED
HIDDEN INACCESSIBILITY
ROAD OF UNDER
ACCIDENTS ETC. ENVIRONMENTAL
DEGRADATION

Inadequate Cost

Increased Poor Traffic Recovery


Higher
income & Mgt. & Inadequate Measures
Population
vehicle Enforcement transport
Growth
ownership Facilities
Inadequately

Root Trained Staff


Increase Incompatible Poor Infra
Problems Increase urban Traffic Mix Maintenance
vehicle used Expansion
Mgt. Etc.

Inefficiently
Inadequate Incompatible urban
Longer Average Operated
Land Use Form Density
Trip-Making Public
Control Configuration
Transport
services

17 Source: Lidasan, Hussein – Lecture Notes on Transportation Planning


Steps in Preparing a Problem Tree
1. List all the problems that come to mind. Problems should be carefully
identified: they should be existing problems, not possible, imagined or
future ones. NOTE: A problem is an existing negative or undesired
situation. It is NOT the absence of a solution.
2. From among the problems listed, identify a core problem (you may
need to go through this by trial and error).
3. Determine which problems are “Causes” and which are “Effects.”
4. Following the structure of a Problem Tree, arrange the problems in
the hierarchy Causes and Effects, i.e., how are they related? which
problem causes or leads to the other, etc.

18
Assignment:
Prepare the following:
A problem tree showing the hierarchy of problems in your locality.
From this problem tree, identify a core problem that needs to be
addressed
Develop an objectives tree that responds to the core problem
through the various impacts that can be brought about by the
outcomes of the outputs of several activities designed to respond
to the problem (see previous slide)
Develop a simple Log-Frame for the entire undertaking

19
LOGFRAME Examples

2
0
Strengthening the Management of Contingent Liabilities
in Build-Operate-Transfer (BOT) Projects, PEGR (AusAid)
Hierarchy Objectively Verifiable Means of Verification Assumption(s)
Indicators

Goal: To improve public Decline in total debt stock plus Review of objective indicators Improved debt and risk
financial management quantified contingent liabilities and debt statistics management system is
through debt and risk as a percentage of Philippine important in improving
management GDP Review of reform agenda public financial
impacts to be undertaken by an management
external reviewer (as suggested
by proponents, partner agencies
or AusAid

Purpose: Strengthen the Decrease in the stock of Debt statistics and budget A good number of
oversight capacity for contingent liabilities reports contingent liabilities have
effective and efficient crystallized into actual
management of Decrease in contingent liabilities of the
government’s contingent liabilities materializing into government
liabilities within a well- actual liabilities
defined and coordinated
framework Ample budgetary reserve for
CL exposure
2
1
Hierarchy Objectively Verifiable Indicators Means of Verification Assumption(s)

OBJECTIVE OF Outputs figure into policy Reports by the Required baseline, diagnostics and
ACTIVITY 1: discussions and planning for agencies; review relevant to the development
Review, clarify and proposed changes in systems or documentations, press of methodologies and frameworks
analyze current functions release and/or policy on guarantee management, risk
systems, mechanism statements management and contingent liability
and arrangements on Oversight agencies adopt management
explicit contingent recommendations made Third-party
liabilities review/assessment of Take stock of current systems,
Updated contingent liabilities data source of data on operational procedures,
shared to and employed by the contingent liabilities arrangements, etc.
oversight agencies in reports and
decision-making

OBJECTIVE OF Elements of the proposed system of Third-party Capacity building activities,


ACTIVITY 2: guarantee management, risk review/assessment methodologies, frameworks and
Strengthen the management, contingent liabilities systems required
management of management and budgetary
government provisioning of contingent liabilities Technical skills need improvement
guarantees, risks and adopted by partner agencies
contingent liabilities

2
2
Hierarchy Objectively Verifiable Means of Verification Assumption(s)
Indicators

OBJECTIVE OF Participants attended all Review of submitted To have holistic capacity


ACTIVITY 3: activities and accomplished all reports building activities, including
Provide participants requirements of the study tour advisory services,
practical exposure to and Third-party coaching, mentoring,
familiarization with good review/assessment consultations, etc.
practice in risk
management Exposure good practices
and management of
explicit contingent
liabilities

2
3
INTERMODAL TRANSPORT DEVELOPMENT PROJECT, Asian Development
Bank (ADB)

Design Summary Performance Monitoring Assumptions


Indicators/Targets Mechanisms and Risks

Goals: GDP increased Government official


Economic growth in statistics
Mindanao and Palawan Per capita income
increased ADB monitoring of
Reduced poverty in baseline indicators
Mindanao and Palawan Number of private
in airport and ADB poverty
increased assessment
indicators
Percentage of
below poverty Baseline surveys
decreased.

Rural employment
increased
2
4
Design Summary Performance Monitoring Assumptions
Indicators/Targets Mechanisms and Risks
Purposes: Passenger traffic increased Government official statistics Purpose to Goal

Improved transport Freight traffic increased Operator statistics Assumptions:


accessibility, efficiency Stable peace and order
and sustainability in Service frequency on Traffic monitoring surveys situation in the project areas
Mindanao and Palawan, selected routes increased
with a focus on high Project Completion Report Facilities will be properly
poverty areas. Accident rates reduced (PCR) maintained and will not
deteriorate.
Transport fares on selected routes Project Performance Audit
decreased Reports (PPAR) New business enterprises will
emerge as a consequence
Travel time on selected ofimproved transport efficiency.
routes decreased
Risk:
Number of direct routes General legal and regulatory
increased framework for PSP is not
improved.
Increased private sector Private operators will be
participation (PSP) in involved in the newly
intermodal transport designed public-private
infrastructure investments partnership investments
and services and operations.

2
5
Design Summary Performance Monitoring Assumptions
Indicators/Targets Mechanisms and Risks

Outputs: Plan prepared and agreed Published intermodal Output to Purpose


upon by the end of July transport strategies, plans, and
Framework for intermodal 2005 programs Assumption:
transport strategy in Mindanao
and Palawan strengthened Agency’s capacity improved Transport infrastructure Competition in transport
maintenance budget and services allows reduction of
Transport infrastructure Selected airports and ports upgraded expenditure records transport costs leading to
and facilities upgraded reduction of transport fares.
Transport service operation Traffic safety measures at selected EA and IA Progress reports
reorganized and ports and airports implemented Risk:
expanded ADB review missions
New routes established Consultant's reports High capital investment in
infrastructure development,
Level of service on selected routes PCR and PPAR limited experience and low
improved capacity in the PSP scheme may
result in poor services.
Sustainable funding mechanism
established

2
6
Design Summary Performance Monitoring Assumptions
Indicators/Targets Mechanisms and Risks

Activities: Implementation period and Project Management Office Activity to Output


agencies responsible for every reports
Intermodal transport activities are to be determined during Assumptions:
reform the PPTA implementation. Training workshop reports Counterpart organization is
amenable to proposed reforms.
Airport construction ADB review missions
Consultant's reports Private sector is interested in the
Port construction infrastructure investments and
PCR and PPAR transport service operations.
Airport/port access road
construction

Land acquisition and


rehabilitation

Transport service development

2
7