RAB IPAL Comunal 50 KK Kec. Murung Danau Usung
RAB IPAL Comunal 50 KK Kec. Murung Danau Usung
SEMESTER I 2015
DINAS PEKERJAAN UMUM KAB MURUNG RAYA
1 Batu Gunung/batu belah M 010 m3 Puruk Cahu 224,532 280,665 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 623,700 779,625 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 548,856 686,070 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 561,330 701,663 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 449,064 561,330 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
2 Batu Pecah 10 - 15 cm M 026 m3 Puruk Cahu 319,788 399,735 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Manual) Saripoi 755,244 944,055 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 619,164 773,955 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 673,596 841,995 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 694,008 867,510 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 489,888 612,360 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 625,968 782,460 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 571,536 714,420 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 489,888 612,360 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 639,576 799,470 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
3 Batu Pecah 5 - 7 cm M 022 m3 Puruk Cahu 427,518 534,398 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Manual) Saripoi 899,262 1,124,078 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 751,842 939,803 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 810,810 1,013,513 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 840,294 1,050,368 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 619,164 773,955 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 766,584 958,230 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 707,616 884,520 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 619,164 773,955 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 796,068 995,085 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
4 Batu Pecah 3 - 5 cm M 023 m3 Puruk Cahu 592,515 740,644 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Alat) (Produksi) Saripoi 854,469 1,068,086 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 754,677 943,346 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 904,365 1,130,456 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
5 Batu Pecah 2 - 3 cm M 024 m3 Puruk Cahu 742,203 927,754 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Alat) (Produksi) Saripoi 1,004,157 1,255,196 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 904,365 1,130,456 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 1,054,053 1,317,566 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
6 Batu Pecah 1 - 2 cm M 025 m3 Puruk Cahu 742,203 927,754 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Alat) (Produksi) Saripoi 1,004,157 1,255,196 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 904,365 1,130,456 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 1,054,053 1,317,566 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
7 Batu Pecah 0,5 - 1 cm M 026 m3 Puruk Cahu 742,203 927,754 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Alat) (Produksi) Saripoi 1,004,157 1,255,196 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 904,365 1,130,456 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 1,054,053 1,317,566 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
8 Batu Pecah Tersaring M 018 m3 Puruk Cahu 742,203 927,754 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Alat) (Produksi) Saripoi 1,004,157 1,255,196 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 904,365 1,130,456 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 1,054,053 1,317,566 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
9 Debu Batu m3 Puruk Cahu 674,730 843,413 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 912,870 1,141,088 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 822,150 1,027,688 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 958,230 1,197,788 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung - - = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian - - = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi - - = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
10 Kerikil Galian Bukit M 011 m3 Puruk Cahu 187,110 233,888 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
(Awcas) Saripoi 461,538 576,923 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 424,116 530,145 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 424,116 530,145 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 486,486 608,108 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 424,116 530,145 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 361,746 452,183 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 486,486 608,108 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
11 Kerikil Sungai M 012 m3 Puruk Cahu 228,690 285,863 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 598,752 748,440 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 449,064 561,330 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 598,752 748,440 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 453,600 567,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
12 Kerikil Sungai Ayak M 013 m3 Puruk Cahu 253,260 316,575 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Tanpa Pasir Saripoi 589,680 737,100 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 453,600 567,000 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 589,680 737,100 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 442,260 552,825 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 442,260 552,825 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 442,260 552,825 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 385,560 481,950 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
13 Pasir Urug / Timbunan M 040 m3 Puruk Cahu 111,132 138,915 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 170,667 213,334 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 178,605 223,256 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 267,908 334,884 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 250,047 312,559 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 309,582 386,978 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 202,419 253,024 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 190,512 238,140 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 190,512 238,140 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 250,047 312,559 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
14 Pasir Ayak Untuk M 041 m3 Puruk Cahu 166,320 207,900 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Beton / Pasir Barito. Saripoi 449,064 561,330 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 349,272 436,590 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 311,850 389,813 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
15 Sirtu (tidak diayak, dari M 042 m3 Puruk Cahu 187,110 233,888 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
sungai) Saripoi 548,856 686,070 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 399,168 498,960 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 548,856 686,070 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 436,590 545,738 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 374,220 467,775 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 498,960 623,700 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
16 Tanah Timbunan M 050 m3 Puruk Cahu 99,225 124,031 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 158,760 198,450 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 166,698 208,373 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 238,140 297,675 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 238,140 297,675 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 297,675 372,094 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 190,512 238,140 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 178,605 223,256 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 178,605 223,256 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 238,140 297,675 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
17 Semen Portland M080 zak Puruk Cahu 124,200 155,250 = [(150.000 + (15.000 x jarak)] / 80 (7) + (11)
(1 zak = 50 kg) Saripoi 142,997 178,747 = [(150.000 + (15.000 x jarak)] / 80 (8) + (11)
Dirung Lingkin 142,997 178,747 = [(150.000 + (15.000 x jarak)] / 80 (8) + (11)
Muara Laung 136,080 170,100 = [(150.000 + (15.000 x jarak)] / 80 (8) + (11)
Makunjung 125,442 156,803 = [(150.000 + (15.000 x jarak)] / 80 (8) + (11)
Tbg Lahung 158,760 198,450 = [(150.000 + (15.000 x jarak)] / 80 (9) + (11)
Tbg Kunyi 201,960 252,450 = [(150.000 + (15.000 x jarak)] / 80 (10) + (11)
Tbg Bantian 190,080 237,600 = [(150.000 + (15.000 x jarak)] / 80 (9) + (11)
Tbg Olong 207,900 259,875 = [(150.000 + (15.000 x jarak)] / 80 (10) + (11)
Muara Joloi 219,780 274,725 = [(150.000 + (15.000 x jarak)] / 80 (10) + (11)
18 Besi Beton Polos (top) M167 Kg Puruk Cahu 13,662 17,078 = [(150.000 + (15.000 x jarak)] / 4.000 (7) + (11)
Saripoi 13,900 17,375 = [(150.000 + (15.000 x jarak)] / 4.000 (8) + (11)
Dirung Lingkin 13,900 17,375 = [(150.000 + (15.000 x jarak)] / 4.000 (8) + (11)
Muara Laung 13,900 17,375 = [(150.000 + (15.000 x jarak)] / 4.000 (8) + (11)
Makunjung 13,662 17,078 = [(150.000 + (15.000 x jarak)] / 4.000 (8) + (11)
Tbg Lahung 14,137 17,672 = [(150.000 + (15.000 x jarak)] / 4.000 (9) + (11)
Tbg Kunyi 14,494 18,117 = [(150.000 + (15.000 x jarak)] / 4.000 (10) + (11)
Tbg Bantian 14,434 18,043 = [(150.000 + (15.000 x jarak)] / 4.000 (9) + (11)
Tbg Olong 14,672 18,340 = [(150.000 + (15.000 x jarak)] / 4.000 (10) + (11)
Muara Joloi 16,276 20,345 = [(150.000 + (15.000 x jarak)] / 4.000 (10) + (11)
19 Kayu Ulin Balok Besar M 181 m3 Puruk Cahu 5,278,500 6,598,125 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 2,328,750 2,910,938 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 5,278,500 6,598,125 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 6,831,000 8,538,750 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 5,589,000 6,986,250 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 4,471,200 5,589,000 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 6,210,000 7,762,500 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 6,210,000 7,762,500 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 2,484,000 3,105,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 4,657,500 5,821,875 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
20 Kayu Ulin Balok Kecil M 181 m3 Puruk Cahu 5,643,000 7,053,750 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 4,455,000 5,568,750 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 5,346,000 6,682,500 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 6,534,000 8,167,500 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 5,346,000 6,682,500 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 5,049,000 6,311,250 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 2,376,000 2,970,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 4,455,000 5,568,750 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
21 Papan Ulin M 181 m3 Puruk Cahu 6,997,320 8,746,650 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 8,167,500 10,209,375 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 8,167,500 10,209,375 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 6,311,250 7,889,063 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 5,940,000 7,425,000 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 2,970,000 3,712,500 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 5,568,750 6,960,938 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
22 Kayu Lanan Balok Kecil m3 Puruk Cahu 2,376,000 2,970,000 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 2,079,000 2,598,750 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 2,376,000 2,970,000 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 1,782,000 2,227,500 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 1,782,000 2,227,500 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 2,524,500 3,155,625 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 2,376,000 2,970,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 2,257,200 2,821,500 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 1,485,000 1,856,250 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 2,079,000 2,598,750 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
23 Papan Lanan m3 Puruk Cahu 2,577,960 3,222,450 = [(150.000 + (15.000 x jarak)] / 3 (7) + (11)
Saripoi 2,227,500 2,784,375 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Dirung Lingkin 2,598,750 3,248,438 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Muara Laung 2,079,000 2,598,750 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Makunjung 2,079,000 2,598,750 = [(150.000 + (15.000 x jarak)] / 3 (8) + (11)
Tbg Lahung 2,524,500 3,155,625 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Kunyi 2,376,000 2,970,000 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Tbg Bantian 2,301,750 2,877,188 = [(150.000 + (15.000 x jarak)] / 3 (9) + (11)
Tbg Olong 1,856,250 2,320,313 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Muara Joloi 2,227,500 2,784,375 = [(150.000 + (15.000 x jarak)] / 3 (10) + (11)
Keterangan :
Regional I : Kecamatan Murung
Catatan :
- Harga Setempat sudah termasuk Pungutan Resmi Lainnya (sesuai daerah ybs).
- Harga Total sudah termasuk Pajak PPn dan Keuntungan Pelaksana.
- Untuk Lokasi yang sulit ditempuh lewat jalan darat dan jauh dari pinggir sungai perlu ditambah dengan
Ongkos Angkut sesuai jauh lokasi atau jarak tempuh angkutan (darat/sungai).
- Harga Bahan Pabrikasi dihitung Harga Pabrik + Ongkos Kirim + Pajak PPN dan Keuntungan Pelaksana.
C. UPAH
REGIONAL
REGION I REGION II REGION III REGION IV
Kec. Tanah Siang Kec. Sumber Barito
Harga Dasar Kec. Barito Tuhup Raya Kec. Sei Babuat Kec. U'ut Murung
No. JENIS KEAHLIAN SAT. KODE Kec. Murung KET.
(Rp.) Kec. Laung Tuhup Kec. Permata Intan Kec. Seribu Riam
Kec. Tanah Siang Selatan
Total Total Total Total
(Rp.) (Rp.) (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10
Keterangan :
Regional I : Kecamatan Murung
NILAI FISIK:
Rp 456,000,000.00
PROGRAM :
Program Pembangunan Prasarana Sanitasi
KEGIATAN :
-
PEKERJAAN :
-
LOKASI :
-
TAHUN :
2017
RENCANA ANGGARAN BIAYA (RAB)
Program : Program Pembangunan Prasarana Sanitasi
Kegiatan : Pembuatan Prasarana Sanitasi ( DAK )
Pekerjaan : Pembangunan Baru SPAL Terpusat Skala Komunal Domestik Kecamatan Murung Paket 2 (DAK)
Lokasi : Desa Danau Usung, Kec. Murung
Tahun : 2017
I PEKERJAAN PENDAHULUAN
1 Pekerjaan Pembersihan Lokasi - 1.00 Keg 1,000,000.00 1,000,000.00
2 Pekerjaan Pengukuran dan Pemasangan Bowplank - 1.00 Keg 1,713,000.00 1,713,000.00
3 Pembuatan Papan Nama Kegiatan - 1.00 Bh 400,000.00 400,000.00
Jumlah I 3,504,980.00
Jumlah II 28,312,099.78
IV PEKERJAAN PEMBESIAN
1 Pembesian Sloof 15/25. A.4.1.1.17 232.20 Kg 14,067.53 3,266,479.31
2 Pembesian Sloof 15/15. A.4.1.1.17 83.28 Kg 14,067.53 1,171,543.48
3 Pembesian Kolom 15/15 A.4.1.1.17 322.48 Kg 14,067.53 4,536,476.71
4 Pembesian ring Balk 15/25. A.4.1.1.17 319.92 Kg 14,067.53 4,500,482.60
5 Pembesian Lantai Bawah T= 10 cm. A.4.1.1.17 445.57 Kg 14,067.53 6,268,114.01
6 Pembesian Lantai Atas atau Dak T= 10 cm. A.4.1.1.17 514.19 Kg 14,067.53 7,233,333.79
7 Pembesian Dinding . A.4.1.1.17 2,286.77 Kg 14,067.53 32,169,147.25
8 Pembesian Untuk Tutup Grease Trap,Black Water dan Manhole. A.4.1.1.17 242.71 Kg 14,067.53 3,414,319.61
9 Pembesian Bak Input Penyaring. A.4.1.1.17 8.27 Kg 14,067.53 116,291.54
Jumlah IV 62,676,188.29
V PEKERJAAN BEKISTING
1 Bekisting Sloof A.4.1.1.21 27.90 M2 166,066.00 4,633,241.40
2 Bekising Kolom A.4.1.1.22 41.82 M2 196,311.00 8,209,726.02
3 Bekisting RingBalk A.4.1.1.23 18.60 M2 198,627.60 3,694,473.36
4 Bekisting Lantai Dak A.4.1.1.24.a 29.93 M2 196,311.00 5,875,588.23
5 Bekisting Dinding A.4.1.1.25.a. 269.07 M2 184,672.00 49,688,956.35
6 Bekisting Bak Input Penyaring. A.4.1.1.25.a. 1.40 M2 184,672.00 258,540.80
Jumlah V 72,360,526.16
VI PEKERJAAN PLESTERAN
1 Pek. Plesteran Bangunan Utama A.4.4.2.3 229.50 M2 67,458.22 15,481,661.07
2 Pek. Plesteran Bak Pengumpul A.4.4.2.3 25.20 M2 67,458.22 1,699,947.10
3 Pek. Plesteran Grease Trap (Bak Kontrol I ) A.4.4.2.3 51.84 M2 67,458.22 3,497,034.03
4 Pek. Plesteran Black Water (Bak Kontrol II ) A.4.4.2.3 51.84 M2 67,458.22 3,497,034.03
5 Pek. Plesteran Manhole A.4.4.2.3 51.20 M2 67,458.22 3,453,860.77
6 Plesteran Untuk Tutup Grease Trap,Black Water dan Manhole. A.4.4.2.3 44.16 M2 67,458.22 2,978,954.91
7 Pek. Plesteran Bak Input Penyaring A.4.4.2.3 1.40 M2 67,458.22 94,441.51
Jumlah VI 30,702,933.42
Terbilang : ### EMPAT RATUS LIMA PULUH ENAM JUTA RUPIAH ###
PERHITUNGAN VOLUME
Program : Program Pembangunan Prasarana Sanitasi
Kegiatan : Pembuatan Prasarana Sanitasi ( DAK )
Pekerjaan : Pembangunan Baru SPAL Terpusat Skala Komunal Domestik Kecamatan Murung Paket 2 (DAK)
Lokasi : Desa Danau Usung, Kec. Murung
Tahun : 2,017
1 2 3 4
I PEKERJAAN PENDAHULUAN
1 Pekerjaan Pembersihan Lokasi
= 1.00 x 1.00 = 1.00 Keg
2 Pekerjaan Pengukuran dan Pemasangan Bowplank
= 1.00 x 1.00 = 1.00 Keg
3 Pembuatan Papan Nama Kegiatan
= 1.00 x 1.00 = 1.00 Bh
II PEKERJAAN TANAH DAN URUGAN
1 a. Galian Tanah Untuk Konstruksi Utama
Area I = 1.00 x 1.00 x 1.75 = 1.75
Area II = 8.00 x 3.00 x 2.50 = 60.00
Area III = 1.00 x 3.00 x 0.90 = 2.70
Area IV = 1.50 x 1.50 x 2.50 = 5.63
70.08 Jumlah = 70.08 M3
1 a. Pek. Sloof Beton 15/25 cm beton mutu f’ = 14.5 Mpa Bangunan Utama
Melintang = 3.00 x 7.00 = 21.00 m
Memanjang = 3.00 x 8.00 = 24.00 m
45.00 m
= 0.15 x 0.25 x 45.00 = 1.69
1.69 Jumlah = 1.688 M3
c. Pek. Sloof Beton 15/15 cm beton mutu f’ = 14.5 MPa Bangunan Inlet
Melintang = 3.00 x 2.00 = 6.00 m
Memanjang = 1.00 x 2.00 = 2.00 m
8.00 m
= 0.15 x 0.15 x 8.00 = 0.18
0.18 Jumlah = 0.180 M3
c. Pek. Sloof Beton 15/15 cm beton mutu f’ = 14.5 MPa Bangunan Bak Pengumpul
Melintang = 1.50 x 2.00 = 3.00 m
Memanjang = 1.50 x 2.00 = 3.00 m
6.00 m
No. URAIAN PEKERJAAN Uraian Perhitungan Jumlah
1 2 3 4
= 0.15 x 0.15 x 6.00 = 0.14
0.14 Jumlah = 0.135 M3
4 a. Pek. Kolom Beton 15/15 cm beton mutu f’ = 14.5 MPa Bangunan Utama
= 0.15 x 0.15 x 2.50 x 22.00 = 1.24
= 0.15 x 0.15 x 1.75 x 2.00 = 0.08
= 0.15 x 0.15 x 0.90 x 2.00 = 0.04
1.36 Jumlah = 1.357 M3
b. Pek. Kolom Beton 15/15 cm beton mutu f’ = 14.5 MPa Bangunan Bak Pengumpul
= 0.15 x 0.15 x 2.35 x 4.00 = 0.21
0.21 Jumlah = 0.212 M3
5 a. Pek. Ring Balk Beton 15/25 cm beton mutu f’ = 14.5 MPa Bangunan Utama
Melintang = 3.00 x 7.00 = 21.00 m
Memanjang = 3.00 x 8.00 = 24.00 m
45.00 m
= 0.15 x 0.25 x 45.00 = 1.69
1.69 Jumlah = 1.688 M3
b. Pek. Ring Balk Beton 15/25 cm beton mutu f’ = 14.5 MPa Bangunan Outlet
Melintang = 1.00 x 1.00 = 1.00 m
Memanjang = 2.00 x 1.00 = 2.00 m
3.00 m
= 0.15 x 0.25 x 3.00 = 0.11
0.11 Jumlah = 0.113 M3
c. Pek. Ring Balk Beton 15/25 cm beton mutu f’ = 14.5 MPa Bangunan Inlet
Melintang = 3.00 x 2.00 = 6.00 m
Memanjang = 2.00 x 1.00 = 2.00 m
8.00 m
= 0.15 x 0.25 x 8.00 = 0.30
0.30 Jumlah = 0.300 M3
d. Pek. Ring Balk Beton 15/25 cm beton mutu f’ = 14.5 MPa Bak Pengumpul
Melintang = 1.50 x 2.00 = 3.00 m
Memanjang = 1.50 x 2.00 = 3.00 m
6.00 m
= 0.15 x 0.25 x 6.00 = 0.23
0.23 Jumlah = 0.225 M3
d. Pek. Balok Beton 10/10 cm beton mutu f’ = 14.5 MPa Bak input penyaring
Melintang = 0.60 x 1.00 = 0.60 m
Memanjang = 1.00 x 1.00 = 1.00 m
1.60 m
= 0.10 x 0.10 x 1.60 = 0.02
0.02 Jumlah = 0.016 M3
9 a. Pek. Dinding Beton t= 15 cm beton mutu f’ = 14.5 MPa untuk Bangunan Utama
Panjang = 3.00 x 6.00 = 18.00 m
= 8.00 x 2.00 = 16.00 m
= 2.00 x 4.00 = 8.00 m
42.00 m
= 0.15 x 2.50 x 42.00 = 15.75
Bak Outlet = 0.15 x 1.75 x 3.00 = 0.79
Bak Saluran Inlet = 0.15 x 0.90 x 5.00 = 0.68
17.21 Jumlah = 17.213 M3
No. URAIAN PEKERJAAN Uraian Perhitungan Jumlah
1 2 3 4
10 a. Pek. Dinding Beton beton mutu f’ = 14.5 MPa untuk Bak Kontrol I Grease Trap
Panjang = 0.60 x 2.00 = 1.20 m
= 0.60 x 2.00 = 1.20 m
2.40 m
= 0.50 x 2.40 x 0.10 x 18.00 = 2.16
2.16 Jumlah = 2.160 M3
b. Pek. Dinding Beton beton mutu f’ = 14.5 MPa untuk Bak Kontrol II Black Water
Panjang = 0.60 x 2.00 = 1.20 m
= 0.60 x 2.00 = 1.20 m
2.40 m
= 0.50 x 2.40 x 0.10 x 18.00 = 2.16
2.16 Jumlah = 2.160 M3
12 Pek. Beton t= 10 cm beton mutu f’ = 14.5 MPa Bak Input Penyaring dinding dan Lantai
= 0.60 x 1.00 x 0.10 x 1.00 = 0.06
= 0.40 x 1.00 x 0.10 x 1.00 = 0.04
0.10 Jumlah = 0.100 M3
IV PEKERJAAN PEMBESIAN
1 2 3 4
Bangunan Utama
Melintang = 8.00 / 0.15 = 53.33
Total = 6.20 x 53.33 x 0.62 = 205.01
Memanjang = 3.00 / 0.15 = 20.00
Total = 16.20 x 20.00 x 0.62 = 200.88
405.89 Jumlah = 405.893 Kg
Bak pengumpul
Melintang = 1.50 / 0.15 = 10.00
Total = 3.20 x 10.00 x 0.62 = 19.84
Memanjang = 1.50 / 0.15 = 10.00
Total = 3.20 x 10.00 x 0.62 = 19.84
39.68 Jumlah = 39.680 Kg
1 2 3 4
2.0 x 17.00 bh Jumlah = 33.728 Kg
V PEKERJAAN BEKISTING
Jumlah = 1.400 m2
VI PEKERJAAN PLESTERAN
1 a.Luasan Bak Utama = 2.00 x 8.00 = 16.00
= 3.00 x 6.00 = 18.00
= 2.00 x 4.00 = 8.00
42.00
Total = 42.00 x 2.50 x 2.00 = 210.00 Jumlah = 210.000 m2
No. URAIAN PEKERJAAN Uraian Perhitungan Jumlah
1 2 3 4
Jumlah = 1.400 m2
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.75 105,575.00 79,181.25
Mandor L.04 OH 0.025 115,500.00 2,887.50
JUMLAH TENAGA KERJA 82,068.75
B BAHAN
Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.5 105,575.00 52,787.50
Mandor L.04 OH 0.05 115,500.00 5,775.00
JUMLAH TENAGA KERJA 58,562.50
B BAHAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3 105,575.00 31,672.50
Mandor L.04 OH 0.01 115,500.00 1,155.00
JUMLAH TENAGA KERJA 32,827.50
B BAHAN
Pasir urug 1.200 112,000.00 134,400.00
JUMLAH HARGA BAHAN 134,400.00
C PERALATAN
A.A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100),
slump (3-6) cm, w/c = 0,87
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 1.2 105,575.00 126,690.00
Tukang Batu L.02 OH 0.2 107,625.00 21,525.00
Kepala Tukang L.03 OH 0.02 112,750.00 2,255.00
Mandor L.04 OH 0.06 115,500.00 6,930.00
JUMLAH TENAGA KERJA 157,400.00
B BAHAN
Semen Portland kg 230 1,400.00 322,000.00
Pasir Beton kg 893 165.58 147,866.88
Kerikil kg 1027 227.27 233,409.09
(Maks 30mm)
Air Liter 200
JUMLAH HARGA BAHAN 703,275.97
C PERALATAN
A. A.4.1.1.5. Membuat 1 m3 beton mutu f’ = 14.5 MPa (K 175). slump (12 ± 2) cm. w/c = 0.66
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.650 105,575.00 174,198.75
Tukang Batu L.02 OH 0.275 107,625.00 29,596.88
Kepala Tukang L.03 OH 0.028 112,750.00 3,157.00
Mandor L.04 OH 0.083 115,500.00 9,586.50
JUMLAH TENAGA KERJA 216,539.13
B BAHAN
Semen Portland kg 326 1,400.00 456,400.00
Pasir Beton kg 760 165.58 125,844.16
Kerikil (Maks 30mm) kg 1029 227.27 233,863.64
Air Liter 215
JUMLAH HARGA BAHAN 816,107.79
C PERALATAN
SNI
2002. Membuat 1 m3 beton tumbuk camp 1pc : 3ps : 5kr
07.6.1
Harga Satuan Jumlah
No Uraian Kode Satuan Koefisien (Rp) Harga
(Rp)
A TENAGA
Pekerja L.01 OH 1.6500 105,575.00 174,198.75
Tukang Batu L.02 OH 0.2500 107,625.00 26,906.25
Kepala Tukang L.03 OH 0.0250 112,750.00 2,818.75
Mandor L.04 OH 0.0800 115,500.00 9,240.00
JUMLAH TENAGA KERJA 213,163.75
B BAHAN
Semen Portland kg 218.0000 1,400.00 305,200.00
Pasir Beton m3 0.5200 231,818.18 120,545.45
Kerikil m3 0.8700 306,818.18 266,931.82
JUMLAH HARGA BAHAN 692,677.27
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.07 105,575.00 7,390.25
Tukang Besi L.02 OH 0.07 107,625.00 7,533.75
Kepala Tukang L.03 OH 0.007 112,750.00 789.25
Mandor L.04 OH 0.004 115,500.00 462.00
JUMLAH TENAGA KERJA 16,175.25
B BAHAN
Besi beton (polos/ulir) kg 10.500 11,500.00 120,750.00
Kawat beton kg 0.15 25,000.00 3,750.00
JUMLAH HARGA BAHAN 124,500.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.52 105,575.00 54,899.00
Tukang Kayu L.02 OH 0.26 107,625.00 27,982.50
Kepala Tukang L.03 OH 0.026 112,750.00 2,931.50
Mandor L.04 OH 0.026 115,500.00 3,003.00
JUMLAH TENAGA KERJA 88,816.00
B BAHAN
Kayu kelas III m3 0.04 1,550,000.00 62,000.00
Paku 5 – 10 cm kg 0.3 25,000.00 7,500.00
Minyak bekisting Liter 0.1
JUMLAH HARGA BAHAN 69,500.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.52 105,575.00 54,899.00
Tukang Kayu L.02 OH 0.26 107,625.00 27,982.50
Kepala Tukang L.03 OH 0.026 112,750.00 2,931.50
Mandor L.04 OH 0.026 115,500.00 3,003.00
JUMLAH TENAGA KERJA 88,816.00
B BAHAN
Kayu kelas III m3 0.045 1,550,000.00 69,750.00
Paku 5 cm – 10 cm kg 0.3 25,000.00 7,500.00
Minyak bekisting Liter 0.1
JUMLAH HARGA BAHAN 77,250.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.66 105,575.00 69,679.50
Tukang Kayu L.02 OH 0.33 107,625.00 35,516.25
Kepala Tukang L.03 OH 0.033 112,750.00 3,720.75
Mandor L.04 OH 0.033 115,500.00 3,811.50
JUMLAH TENAGA KERJA 112,728.00
B BAHAN
Kayu kelas III m3 0.040 1,550,000.00 62,000.00
Paku 5 cm – 12 cm kg 0.400 25,000.00 10,000.00
Minyak bekisting Liter
Balok kayu Bekisting m3 0.015 772,200.00 11,583.00
Dolken kayu galam. 8–10 cm
Batang
panjang 4 m
JUMLAH HARGA BAHAN 83,583.00
C PERALATAN
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.66 105,575.00 69,679.50
Tukang Kayu L.02 OH 0.33 107,625.00 35,516.25
Kepala Tukang L.03 OH 0.033 112,750.00 3,720.75
Mandor L.04 OH 0.033 115,500.00 3,811.50
JUMLAH TENAGA KERJA 112,728.00
B BAHAN
Kayu kelas III m3 0.030 1,550,000.00 46,500.00
Paku 5 cm – 12 cm kg 0.400 25,000.00 10,000.00
-
Balok kayu Bekisting m3 0.020 772,200.00 15,444.00
Dolken kayu , 8–10 cm, panj. 4 m
Batang 0.250
JUMLAH HARGA BAHAN 71,944.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 184,672.00
E Harga Satuan Pekerjaan 184,672.00
Harga Jumlah
No Uraian Kode Satuan Koefisien Satuan Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.200 105,575.00 21,115.00
Tukang Batu L.03 OH 0.100 107,625.00 10,762.50
Kepala Tukang L.03 OH 0.010 107,625.00 1,076.25
Mandor L.04 OH 0.010 115,500.00 1,155.00
JUMLAH TENAGA KERJA 34,108.75
B BAHAN
Semen PC Kg 3.250 1,400.00 4,550.00
JUMLAH HARGA BAHAN 4,550.00
C PERALATAN
A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1SP : 3PP
A. BAHAN
Keterangan :
Regional I : Kecamatan Murung
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
(7) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(8) + (11)
(9) + (11)
(10) + (11)
(9) + (11)
(10) + (11)
(10) + (11)
AN UMUM
Diameter besi Berat jenis pjg 1 btg Berat 1
(mm) (kg/m') btg (kg)
12 0.887 11.5 10.2005
10 0.62 11.5 7.13
8 0.393 11.5 4.5195
6 0.22 11.5 2.53
16 1.58 11.5 18.17
10.2005
4.5195
Diameter x Berat Jenis x 11,5 / 1
7.13
Harga di Twh Harga di Twh Carter truk kap (kg) Biaya jrk (km) Biaya angkt
(Rp) (Rp)/kg Bjm-Twh 5000 Rp/kg 450 Rp/(kg/km)
22,000.00 2,156.76 1,500,000 5,000 300.00 450 0.67
18,000.00 2,524.54 1,750,000 5,000 350.00 450 0.78 0.78
13,000.00 2,876.42 2,000,000 5,000 400.00 450 0.89
7,000.00 2,766.80
55,000.00 3,026.97 carter truk
1 2 3 4
Catatan :
- Harga Setempat sudah termasuk Pungutan Resmi Lainnya (sesuai daerah ybs);
- Harga Total sudah termasuk Pajak PPn dan Keuntungan Pelaksana;
- Harga Satuan ini bukan Harga Mutlak yang dijadikan pedoman pengadaan barang dan jasa pemerintah sesuai
ketentuan peraturan perundang-undangan;
- Untuk Lokasi yang sulit ditempuh lewat jalan darat dan jauh dari pinggir sungai perlu ditambah dengan
Ongkos Angkut sesuai jauh lokasi atau jarak tempuh angkutan (darat/sungai).
- Harga Bahan Pabrikasi dihitung Harga Pabrik + Ongkos Kirim + Pajak PPN dan Keuntungan Pelaksana.
C. UPAH
1 2 3 4
Keterangan :
Regional I : Kecamatan Murung
Kec.
Harga Dasar
Muru
(Rp.)
ng
Total
(Rp.)
5 6
90,000.00 ###
10,000.00 ###
6,000.00 ###
178,000.00 ###
400,000.00 ###
12,500.00 ###
510,000.00 ###
47,500.00 ###
594,000.00 ###
831,600.00 ###
1,500.00 ###
-
20,150.00 ###
450,000.00 ###
5,500.00 ###
1,100.00 ###
5,000.00 ###
8,000.00 ###
415,000.00 ###
653,000.00 ###
772,000.00 ###
1,040,000.00 ###
1,600,000.00 ###
82,000.00 ###
36,000.00 ###
110,000.00 ###
16,000.00 ###
150,000.00 ###
25,000.00 ###
30,000.00 ###
55,000.00 ###
200,000.00 ###
55,000.00 ###
60,000.00 ###
35,000.00 ###
160,000.00 ###
80,000.00 ###
85,000.00 ###
3,500,000.00 ###
400,000.00 ###
13,000.00 ###
50,000.00 ###
25,000.00 ###
10,000.00 ###
30,000.00 ###
15,000.00 ###
40,000.00 ###
275,000.00 ###
15,000.00 ###
25,000.00 ###
45,000.00 ###
142,500.00 ###
211,000.00 ###
182,000.00 ###
274,000.00 ###
105,000.00 ###
153,000.00 ###
850,000.00 ###
1,255,000.00 ###
356,999.00 ###
515,000.00 ###
830,000.00 ###
23,750.00 ###
3,100,000.00 ###
4,150,000.00 ###
7,130,000.00 ###
38,000.00 ###
35,000.00 ###
15,000.00 ###
20,000.00 ###
10,000.00 ###
60,000.00 ###
15,000.00 ###
10,000.00 ###
15,000.00 ###
10,000.00 ###
17,850.00 ###
119,000.00 ###
135,000.00 ###
150,000.00 ###
50,000.00 ###
15,000.00 ###
2,000.00 ###
2,500.00 ###
25,000.00 ###
45,000.00 ###
17,500.00 ###
125,000.00 ###
25,000.00 ###
118,800.00 ###
772,200.00 ###
9,500.00 ###
3,000.00 ###
3,000.00 ###
3,700.00 ###
7,000.00 ###
7,700.00 ###
18,000.00 ###
17,000.00 ###
28,000.00 ###
405,000.00 ###
660,000.00 ###
7,750.00 ###
24,000.00 ###
46,000.00 ###
196,000.00 ###
282,000.00 ###
445,000.00 ###
534,000.00 ###
772,000.00 ###
890,000.00 ###
18,000.00 ###
25,000.00 ###
50,000.00 ###
149,000.00 ###
335,000.00 ###
7,000.00 ###
42,000.00 ###
110,000.00 ###
80,000.00 ###
45,000.00 ###
60,000.00 ###
5,000.00 ###
25,000.00 ###
21,384.00 ###
35,000.00 ###
30,000.00 ###
20,000.00 ###
60,000.00 ###
35,000.00 ###
2,357,000.00 ###
19,000.00 ###
18,000.00 ###
30,000.00 ###
30,000.00 ###
30,000.00 ###
30,000.00 ###
25,000.00 ###
25,000.00 ###
30,000.00 ###
30,000.00 ###
30,000.00 ###
30,000.00 ###
30,000.00 ###
1,550,000.00 ###
1,550,000.00 ###
95,000.00 ###
75,000.00 ###
4,000.00 ###
365,000.00 ###
558,000.00 ###
1,020,000.00 ###
1,650,000.00 ###
40,000.00 ###
65,000.00 ###
30,000.00 ###
1,704,000.00 ###
2,806,000.00 ###
80,000.00 ###
123,000.00 ###
155,000.00 ###
240,000.00 ###
30,000.00 ###
190,000.00 ###
349,000.00 ###
721,000.00 ###
1,096,000.00 ###
32,700.00 ###
94,000.00 ###
19,200.00 ###
13,000.00 ###
2,266,000.00 ###
3,810,000.00 ###
5,826,000.00 ###
7,104,000.00 ###
182,000.00 ###
320,000.00 ###
452,000.00 ###
982,000.00 ###
1,485,000.00 ###
98,000.00 ###
85,000.00 ###
25,000.00 ###
6,000.00 ###
194,000.00 ###
75,000.00 ###
125,000.00 ###
175,000.00 ###
475,000.00 ###
800,000.00 ###
23,760.00 ###
131,000.00 ###
297,000.00 ###
475,000.00 ###
10,000.00 ###
297,000.00 ###
39,000.00 ###
831,000.00 ###
1,069,000.00 ###
20,000.00 ###
20,000.00 ###
891,000.00 ###
10,000.00 ###
5,000.00 ###
15,000.00 ###
20,000.00 ###
45,000.00 ###
45,000.00 ###
108,108.00 ###
5,000.00 ###
20,000.00 ###
12,000.00 ###
100,000.00 ###
20,000.00 ###
18,750.00 ###
75,000.00 ###
1,450,000.00 ###
2,850,000.00 ###
2,688,000.00 ###
110,000.00 ###
150,000.00 ###
178,200.00 ###
205,000.00 ###
294,000.00 ###
359,000.00 ###
545,000.00 ###
956,000.00 ###
1,972,000.00 ###
8,500.00 ###
450,000.00 ###
77,200.00 ###
35,000.00 ###
REG
ION
AL I
REGION
Kec.
Harga Dasar
Muru
(Rp.)
ng
Kec.
Harga Dasar
Muru
(Rp.)
ng
Total
(Rp.)
5 6
115,500.00 ###
111,100.00 ###
112,750.00 ###
107,625.00 ###
105,575.00 ###
300,000.00 ###
120,000.00 ###
150,000.00 ###
107,625.00 ###