You are on page 1of 1

AVON PRODUCT MANUFACTURING INC

ELECTRICAL PREVENTIVE MAINTENANCE


ID Task Name H-2 H-1 H1 H2 H3 H4 H5 H6 H7 H8 H9 H10 H11 H12 H13
1 OVERALL SHUTDOWN
2 First Private Pole
3 General Cleaning
4 Re-tightening
5 Testing
6 3MVA Transformer
7 General Cleaning
8 Testing
9 Re-tightening
10 LVSG
11 General Cleaning
12 Contact and Insulation
Resistance Test
13 Trip Test
14 DPL1
15 General Cleaning
16 Contact and Insulation
Resistance Test
17 Trip Test
18 Dry Type Transformer
19 2 -500KVA
20 General Cleaning
21 Testing
22 Re-tightening
23 2- 750KVA
24 General Cleaning
25 Testing
26 Re-tightening
27 HouseKeeping
28 Energization

Task Project Summary Manual Task Start-only Deadline


MASTERPACT Split Inactive Task Duration-only Finish-only Progress

TECHNO-SOLUTION INC Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1

You might also like