You are on page 1of 68

DAFTAR HARGA SATUAN BAHAN DAN UPAH

SEMESTER I 2015
DINAS PEKERJAAN UMUM KAB MURUNG RAYA

A. BAHAN LOKAL DOMINAN YANG SANGAT DIPENGARUHI BIAYA ANGKUT


HARGA HARGA DASAR HARGA DESAIN =
ONGKOS ANGKUT KE LOKASI
NO. BAHAN KODE SAT SUMBER BAHAN SETEMPAT REGIONAL REGIONAL HARGA DASAR +
REGIONAL I REGIONAL II PEKERJAAN
(RP.) III IV ONGKOS ANGKUT
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12)

1 Batu Gunung/batu belah M 010 m3 Puruk Cahu 224,532 280,665 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 623,700 779,625 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 548,856 686,070 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 561,330 701,663 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 449,064 561,330 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

2 Batu Pecah 10 - 15 cm M 026 m3 Puruk Cahu 319,788 399,735 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Manual) Saripoi 755,244 944,055 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 619,164 773,955 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 673,596 841,995 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 694,008 867,510 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 489,888 612,360 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 625,968 782,460 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 571,536 714,420 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 489,888 612,360 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 639,576 799,470 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

3 Batu Pecah 5 - 7 cm M 022 m3 Puruk Cahu 427,518 534,398 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Manual) Saripoi 899,262 1,124,078 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 751,842 939,803 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 810,810 1,013,513 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 840,294 1,050,368 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 619,164 773,955 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 766,584 958,230 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 707,616 884,520 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 619,164 773,955 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 796,068 995,085 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
4 Batu Pecah 3 - 5 cm M 023 m3 Puruk Cahu 592,515 740,644 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Alat) (Produksi) Saripoi 854,469 1,068,086 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 754,677 943,346 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 904,365 1,130,456 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

5 Batu Pecah 2 - 3 cm M 024 m3 Puruk Cahu 742,203 927,754 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Alat) (Produksi) Saripoi 1,004,157 1,255,196 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 904,365 1,130,456 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 1,054,053 1,317,566 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

6 Batu Pecah 1 - 2 cm M 025 m3 Puruk Cahu 742,203 927,754 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Alat) (Produksi) Saripoi 1,004,157 1,255,196 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 904,365 1,130,456 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 1,054,053 1,317,566 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

7 Batu Pecah 0,5 - 1 cm M 026 m3 Puruk Cahu 742,203 927,754 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Alat) (Produksi) Saripoi 1,004,157 1,255,196 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 904,365 1,130,456 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 1,054,053 1,317,566 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
8 Batu Pecah Tersaring M 018 m3 Puruk Cahu 742,203 927,754 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Alat) (Produksi) Saripoi 1,004,157 1,255,196 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 904,365 1,130,456 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 1,054,053 1,317,566 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

9 Debu Batu m3 Puruk Cahu 674,730 843,413 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 912,870 1,141,088 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 822,150 1,027,688 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 958,230 1,197,788 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

10 Kerikil Galian Bukit M 011 m3 Puruk Cahu 187,110 233,888 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Awcas) Saripoi 461,538 576,923 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 424,116 530,145 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 424,116 530,145 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 486,486 608,108 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 424,116 530,145 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 361,746 452,183 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 486,486 608,108 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

11 Kerikil Sungai M 012 m3 Puruk Cahu 228,690 285,863 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 598,752 748,440 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 449,064 561,330 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 598,752 748,440 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 453,600 567,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
12 Kerikil Sungai Ayak M 013 m3 Puruk Cahu 253,260 316,575 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Tanpa Pasir Saripoi 589,680 737,100 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 453,600 567,000 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 589,680 737,100 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 442,260 552,825 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 442,260 552,825 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 442,260 552,825 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 385,560 481,950 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

13 Pasir Urug / Timbunan M 040 m3 Puruk Cahu 111,132 138,915 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 170,667 213,334 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 178,605 223,256 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 267,908 334,884 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 250,047 312,559 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 309,582 386,978 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 202,419 253,024 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 190,512 238,140 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 190,512 238,140 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 250,047 312,559 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

14 Pasir Ayak Untuk M 041 m3 Puruk Cahu 166,320 207,900 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Beton / Pasir Barito. Saripoi 449,064 561,330 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 349,272 436,590 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 311,850 389,813 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

15 Sirtu (tidak diayak, dari M 042 m3 Puruk Cahu 187,110 233,888 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
sungai) Saripoi 548,856 686,070 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 399,168 498,960 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 548,856 686,070 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
16 Tanah Timbunan M 050 m3 Puruk Cahu 99,225 124,031 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 158,760 198,450 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 166,698 208,373 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 238,140 297,675 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 238,140 297,675 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 297,675 372,094 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 190,512 238,140 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 178,605 223,256 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 178,605 223,256 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 238,140 297,675 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

17 Semen Portland M080 zak Puruk Cahu 124,200 155,250 = [(150.000 + (15.000 x jarak)] / 80 (7) + (11)
(1 zak = 50 kg) Saripoi 142,997 178,747 = [(150.000 + (15.000 x jarak)] / 80 (8) + (11)
Dirung Lingkin 142,997 178,747 = [(150.000 + (15.000 x jarak)] / 80 (8) + (11)
Muara Laung 136,080 170,100 = [(150.000 + (15.000 x jarak)] / 80 (8) + (11)
Makunjung 125,442 156,803 = [(150.000 + (15.000 x jarak)] / 80 (8) + (11)
Tbg Lahung 158,760 198,450 = [(150.000 + (15.000 x jarak)] / 80 (9) + (11)
Tbg Kunyi 201,960 252,450 = [(150.000 + (15.000 x jarak)] / 80 (10) + (11)
Tbg Bantian 190,080 237,600 = [(150.000 + (15.000 x jarak)] / 80 (9) + (11)
Tbg Olong 207,900 259,875 = [(150.000 + (15.000 x jarak)] / 80 (10) + (11)
Muara Joloi 219,780 274,725 = [(150.000 + (15.000 x jarak)] / 80 (10) + (11)

18 Besi Beton Polos (top) M167 Kg Puruk Cahu 13,662 17,078 = [(150.000 + (15.000 x jarak)] / 4.000 (7) + (11)
Saripoi 13,900 17,375 = [(150.000 + (15.000 x jarak)] / 4.000 (8) + (11)
Dirung Lingkin 13,900 17,375 = [(150.000 + (15.000 x jarak)] / 4.000 (8) + (11)
Muara Laung 13,900 17,375 = [(150.000 + (15.000 x jarak)] / 4.000 (8) + (11)
Makunjung 13,662 17,078 = [(150.000 + (15.000 x jarak)] / 4.000 (8) + (11)
Tbg Lahung 14,137 17,672 = [(150.000 + (15.000 x jarak)] / 4.000 (9) + (11)
Tbg Kunyi 14,494 18,117 = [(150.000 + (15.000 x jarak)] / 4.000 (10) + (11)
Tbg Bantian 14,434 18,043 = [(150.000 + (15.000 x jarak)] / 4.000 (9) + (11)
Tbg Olong 14,672 18,340 = [(150.000 + (15.000 x jarak)] / 4.000 (10) + (11)
Muara Joloi 16,276 20,345 = [(150.000 + (15.000 x jarak)] / 4.000 (10) + (11)

19 Kayu Ulin Balok Besar M 181 m3 Puruk Cahu 5,278,500 6,598,125 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 2,328,750 2,910,938 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 5,278,500 6,598,125 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 6,831,000 8,538,750 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 5,589,000 6,986,250 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 4,471,200 5,589,000 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 6,210,000 7,762,500 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 6,210,000 7,762,500 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 2,484,000 3,105,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 4,657,500 5,821,875 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
20 Kayu Ulin Balok Kecil M 181 m3 Puruk Cahu 5,643,000 7,053,750 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 4,455,000 5,568,750 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 5,346,000 6,682,500 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 6,534,000 8,167,500 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 5,346,000 6,682,500 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 5,049,000 6,311,250 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 2,376,000 2,970,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 4,455,000 5,568,750 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

21 Papan Ulin M 181 m3 Puruk Cahu 6,997,320 8,746,650 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 8,167,500 10,209,375 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 8,167,500 10,209,375 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 6,311,250 7,889,063 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 2,970,000 3,712,500 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 5,568,750 6,960,938 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

22 Kayu Lanan Balok Kecil m3 Puruk Cahu 2,376,000 2,970,000 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 2,079,000 2,598,750 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 2,376,000 2,970,000 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 1,782,000 2,227,500 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 1,782,000 2,227,500 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 2,524,500 3,155,625 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 2,376,000 2,970,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 2,257,200 2,821,500 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 1,485,000 1,856,250 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 2,079,000 2,598,750 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)

23 Papan Lanan m3 Puruk Cahu 2,577,960 3,222,450 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 2,227,500 2,784,375 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 2,598,750 3,248,438 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 2,079,000 2,598,750 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 2,079,000 2,598,750 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 2,524,500 3,155,625 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 2,376,000 2,970,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 2,301,750 2,877,188 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 1,856,250 2,320,313 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 2,227,500 2,784,375 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Keterangan :
Regional I : Kecamatan Murung

Regional II : Kecamatan Tanah Siang Puruk Cahu, Juni 2008


Kecamatan Tanah Siang Selatan
Kecamatan Laung Tuhup KEPALA DINAS PEKERJAAN UMUM
Kecamatan Barito Tuhup Raya KAB. MURUNG RAYA

Regional III : Kecamatan Permata Intan


Kecamatan Sei Babuat

Regional IV : Kecamatan Sumber Barito Ir. ADRIAN WT, MM


Kecamatan Uut Murung NIP. 530 007 565
Kecamatan Seribu Riam
B. BAHAN UMUM
REGIONAL
REGION I REGION II REGION III REGION IV
Kec. Tanah Siang Kec. Sumber Barito
Harga Dasar Kec. Laung Tuhup Kec. Permata Intan Kec. U'ut Murung
No. NAMA BAHAN SAT. KODE Kec. Murung KET.
(Rp.) Kec. Barito Tuhup Raya Kec. Sei Babuat Kec. Seribu Riam
Kec. Tanah Siang Selatan
Total Total Total Total
(Rp.) (Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10

1 Alat Bantu Set M.170 89,100.00 111,375.00 115,830.00 120,285.00 124,740.00


2 Ampelas Lbr 5,940.00 7,425.00 7,722.00 8,019.00 8,316.00
3 Angker Bh 5,940.00 7,425.00 7,722.00 8,019.00 8,316.00
4 Arde Tanah Bh 178,200.00 222,750.00 231,660.00 240,570.00 249,480.00
5 Armatur Lampu Set 403,920.00 504,900.00 525,096.00 545,292.00 565,488.00
6 Aspal Pen 60/70 Kg M.061 12,474.00 15,592.50 16,216.20 16,839.90 17,463.60
7 Astelin Btl 534,600.00 668,250.00 694,980.00 721,710.00 748,440.00
8 Atap Genteng Metal merk Sakura Color (77 x 80 cm) Tipe Classic (2 Susun) Lbr 47,520.00 59,400.00 61,776.00 64,152.00 66,528.00
9 Atap Polycarbonate + Rangka Besi Biasa (Set) M2 594,000.00 742,500.00 772,200.00 801,900.00 831,600.00
10 Atap Polycarbonate + Rangka Steinless (Set) M2 831,600.00 1,039,500.00 1,081,080.00 1,122,660.00 1,164,240.00
11 Atap Sirap Ulin Lbr 1,425.60 1,782.00 1,853.28 1,924.56 1,995.84 Lokal
12 Baja Profil WF Kg M.165 29,106.00 36,382.50 37,837.80 39,293.10 40,748.40
13 Baja Ulir 1" / Profil Kg 20,124.72 25,155.90 26,162.14 27,168.37 28,174.61
14 Bak Mandi Fibreglass (70 cm x 70 cm Segi Empat Besar) Unit 475,200.00 594,000.00 617,760.00 641,520.00 665,280.00
15 Batako Bh 5,464.80 6,831.00 7,104.24 7,377.48 7,650.72 Lokal
16 Batu - Bata Merah (5 x 11 x 22 cm) Bh 1,128.60 1,410.75 1,467.18 1,523.61 1,580.04 Lokal
17 Baut dan Beugel 10 cm Biji 2,376.00 2,970.00 3,088.80 3,207.60 3,326.40
18 Baut dan Beugel 20 cm Biji 9,504.00 11,880.00 12,355.20 12,830.40 13,305.60
19 Besi Plat 5 mm Lbr 1,550,340.00 1,937,925.00 2,015,442.00 2,092,959.00 2,170,476.00
20 Besi Siku 4 cm panajang 6 cm Bh 81,972.00 102,465.00 106,563.60 110,662.20 114,760.80
21 Besi U, 10 x 10 x 6 m Btg 106,920.00 133,650.00 138,996.00 144,342.00 149,688.00
22 Besi Strip Bh 35,877.60 44,847.00 46,640.88 48,434.76 50,228.64
23 Besi Ulir (U - 39) 12 m Kg 16,038.00 20,047.50 20,849.40 21,651.30 22,453.20
24 Box Zekering Kas 2 Group Bh 149,688.00 187,110.00 194,594.40 202,078.80 209,563.20
25 Bubungan Atap Sakura Color 15 cm Lbr 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
26 Cat Dasar Kayu merk Kembang Kg 21,384.00 26,730.00 27,799.20 28,868.40 29,937.60
27 Cat Kilap Kayu setara merk Jotun Kg 95,040.00 118,800.00 123,552.00 128,304.00 133,056.00
28 Cat Kilap Kayu setara merk Glotex Kg 45,144.00 56,430.00 58,687.20 60,944.40 63,201.60
29 Cat Kilap Kayu setara merk Platone Kg 45,144.00 56,430.00 58,687.20 60,944.40 63,201.60
30 Cat Kilap Kayu setara setara Avia Paint Kg 46,332.00 57,915.00 60,231.60 62,548.20 64,864.80
31 Cat Menie Kg 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
32 Cat Tembok merk setara Kimex Kg 16,632.00 20,790.00 21,621.60 22,453.20 23,284.80
33 Cat Tembok setara merk Matek Kg 16,632.00 20,790.00 21,621.60 22,453.20 23,284.80
34 Closed Duduk setaramerk American Standard Set 2,316,600.00 2,895,750.00 3,011,580.00 3,127,410.00 3,243,240.00
35 Closed Jongkok setara merk American Standard Bh 237,600.00 297,000.00 308,880.00 320,760.00 332,640.00
36 Elbow 2" PVC (AW) 90˚ Bh 10,692.00 13,365.00 13,899.60 14,434.20 14,968.80
37 Elbow 4" PVC (AW) 90˚ Bh 59,400.00 74,250.00 77,220.00 80,190.00 83,160.00
38 Engsel Lokal 3" setara merk Picaso Bh 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
39 Engsel Lokal 4" setara merk Picaso Bh 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
40 Engsel Lokal 4" setara merk Iron Bh 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
41 Espanyolet Tanam setara merk SES Bh 149,688.00 187,110.00 194,594.40 202,078.80 209,563.20
42 Fiting Lampu Gantung Biasa Bh 11,880.00 14,850.00 15,444.00 16,038.00 16,632.00
43 Fiting Lampu Gantung Tipe E 40 Bh 89,100.00 111,375.00 115,830.00 120,285.00 124,740.00
44 Fiting Lampu Gipsum Bh 101,574.00 126,967.50 132,046.20 137,124.90 142,203.60
45 Flange Adaptor Ø 2" merk Maspion Bh 104,544.00 130,680.00 135,907.20 141,134.40 146,361.60
46 Flange Adaptor Ø 3" merk Maspion Bh 142,560.00 178,200.00 185,328.00 192,456.00 199,584.00
47 Flange Adaptor Ø 4" merk Maspion Bh 181,170.00 226,462.50 235,521.00 244,579.50 253,638.00
48 Flange Adaptor Ø 6" merk Maspion Bh 356,518.80 445,648.50 463,474.44 481,300.38 499,126.32
49 Flange Adaptor Ø 2" merk Vinilon Bh 153,608.40 192,010.50 199,690.92 207,371.34 215,051.76
50 Flange Adaptor Ø 3" merk Vinilon Bh 211,464.00 264,330.00 274,903.20 285,476.40 296,049.60
51 Flange Adaptor Ø 4" merk Vinilon Bh 278,942.40 348,678.00 362,625.12 376,572.24 390,519.36
52 Flange Adaptor Ø 6" merk Vinilon Bh 514,522.80 643,153.50 668,879.64 694,605.78 720,331.92
53 Flange Adaptor Ø 8" merk Vinilon Bh 829,105.20 1,036,381.50 1,077,836.76 1,119,292.02 1,160,747.28
54 Flange Adaptor Ø 10" merk Vinilon Bh 850,370.40 1,062,963.00 1,105,481.52 1,148,000.04 1,190,518.56
55 Flange Adaptor Ø 12" merk Vinilon Bh 1,294,563.60 1,618,204.50 1,682,932.68 1,747,660.86 1,812,389.04
56 Floor Strainer Bh 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
57 Kunci Gembok + Plat (Besar) Set 53,460.00 66,825.00 69,498.00 72,171.00 74,844.00
58 Glassbeads Kg 38,016.00 47,520.00 49,420.80 51,321.60 53,222.40
59 Glassblock Bh 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
60 Grendel 2" setara merk Omco Bh 5,940.00 7,425.00 7,722.00 8,019.00 8,316.00
61 Grendel 3" setara merk Omco Bh 9,504.00 11,880.00 12,355.20 12,830.40 13,305.60
62 Handle Listrik 30 Ampere Bh 59,400.00 74,250.00 77,220.00 80,190.00 83,160.00
63 Handle / Tarikan Kuning setara merk Top Bh 5,940.00 7,425.00 7,722.00 8,019.00 8,316.00
64 Isolasi Listrik Buah 7,128.00 8,910.00 9,266.40 9,622.80 9,979.20
65 Kabel NYA 2,5" M' 1,663.20 2,079.00 2,162.16 2,245.32 2,328.48
66 Kabel Power tipe NYM 3 x 2,5 mm setara merk Spring M' 6,534.00 8,167.50 8,494.20 8,820.90 9,147.60
67 Kabel Tanam 2 x 2,5" setara merk Spring M' 4,752.00 5,940.00 6,177.60 6,415.20 6,652.80
68 Kabel tipe NYFGBY 4 x 10 mm M' 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
69 Kaca Bening ≠ 3 mm M2 118,800.00 148,500.00 154,440.00 160,380.00 166,320.00
70 Kaca Bening ≠ 5 mm M2 130,680.00 163,350.00 169,884.00 176,418.00 182,952.00
71 Kaca Hitam / Ryben ≠ 5 mm M2 148,500.00 185,625.00 193,050.00 200,475.00 207,900.00
72 Kait Angin Kuning Pasang 11,880.00 14,850.00 15,444.00 16,038.00 16,632.00
73 Kait Talang Air merk Maspion Bh 9,504.00 11,880.00 12,355.20 12,830.40 13,305.60
74 Kapur Pasang / Kapur Padam Kg M.081 1,960.20 2,450.25 2,548.26 2,646.27 2,744.28
75 Kawat Berduri M' 7,128.00 8,910.00 9,266.40 9,622.80 9,979.20
76 Kawat Beton (Bindrat) Kg 21,384.00 26,730.00 27,799.20 28,868.40 29,937.60
77 Kawat Bronjong Kg M.162 41,164.20 51,455.25 53,513.46 55,571.67 57,629.88
78 Kawat Harmonika M2 15,444.00 19,305.00 20,077.20 20,849.40 21,621.60
79 Kawat Las Dos 160,380.00 200,475.00 208,494.00 216,513.00 224,532.00
80 Kawat Nyamuk (Besi) M2 11,880.00 14,850.00 15,444.00 16,038.00 16,632.00
81 Kayu Bakar M3 M.070 118,800.00 148,500.00 154,440.00 160,380.00 166,320.00 Lokal
82 Kayu Bekisting M3 M.180 772,200.00 965,250.00 1,003,860.00 1,042,470.00 1,081,080.00 Lokal
83 Kayu Bulat Ø 6 - 10 cm panjang 4 m Btg 9,355.50 11,694.38 12,162.15 12,629.93 13,097.70 Lokal
84 Kayu Log Ø 50 - 70 cm panjang 4 m Btg 810,810.00 1,013,512.50 1,054,053.00 1,094,593.50 1,135,134.00 Lokal
85 Keramik 20 x 20 cm merk Roman Bh 3,088.80 3,861.00 4,015.44 4,169.88 4,324.32
86 Keramik 20 x 20 cm merk Mulia Bh 3,088.80 3,861.00 4,015.44 4,169.88 4,324.32
87 Keramik 20 x 25 cm merk Mulia Bh 3,861.00 4,826.25 5,019.30 5,212.35 5,405.40
88 Keramik 30 x 30 cm merk Roman Bh 8,672.40 10,840.50 11,274.12 11,707.74 12,141.36
89 Keramik 40 x 40 cm merk Roman Bh 17,938.80 22,423.50 23,320.44 24,217.38 25,114.32
90 Keramik 30 x 30 cm Putih merk Mulia Bh 7,484.40 9,355.50 9,729.72 10,103.94 10,478.16
91 Klam Pipa Listrik Bungkus 11,880.00 14,850.00 15,444.00 16,038.00 16,632.00
92 Knee PVC Ø 2" merk Maspion (DV) Bh 7,722.00 9,652.50 10,038.60 10,424.70 10,810.80
93 Knee PVC Ø 3" merk Maspion (DV) Bh 23,878.80 29,848.50 31,042.44 32,236.38 33,430.32
94 Knee PVC Ø 4" merk Maspion (DV) Bh 45,738.00 57,172.50 59,459.40 61,746.30 64,033.20
95 Knee PVC Ø 6" merk Maspion (DV) Bh 196,020.00 245,025.00 254,826.00 264,627.00 274,428.00
96 Knee PVC Ø 8" merk Maspion (DV) Bh 281,556.00 351,945.00 366,022.80 380,100.60 394,178.40
97 Knee PVC Ø 10" merk Maspion (DV) Bh 403,920.00 504,900.00 525,096.00 545,292.00 565,488.00
98 Knee PVC Ø 12" merk Maspion (DV) Bh 659,340.00 824,175.00 857,142.00 890,109.00 923,076.00
99 Knee PVC Ø 2" merk Vinilon Bh 27,918.00 34,897.50 36,293.40 37,689.30 39,085.20
100 Knee PVC RRJ Ø 3" merk Vinilon Bh 445,500.00 556,875.00 579,150.00 601,425.00 623,700.00
102 Kran Air Ø 1/2" setara merk Amico Bh 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
103 Kran Air Ø 3/4" setara merk Amico Bh 21,384.00 26,730.00 27,799.20 28,868.40 29,937.60
104 Kunci Tanam setara merk Kodai Bh 148,500.00 185,625.00 193,050.00 200,475.00 207,900.00
105 Kunci Tanam setara merk SES Bh 415,800.00 519,750.00 540,540.00 561,330.00 582,120.00
106 Lem Isarplast (700 gr) Kg 154,440.00 193,050.00 200,772.00 208,494.00 216,216.00
107 Lem Kayu merk Fox Kg 41,580.00 51,975.00 54,054.00 56,133.00 58,212.00
108 List Profil Kayu 4 Cm M' 3,861.00 4,826.25 5,019.30 5,212.35 5,405.40 Lokal
109 List Profil Gipsum M' 53,460.00 66,825.00 69,498.00 72,171.00 74,844.00
110 MCB merk Elitech Buah 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
111 Minyak Bakar / Minyak Tanah Ltr M.065 10,692.00 13,365.00 13,899.60 14,434.20 14,968.80
112 Minyak Cat / Thinner A Ltr 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
113 Minyak Cat / Thinner B Ltr 21,384.00 26,730.00 27,799.20 28,868.40 29,937.60
114 Minyak Cat Biasa (600 ml) Btl 6,534.00 8,167.50 8,494.20 8,820.90 9,147.60
115 Minyak Cat merk Super Ltr 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
116 Minyak Pelumas (SAE 30) Ltr M.185 35,046.00 43,807.50 45,559.80 47,312.10 49,064.40
117 Moulding Lanan (Lebar 10 Cm) Keping 19,008.00 23,760.00 24,710.40 25,660.80 26,611.20 Lokal
118 Moulding Lanan M3 2,356,992.00 2,946,240.00 3,064,089.60 3,181,939.20 3,299,788.80 Lokal
119 Paking Pipa Karet (3 mm) Bh 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
120 Paku Atap Genteng Metal Kg 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
121 Paku Jembatan Kg M.166 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
122 Paku Kayu (≤ 1") Kg 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
123 Paku Kayu ( 1 1/4" - 1,5") Kg 21,384.00 26,730.00 27,799.20 28,868.40 29,937.60
124 Paku Kayu (2") Kg 21,384.00 26,730.00 27,799.20 28,868.40 29,937.60
125 Paku Kayu (2,5" - 5") Kg 21,384.00 26,730.00 27,799.20 28,868.40 29,937.60
126 Paku Plywood Kg 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
127 Paku Seng Kg 29,700.00 37,125.00 38,610.00 40,095.00 41,580.00
128 Paku Sirap Kg 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
129 Paku Ulin (2,5" - 5") Kg 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
130 Paku Ulin (≤ 2") Kg 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
131 Papan Bekisting M3 1,620,432.00 2,025,540.00 2,106,561.60 2,187,583.20 2,268,604.80 Lokal
132 Papan Kayu Bouwplank M3 1,915,056.00 2,393,820.00 2,489,572.80 2,585,325.60 2,681,078.40 Lokal
133 Lampu TL 20 watt merk Phillips Lengkap Set 100,980.00 126,225.00 131,274.00 136,323.00 141,372.00
134 Lampu SL 18 watt merk Philips Bh 41,580.00 51,975.00 54,054.00 56,133.00 58,212.00
135 Lampu Pijar 25 watt merk Philips Bh 5,940.00 7,425.00 7,722.00 8,019.00 8,316.00
136 Pasangan Instalasi Listrik (Rumah Beton) Bh 95,040.00 118,800.00 123,552.00 128,304.00 133,056.00
137 Pasangan Instalasi Listrik (Rumah Kayu) Bh 71,280.00 89,100.00 92,664.00 96,228.00 99,792.00
138 Tangki Air 1.200 ltr setara merk Grand Bh 1,603,800.00 2,004,750.00 2,084,940.00 2,165,130.00 2,245,320.00
139 Tangki Air 2.200 ltr setara merk Grand Bh 3,267,000.00 4,083,750.00 4,247,100.00 4,410,450.00 4,573,800.00
140 Paving Block Bh 3,920.40 4,900.50 5,096.52 5,292.54 5,488.56 Lokal
141 Pipa Galvanis Ø 2" panjang 4 m Btg 363,528.00 454,410.00 472,586.40 490,762.80 508,939.20
142 Pipa Galvanis Ø 3" panjang 6 m Btg 557,172.00 696,465.00 724,323.60 752,182.20 780,040.80
143 Pipa Galvanis Ø 4" panjang 6 m Btg 1,016,928.00 1,271,160.00 1,322,006.40 1,372,852.80 1,423,699.20
144 Pipa Galvanis Ø 6" panjang 6 m Btg 1,647,162.00 2,058,952.50 2,141,310.60 2,223,668.70 2,306,026.80
145 Pipa Paralon PVC Ø 1/2" AW, panjang 4 m merk Super Intilon Btg 18,414.00 23,017.50 23,938.20 24,858.90 25,779.60
146 Pipa Paralon PVC Ø 3/4" AW, panjang 4 m merk Super Intilon Btg 24,948.00 31,185.00 32,432.40 33,679.80 34,927.20
147 Pipa Paralon PVC Ø 1" AW, panjang 4 m merk Super Intilon Btg 31,482.00 39,352.50 40,926.60 42,500.70 44,074.80
148 Pipa Paralon PVC Ø 1,5" AW, panjang 4 m merk Super Intilon Btg 54,648.00 68,310.00 71,042.40 73,774.80 76,507.20
149 Pipa Paralon PVC Ø 2" AW, panjang 4 m merk Super Intilon Btg 59,400.00 74,250.00 77,220.00 80,190.00 83,160.00
150 Pipa Paralon PVC Ø 3" AW, panjang 4 m merk Super Intilon Btg 142,560.00 178,200.00 185,328.00 192,456.00 199,584.00
151 Pipa Paralon PVC Ø 4" AW, panjang 4 m merk Super Intilon Btg 190,080.00 237,600.00 247,104.00 256,608.00 266,112.00
152 Pipa Paralon PVC Ø 2", panjang 6 m merk Maspion Btg 122,958.00 153,697.50 159,845.40 165,993.30 172,141.20
153 Pipa Paralon PVC Ø 3", panjang 6 m merk Maspion Btg 239,668.31 299,585.39 311,568.80 323,552.22 335,535.63
154 Pipa Paralon PVC Ø 4", panjang 6 m merk Maspion Btg 348,410.70 435,513.38 452,933.91 470,354.45 487,774.98
155 Pipa Paralon PVC Ø 6", panjang 6 m merk Maspion Btg 721,116.00 901,395.00 937,450.80 973,506.60 1,009,562.40
156 Pipa Paralon PVC Ø 8", panjang 6 m merk Maspion Btg 1,095,930.00 1,369,912.50 1,424,709.00 1,479,505.50 1,534,302.00
157 Pipa Paralon PVC Ø 10", panjang 6 m merk Maspion Btg 1,703,295.00 2,129,118.75 2,214,283.50 2,299,448.25 2,384,613.00
158 Pipa Paralon PVC Ø 12", panjang 6 m merk Maspion Btg 2,806,650.00 3,508,312.50 3,648,645.00 3,788,977.50 3,929,310.00
159 Pipa PVC SNI 06-0084-2002 type S-10 SCJ Ø1/2", panjang 4 m merk Vinilon Btg 12,952.76 16,190.96 16,838.59 17,486.23 18,133.87
160 Pipa PVC SNI 06-0084-2002 type S-10 SCJ Ø 3/4", panjang 4 m merk Vinilon Btg 19,111.36 23,889.20 24,844.76 25,800.33 26,755.90
161 Pipa PVC SNI 06-0084-2002 type S-10 SCJ Ø 1", panjang 4 m merk Vinilon Btg 32,658.12 40,822.65 42,455.56 44,088.46 45,721.37
162 Pipa PVC SNI 06-0084-2002 type S-10 SCJ Ø 1,5", panjang 4 m merk Vinilon Btg 94,029.01 117,536.27 122,237.72 126,939.17 131,640.62
163 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 2", panjang 6 m merk Vinilon Btg 182,045.56 227,556.95 236,659.22 245,761.50 254,863.78
164 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 3", panjang 6 m merk Vinilon Btg 310,473.11 388,091.39 403,615.04 419,138.70 434,662.35
165 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 4", panjang 6 m merk Vinilon Btg 451,529.10 564,411.38 586,987.83 609,564.29 632,140.74
166 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 6", panjang 6 m merk Vinilon Btg 981,050.40 1,226,313.00 1,275,365.52 1,324,418.04 1,373,470.56
167 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 8", panjang 6 m merk Vinilon Btg 1,484,168.40 1,855,210.50 1,929,418.92 2,003,627.34 2,077,835.76
168 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 10", panjang 6 m merk Vinilon Btg 2,266,407.00 2,833,008.75 2,946,329.10 3,059,649.45 3,172,969.80
169 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 12", panjang 6 m merk Vinilon Btg 3,805,282.80 4,756,603.50 4,946,867.64 5,137,131.78 5,327,395.92
170 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 14", panjang 6 m merk Vinilon Btg 5,826,189.60 7,282,737.00 7,574,046.48 7,865,355.96 8,156,665.44
171 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 16", panjang 6 m merk Vinilon Btg 7,103,170.80 8,878,963.50 9,234,122.04 9,589,280.58 9,944,439.12
172 Plafond Gipsum (1,20 m x 2,40 m) Lbr 98,010.00 122,512.50 127,413.00 132,313.50 137,214.00
173 Plafond Kalsiboard (1,20 m x 2,40 m) Lbr 80,190.00 100,237.50 104,247.00 108,256.50 112,266.00
174 Plamur Tembok setara merk Boyo Kg 10,692.00 13,365.00 13,899.60 14,434.20 14,968.80
175 Plastik Cor M3 65,340.00 81,675.00 84,942.00 88,209.00 91,476.00
176 Plywood / Triplek (3 mm) Lbr 53,460.00 66,825.00 69,498.00 72,171.00 74,844.00
177 Pompa Air Jet Pump setara merk Panasonic 125 w Unit 415,800.00 519,750.00 540,540.00 561,330.00 582,120.00
178 Pompa Air Jet Pump setara merk Panasonic 200 w Unit 653,400.00 816,750.00 849,420.00 882,090.00 914,760.00
179 Premium (Bensin) Ltr M.184 9,682.20 12,102.75 12,586.86 13,070.97 13,555.08
180 Rangka Plafond Gipsum M2 130,977.00 163,721.25 170,270.10 176,818.95 183,367.80
181 Reducer Socket RR 4" x 3" merk Maspion (DV) Bh 10,098.00 12,622.50 13,127.40 13,632.30 14,137.20
182 Reducer Socket RR 6" x 4" merk Maspion (DV) Bh 38,610.00 48,262.50 50,193.00 52,123.50 54,054.00
183 Reducer Socket RR 3" x 2" Merk Vinilon Bh 297,000.00 371,250.00 386,100.00 400,950.00 415,800.00
184 Reducer Socket RR 4" x 3" merk Vinilon Bh 297,000.00 371,250.00 386,100.00 400,950.00 415,800.00
185 Reducer Socket RR 6" x 4" merk Vinilon Bh 831,600.00 1,039,500.00 1,081,080.00 1,122,660.00 1,164,240.00
186 Reducer Socket RR 4" x 2" merk Vinilon Bh 475,200.00 594,000.00 617,760.00 641,520.00 665,280.00
186 Saklar Ganda setara merk Broco Bh 23,760.00 29,700.00 30,888.00 32,076.00 33,264.00
187 Reducer Socket RR 8" x 6" merk Vinilon Bh 1,069,200.00 1,336,500.00 1,389,960.00 1,443,420.00 1,496,880.00
187 Saklar Tunggal setara merk Broco Bh 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
188 Stop Kontak setara merk Broco Bh 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
189 Selang Fleksibel (Karet) Ø 4" M' 891,000.00 1,113,750.00 1,158,300.00 1,202,850.00 1,247,400.00
190 Selotif Pipa merk Onda Buah 3,564.00 4,455.00 4,633.20 4,811.40 4,989.60
191 Semen Putih 50 kg Kg 2,970.00 3,712.50 3,861.00 4,009.50 4,158.00
192 Seng Bubungan Plat BJLS 30, Lebar 40 cm M' 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
193 Seng Bubungan Plat BJLS 30, Lebar 30 cm M' 14,256.00 17,820.00 18,532.80 19,245.60 19,958.40
194 Seng Gelombang Kecil BJLS 30 Lbr 42,768.00 53,460.00 55,598.40 57,736.80 59,875.20
195 Seng Plat Besar Biasa BJLS 30 Lbr 59,400.00 74,250.00 77,220.00 80,190.00 83,160.00
196 Solar Ltr M.183 10,632.60 13,290.75 13,822.38 14,354.01 14,885.64
197 Stop Kran Ø 2" PVC Bh 89,100.00 111,375.00 115,830.00 120,285.00 124,740.00
198 Stop Kran Ø 1/2" PVC Bh 11,880.00 14,850.00 15,444.00 16,038.00 16,632.00
199 Stop Kran Ø 3/4" PVC Bh 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
200 Spring Knife setara merk Subur Bh 8,316.00 10,395.00 10,810.80 11,226.60 11,642.40
201 Talang Air PVC merk Maspion @ 4 m M' 26,730.00 33,412.50 34,749.00 36,085.50 37,422.00
202 Talang Air PVC merk Champion @ 4 m M' 17,820.00 22,275.00 23,166.00 24,057.00 24,948.00
203 Tee All RR Ø 2" merk Maspion Bh 108,108.00 135,135.00 140,540.40 145,945.80 151,351.20
204 Tee All RR Ø 3" merk Maspion Bh 178,200.00 222,750.00 231,660.00 240,570.00 249,480.00
205 Tee All RR Ø 4" merk Maspion Bh 294,030.00 367,537.50 382,239.00 396,940.50 411,642.00
206 Tee All RR Ø 6" merk Maspion Bh 545,292.00 681,615.00 708,879.60 736,144.20 763,408.80
207 Tee All RR Ø 2" merk Vinilon Bh 150,876.00 188,595.00 196,138.80 203,682.60 211,226.40
208 Tee All RR Ø 3" merk Vinilon Bh 205,048.80 256,311.00 266,563.44 276,815.88 287,068.32
209 Tee All RR Ø 4" merk Vinilon Bh 359,251.20 449,064.00 467,026.56 484,989.12 502,951.68
210 Tee All RR Ø 6" merk Vinilon Bh 956,458.80 1,195,573.50 1,243,396.44 1,291,219.38 1,339,042.32
211 Tee All RR Ø 8" merk Vinilon Bh 1,972,555.20 2,465,694.00 2,564,321.76 2,662,949.52 2,761,577.28
212 Tee All RR Ø 10" merk Vinilon Bh 2,688,800.40 3,361,000.50 3,495,440.52 3,629,880.54 3,764,320.56
213 Teer / Residu Ltr 8,316.00 10,395.00 10,810.80 11,226.60 11,642.40
214 Teralis Besi M2 415,800.00 519,750.00 540,540.00 561,330.00 582,120.00
215 Terminal Kabel dan MCB 6 A Bh 77,220.00 96,525.00 100,386.00 104,247.00 108,108.00
216 Thermoplastic Kg 35,640.00 44,550.00 46,332.00 48,114.00 49,896.00
217 Knee PVC RRJ Ø 4" merk Vinilon Bh 534,600.00 668,250.00 694,980.00 721,710.00 748,440.00
218 Knee PVC RRJ Ø 6" merk Vinilon Bh 772,200.00 965,250.00 1,003,860.00 1,042,470.00 1,081,080.00
219 Knee PVC RRJ Ø 8" merk Vinilon Bh 891,000.00 1,113,750.00 1,158,300.00 1,202,850.00 1,247,400.00
220 Get Valve RR Ø 8" Bh 7,128,000.00 8,910,000.00 9,266,400.00 9,622,800.00 9,979,200.00
221 Get Valve RR Ø 6" Bh 4,158,000.00 5,197,500.00 5,405,400.00 5,613,300.00 5,821,200.00
222 Get Valve RR Ø 4" Bh 3,088,800.00 3,861,000.00 4,015,440.00 4,169,880.00 4,324,320.00
223 Bend RR Ø 8" Bh 1,039,500.00 1,299,375.00 1,351,350.00 1,403,325.00 1,455,300.00
224 Bend RR Ø 6" Bh 772,200.00 965,250.00 1,003,860.00 1,042,470.00 1,081,080.00
225 Bend RR Ø 4" Bh 653,400.00 816,750.00 849,420.00 882,090.00 914,760.00
226 Bend RR Ø 3" Bh 415,800.00 519,750.00 540,540.00 561,330.00 582,120.00

Catatan :
- Harga Setempat sudah termasuk Pungutan Resmi Lainnya (sesuai daerah ybs).
- Harga Total sudah termasuk Pajak PPn dan Keuntungan Pelaksana.
- Untuk Lokasi yang sulit ditempuh lewat jalan darat dan jauh dari pinggir sungai perlu ditambah dengan
Ongkos Angkut sesuai jauh lokasi atau jarak tempuh angkutan (darat/sungai).
- Harga Bahan Pabrikasi dihitung Harga Pabrik + Ongkos Kirim + Pajak PPN dan Keuntungan Pelaksana.
C. UPAH
REGIONAL
REGION I REGION II REGION III REGION IV
Kec. Tanah Siang Kec. Sumber Barito
Harga Dasar Kec. Barito Tuhup Raya Kec. Sei Babuat Kec. U'ut Murung
No. JENIS KEAHLIAN SAT. KODE Kec. Murung KET.
(Rp.) Kec. Laung Tuhup Kec. Permata Intan Kec. Seribu Riam
Kec. Tanah Siang Selatan
Total Total Total Total
(Rp.) (Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10

1 Mandor /Hari L.061 115,500.00 144,375.00 150,150.00 155,925.00 161,700.00


2 Mekanik /Hari L.071 111,100.00 138,875.00 144,430.00 149,985.00 155,540.00
3 Kepala Tukang (Batu, Besi, Kayu, Cat, Gali ) /Hari L.073 112,750.00 140,937.50 146,575.00 152,212.50 157,850.00
4 Tukang (Batu, Besi, Kayu, Cat, Gali ) /Hari L.079 107,625.00 134,531.25 139,912.50 145,293.75 150,675.00
5 Pekerja / Buruh Semi Terlatih /Hari L.103 105,575.00 131,968.75 137,247.50 142,526.25 147,805.00
6 Operator Terlatih /Hari L.081 300,000.00 375,000.00 390,000.00 405,000.00 420,000.00
7 Operator Kurang Terlatih / Pembantu Operator /Hari L.082 120,000.00 150,000.00 156,000.00 162,000.00 168,000.00
8 Sopir Terlatih /Hari L.091 150,000.00 187,500.00 195,000.00 202,500.00 210,000.00
9 Pembantu Sopir /Hari L.099 107,625.00 134,531.25 139,912.50 145,293.75 150,675.00

Keterangan :
Regional I : Kecamatan Murung

Regional II : Kecamatan Tanah Siang


Kecamatan Tanah Siang Selatan
Kecamatan Laung Tuhup
Kecamatan Barito Tuhup Raya

Regional III : Kecamatan Permata Intan


Kecamatan Sei Babuat

Regional IV : Kecamatan Sumber Barito


Kecamatan U'ut Murung
Kecamatan Seribu Riam
PEMERINTAH DAERAH KABUPATEN MURUNG RAYA
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jl. Letjend Soeprapto Telp. (0528) 31801 Fax. (0528) 31692 Puruk Cahu 73911

RENCANA ANGGARAN BIAYA

PROGRAM : Program Pembangunan Prasarana Sanitasi


KEGIATAN : Pembuatan Prasarana Sanitasi ( DAK )
PEKERJAA : Pembangunan Baru SPAL Terpusat Skala Komunal Domestik Kecamatan Murung Paket 2 (D
LOKASI : Desa Danau Usung, Kec. Murung
TAHUN : 2017
RENCANA ANGGARAN BIAYA
(RAB)

NILAI FISIK:
Rp 456,000,000.00

### EMPAT RATUS LIMA PULUH ENAM JUTA RUPIAH ###

PROGRAM :
Program Pembangunan Prasarana Sanitasi

KEGIATAN :
-

PEKERJAAN :
-

LOKASI :
-

TAHUN :
2017
RENCANA ANGGARAN BIAYA (RAB)
Program : Program Pembangunan Prasarana Sanitasi
Kegiatan : Pembuatan Prasarana Sanitasi ( DAK )
Pekerjaan : Pembangunan Baru SPAL Terpusat Skala Komunal Domestik Kecamatan Murung Paket 2 (DAK)
Lokasi : Desa Danau Usung, Kec. Murung
Tahun : 2017

Harga satuan Total Harga


No Uraian Pekerjaan Analisa Volume
(Rp.) (Rp.)
1 2 3 4 5 6

I PEKERJAAN PENDAHULUAN
1 Pekerjaan Pembersihan Lokasi - 1.00 Keg 1,000,000.00 1,000,000.00
2 Pekerjaan Pengukuran dan Pemasangan Bowplank - 1.00 Keg 1,713,000.00 1,713,000.00
3 Pembuatan Papan Nama Kegiatan - 1.00 Bh 400,000.00 400,000.00
Jumlah I 3,504,980.00

II PEKERJAAN TANAH DAN URUGAN


1 Galian Tanah A.2.3.1.1 290.55 M3 82,068.75 23,845,157.38
2 Urugan Tanah Kembali A.2.3.1.9 69.19 M3 58,562.50 4,052,134.58
3 Urugan Pasir A.2.3.1.11 2.48 M3 167,227.50 414,807.81

Jumlah II 28,312,099.78

III PEKERJAAN SLOOF, KOLOM, BALOK , RINGBALK BETON, DAN PASANGAN


1 Pek. Sloof Beton 15/25 A. A.4.1.1.5. 1.69 M3 1,032,646.92 1,742,591.67
2 Pek. Sloof Beton 15/15 A. A.4.1.1.5. 0.41 M3 1,032,646.92 418,222.00
3 Pek. Kolom Beton 15/15 A. A.4.1.1.5. 1.57 M3 1,032,646.92 1,619,448.53
4 Pek. Ring Balk 15/25. A. A.4.1.1.5. 2.33 M3 1,032,646.92 2,400,904.08
5 Pek. Balok 10/10. A. A.4.1.1.5. 0.02 M3 1,032,646.92 16,522.35
6 Pek. Beton Plat Lantai T= 10 cm. A. A.4.1.1.5. 2.63 M3 1,032,646.92 2,710,698.16
7 Pek Cor Beton Lantai T= 10 cm. A. A.4.1.1.4. 1.70 M3 860,675.97 1,459,706.45
8 Pek. Plat lantai Dak Atas T= 15 cm. A. A.4.1.1.5. 4.58 M3 1,032,646.92 4,729,006.56
9 Pek. Dinding Beton. A. A.4.1.1.5. 23.77 M3 1,032,646.92 24,548,598.84
10 Pek. Dinding Bata. A. 4.4.1.2 12.60 M2 311,815.45 3,928,874.73
11 Pek. Beton Plat Tutup Grease Trap,Black Water dan Manhole. A. A.4.1.1.5. 1.10 M3 1,032,646.92 1,140,042.20
12 Pek. Bak Input Penyaring. A. A.4.1.1.5. 0.10 M3 1,032,646.92 103,264.69
13 Pek. Beton penyangga Saringan 10/10. A. A.4.1.1.5. 0.02 M3 1,032,646.92 20,652.94

Jumlah III 44,838,533.20

IV PEKERJAAN PEMBESIAN
1 Pembesian Sloof 15/25. A.4.1.1.17 232.20 Kg 14,067.53 3,266,479.31
2 Pembesian Sloof 15/15. A.4.1.1.17 83.28 Kg 14,067.53 1,171,543.48
3 Pembesian Kolom 15/15 A.4.1.1.17 322.48 Kg 14,067.53 4,536,476.71
4 Pembesian ring Balk 15/25. A.4.1.1.17 319.92 Kg 14,067.53 4,500,482.60
5 Pembesian Lantai Bawah T= 10 cm. A.4.1.1.17 445.57 Kg 14,067.53 6,268,114.01
6 Pembesian Lantai Atas atau Dak T= 10 cm. A.4.1.1.17 514.19 Kg 14,067.53 7,233,333.79
7 Pembesian Dinding . A.4.1.1.17 2,286.77 Kg 14,067.53 32,169,147.25
8 Pembesian Untuk Tutup Grease Trap,Black Water dan Manhole. A.4.1.1.17 242.71 Kg 14,067.53 3,414,319.61
9 Pembesian Bak Input Penyaring. A.4.1.1.17 8.27 Kg 14,067.53 116,291.54

Jumlah IV 62,676,188.29

V PEKERJAAN BEKISTING
1 Bekisting Sloof A.4.1.1.21 27.90 M2 166,066.00 4,633,241.40
2 Bekising Kolom A.4.1.1.22 41.82 M2 196,311.00 8,209,726.02
3 Bekisting RingBalk A.4.1.1.23 18.60 M2 198,627.60 3,694,473.36
4 Bekisting Lantai Dak A.4.1.1.24.a 29.93 M2 196,311.00 5,875,588.23
5 Bekisting Dinding A.4.1.1.25.a. 269.07 M2 184,672.00 49,688,956.35
6 Bekisting Bak Input Penyaring. A.4.1.1.25.a. 1.40 M2 184,672.00 258,540.80

Jumlah V 72,360,526.16

VI PEKERJAAN PLESTERAN
1 Pek. Plesteran Bangunan Utama A.4.4.2.3 229.50 M2 67,458.22 15,481,661.07
2 Pek. Plesteran Bak Pengumpul A.4.4.2.3 25.20 M2 67,458.22 1,699,947.10
3 Pek. Plesteran Grease Trap (Bak Kontrol I ) A.4.4.2.3 51.84 M2 67,458.22 3,497,034.03
4 Pek. Plesteran Black Water (Bak Kontrol II ) A.4.4.2.3 51.84 M2 67,458.22 3,497,034.03
5 Pek. Plesteran Manhole A.4.4.2.3 51.20 M2 67,458.22 3,453,860.77
6 Plesteran Untuk Tutup Grease Trap,Black Water dan Manhole. A.4.4.2.3 44.16 M2 67,458.22 2,978,954.91
7 Pek. Plesteran Bak Input Penyaring A.4.4.2.3 1.40 M2 67,458.22 94,441.51

Jumlah VI 30,702,933.42

VII PEKERJAAN ACIAN


1 Acian Bangunan Utama A.4.4.2.27 229.50 M2 38,658.75 8,872,183.13
2 AcianBak Pengumpul A.4.4.2.27 25.20 M2 38,658.75 974,200.50
3 Acian Grease Trap A.4.4.2.27 51.84 M2 38,658.75 2,004,069.60
4 Acian Bak Kontrol II A.4.4.2.27 51.84 M2 38,658.75 2,004,069.60
5 Acian Manhole A.4.4.2.27 51.20 M2 38,658.75 1,979,328.00
6 Acian Tutup Manhole dan Bak Input Penyaring A.4.4.2.27 45.56 M2 38,658.75 1,761,292.65

Jumlah VII 17,595,143.48

VIII PEKERJAAN PAS. PIPA DAN AKSESORIS


1 Pas. Pipa PVC Ø 6" A.8.4.1.4 460.70 M 140,360.39 64,664,032.44
2 Pas. Pipa PVC Ø 4" A.8.4.1.2 1,066.40 M 63,521.93 67,739,780.82
3 Pas. Pipa PVC Ø 3" A.8.4.1.1 898.26 M 52,638.20 47,282,789.53
4 Pas. Tee PVC Ø 3" A.8.4.3.15 96.00 Bh 42,165.58 4,047,895.20
5 Pas. Knee PVC Ø 3" A.8.4.3.1 18.00 Bh 268,335.05 4,830,030.90
6 Pas. Arang Untuk Filter - 1,277.15 Kg 5,000.00 6,385,732.32
7 Pas. Penyaring Ulin 5/5 - 0.20 M3 5,300,000.00 1,060,000.00

Jumlah VIII 196,010,261.22


REKAPITULASI RENCANA ANGGARAN BIAYA
No URAIAN PEKERJAAN JUMLAH
I PEKERJAAN PENDAHULUAN 3,504,980.00
II PEKERJAAN TANAH DAN URUGAN 28,312,099.78
III PEKERJAAN SLOOF, KOLOM, BALOK , RINGBALK BETON, DAN PASANGAN 44,838,533.20
IV PEKERJAAN PEMBESIAN 62,676,188.29
V PEKERJAAN BEKISTING 72,360,526.16
VI PEKERJAAN PLESTERAN 30,702,933.42
VII PEKERJAAN ACIAN 17,595,143.48
VIII PEKERJAAN PAS. PIPA DAN AKSESORIS 196,010,261.22

JUMLAH TOTAL 456,000,665.54


DIBULATKAN 456,000,000.00

Terbilang : ### EMPAT RATUS LIMA PULUH ENAM JUTA RUPIAH ###
PERHITUNGAN VOLUME
Program : Program Pembangunan Prasarana Sanitasi
Kegiatan : Pembuatan Prasarana Sanitasi ( DAK )
Pekerjaan : Pembangunan Baru SPAL Terpusat Skala Komunal Domestik Kecamatan Murung Paket 2 (DAK)
Lokasi : Desa Danau Usung, Kec. Murung
Tahun : 2,017

No. URAIAN PEKERJAAN Uraian Perhitungan Jumlah

1 2 3 4
I PEKERJAAN PENDAHULUAN
1 Pekerjaan Pembersihan Lokasi
= 1.00 x 1.00 = 1.00 Keg
2 Pekerjaan Pengukuran dan Pemasangan Bowplank
= 1.00 x 1.00 = 1.00 Keg
3 Pembuatan Papan Nama Kegiatan
= 1.00 x 1.00 = 1.00 Bh
II PEKERJAAN TANAH DAN URUGAN
1 a. Galian Tanah Untuk Konstruksi Utama
Area I = 1.00 x 1.00 x 1.75 = 1.75
Area II = 8.00 x 3.00 x 2.50 = 60.00
Area III = 1.00 x 3.00 x 0.90 = 2.70
Area IV = 1.50 x 1.50 x 2.50 = 5.63
70.08 Jumlah = 70.08 M3

b. Galian Tanah Untuk Grease Trap Bak Kontrol I


= 0.60 x 0.60 x 0.60 x 18.00 = 3.89 Jumlah = 3.89 M3

c. Galian Tanah Untuk Black Water Bak Kontrol II


= 0.60 x 0.60 x 0.60 x 18.00 = 3.89 Jumlah = 3.89 M3

d. Galian Tanah Untuk Bak Manhole


= 0.80 x 0.80 x 0.80 x 10.00 = 5.12 Jumlah = 5.12 M3

2 a. Urugan Pasir Untuk Konstruksi Utama


Area I = 1.00 x 1.00 x 0.05 = 0.05
Area II = 8.00 x 3.00 x 0.05 = 1.20
Area III = 1.00 x 3.00 x 0.05 = 0.15
Area IV = 1.50 x 1.50 x 0.05 = 0.11
1.51 Jumlah = 1.513 M3

b. Urugan Pasir Untuk Grease Trap Bak Kontrol I


= 0.60 x 0.60 x 0.05 x 18.00 = 0.32 Jumlah = 0.32 M3

c. Urugan Pasir Untuk Black Water Bak Kontrol II


= 0.60 x 0.60 x 0.05 x 18.00 = 0.32 Jumlah = 0.32 M3

d. Urugan pasir Untuk Bak Manhole


= 0.80 x 0.80 x 0.05 x 10.00 = 0.32 Jumlah = 0.32 M3

III PEKERJAAN SLOOF, KOLOM, BALOK , RINGBALK BETON, DAN PASANGAN

1 a. Pek. Sloof Beton 15/25 cm beton mutu f’ = 14.5 Mpa Bangunan Utama
Melintang = 3.00 x 7.00 = 21.00 m
Memanjang = 3.00 x 8.00 = 24.00 m
45.00 m
= 0.15 x 0.25 x 45.00 = 1.69
1.69 Jumlah = 1.688 M3

b. Pek. Sloof 15/15 cm beton mutu f’ = 14.5 MPa Bangunan Outlet


Melintang = 1.00 x 2.00 = 2.00 m
Memanjang = 1.00 x 2.00 = 2.00 m
4.00 m
= 0.15 x 0.15 x 4.00 = 0.09
0.09 Jumlah = 0.090 M3

c. Pek. Sloof Beton 15/15 cm beton mutu f’ = 14.5 MPa Bangunan Inlet
Melintang = 3.00 x 2.00 = 6.00 m
Memanjang = 1.00 x 2.00 = 2.00 m
8.00 m
= 0.15 x 0.15 x 8.00 = 0.18
0.18 Jumlah = 0.180 M3

c. Pek. Sloof Beton 15/15 cm beton mutu f’ = 14.5 MPa Bangunan Bak Pengumpul
Melintang = 1.50 x 2.00 = 3.00 m
Memanjang = 1.50 x 2.00 = 3.00 m
6.00 m
No. URAIAN PEKERJAAN Uraian Perhitungan Jumlah

1 2 3 4
= 0.15 x 0.15 x 6.00 = 0.14
0.14 Jumlah = 0.135 M3

4 a. Pek. Kolom Beton 15/15 cm beton mutu f’ = 14.5 MPa Bangunan Utama
= 0.15 x 0.15 x 2.50 x 22.00 = 1.24
= 0.15 x 0.15 x 1.75 x 2.00 = 0.08
= 0.15 x 0.15 x 0.90 x 2.00 = 0.04
1.36 Jumlah = 1.357 M3

b. Pek. Kolom Beton 15/15 cm beton mutu f’ = 14.5 MPa Bangunan Bak Pengumpul
= 0.15 x 0.15 x 2.35 x 4.00 = 0.21
0.21 Jumlah = 0.212 M3

5 a. Pek. Ring Balk Beton 15/25 cm beton mutu f’ = 14.5 MPa Bangunan Utama
Melintang = 3.00 x 7.00 = 21.00 m
Memanjang = 3.00 x 8.00 = 24.00 m
45.00 m
= 0.15 x 0.25 x 45.00 = 1.69
1.69 Jumlah = 1.688 M3

b. Pek. Ring Balk Beton 15/25 cm beton mutu f’ = 14.5 MPa Bangunan Outlet
Melintang = 1.00 x 1.00 = 1.00 m
Memanjang = 2.00 x 1.00 = 2.00 m
3.00 m
= 0.15 x 0.25 x 3.00 = 0.11
0.11 Jumlah = 0.113 M3

c. Pek. Ring Balk Beton 15/25 cm beton mutu f’ = 14.5 MPa Bangunan Inlet
Melintang = 3.00 x 2.00 = 6.00 m
Memanjang = 2.00 x 1.00 = 2.00 m
8.00 m
= 0.15 x 0.25 x 8.00 = 0.30
0.30 Jumlah = 0.300 M3

d. Pek. Ring Balk Beton 15/25 cm beton mutu f’ = 14.5 MPa Bak Pengumpul
Melintang = 1.50 x 2.00 = 3.00 m
Memanjang = 1.50 x 2.00 = 3.00 m
6.00 m
= 0.15 x 0.25 x 6.00 = 0.23
0.23 Jumlah = 0.225 M3

d. Pek. Balok Beton 10/10 cm beton mutu f’ = 14.5 MPa Bak input penyaring
Melintang = 0.60 x 1.00 = 0.60 m
Memanjang = 1.00 x 1.00 = 1.00 m
1.60 m
= 0.10 x 0.10 x 1.60 = 0.02
0.02 Jumlah = 0.016 M3

6 a. Pek. Beton Plat t= 10 cm beton mutu f’ = 14.5 MPa Lantai Bawah


Bangunan Utama = 3.00 x 8.00 x 0.10 = 2.40
Bak Pengumpul = 1.50 x 1.50 x 0.10 = 0.23
2.63 Jumlah = 2.63 M3

7 Pek. Beton Lantai mutu f’c = 7,4 MPa t= 10 cm


Bangunan Outlet = 1.00 x 1.00 x 0.10 = 0.10
Bangunan Inlet = 1.00 x 3.00 x 0.10 = 0.30
Bak Grease Trap = 0.60 x 0.60 x 0.10 x 18.00 = 0.65
Bak Black Water = 0.60 x 0.60 x 0.10 x 18.00 = 0.65
Bak manhole = 0.80 x 0.80 x 0.10 x 10.00 = 0.64
1.70 Jumlah = 1.70 M3
8 Pek. Beton Dak Plat t= 15 cm beton mutu f’ = 14.5 Mpa
Bangunan Utama = 3.00 x 9.00 x 0.15 = 4.05
Bak Outlet = 1.00 x 1.00 x 0.15 = 0.15
Bak Inlet = 1.00 x 3.00 x 0.15 = 0.45
Bak Pengumpul = 1.50 x 1.50 x 0.15 = 0.34
Dikurang Tutup Manhole = 0.40 x 0.40 x 0.15 x 17.00 Bh = 0.41
4.58 Jumlah = 4.58 M3

9 a. Pek. Dinding Beton t= 15 cm beton mutu f’ = 14.5 MPa untuk Bangunan Utama
Panjang = 3.00 x 6.00 = 18.00 m
= 8.00 x 2.00 = 16.00 m
= 2.00 x 4.00 = 8.00 m
42.00 m
= 0.15 x 2.50 x 42.00 = 15.75
Bak Outlet = 0.15 x 1.75 x 3.00 = 0.79
Bak Saluran Inlet = 0.15 x 0.90 x 5.00 = 0.68
17.21 Jumlah = 17.213 M3
No. URAIAN PEKERJAAN Uraian Perhitungan Jumlah

1 2 3 4

b. Pek. Dinding Bata Untuk Bak Pengumpul


Panjang = 1.50 x 2.00 = 3.00 m
= 1.50 x 2.00 = 3.00 m
6.00 m
= 6.00 x 2.10 = 12.60
12.60 Jumlah = 12.600 M2

10 a. Pek. Dinding Beton beton mutu f’ = 14.5 MPa untuk Bak Kontrol I Grease Trap
Panjang = 0.60 x 2.00 = 1.20 m
= 0.60 x 2.00 = 1.20 m
2.40 m
= 0.50 x 2.40 x 0.10 x 18.00 = 2.16
2.16 Jumlah = 2.160 M3

b. Pek. Dinding Beton beton mutu f’ = 14.5 MPa untuk Bak Kontrol II Black Water
Panjang = 0.60 x 2.00 = 1.20 m
= 0.60 x 2.00 = 1.20 m
2.40 m
= 0.50 x 2.40 x 0.10 x 18.00 = 2.16
2.16 Jumlah = 2.160 M3

c. Pek. Dinding Beton beton mutu f’ = 14.5 MPa untuk Manhole


Panjang = 0.80 x 2.00 = 1.60 m
= 0.80 x 2.00 = 1.60 m
3.20 m
= 0.70 x 3.20 x 0.10 x 10.00 = 2.24
2.24 Jumlah = 2.240 M3

11 Pek. Beton Plat t= 5 cm beton mutu f’ = 14.5 MPa Tutup Manhole


= 0.40 x 0.40 x 0.05 x 17.00 = 0.14
= 0.60 x 0.60 x 0.05 x 18.00 = 0.32
= 0.60 x 0.60 x 0.05 x 18.00 = 0.32
= 0.80 x 0.80 x 0.05 x 10.00 = 0.32
1.10 Jumlah = 1.104 M3

12 Pek. Beton t= 10 cm beton mutu f’ = 14.5 MPa Bak Input Penyaring dinding dan Lantai
= 0.60 x 1.00 x 0.10 x 1.00 = 0.06
= 0.40 x 1.00 x 0.10 x 1.00 = 0.04
0.10 Jumlah = 0.100 M3

13 Pek. Beton Kotak Penyangga 10/10


= 0.10 x 0.10 x 0.10 x 4.00 x 5.00 = 0.02

0.02 Jumlah = 0.020 M3

IV PEKERJAAN PEMBESIAN

1 Pek. Pembesian Sloof 15/25 4 Ø 12


Total Panjang = 45.00 m
= 4.00 x 45.00 x 0.89 = 160.20
Cincin Ø 8 - 150 = 45.00 ; 0.15 = 300.00
= 0.60 x 300.00 x 0.40 = 72.00
232.20 Jumlah = 232.200 Kg

2 Pek. Pembesian Sloof 15/15 4 Ø 12


Total Panjang = 18.00 m
= 4.00 x 18.00 x 0.89 = 64.08
Cincin Ø 8 - 150 = 18.00 ; 0.15 = 120.00
= 0.40 x 120.00 x 0.40 = 19.20
83.28 Jumlah = 83.280 Kg

3 Pek. Pembesian Kolom Praktis 15/15 4 Ø 12


Total Panjang = 69.70 m
= 4.00 x 69.70 x 0.89 = 248.13
Cincin Ø 8 - 150 = 69.70 ; 0.15 = 464.67
= 0.40 x 464.67 x 0.40 = 74.35
322.48 Jumlah = 322.479 Kg

4 Pek. Pembesian Ring Balk 15/25 4 Ø 12


Total Panjang = 62.00 m
= 4.00 x 62.00 x 0.89 = 220.72
Cincin Ø 8 - 150 = 62.00 ; 0.15 = 413.33
= 0.60 x 413.33 x 0.40 = 99.20
319.92 Jumlah = 319.920 Kg

5 Pek. Pembesian Lantai t= 10 cm Ø 10 - 150


No. URAIAN PEKERJAAN Uraian Perhitungan Jumlah

1 2 3 4
Bangunan Utama
Melintang = 8.00 / 0.15 = 53.33
Total = 6.20 x 53.33 x 0.62 = 205.01
Memanjang = 3.00 / 0.15 = 20.00
Total = 16.20 x 20.00 x 0.62 = 200.88
405.89 Jumlah = 405.893 Kg
Bak pengumpul
Melintang = 1.50 / 0.15 = 10.00
Total = 3.20 x 10.00 x 0.62 = 19.84
Memanjang = 1.50 / 0.15 = 10.00
Total = 3.20 x 10.00 x 0.62 = 19.84
39.68 Jumlah = 39.680 Kg

6 a. Pek. Pembesian Dak t= 15 cm Ø 10 - 150 Bangunan Utama dan saluran Inlet


Melintang = 3.00 / 0.15 = 20.00
Total = 18.20 x 20.00 x 0.62 = 225.68
Memanjang = 9.00 / 0.15 = 60.00
Total = 6.20 x 60.00 x 0.62 = 230.64

b. Bak Outlet Melintang = 1.00 / 0.15 = 6.67


Total = 2.20 x 6.67 x 0.62 = 9.09
Memanjang = 1.00 / 0.15 = 6.67
Total = 2.20 x 6.67 x 0.62 = 9.09
474.51 Jumlah = 474.507 Kg

c. Pek. Pembesian Dak t= 15 cm Ø 10 - 150 Bak Pengumpul


Melintang = 1.50 / 0.15 = 10.00
Total = 3.20 x 10.00 x 0.62 = 19.84
Memanjang = 1.50 / 0.15 = 10.00
Total = 3.20 x 10.00 x 0.62 = 19.84
39.68 Jumlah = 39.680 Kg

7 a. Pek. Pembesian Dinding Beton t= 15 cm Ø 10 - 150 Bangunan Utama


Vertikal = 3.00 / 0.15 = 20.00
Total = 84.20 x 20.00 x 0.62 = 1,044
Horizontal = 42.00 / 0.15 = 280.00
Total = 6.20 x 280.00 x 0.62 = 1,076
2,120.4 Jumlah = 2,120.400 Kg
Bak Saluran Outlet
Vertikal = 1.75 / 0.15 = 11.67
Total = 6.20 x 11.67 x 0.62 = 44.85
Horizontal = 3.00 / 0.15 = 20.00
Total = 3.65 x 20.00 x 0.62 = 45.26
90.1 Jumlah = 90.107 Kg

Bak Saluran Inlet


Vertikal = 1.00 / 0.15 = 6.67
Total = 10.20 x 6.67 x 0.62 = 42.16
Horizontal = 5.00 / 0.20 = 25.00
Total = 2.20 x 25.00 x 0.62 = 34.10
76.3 Jumlah = 76.260 Kg

8 a. Pek. Pembesian Tutup Manhole 80 x 80 t= 5 cm Ø 10 - 150


Vertikal = 0.80 / 0.15 = 5.33
Total = 1.00 x 5.33 x 0.62 = 3.31
Horizontal = 0.80 / 0.15 = 5.33
Total = 1.00 x 5.33 x 0.62 = 3.31
6.6 x 10.00 bh Jumlah = 66.133 Kg

b. Pek. Pembesian Tutup Grease Trap 60 x 60 t= 5 cm Ø 10 - 150


Vertikal = 0.60 / 0.15 = 4.00
Total = 0.80 x 4.00 x 0.62 = 1.98
Horizontal = 0.60 / 0.15 = 4.00
Total = 0.80 x 4.00 x 0.62 = 1.98
4.0 x 18.00 bh Jumlah = 71.424 Kg

c. Pek. Pembesian Tutup Bak Kontrol II 60 x 60 t= 5 cm Ø 10 - 150


Vertikal = 0.60 / 0.15 = 4.00
Total = 0.80 x 4.00 x 0.62 = 1.98
Horizontal = 0.60 / 0.15 = 4.00
Total = 0.80 x 4.00 x 0.62 = 1.98
4.0 x 18.00 bh Jumlah = 71.424 Kg

d. Pek. Pembesian Tutup Manhole Septictank 40 x 40 t= 5 cm Ø 10 - 150


Vertikal = 0.40 / 0.15 = 2.67
Total = 0.60 x 2.67 x 0.62 = 0.99
Horizontal = 0.40 / 0.15 = 2.67
Total = 0.60 x 2.67 x 0.62 = 0.99
No. URAIAN PEKERJAAN Uraian Perhitungan Jumlah

1 2 3 4
2.0 x 17.00 bh Jumlah = 33.728 Kg

e. Pek. Pembesian Bak Input Penyaring dinding dan Lantai Ø 10 - 150


Memanjang = 1.00 / 0.15 = 6.67
Total = 1.00 x 6.67 x 0.62 = 4.13
Melintang = 1.00 / 0.15 = 6.67
Total = 1.00 x 6.67 x 0.62 = 4.13
8.3 Jumlah = 8.267 Kg

V PEKERJAAN BEKISTING

2 Pek. Bekisting Sloof 15/25


Total Panjang = 45.00 m
= 0.25 + 0.25 = 0.50
= 45.00 x 0.50 = 22.50 Jumlah = 22.500 m2

3 Pek. Bekisting Sloof 15/15


Total Panjang = 18.00 m
= 0.15 + 0.15 = 0.30
= 18.00 x 0.30 = 5.40 Jumlah = 5.400 m2

4 Pek. Bekisting Kolom 15/15


Total Panjang = 69.70 m
= 0.15 + 0.15 + 0.15 + 0.15 = 0.60
= 69.70 x 0.60 = 41.82 Jumlah = 41.820 m2

5 Pek. Bekisting Ring Balk 15/25


Total Panjang = 62.00 m
= 0.15 + 0.15 = 0.30
= 62.00 x 0.30 = 18.60 Jumlah = 18.600 m2

6 a. Pek. Bekisting Lantai DAK Bangunan Utama


= 3.00 x 9.00 = 27.00
= 1.00 x 1.00 = 1.00
= 26.00 x 0.15 = 3.90
Luasan Tutup Manhole = 0.40 x 0.40 x 16.00 = 2.56
29.34 Jumlah = 29.340 m2

b. Pek. Bekisting Lantai DAK Bak Pengumpul


= 1.50 x 1.50 = 2.25
= 6.00 x 0.15 = 0.90
Luasan Tutup Manhole = 0.40 x 0.40 x 16.00 = 2.56
0.59 Jumlah = 0.590 m2

8 Pek. Bekisting Dinding


a.Luasan Bak Utama = 2.00 x 8.00 = 16.00
= 3.00 x 6.00 = 18.00
= 2.00 x 4.00 = 8.00
42.00
Total = 42.00 x 2.50 x 2.00 = 210.00 Jumlah = 210.000 m2

Dinding Bak Outlet = 1.75 x 3.00 x 2.00 = 10.50 Jumlah = 10.500 m2


Dinding Sal . Inlet = 0.90 x 5.00 x 2.00 = 9.00 Jumlah = 9.000 m2

b.Luasan Dinding Grease Trap


Luasan = 0.60 x 2.40 x 2.00 x 18.00 = 51.84 Jumlah = 51.840 m2

b.Luasan Dinding Bak Kontrol II


Luasan = 0.60 x 2.40 x 2.00 x 18.00 = 51.84 Jumlah = 51.840 m2

d.Luasan Dinding manhole


Luasan = 0.80 x 3.20 x 2.00 x 10.00 = 51.20 Jumlah = 51.200 m2
Total Bekisting Dinding = 384.380 m2
Karena Penggunaan Bisa Berulang Maka Kebutuhan Bekisting = 384.38 x 0.70 = 269.066 m2

8 Pek. Bekisting Bak Input Penyaring


Lantai = 0.60 x 1.00 = 0.60
Dinding = 0.40 x 1.00 x 2.00 ;= 0.80
1.40

Jumlah = 1.400 m2

VI PEKERJAAN PLESTERAN
1 a.Luasan Bak Utama = 2.00 x 8.00 = 16.00
= 3.00 x 6.00 = 18.00
= 2.00 x 4.00 = 8.00
42.00
Total = 42.00 x 2.50 x 2.00 = 210.00 Jumlah = 210.000 m2
No. URAIAN PEKERJAAN Uraian Perhitungan Jumlah

1 2 3 4

Dinding Bak Outlet = 1.75 x 3.00 x 2.00 = 10.50 Jumlah = 10.500 m2


Dinding Sal . Inlet = 0.90 x 5.00 x 2.00 = 9.00 Jumlah = 9.000 m2

Luasan Bak Pengumpul = 6.00 x 2.10 x 2.00 = 25.20 Jumlah = 25.200 m2

b.Luasan Dinding Grease Trap


Luasan = 0.60 x 2.40 x 2.00 x 18.00 = 51.84 Jumlah = 51.840 m2

c.Luasan Dinding Bak Kontrol II


Luasan = 0.60 x 2.40 x 2.00 x 18.00 = 51.84 Jumlah = 51.840 m2

d.Luasan Dinding manhole


Luasan = 0.80 x 3.20 x 2.00 x 10.00 = 51.20 Jumlah = 51.200 m2

2 Pek. Plesteran Beton Plat t= 5 cm ( K 175 ) Tutup Manhole


= 0.40 x 0.40 x 2.00 x 17.00 = 5.44
= 0.60 x 0.60 x 2.00 x 18.00 = 12.96
= 0.60 x 0.60 x 2.00 x 18.00 = 12.96
= 0.80 x 0.80 x 2.00 x 10.00 = 12.80
44.16 Jumlah = 44.160 M2

3 Pek. Plesteran Beton Bak Input Penyaring


Lantai = 0.60 x 1.00 = 0.60
Dinding = 0.40 x 1.00 x 2.00 ;= 0.80
1.40

Jumlah = 1.400 m2

VII PEKERJAAN ACIAN


1 Acian Bangunan Utama Jumlah = 229.500 m2
2 AcianBak Pengumpul Jumlah = 25.200 m2
3 Acian Grease Trap Jumlah = 51.840 m2
4 Acian Bak Kontrol II Jumlah = 51.840 m2
5 Acian Manhole Jumlah = 51.200 m2
6 Acian TutupManhole dan Bak Input Penyaring Jumlah = 45.560 m2

VIII PEKERJAAN PAS. PIPA DAN AKSESORIS


1 Bangunan Utama
Pas. Pipa PVC Ø 3" = 1.56 x 3.00 x 12.00 = 56.16 m
Pas. Pipa PVC Ø 3" = 1.00 x 3.00 x 1.00 = 3.00 m
Pipa Pengisap = 1.20 = 1.20 m
Pipa Outlet = 0.60 = 0.60 m
60.96 Jumlah = 60.960 m
Pas. Tee PVC Ø 3" = 2.00 x 3.00 x 13.00 = 78.00 Bh Jumlah = 78.000 Bh
Ulin 5/5 untuk penyaring = 0.05 x 0.05 x 1.00 x 16.00 x 5.00 bh Jumlah = 0.200 M3
Kebutuhan Arang
Hasil Survey Arang = 0.60 x 0.30 x 0.11 = 0.0198 M3
Harga 1 Zak = 45,000
Berat 1 Zak = 10.00 Kg
Untuk Perhitungan Kebutuhan = 0.85 x 0.85 x 0.70 x 5.00 = 2.53 M3
Untuk Berat 1 Kg = 0.01980 / 10.00 = 0.00198 M3
Untuk Kebutuhan Arang = 2.53 / 0.00198 = 1,277.15 Kg 0.51

2 Bak Grease Trap Kontrol I

Pas. Tee PVC Ø 3" = 1.00 x 18.00 = 18.00 Bh Jumlah = 18.000 Bh


Pas. Knee PVC Ø 3" = 1.00 x 18.00 = 18.00 Bh Jumlah = 18.000 Bh

3 Pas. Pipa Jaringan


Pas. Pipa PVC Ø 6" Untuk Jaringan 50 KK Jumlah = 460.700 m
Galian = 0.30 x 0.40 x 460.70 = 55.28 = 55.284 M3
Urugan = 0.33 x 55.28 = 18.43 18.428 M3

Pas. Pipa PVC Ø 4" Untuk Jaringan 50 KK Jumlah = 1,066.400 m


Galian = 0.20 x 0.40 x 1066.40 = 85.31 = 85.312 M3
Urugan = 0.33 x 85.31 = 28.44 28.437 M3

Pas. Pipa PVC Ø 3" Untuk Jaringan 50 KK Jumlah = 837.300 m


Galian = 0.20 x 0.40 x 837.30 = 66.98 = 66.984 M3
Urugan = 0.33 x 66.98 = 22.33 22.328 M3
ANALISA HARGA SATUAN
A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.75 105,575.00 79,181.25
Mandor L.04 OH 0.025 115,500.00 2,887.50
JUMLAH TENAGA KERJA 82,068.75
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 82,068.75


E Harga Satuan Pekerjaan (D+E) 82,068.75

A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah

Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.5 105,575.00 52,787.50
Mandor L.04 OH 0.05 115,500.00 5,775.00
JUMLAH TENAGA KERJA 58,562.50
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 58,562.50
E Harga Satuan Pekerjaan (D+E) 58,562.50

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3 105,575.00 31,672.50
Mandor L.04 OH 0.01 115,500.00 1,155.00
JUMLAH TENAGA KERJA 32,827.50
B BAHAN
Pasir urug 1.200 112,000.00 134,400.00
JUMLAH HARGA BAHAN 134,400.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 167,227.50
E Harga Satuan Pekerjaan (D+E) 167,227.50
CATATAN
Bobot isi pasir = 1.400 kg/m3. Bobot isi kerikil = 1.350 kg/m3. Buckling factor pasir = 20 %

A.A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100),
slump (3-6) cm, w/c = 0,87
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 1.2 105,575.00 126,690.00
Tukang Batu L.02 OH 0.2 107,625.00 21,525.00
Kepala Tukang L.03 OH 0.02 112,750.00 2,255.00
Mandor L.04 OH 0.06 115,500.00 6,930.00
JUMLAH TENAGA KERJA 157,400.00
B BAHAN
Semen Portland kg 230 1,400.00 322,000.00
Pasir Beton kg 893 165.58 147,866.88
Kerikil kg 1027 227.27 233,409.09
(Maks 30mm)
Air Liter 200
JUMLAH HARGA BAHAN 703,275.97
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 860,675.97
E Harga Satuan Pekerjaan (D+E) 860,675.97

A. A.4.1.1.5. Membuat 1 m3 beton mutu f’ = 14.5 MPa (K 175). slump (12 ± 2) cm. w/c = 0.66

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 105,575.00 174,198.75
Tukang Batu L.02 OH 0.275 107,625.00 29,596.88
Kepala Tukang L.03 OH 0.028 112,750.00 3,157.00
Mandor L.04 OH 0.083 115,500.00 9,586.50
JUMLAH TENAGA KERJA 216,539.13
B BAHAN
Semen Portland kg 326 1,400.00 456,400.00
Pasir Beton kg 760 165.58 125,844.16
Kerikil (Maks 30mm) kg 1029 227.27 233,863.64
Air Liter 215
JUMLAH HARGA BAHAN 816,107.79
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,032,646.92


E Harga Satuan Pekerjaan (D+E) 1,032,646.92

SNI
2002. Membuat 1 m3 beton tumbuk camp 1pc : 3ps : 5kr
07.6.1
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 105,575.00 174,198.75
Tukang Batu L.02 OH 0.2500 107,625.00 26,906.25
Kepala Tukang L.03 OH 0.0250 112,750.00 2,818.75
Mandor L.04 OH 0.0800 115,500.00 9,240.00
JUMLAH TENAGA KERJA 213,163.75
B BAHAN
Semen Portland kg 218.0000 1,400.00 305,200.00
Pasir Beton m3 0.5200 231,818.18 120,545.45
Kerikil m3 0.8700 306,818.18 266,931.82
JUMLAH HARGA BAHAN 692,677.27
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 905,841.02
E Harga Satuan Pekerjaan (D+E) 905,841.02

A.4.1.1.17. Pembesian 10 kg dengan besi polos atau besi ulir

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.07 105,575.00 7,390.25
Tukang Besi L.02 OH 0.07 107,625.00 7,533.75
Kepala Tukang L.03 OH 0.007 112,750.00 789.25
Mandor L.04 OH 0.004 115,500.00 462.00
JUMLAH TENAGA KERJA 16,175.25
B BAHAN
Besi beton (polos/ulir) kg 10.500 11,500.00 120,750.00
Kawat beton kg 0.15 25,000.00 3,750.00
JUMLAH HARGA BAHAN 124,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 140,675.25


E Harga Satuan Pekerjaan (D+E) 10 Kg 140,675.25
F Untuk 1 Kg 14,067.53

A.4.1.1.20 Pemasangan 1 m2 bekisting untuk pondasi

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.52 105,575.00 54,899.00
Tukang Kayu L.02 OH 0.26 107,625.00 27,982.50
Kepala Tukang L.03 OH 0.026 112,750.00 2,931.50
Mandor L.04 OH 0.026 115,500.00 3,003.00
JUMLAH TENAGA KERJA 88,816.00
B BAHAN
Kayu kelas III m3 0.04 1,550,000.00 62,000.00
Paku 5 – 10 cm kg 0.3 25,000.00 7,500.00
Minyak bekisting Liter 0.1
JUMLAH HARGA BAHAN 69,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 158,316.00


e Harga Satuan Pekerjaan (D+E) 158,316.00
A.4.1.1.21 Pemasangan 1 m2 bekisting untuk sloof

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.52 105,575.00 54,899.00
Tukang Kayu L.02 OH 0.26 107,625.00 27,982.50
Kepala Tukang L.03 OH 0.026 112,750.00 2,931.50
Mandor L.04 OH 0.026 115,500.00 3,003.00
JUMLAH TENAGA KERJA 88,816.00
B BAHAN
Kayu kelas III m3 0.045 1,550,000.00 69,750.00
Paku 5 cm – 10 cm kg 0.3 25,000.00 7,500.00
Minyak bekisting Liter 0.1
JUMLAH HARGA BAHAN 77,250.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 166,066.00


E Harga Satuan Pekerjaan (D+E) 166,066.00

A.4.1.1.22 Pemasangan 1 m2 bekisting untuk kolom

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.66 105,575.00 69,679.50
Tukang Kayu L.02 OH 0.33 107,625.00 35,516.25
Kepala Tukang L.03 OH 0.033 112,750.00 3,720.75
Mandor L.04 OH 0.033 115,500.00 3,811.50
JUMLAH TENAGA KERJA 112,728.00
B BAHAN
Kayu kelas III m3 0.04 1,550,000.00 62,000.00
Paku 5 cm – 12 cm kg 0.4 25,000.00 10,000.00
Minyak bekisting Liter 0.2 - -
Balok kayu kelas II m3 0.015 772,200.00 11,583.00
Plywood tebal 9 mm Lbr 0.35
Dolken kayu
Batang 2 - -
8-10cm –panj 4 m
JUMLAH HARGA BAHAN 83,583.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 196,311.00


E Harga Satuan Pekerjaan (D+E) 196,311.00

A.4.1.1.23 Pemasangan 1 m2 bekisting untuk balok

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.66 105,575.00 69,679.50
Tukang Kayu L.02 OH 0.33 107,625.00 35,516.25
Kepala Tukang L.03 OH 0.033 112,750.00 3,720.75
Mandor L.04 OH 0.033 115,500.00 3,811.50
JUMLAH TENAGA KERJA 112,728.00
B BAHAN
Kayu kelas III m3 0.04 1,550,000.00 62,000.00
Paku 5 cm – 12 cm kg 0.4 25,000.00 10,000.00
Minyak bekisting Liter 0.2 - -
Balok kayu kelas II m3 0.018 772,200.00 13,899.60
Plywood tebal 9 mm Lbr 0.35 -
Dolken kayu g
Batang 2 - -
8–10)cm panj4 m
JUMLAH HARGA BAHAN 85,899.60
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 198,627.60
F Harga Satuan Pekerjaan (D+E) 198,627.60

A.4.1.1.24.a. Pemasangan 1 m2 bekisting untuk lantai

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.66 105,575.00 69,679.50
Tukang Kayu L.02 OH 0.33 107,625.00 35,516.25
Kepala Tukang L.03 OH 0.033 112,750.00 3,720.75
Mandor L.04 OH 0.033 115,500.00 3,811.50
JUMLAH TENAGA KERJA 112,728.00
B BAHAN
Kayu kelas III m3 0.040 1,550,000.00 62,000.00
Paku 5 cm – 12 cm kg 0.400 25,000.00 10,000.00
Minyak bekisting Liter
Balok kayu Bekisting m3 0.015 772,200.00 11,583.00
Dolken kayu galam. 8–10 cm
Batang
panjang 4 m
JUMLAH HARGA BAHAN 83,583.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 196,311.00
e Harga Satuan Pekerjaan (D+E) 196,311.00

A.4.1.1.25.a. Pemasangan 1 m2 bekisting untuk dinding

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.66 105,575.00 69,679.50
Tukang Kayu L.02 OH 0.33 107,625.00 35,516.25
Kepala Tukang L.03 OH 0.033 112,750.00 3,720.75
Mandor L.04 OH 0.033 115,500.00 3,811.50
JUMLAH TENAGA KERJA 112,728.00
B BAHAN
Kayu kelas III m3 0.030 1,550,000.00 46,500.00
Paku 5 cm – 12 cm kg 0.400 25,000.00 10,000.00
-
Balok kayu Bekisting m3 0.020 772,200.00 15,444.00
Dolken kayu , 8–10 cm, panj. 4 m
Batang 0.250
JUMLAH HARGA BAHAN 71,944.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 184,672.00
E Harga Satuan Pekerjaan 184,672.00

A.4.4.2.3. Pemasangan 1 m2 plesteran 1SP : 3PP tebal 15mm.

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.3 105,575.00 31,672.50
Tukang Batu L.03 OH 0.15 107,625.00 16,143.75
Kepala Tukang L.03 OH 0.015 112,750.00 1,691.25
Mandor L.04 OH 0.015 115,500.00 1,732.50
JUMLAH TENAGA KERJA 51,240.00
B BAHAN
1.    PC Kg 7.776 1,400.00 10,886.40
2.    PP m3 0.023 231,818.18 5,331.82
JUMLAH HARGA BAHAN 16,218.22
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 67,458.22


E Harga Satuan Pekerjaan (D+E) 67,458.22
A.4.4.2.27. Pemasangan 1 m2 acian.

Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 105,575.00 21,115.00
Tukang Batu L.03 OH 0.100 107,625.00 10,762.50
Kepala Tukang L.03 OH 0.010 107,625.00 1,076.25
Mandor L.04 OH 0.010 115,500.00 1,155.00
JUMLAH TENAGA KERJA 34,108.75
B BAHAN
Semen PC Kg 3.250 1,400.00 4,550.00
JUMLAH HARGA BAHAN 4,550.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 38,658.75


E Harga Satuan Pekerjaan (D+E) 38,658.75

A.8.4.1.4 Pemasangan 1 m pipa PVC Ø 6 "

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.118 105,575.00 12,457.85
Tukang pipa L.02 OH 0.059 107,625.00 6,349.88
Mandor L.04 OH 0.012 115,500.00 1,386.00
JUMLAH TENAGA KERJA 20,193.73
B BAHAN
Pipa Baja Ø 6" m 1 120,166.67 120,166.67
JUMLAH HARGA BAHAN 120,166.67
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 140,360.39
E Harga Satuan Pekerjaan (D+E) 140,360.39

A.8.4.1.2 Pemasangan 1 m pipa PVC Ø 4"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.094 105,575.00 9,924.05
Tukang pipa L.02 OH 0.047 107,625.00 5,058.38
Mandor L.04 OH 0.009 115,500.00 1,039.50
16,021.93
JUMLAH TENAGA KERJA
B BAHAN
Pipa PVC Ø 4" m 1 47,500.00 47,500.00
JUMLAH HARGA BAHAN 47,500.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 63,521.93


E Harga Satuan Pekerjaan (D+E) 63,521.93

A.8.4.1.1 Pemasangan 1 m pipa PVC Ø 3"


Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.081 105,575.00 8,551.58
Tukang pipa L.02 OH 0.041 107,625.00 4,412.63
Mandor L.04 OH 0.008 115,500.00 924.00
13,888.20
JUMLAH TENAGA KERJA
B BAHAN
Pipa PVC Ø 3" m 1 38,750.00 38,750.00
JUMLAH HARGA BAHAN 38,750.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 52,638.20


E Harga Satuan Pekerjaan (D+E) 52,638.20
A.8.4.3.15 Pemasangan 1 buah Tee Ø 3"

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.106 105,575.00 11,190.95
Tukang pipa L.02 OH 0.053 107,625.00 5,704.13
Mandor L.04 OH 0.011 115,500.00 1,270.50

JUMLAH TENAGA KERJA 18,165.58


B BAHAN
Tee Ø 3 " bh 1 24,000.00 24,000.00
JUMLAH HARGA BAHAN 24,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 42,165.58


E Harga Satuan Pekerjaan (D+E) 42,165.58

A.8.4.3.1 Pemasangan 1 buah Knee Ø 3 "

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 1.429 105,575.00 150,866.68
Tukang pipa L.02 OH 0.715 107,625.00 76,951.88
Mandor L.04 OH 0.143 115,500.00 16,516.50

JUMLAH TENAGA KERJA 244,335.05


B BAHAN
Knee Ø 3" bh 1 24,000.00 24,000.00
JUMLAH HARGA BAHAN 24,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 268,335.05


E Harga Satuan Pekerjaan (D+E) 268,335.05

A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP

Harga Satuan Jumlah


No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 0.6 105,575.00 63,345.00
Tukang Batu L.02 OH 0.2 107,625.00 21,525.00
Kepala Tukang L.03 OH 0.02 112,750.00 2,255.00
Mandor L.04 OH 0.03 115,500.00 3,465.00
JUMLAH TENAGA KERJA 90,590.00
B BAHAN
Bata merah m3 140 1,100.00 154,000.00
Semen Portlan Kg 32.95 1,400.00 46,130.00
Pasir Pasang m3 0.091 231,818.18 21,095.45
JUMLAH HARGA BAHAN 221,225.45
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 311,815.45


E Harga Satuan Pekerjaan (D+E) 311,815.45
HARGA SATUAN UPAH DAN BAHAN

Program : Program Percepatan Pembangunan Sanitasi Permukiman


Kegiatan : Percepatan Pembangunan Sanitasi Permukimnan
Pekerjaan : Sanitasi (DAK)
Lokasi : Kec. Murung
Tahun : 2017

A. BAHAN

No. Nama Bahan Satuan Kode Harga

1 Kerikil Sungai M3 M 012 281,818.18


2 Kerikil Sungai Ayak Tanpa Pasir M3 M 013 306,818.18
3 Pasir Urug / Timbunan M3 M 040 112,000.00
4 Pasir Ayak Untuk Beton M3 M 041 231,818.18
5 Semen Portland (PC) Lokal Kalimantan Setara merk Conch (1 zak = 50 kg) Zak M 080 70,000.00
6 Besi Beton Polos (top) Kg M 167 11,500.00
8 Kawat Beton (Bindrat) Kg 25,000.00
9 Kayu Bekisting M3 M.180 772,200.00
10 Kayu Bulat Ø 6 - 10 cm panjang 4 m Btg 9,500.00
11 Minyak Pelumas (SAE 30) / Minyak Bekisting Ltr M.185 35,000.00
12 Paku Kayu (2") Kg 25,000.00
13 Paku Kayu (2,5" - 5") Kg 25,000.00
14 Papan Bekisting M3 1,550,000.00
15 Plastik Cor M2 6,000.00
17 Pipa Paralon PVC Ø 4" AW, panjang 4 m Setara merk Super Intilon M 47,500.00
18 Pipa Paralon PVC Ø 3" AW, panjang 4 m Setara merk Super Intilon M 38,750.00
19 Pipa Paralon PVC Ø 6" AW, panjang 6 m Setara merk Maspion M 120,166.67
36 Knee PVC Ø 3" setara merk Maspion (DV) Bh 24,000.00
37 Tee Pipa Ø 3' Bh 24,000.00
38 Bata merah Bh 1,100.00
39 Balok Ulin Kecil M3 5,300,000.00
40 Arang Kg 5,000.00

B. UPAH TENAGA KERJA

No. Jenis Keahlian Satuan Kode Harga

1 Mandor Oh L.061 115,500.00


2 Kepala Tukang (Batu, Besi, Kayu, Cat, Gali ) Oh L.073 112,750.00
3 Tukang (Batu, Besi, Kayu, Cat, Gali ) Oh L.079 107,625.00
4 Pekerja / Buruh Semi Terlatih Oh L.106 105,575.00
DAFTAR HARGA SATUAN B
SEMESTER I
DINAS PEKERJAAN UMUM K

A. BAHAN LOKAL DOMINAN YANG SANGAT DIPENGARUHI BIAYA ANGKUT


HARGA
DASAR
NO. BAHAN KODE SAT SUMBER BAHAN
SETEMPAT
(1) (2) (3) (4) (5) (RP.)
(6)

1 Batu Gunung/Batu Belah M 010 m3 Puruk Cahu 204,545


Saripoi 390,000
Dirung Lingkin 350,000
Muara Laung 390,000
Makunjung 450,000
Tbg Lahung 374,000
Tbg Kunyi 650,000
Tbg Bantian 475,000
Tbg Olong 374,000
Muara Joloi 500,000

2 Batu Pecah 10 - 15 cm M 026 m3 Puruk Cahu 379,545


(Manual) Saripoi 565,000
Dirung Lingkin 525,000
Muara Laung 565,000
Makunjung 694,000
Tbg Lahung 490,000
Tbg Kunyi 626,000
Tbg Bantian 572,000
Tbg Olong 490,000
Muara Joloi 640,000

3 Batu Pecah 5 - 7 cm M 022 m3 Puruk Cahu 429,545


(Manual) Saripoi 615,000
Dirung Lingkin 575,000
Muara Laung 615,000
Makunjung 840,000
Tbg Lahung 619,000
Tbg Kunyi 767,000
Tbg Bantian 708,000
Tbg Olong 619,000
Muara Joloi 796,000

4 Batu Pecah 3 - 5 cm M 023 m3 Puruk Cahu 454,545


(Alat) (Produksi) Saripoi 640,000
Dirung Lingkin 600,000
Muara Laung 640,000
Makunjung -
Tbg Lahung -
Tbg Kunyi -
Tbg Bantian -
Tbg Olong -
Muara Joloi -

5 Batu Pecah 2 - 3 cm M 024 m3 Puruk Cahu 454,545


(Alat) (Produksi) Saripoi 640,000
Dirung Lingkin 600,000
Muara Laung 640,000
Makunjung -
Tbg Lahung -
Tbg Kunyi -
Tbg Bantian -
Tbg Olong -
Muara Joloi -

6 Batu Pecah 1 - 2 cm M 025 m3 Puruk Cahu 454,545


(Alat) (Produksi) Saripoi 640,000
Dirung Lingkin 600,000
Muara Laung 640,000
Makunjung -
Tbg Lahung -
Tbg Kunyi -
Tbg Bantian -
Tbg Olong -
Muara Joloi -

7 Batu Pecah 0,5 - 1 cm M 026 m3 Puruk Cahu 454,545


(Alat) (Produksi) Saripoi 640,000
Dirung Lingkin 600,000
Muara Laung 640,000
Makunjung -
Tbg Lahung -
Tbg Kunyi -
Tbg Bantian -
Tbg Olong -
Muara Joloi -

8 Batu Pecah Tersaring M 018 m3 Puruk Cahu 454,545


(Alat) (Produksi) Saripoi 640,000
Dirung Lingkin 600,000
Muara Laung 640,000
Makunjung -
Tbg Lahung -
Tbg Kunyi -
Tbg Bantian -
Tbg Olong -
Muara Joloi -

9 Debu Batu m3 Puruk Cahu 454,545


Saripoi 640,000
Dirung Lingkin 600,000
Muara Laung 640,000
Makunjung -
Tbg Lahung -
Tbg Kunyi -
Tbg Bantian -
Tbg Olong -
Muara Joloi -

10 Kerikil Galian Bukit M 011 m3 Puruk Cahu 181,818


(Awcas) Saripoi 370,000
Dirung Lingkin 330,000
Muara Laung 370,000
Makunjung -
Tbg Lahung -
Tbg Kunyi -
Tbg Bantian -
Tbg Olong -
Muara Joloi -

11 Kerikil Sungai M 012 m3 Puruk Cahu 281,818


Saripoi 470,000
Dirung Lingkin 430,000
Muara Laung 470,000
Makunjung 437,000
Tbg Lahung 450,000
Tbg Kunyi 499,000
Tbg Bantian 437,000
Tbg Olong 374,000
Muara Joloi 454,000

12 Kerikil Sungai Ayak M 013 m3 Puruk Cahu 306,818


Tanpa Pasir Saripoi 495,000
Dirung Lingkin 455,000
Muara Laung 495,000
Makunjung 400,000
Tbg Lahung 600,000
Tbg Kunyi 522,000
Tbg Bantian 460,000
Tbg Olong 397,000
Muara Joloi 477,000

13 Pasir Urug / Timbunan M 040 m3 Puruk Cahu 112,000


Saripoi 171,000
Dirung Lingkin 179,000
Muara Laung 268,000
Makunjung 300,000
Tbg Lahung 310,000
Tbg Kunyi 202,000
Tbg Bantian 191,000
Tbg Olong 191,000
Muara Joloi 250,000

14 Pasir Ayak Untuk M 041 m3 Puruk Cahu 231,818


Beton / Pasir Barito. Saripoi 420,000
Dirung Lingkin 380,000
Muara Laung 420,000
Makunjung 374,000
Tbg Lahung 400,000
Tbg Kunyi 600,000
Tbg Bantian 500,000
Tbg Olong 400,000
Muara Joloi 500,000

15 Sirtu (tidak diayak, dari M 042 m3 Puruk Cahu 166,818


sungai) Saripoi 355,000
Dirung Lingkin 315,000
Muara Laung 355,000
Makunjung 437,000
Tbg Lahung 437,000
Tbg Kunyi 534,000
Tbg Bantian 400,000
Tbg Olong 400,000
Muara Joloi 500,000

16 Tanah Timbunan M 050 m3 Puruk Cahu 80,000


Saripoi 150,000
Dirung Lingkin 150,000
Muara Laung 150,000
Makunjung 238,000
Tbg Lahung 250,000
Tbg Kunyi 200,000
Tbg Bantian 179,000
Tbg Olong 179,000
Muara Joloi 238,000

17.a Semen Portland M 080 zak Puruk Cahu 70,000


Lokal Kalimantan Saripoi 85,000
Setara merk Conch Dirung Lingkin 85,000
(1 zak = 50 kg) Muara Laung 80,000
Makunjung 68,000
Tbg Lahung 88,000
Tbg Kunyi 170,000
Tbg Bantian 133,000
Tbg Olong 143,000
Muara Joloi 220,000

17.b Semen Portland M 080 zak Puruk Cahu 85,000


Non Lokal Kalimantan Saripoi 100,000
Setara merk Semen Gresik Dirung Lingkin 100,000
(1 zak = 50 kg) Muara Laung 95,000
Makunjung 85,000
Tbg Lahung 103,000
Tbg Kunyi 200,000
Tbg Bantian 148,000
Tbg Olong 158,000
Muara Joloi 236,000
18 Besi Beton Polos (top) M 167 Kg Puruk Cahu 11,500
Saripoi 13,000
Dirung Lingkin 13,000
Muara Laung 13,000
Makunjung 13,500
Tbg Lahung 14,000
Tbg Kunyi 14,500
Tbg Bantian 14,400
Tbg Olong 14,600
Muara Joloi 15,000

19 Kayu Ulin Balok Besar M 181 m3 Puruk Cahu 5,300,000


Saripoi 5,100,000
Dirung Lingkin 5,300,000
Muara Laung 6,800,000
Makunjung 5,600,000
Tbg Lahung 4,500,000
Tbg Kunyi 6,200,000
Tbg Bantian 6,200,000
Tbg Olong 5,000,000
Muara Joloi 4,700,000

20 Kayu Ulin Balok Kecil M 181 m3 Puruk Cahu 5,500,000


Saripoi 5,100,000
Dirung Lingkin 5,300,000
Muara Laung 6,500,000
Makunjung 5,400,000
Tbg Lahung 5,000,000
Tbg Kunyi 6,000,000
Tbg Bantian 6,000,000
Tbg Olong 5,000,000
Muara Joloi 4,500,000

21 Papan Ulin M 181 m3 Puruk Cahu 6,000,000


Saripoi 5,900,000
Dirung Lingkin 5,900,000
Muara Laung 8,100,000
Makunjung 8,100,000
Tbg Lahung 6,300,000
Tbg Kunyi 6,000,000
Tbg Bantian 6,000,000
Tbg Olong 5,300,000
Muara Joloi 5,500,000

22 Kayu Lanan Balok Kecil m3 Puruk Cahu 2,600,000


Saripoi 2,500,000
Dirung Lingkin 2,400,000
Muara Laung 1,800,000
Makunjung 1,800,000
Tbg Lahung 2,500,000
Tbg Kunyi 2,400,000
Tbg Bantian 2,300,000
Tbg Olong 2,300,000
Muara Joloi 2,100,000

23 Papan Lanan m3 Puruk Cahu 2,600,000


Saripoi 2,500,000
Dirung Lingkin 2,600,000
Muara Laung 2,100,000
Makunjung 2,100,000
Tbg Lahung 2,500,000
Tbg Kunyi 2,400,000
Tbg Bantian 2,300,000
Tbg Olong 2,300,000
Muara Joloi 2,200,000

Keterangan :
Regional I : Kecamatan Murung

Regional II : Kecamatan Tanah Siang


Kecamatan Tanah Siang Selatan
Kecamatan Laung Tuhup
Kecamatan Barito Tuhup Raya

Regional III : Kecamatan Permata Intan


Kecamatan Sei Babuat

Regional IV : Kecamatan Sumber Barito


Kecamatan Uut Murung
Kecamatan Seribu Riam
AR HARGA SATUAN BAHAN DAN UPAH
SEMESTER I 2017
PEKERJAAN UMUM KAB MURUNG RAYA

HARGA REGIONAL ONGKOS ANGKUT KE LOKASI


REGIONAL I REGIONAL II REGIONAL III REGIONAL IV PEKERJAAN
(7) (8) (9) (10) (11)

255,682 = [(150.000 + (15.000 x jarak)] / 3


487,500 = [(150.000 + (15.000 x jarak)] / 3
437,500 = [(150.000 + (15.000 x jarak)] / 3
487,500 = [(150.000 + (15.000 x jarak)] / 3
562,500 = [(150.000 + (15.000 x jarak)] / 3
467,500 = [(150.000 + (15.000 x jarak)] / 3
812,500 = [(150.000 + (15.000 x jarak)] / 3
593,750 = [(150.000 + (15.000 x jarak)] / 3
467,500 = [(150.000 + (15.000 x jarak)] / 3
625,000 = [(150.000 + (15.000 x jarak)] / 3

474,432 = [(150.000 + (15.000 x jarak)] / 3


706,250 = [(150.000 + (15.000 x jarak)] / 3
656,250 = [(150.000 + (15.000 x jarak)] / 3
706,250 = [(150.000 + (15.000 x jarak)] / 3
867,500 = [(150.000 + (15.000 x jarak)] / 3
612,500 = [(150.000 + (15.000 x jarak)] / 3
782,500 = [(150.000 + (15.000 x jarak)] / 3
715,000 = [(150.000 + (15.000 x jarak)] / 3
612,500 = [(150.000 + (15.000 x jarak)] / 3
800,000 = [(150.000 + (15.000 x jarak)] / 3

536,932 = [(150.000 + (15.000 x jarak)] / 3


768,750 = [(150.000 + (15.000 x jarak)] / 3
718,750 = [(150.000 + (15.000 x jarak)] / 3
768,750 = [(150.000 + (15.000 x jarak)] / 3
1,050,000 = [(150.000 + (15.000 x jarak)] / 3
773,750 = [(150.000 + (15.000 x jarak)] / 3
958,750 = [(150.000 + (15.000 x jarak)] / 3
885,000 = [(150.000 + (15.000 x jarak)] / 3
773,750 = [(150.000 + (15.000 x jarak)] / 3
995,000 = [(150.000 + (15.000 x jarak)] / 3

568,182 = [(150.000 + (15.000 x jarak)] / 3


800,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
800,000 = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3

568,182 = [(150.000 + (15.000 x jarak)] / 3


800,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
800,000 = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3

568,182 = [(150.000 + (15.000 x jarak)] / 3


800,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
800,000 = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3

568,182 = [(150.000 + (15.000 x jarak)] / 3


800,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
800,000 = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3

568,182 = [(150.000 + (15.000 x jarak)] / 3


800,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
800,000 = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3

568,182 = [(150.000 + (15.000 x jarak)] / 3


800,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
800,000 = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3

227,273 = [(150.000 + (15.000 x jarak)] / 3


462,500 = [(150.000 + (15.000 x jarak)] / 3
412,500 = [(150.000 + (15.000 x jarak)] / 3
462,500 = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3
- = [(150.000 + (15.000 x jarak)] / 3

352,273 = [(150.000 + (15.000 x jarak)] / 3


587,500 = [(150.000 + (15.000 x jarak)] / 3
537,500 = [(150.000 + (15.000 x jarak)] / 3
587,500 = [(150.000 + (15.000 x jarak)] / 3
546,250 = [(150.000 + (15.000 x jarak)] / 3
562,500 = [(150.000 + (15.000 x jarak)] / 3
623,750 = [(150.000 + (15.000 x jarak)] / 3
546,250 = [(150.000 + (15.000 x jarak)] / 3
467,500 = [(150.000 + (15.000 x jarak)] / 3
567,500 = [(150.000 + (15.000 x jarak)] / 3

383,523 = [(150.000 + (15.000 x jarak)] / 3


618,750 = [(150.000 + (15.000 x jarak)] / 3
568,750 = [(150.000 + (15.000 x jarak)] / 3
618,750 = [(150.000 + (15.000 x jarak)] / 3
500,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
652,500 = [(150.000 + (15.000 x jarak)] / 3
575,000 = [(150.000 + (15.000 x jarak)] / 3
496,250 = [(150.000 + (15.000 x jarak)] / 3
596,250 = [(150.000 + (15.000 x jarak)] / 3

140,000 = [(150.000 + (15.000 x jarak)] / 3


213,750 = [(150.000 + (15.000 x jarak)] / 3
223,750 = [(150.000 + (15.000 x jarak)] / 3
335,000 = [(150.000 + (15.000 x jarak)] / 3
375,000 = [(150.000 + (15.000 x jarak)] / 3
387,500 = [(150.000 + (15.000 x jarak)] / 3
252,500 = [(150.000 + (15.000 x jarak)] / 3
238,750 = [(150.000 + (15.000 x jarak)] / 3
238,750 = [(150.000 + (15.000 x jarak)] / 3
312,500 = [(150.000 + (15.000 x jarak)] / 3

289,773 = [(150.000 + (15.000 x jarak)] / 3


525,000 = [(150.000 + (15.000 x jarak)] / 3
475,000 = [(150.000 + (15.000 x jarak)] / 3
525,000 = [(150.000 + (15.000 x jarak)] / 3
467,500 = [(150.000 + (15.000 x jarak)] / 3
500,000 = [(150.000 + (15.000 x jarak)] / 3
750,000 = [(150.000 + (15.000 x jarak)] / 3
625,000 = [(150.000 + (15.000 x jarak)] / 3
500,000 = [(150.000 + (15.000 x jarak)] / 3
625,000 = [(150.000 + (15.000 x jarak)] / 3

208,523 = [(150.000 + (15.000 x jarak)] / 3


443,750 = [(150.000 + (15.000 x jarak)] / 3
393,750 = [(150.000 + (15.000 x jarak)] / 3
443,750 = [(150.000 + (15.000 x jarak)] / 3
546,250 = [(150.000 + (15.000 x jarak)] / 3
546,250 = [(150.000 + (15.000 x jarak)] / 3
667,500 = [(150.000 + (15.000 x jarak)] / 3
500,000 = [(150.000 + (15.000 x jarak)] / 3
500,000 = [(150.000 + (15.000 x jarak)] / 3
625,000 = [(150.000 + (15.000 x jarak)] / 3

100,000 = [(150.000 + (15.000 x jarak)] / 3


187,500 = [(150.000 + (15.000 x jarak)] / 3
187,500 = [(150.000 + (15.000 x jarak)] / 3
187,500 = [(150.000 + (15.000 x jarak)] / 3
297,500 = [(150.000 + (15.000 x jarak)] / 3
312,500 = [(150.000 + (15.000 x jarak)] / 3
250,000 = [(150.000 + (15.000 x jarak)] / 3
223,750 = [(150.000 + (15.000 x jarak)] / 3
223,750 = [(150.000 + (15.000 x jarak)] / 3
297,500 = [(150.000 + (15.000 x jarak)] / 3

87,500 = [(150.000 + (15.000 x jarak)] / 80


106,250 = [(150.000 + (15.000 x jarak)] / 80
106,250 = [(150.000 + (15.000 x jarak)] / 80
100,000 = [(150.000 + (15.000 x jarak)] / 80
85,000 = [(150.000 + (15.000 x jarak)] / 80
110,000 = [(150.000 + (15.000 x jarak)] / 80
212,500 = [(150.000 + (15.000 x jarak)] / 80
166,250 = [(150.000 + (15.000 x jarak)] / 80
178,750 = [(150.000 + (15.000 x jarak)] / 80
275,000 = [(150.000 + (15.000 x jarak)] / 80

106,250 = [(150.000 + (15.000 x jarak)] / 80


125,000 = [(150.000 + (15.000 x jarak)] / 80
125,000 = [(150.000 + (15.000 x jarak)] / 80
118,750 = [(150.000 + (15.000 x jarak)] / 80
106,250 = [(150.000 + (15.000 x jarak)] / 80
128,750 = [(150.000 + (15.000 x jarak)] / 80
250,000 = [(150.000 + (15.000 x jarak)] / 80
185,000 = [(150.000 + (15.000 x jarak)] / 80
197,500 = [(150.000 + (15.000 x jarak)] / 80
295,000 = [(150.000 + (15.000 x jarak)] / 80
14,375 = [(150.000 + (15.000 x jarak)] / 4.000
16,250 = [(150.000 + (15.000 x jarak)] / 4.000
16,250 = [(150.000 + (15.000 x jarak)] / 4.000
16,250 = [(150.000 + (15.000 x jarak)] / 4.000
16,875 = [(150.000 + (15.000 x jarak)] / 4.000
17,500 = [(150.000 + (15.000 x jarak)] / 4.000
18,125 = [(150.000 + (15.000 x jarak)] / 4.000
18,000 = [(150.000 + (15.000 x jarak)] / 4.000
18,250 = [(150.000 + (15.000 x jarak)] / 4.000
18,750 = [(150.000 + (15.000 x jarak)] / 4.000

6,625,000 = [(150.000 + (15.000 x jarak)] / 3


6,375,000 = [(150.000 + (15.000 x jarak)] / 3
6,625,000 = [(150.000 + (15.000 x jarak)] / 3
8,500,000 = [(150.000 + (15.000 x jarak)] / 3
7,000,000 = [(150.000 + (15.000 x jarak)] / 3
5,625,000 = [(150.000 + (15.000 x jarak)] / 3
7,750,000 = [(150.000 + (15.000 x jarak)] / 3
7,750,000 = [(150.000 + (15.000 x jarak)] / 3
6,250,000 = [(150.000 + (15.000 x jarak)] / 3
5,875,000 = [(150.000 + (15.000 x jarak)] / 3

6,875,000 = [(150.000 + (15.000 x jarak)] / 3


6,375,000 = [(150.000 + (15.000 x jarak)] / 3
6,625,000 = [(150.000 + (15.000 x jarak)] / 3
8,125,000 = [(150.000 + (15.000 x jarak)] / 3
6,750,000 = [(150.000 + (15.000 x jarak)] / 3
6,250,000 = [(150.000 + (15.000 x jarak)] / 3
7,500,000 = [(150.000 + (15.000 x jarak)] / 3
7,500,000 = [(150.000 + (15.000 x jarak)] / 3
6,250,000 = [(150.000 + (15.000 x jarak)] / 3
5,625,000 = [(150.000 + (15.000 x jarak)] / 3

7,500,000 = [(150.000 + (15.000 x jarak)] / 3


7,375,000 = [(150.000 + (15.000 x jarak)] / 3
7,375,000 = [(150.000 + (15.000 x jarak)] / 3
10,125,000 = [(150.000 + (15.000 x jarak)] / 3
10,125,000 = [(150.000 + (15.000 x jarak)] / 3
7,875,000 = [(150.000 + (15.000 x jarak)] / 3
7,500,000 = [(150.000 + (15.000 x jarak)] / 3
7,500,000 = [(150.000 + (15.000 x jarak)] / 3
6,625,000 = [(150.000 + (15.000 x jarak)] / 3
6,875,000 = [(150.000 + (15.000 x jarak)] / 3

3,250,000 = [(150.000 + (15.000 x jarak)] / 3


3,125,000 = [(150.000 + (15.000 x jarak)] / 3
3,000,000 = [(150.000 + (15.000 x jarak)] / 3
2,250,000 = [(150.000 + (15.000 x jarak)] / 3
2,250,000 = [(150.000 + (15.000 x jarak)] / 3
3,125,000 = [(150.000 + (15.000 x jarak)] / 3
3,000,000 = [(150.000 + (15.000 x jarak)] / 3
2,875,000 = [(150.000 + (15.000 x jarak)] / 3
2,875,000 = [(150.000 + (15.000 x jarak)] / 3
2,625,000 = [(150.000 + (15.000 x jarak)] / 3

3,250,000 = [(150.000 + (15.000 x jarak)] / 3


3,125,000 = [(150.000 + (15.000 x jarak)] / 3
3,250,000 = [(150.000 + (15.000 x jarak)] / 3
2,625,000 = [(150.000 + (15.000 x jarak)] / 3
2,625,000 = [(150.000 + (15.000 x jarak)] / 3
3,125,000 = [(150.000 + (15.000 x jarak)] / 3
3,000,000 = [(150.000 + (15.000 x jarak)] / 3
2,875,000 = [(150.000 + (15.000 x jarak)] / 3
2,875,000 = [(150.000 + (15.000 x jarak)] / 3
2,750,000 = [(150.000 + (15.000 x jarak)] / 3

Puruk Cahu, Juni 2008

KEPALA DINAS PEKERJAAN UMUM


KAB. MURUNG RAYA

Ir. ADRIAN WT, MM


NIP. 530 007 565
HARGA DESAIN =
HARGA DASAR +
ONGKOS ANGKUT
(12)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)

AN UMUM
Diameter besi Berat jenis pjg 1 btg Berat 1
(mm) (kg/m') btg (kg)
12 0.887 11.5 10.2005
10 0.62 11.5 7.13
8 0.393 11.5 4.5195
6 0.22 11.5 2.53
16 1.58 11.5 18.17

10.2005
4.5195
Diameter x Berat Jenis x 11,5 / 1
7.13
Harga di Twh Harga di Twh Carter truk kap (kg) Biaya jrk (km) Biaya angkt
(Rp) (Rp)/kg Bjm-Twh 5000 Rp/kg 450 Rp/(kg/km)
22,000.00 2,156.76 1,500,000 5,000 300.00 450 0.67
18,000.00 2,524.54 1,750,000 5,000 350.00 450 0.78 0.78
13,000.00 2,876.42 2,000,000 5,000 400.00 450 0.89
7,000.00 2,766.80
55,000.00 3,026.97 carter truk

ter x Berat Jenis x 11,5 / 12


1,250,000 5,000 250.00 100 2.50
B. BAHAN UMUM

No. NAMA BAHAN SAT. KODE

1 2 3 4

1 Alat Bantu Set M.170


2 Ampelas Lbr
3 Angker Bh
4 Arde Tanah Bh
5 Armatur Lampu Set
6 Aspal Pen 60/70 Kg M.061
7 Astelin Btl
8 Atap Genteng Metal merk Sakura Elang (77 x 80 cm) Tipe Classic (2 Susun) Lbr
9 Atap Polycarbonate + Rangka Besi Biasa (Set) M2
10 Atap Polycarbonate + Rangka Steinless (Set) M2
11 Atap Sirap Ulin Lbr
12 Baja Profil WF Kg M.165
13 Baja Ulir 1" / Profil Kg
14 Bak Mandi Fibreglass (70 cm x 70 cm Segi Empat Besar) Unit
15 Batako Bh
16 Batu - Bata Merah (5 x 11 x 22 cm) Bh
17 Baut dan Beugel 10 cm Biji
18 Baut dan Beugel 20 cm Biji
19 Bend RR Ø 3" Bh
20 Bend RR Ø 4" Bh
21 Bend RR Ø 6" Bh
22 Bend RR Ø 8" Bh
23 Besi Plat 5 mm Lbr
24 Besi Siku 4 cm panjang 6 cm Bh
25 Besi Strip Bh
26 Besi U, 10 x 10 x 6 m Btg
27 Besi Ulir (U - 39) 12 m Kg
28 Box Zekering Kas 2 Group Bh
29 Bubungan Atap Sakura Color 15 cm Lbr
30 Cat Dasar Kayu setara merk Kembang Kg
31 Cat Kilap Kayu setara merk Glotex Kg
32 Cat Kilap Kayu setara merk Jotun Kg
33 Cat Kilap Kayu setara merk Platone Kg
34 Cat Kilap Kayu setara setara Avia Paint Kg
35 Cat Menie Kg
36 Cat Tembok setara merk Jotun Kg
37 Cat Tembok setara merk Kimex Kg
38 Cat Tembok setara merk Matek Kg
39 Closed Duduk setara merk Toto Set
40 Closed Jongkok setara merk American Standart Bh
41 Elbow 2" PVC (AW) 90˚ Bh
42 Elbow 4" PVC (AW) 90˚ Panjang Bh
43 Elbow 4" PVC (AW) 90˚ Pendek Bh
44 Engsel Lokal 3" setara merk 777 Bh
45 Engsel Lokal 3" setara merk Imperial Bh
46 Engsel Lokal 4" setara merk 777 Bh
47 Engsel Lokal 4" setara merk Imperial Bh
48 Espanyolet Tanam setara merk SES Bh
49 Fiting Lampu Gantung Biasa Bh
50 Fiting Lampu Gantung Tipe E 40 Bh
51 Fiting Lampu Gipsum Bh
52 Flange Adaptor Ø 3" merk Maspion Bh
53 Flange Adaptor Ø 3" merk Vinilon Bh
54 Flange Adaptor Ø 4" merk Maspion Bh
55 Flange Adaptor Ø 4" merk Vinilon Bh
56 Flange Adaptor Ø 2" merk Maspion Bh
57 Flange Adaptor Ø 2" merk Vinilon Bh
58 Flange Adaptor Ø 10" merk Vinilon Bh
59 Flange Adaptor Ø 12" merk Vinilon Bh
60 Flange Adaptor Ø 6" merk Maspion Bh
61 Flange Adaptor Ø 6" merk Vinilon Bh
62 Flange Adaptor Ø 8" merk Vinilon Bh
63 Floor Strainer Bh
64 Get Valve RR Ø 4" Bh
65 Get Valve RR Ø 6" Bh
66 Get Valve RR Ø 8" Bh
67 Glassbeads Kg
68 Glassblock Bh
69 Grendel 2" setara merk Omco Bh
70 Grendel 3" setara merk Omco Bh
71 Handle / Tarikan Kuning setara merk Top Bh
72 Handle Listrik 30 Ampere Bh
73 Isolasi Listrik Buah
74 Kabel NYA 2,5" M'
75 Kabel Power tipe NYM 3 x 2,5 mm setara merk Spring M'
76 Kabel Tanam 2 x 2,5" setara merk Spring M'
77 Kabel tipe NYFGBY 4 x 10 mm M'
78 Kaca Bening ≠ 3 mm M2
79 Kaca Bening ≠ 5 mm M2
80 Kaca Hitam / Ryben ≠ 5 mm M2
81 Kait Angin Kuning Pasang
82 Kait Talang Air merk Maspion Bh
83 Kapur Pasang / Kapur Padam Kg M.081
84 Kawat Berduri M'
85 Kawat Beton (Bindrat) Kg
86 Kawat Bronjong Roll
87 Kawat Harmonika M2
88 Kawat Las Dos
89 Kawat Nyamuk (Besi) M2
90 Kayu Bakar M3 M.070
91 Kayu Bekisting M3 M.180
92 Kayu Bulat Ø 6 - 10 cm panjang 4 m Btg
93 Keramik 20 x 20 cm setara merk Mulia Bh
94 Keramik 20 x 20 cm setara merk Roman Bh
95 Keramik 20 x 25 cm setara merk Mulia Bh
96 Keramik 30 x 30 cm Putih setara merk Mulia Bh
97 Keramik 30 x 30 cm setara merk Roman Bh
98 Keramik 40 x 40 cm setara merk Roman Bh
99 Klam Pipa Listrik Bungkus
100 Knee PVC Ø 2" merk Vinilon Bh
101 Knee PVC Ø 10" merk Maspion (DV) Bh
102 Knee PVC Ø 12" merk Maspion (DV) Bh
103 Knee PVC Ø 2" merk Maspion (DV) Bh
104 Knee PVC Ø 3" merk Maspion (DV) Bh
105 Knee PVC Ø 4" merk Maspion (DV) Bh
106 Knee PVC Ø 6" merk Maspion (DV) Bh
107 Knee PVC Ø 8" merk Maspion (DV) Bh
108 Knee PVC RRJ Ø 3" merk Vinilon Bh
109 Knee PVC RRJ Ø 4" merk Vinilon Bh
110 Knee PVC RRJ Ø 6" merk Vinilon Bh
111 Knee PVC RRJ Ø 8" merk Vinilon Bh
112 Kran Air Ø 1/2" setara merk Amico Bh
113 Kran Air Ø 3/4" setara merk Amico Bh
114 Kunci Gembok + Plat (Besar) Set
115 Kunci Tanam setara merk Kodai Bh
116 Kunci Tanam setara merk SES Bh
117 Lampu Pijar 25 watt merk Philips Bh
118 Lampu SL 18 watt merk Philips Bh
119 Lampu TL 20 watt merk Phillips Lengkap Set
120 Lem Isarplast Kg
121 Lem Kayu merk Fox Kg
122 List Profil Gipsum M'
123 List Profil Kayu 4 Cm M'
124 MCB merk Elitech Buah
125 Minyak Bakar / Minyak Tanah Ltr M.065
126 Minyak Cat / Thinner A Ltr
127 Minyak Cat / Thinner B Ltr
128 Minyak Cat Biasa (600 ml) Btl
129 Minyak Cat merk Super Ltr
130 Minyak Pelumas (SAE 30) Ltr M.185
131 Moulding Lanan M3
132 Moulding Lanan (Lebar 10 Cm) Keping
133 Paking Pipa Karet (3 mm) Bh
134 Paku Atap Genteng Metal Kg
135 Paku Jembatan Kg M.166
136 Paku Kayu ( 1 1/4" - 1,5") Kg
137 Paku Kayu (≤ 1") Kg
138 Paku Kayu (2") Kg
139 Paku Kayu (2,5" - 5") Kg
140 Paku Plywood Kg
141 Paku Seng Kg
142 Paku Sirap Kg
143 Paku Ulin (2,5" - 5") Kg
144 Paku Ulin (≤ 2") Kg
145 Papan Bekisting M3
146 Papan Kayu Bouwplank M3
147 Pasangan Instalasi Listrik (Rumah Beton) Bh
148 Pasangan Instalasi Listrik (Rumah Kayu) Bh
149 Paving Block Bh
150 Pipa Galvanis Ø 2" panjang 4 m Btg
151 Pipa Galvanis Ø 3" panjang 6 m Btg
152 Pipa Galvanis Ø 4" panjang 6 m Btg
153 Pipa Galvanis Ø 6" panjang 6 m Btg
154 Pipa Paralon PVC Ø 1" AW, panjang 4 m merk Super Intilon Btg
155 Pipa Paralon PVC Ø 1,5" AW, panjang 4 m merk Super Intilon Btg
156 Pipa Paralon PVC Ø 1/2" AW, panjang 4 m merk Super Intilon Btg
157 Pipa Paralon PVC Ø 10", panjang 6 m merk Maspion Btg
158 Pipa Paralon PVC Ø 12", panjang 6 m merk Maspion Btg
159 Pipa Paralon PVC Ø 2" AW, panjang 4 m merk Super Intilon Btg
160 Pipa Paralon PVC Ø 2", panjang 6 m merk Maspion Btg
161 Pipa Paralon PVC Ø 3" AW, panjang 4 m merk Super Intilon Btg
162 Pipa Paralon PVC Ø 3", panjang 6 m merk Maspion Btg
163 Pipa Paralon PVC Ø 3/4" AW, panjang 4 m merk Super Intilon Btg
164 Pipa Paralon PVC Ø 4" AW, panjang 4 m merk Super Intilon Btg
165 Pipa Paralon PVC Ø 4", panjang 6 m merk Maspion Btg
166 Pipa Paralon PVC Ø 6", panjang 6 m merk Maspion Btg
167 Pipa Paralon PVC Ø 8", panjang 6 m merk Maspion Btg
168 Pipa PVC SNI 06-0084-2002 type S-10 SCJ Ø 1", panjang 4 m merk Vinilon Btg
169 Pipa PVC SNI 06-0084-2002 type S-10 SCJ Ø 1,5", panjang 4 m merk Vinilon Btg
170 Pipa PVC SNI 06-0084-2002 type S-10 SCJ Ø 3/4", panjang 4 m merk Vinilon Btg
171 Pipa PVC SNI 06-0084-2002 type S-10 SCJ Ø1/2", panjang 4 m merk Vinilon Btg
172 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 10", panjang 6 m merk Vinilon Btg
173 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 12", panjang 6 m merk Vinilon Btg
174 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 14", panjang 6 m merk Vinilon Btg
175 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 16", panjang 6 m merk Vinilon Btg
176 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 2", panjang 6 m merk Vinilon Btg
177 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 3", panjang 6 m merk Vinilon Btg
178 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 4", panjang 6 m merk Vinilon Btg
179 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 6", panjang 6 m merk Vinilon Btg
180 Pipa PVC SNI 06-0084-2002 type S-12,5 RRJ Ø 8", panjang 6 m merk Vinilon Btg
181 Plafond Gipsum (1,20 m x 2,40 m) Lbr
182 Plafond Kalsiboard (1,20 m x 2,40 m) Lbr
183 Plamur Tembok setara merk RJ Kg
184 Plastik Cor M2
185 Plywood / Triplek (12 mm) Lbr
186 Plywood / Triplek (3 mm) Lbr
187 Plywood / Triplek (5 mm) Lbr
188 Plywood / Triplek (9 mm) Lbr
189 Pompa Air Jet Pump setara merk Panasonic 125 w Unit
190 Pompa Air Jet Pump setara merk Panasonic 200 w Unit
191 Premium (Bensin) Ltr M.184
192 Rangka Plafond Gipsum M2
193 Reducer Socket RR 3" x 2" Merk Vinilon Bh
194 Reducer Socket RR 4" x 2" merk Vinilon Bh
195 Reducer Socket RR 4" x 3" merk Maspion (DV) Bh
196 Reducer Socket RR 4" x 3" merk Vinilon Bh
197 Reducer Socket RR 6" x 4" merk Maspion (DV) Bh
198 Reducer Socket RR 6" x 4" merk Vinilon Bh
199 Reducer Socket RR 8" x 6" merk Vinilon Bh
200 Saklar Ganda setara merk Broco Bh
201 Saklar Tunggal setara merk Broco Bh
202 Selang Fleksibel (Karet) Ø 4" M'
203 Selotif Pipa merk Onda Buah
204 Semen Putih 50 kg Kg
205 Seng Bubungan Plat BJLS 30, Lebar 30 cm M'
206 Seng Bubungan Plat BJLS 30, Lebar 40 cm M'
207 Seng Gelombang Kecil BJLS 30 Lbr
208 Seng Plat Besar Biasa BJLS 30 Lbr
209 Solar Ltr M.183
210 Spring Knife setara merk Subur Bh
211 Stop Kontak setara merk Broco Bh
212 Stop Kran Ø 1/2" PVC Bh
213 Stop Kran Ø 2" PVC Bh
214 Stop Kran Ø 3/4" PVC Bh
215 Talang Air PVC merk Champion @ 4 m M'
216 Talang Air PVC merk Maspion @ 4 m M'
217 Tangki Air 1.200 ltr setara merk Grand Bh
218 Tangki Air 2.200 ltr setara merk Grand Bh
219 Tee All RR Ø 10" merk Vinilon Bh
220 Tee All RR Ø 2" merk Maspion Bh
221 Tee All RR Ø 2" merk Vinilon Bh
222 Tee All RR Ø 3" merk Maspion Bh
223 Tee All RR Ø 3" merk Vinilon Bh
224 Tee All RR Ø 4" merk Maspion Bh
225 Tee All RR Ø 4" merk Vinilon Bh
226 Tee All RR Ø 6" merk Maspion Bh
227 Tee All RR Ø 6" merk Vinilon Bh
228 Tee All RR Ø 8" merk Vinilon Bh
229 Teer / Residu Ltr
230 Teralis Besi M2
231 Terminal Kabel dan MCB 6 A Bh
232 Thermoplastic Kg

Catatan :
- Harga Setempat sudah termasuk Pungutan Resmi Lainnya (sesuai daerah ybs);
- Harga Total sudah termasuk Pajak PPn dan Keuntungan Pelaksana;
- Harga Satuan ini bukan Harga Mutlak yang dijadikan pedoman pengadaan barang dan jasa pemerintah sesuai
ketentuan peraturan perundang-undangan;
- Untuk Lokasi yang sulit ditempuh lewat jalan darat dan jauh dari pinggir sungai perlu ditambah dengan
Ongkos Angkut sesuai jauh lokasi atau jarak tempuh angkutan (darat/sungai).
- Harga Bahan Pabrikasi dihitung Harga Pabrik + Ongkos Kirim + Pajak PPN dan Keuntungan Pelaksana.

EKERJAAN UMUM KAB. MURUNG RAYA TA. 2010

C. UPAH

No. JENIS KEAHLIAN SAT. KODE


No. JENIS KEAHLIAN SAT. KODE

1 2 3 4

1 Mandor /Hari L.061


2 Mekanik /Hari L.071
3 Kepala Tukang (Batu, Besi, Kayu, Cat, Gali ) /Hari L.073
4 Tukang (Batu, Besi, Kayu, Cat, Gali ) /Hari L.079
5 Pekerja / Buruh Semi Terlatih /Hari L.103
6 Operator Terlatih /Hari L.081
7 Operator Kurang Terlatih / Pembantu Operator /Hari L.082
8 Sopir Terlatih /Hari L.091
9 Pembantu Sopir /Hari L.099

Keterangan :
Regional I : Kecamatan Murung

Regional II : Kecamatan Tanah Siang


Kecamatan Tanah Siang Selatan
Kecamatan Laung Tuhup
Kecamatan Barito Tuhup Raya

Regional III : Kecamatan Permata Intan


Kecamatan Sei Babuat

Regional IV : Kecamatan Sumber Barito


Kecamatan U'ut Murung
Kecamatan Seribu Riam
REG
ION
AL I
REGION

Kec.
Harga Dasar
Muru
(Rp.)
ng
Total
(Rp.)
5 6

90,000.00 ###
10,000.00 ###
6,000.00 ###
178,000.00 ###
400,000.00 ###
12,500.00 ###
510,000.00 ###
47,500.00 ###
594,000.00 ###
831,600.00 ###
1,500.00 ###
-
20,150.00 ###
450,000.00 ###
5,500.00 ###
1,100.00 ###
5,000.00 ###
8,000.00 ###
415,000.00 ###
653,000.00 ###
772,000.00 ###
1,040,000.00 ###
1,600,000.00 ###
82,000.00 ###
36,000.00 ###
110,000.00 ###
16,000.00 ###
150,000.00 ###
25,000.00 ###
30,000.00 ###
55,000.00 ###
200,000.00 ###
55,000.00 ###
60,000.00 ###
35,000.00 ###
160,000.00 ###
80,000.00 ###
85,000.00 ###
3,500,000.00 ###
400,000.00 ###
13,000.00 ###
50,000.00 ###
25,000.00 ###
10,000.00 ###
30,000.00 ###
15,000.00 ###
40,000.00 ###
275,000.00 ###
15,000.00 ###
25,000.00 ###
45,000.00 ###
142,500.00 ###
211,000.00 ###
182,000.00 ###
274,000.00 ###
105,000.00 ###
153,000.00 ###
850,000.00 ###
1,255,000.00 ###
356,999.00 ###
515,000.00 ###
830,000.00 ###
23,750.00 ###
3,100,000.00 ###
4,150,000.00 ###
7,130,000.00 ###
38,000.00 ###
35,000.00 ###
15,000.00 ###
20,000.00 ###
10,000.00 ###
60,000.00 ###
15,000.00 ###
10,000.00 ###
15,000.00 ###
10,000.00 ###
17,850.00 ###
119,000.00 ###
135,000.00 ###
150,000.00 ###
50,000.00 ###
15,000.00 ###
2,000.00 ###
2,500.00 ###
25,000.00 ###
45,000.00 ###
17,500.00 ###
125,000.00 ###
25,000.00 ###
118,800.00 ###
772,200.00 ###
9,500.00 ###
3,000.00 ###
3,000.00 ###
3,700.00 ###
7,000.00 ###
7,700.00 ###
18,000.00 ###
17,000.00 ###
28,000.00 ###
405,000.00 ###
660,000.00 ###
7,750.00 ###
24,000.00 ###
46,000.00 ###
196,000.00 ###
282,000.00 ###
445,000.00 ###
534,000.00 ###
772,000.00 ###
890,000.00 ###
18,000.00 ###
25,000.00 ###
50,000.00 ###
149,000.00 ###
335,000.00 ###
7,000.00 ###
42,000.00 ###
110,000.00 ###
80,000.00 ###
45,000.00 ###
60,000.00 ###
5,000.00 ###
25,000.00 ###
21,384.00 ###
35,000.00 ###
30,000.00 ###
20,000.00 ###
60,000.00 ###
35,000.00 ###
2,357,000.00 ###
19,000.00 ###
18,000.00 ###
30,000.00 ###
30,000.00 ###
30,000.00 ###
30,000.00 ###
25,000.00 ###
25,000.00 ###
30,000.00 ###
30,000.00 ###
30,000.00 ###
30,000.00 ###
30,000.00 ###
1,550,000.00 ###
1,550,000.00 ###
95,000.00 ###
75,000.00 ###
4,000.00 ###
365,000.00 ###
558,000.00 ###
1,020,000.00 ###
1,650,000.00 ###
40,000.00 ###
65,000.00 ###
30,000.00 ###
1,704,000.00 ###
2,806,000.00 ###
80,000.00 ###
123,000.00 ###
155,000.00 ###
240,000.00 ###
30,000.00 ###
190,000.00 ###
349,000.00 ###
721,000.00 ###
1,096,000.00 ###
32,700.00 ###
94,000.00 ###
19,200.00 ###
13,000.00 ###
2,266,000.00 ###
3,810,000.00 ###
5,826,000.00 ###
7,104,000.00 ###
182,000.00 ###
320,000.00 ###
452,000.00 ###
982,000.00 ###
1,485,000.00 ###
98,000.00 ###
85,000.00 ###
25,000.00 ###
6,000.00 ###
194,000.00 ###
75,000.00 ###
125,000.00 ###
175,000.00 ###
475,000.00 ###
800,000.00 ###
23,760.00 ###
131,000.00 ###
297,000.00 ###
475,000.00 ###
10,000.00 ###
297,000.00 ###
39,000.00 ###
831,000.00 ###
1,069,000.00 ###
20,000.00 ###
20,000.00 ###
891,000.00 ###
10,000.00 ###
5,000.00 ###
15,000.00 ###
20,000.00 ###
45,000.00 ###
45,000.00 ###
108,108.00 ###
5,000.00 ###
20,000.00 ###
12,000.00 ###
100,000.00 ###
20,000.00 ###
18,750.00 ###
75,000.00 ###
1,450,000.00 ###
2,850,000.00 ###
2,688,000.00 ###
110,000.00 ###
150,000.00 ###
178,200.00 ###
205,000.00 ###
294,000.00 ###
359,000.00 ###
545,000.00 ###
956,000.00 ###
1,972,000.00 ###
8,500.00 ###
450,000.00 ###
77,200.00 ###
35,000.00 ###

REG
ION
AL I
REGION

Kec.
Harga Dasar
Muru
(Rp.)
ng
Kec.
Harga Dasar
Muru
(Rp.)
ng
Total
(Rp.)
5 6

115,500.00 ###
111,100.00 ###
112,750.00 ###
107,625.00 ###
105,575.00 ###
300,000.00 ###
120,000.00 ###
150,000.00 ###
107,625.00 ###

You might also like