Rekapitulasi RAB

Pekerjaan : VOLUME PEKERJAAN PERBAIKAN SITE RADAR


Tahun Anggaran : 2023
Lokasi : Site Radar Aluh-aluh dan Sungai Rasau

No. Uraian Pekerjaan Harga Upah (Rp) Harga Bahan (Rp) TOTAL (Rp)
(1) (2) (3) (4) (5)

A Pembuatan pondasi angkur kabel tower triangle Site Aluh-Aluh 21,616,200.00 29,520,120.00 51,136,320.00
B Pengengencangan kembali kabel tower triangle Site Aluh-Aluh 234,000,000.00 225,000,000.00 459,000,000.00
C Perbaikan pintu pagar BRC Site Sungai Rasau 33,118,500.00 84,057,500.00 117,176,000.00

[A] JUMLAH = 627,312,320.00


[B] PPN 11% = [A] × 11% = 69,004,355.20
[C] JUMLAH KESELURUHAN = [A] + [B] = 696,316,675.20
[D] PEMBULATAN = [C] = 696,316,700.00
Terbilang:
Enam Ratus Sembilan Puluh Enam Juta Tiga Ratus Enam Belas Ribu Tujuh Ratus Rupiah

JEMBER, 03 MEI 2023


KONTRAKTOR PELAKSANA
PT GLOBAL KALINDA TEKNIKA

Ir. AKHMAD NILUL MAROM, M.T.


DIREKTUR UTAMA