You are on page 1of 2

To Dated: 04-05-2023

HESHAL GUNAWARDHANA
Quantity Surveyor
Gulf National Ways L.L.C
SUBJECT: QUOTATION FOR THE CONSTRUCTION OF 5 CELL CULVERT AT DUALIZATION
OF HALBAN STREET PROJECT.
Dear Sir,
Kindly check our best competitive rates for the aforementioned subject as below mentioned
terms and conditioned.

Dualization of Halban Street project


RATE
Sr
Description QTY Unit (OMR) Amount(OMR)
Construction of 5 Cell
A concrete culvert as per the
drawings
1 C15 Blinding Concrete 37.43 m3 Completed
C43.5/20 MS7 Concrete in
2 Box culvert.(Including 319.19 m3 22 7022.18
Formwork material)
(Concrete will supply by
GNW)
Reinforcement work (Cutting
3 31.84 Ton 55 1751.2
bending and Fixing)

Total Amount exclusive of VAT


8773.38

GENERAL TERMS AND CONDITION.

RESPONSIBILITIES OF M/S GULF NATIONAL WAYS (MAINCONTRACTOR)


1-Water Stopper, Hazen Clothe and curing compound, Dowell bar, expansion joint sheet and
sealant, concrete cover or binding wire shall be in the scope of GULF NATIONAL WAYS
2- Additional Requirements like electricity, water supply for site as well as preparation of area.
3-GNW Shall provide Concrete, Reinforcement Steel for the quoted works.
4. All Heavy Machinery wherever required.
RESPONSIBILITIES OF M/S WHITE PEARL INTERNATIONAL SUBCONTRACTOR:

1. Medical Facility for the workers.


2. Mobilization and de-mobilization of workers.
3. Rest all the items are included as per the aforementioned Bill of quantities.
4. All manpower and tools required to carry out the described works will be provided by the
Subcontractor.
5. Shuttering shall be in the scope of White Pearl International. Also Cutting and bending
machine for steel.
6. The Subcontractor shall observe all Health, Safety and Environmental (HSE) requirements.
All workers shall be equipped with full Personal Protection Equipment (PPE) by the
Subcontractor.
7. Subcontractor representative qualified English speaking Foreman will be available on the
Site.
8. Subcontractor will commence the works as per further written instruction by the
Contractor.
9- Food, Transportation and Accommodation shall be provided by the subcontractor
Contractor.

Basis of Rates

All unit rates are in OMANI Rial.

Financial Terms and Conditions


1. 30 Days after submission of invoice
2. 5% VAT will be charge with monthly invoice
3. 10 % advance payment for Mobilization.

We assure you our best Support.

REGARDS: M/S WHITE PEARL INTERNATIONAL.

(Mobile: +968-97054488)