Professional Documents
Culture Documents
STANDARDS
VOLUME1
Speakers: QA TEAM
OUTLINE
Review of End To End Process
o Pre-PAT to PAT
o CRFS to FAT
FTTH Overview
Aerial Installation Standards
Underground Installation
Safety Awareness
o Daily Safety Huddle
• Safety Inspection
Assessment Exam
2
PRE-PAT TO FAT PROCESS
3
GLOBE OSP ACCEPTANCE PROCESS
4
PREPAT TO PAT
At 75%
PS to Submit QA
Site Project Build PRE-PAT
Pre-PAT Requests
Inspection GT for PAT
Docs to QA
All Physical
Conduct Conduct Deficiency List
Deficiencies Inspection OPM results
Quality Quality should be and Grounding test
Inspection Inspection rectified At Optical test
at 25% at 50% this point.
Remaining
Project Supervisor’s Scope
Submit copy of Pre-PAT (25% and 50%) thru Email and Viber to
Deficiencies should
be rectified before
GOAL
QA Team PAT
5
Before PAT
Make sure you bring all PAT forms and Transmittal Form
Be ready with FAT forms as well
Provide an accurate REDLINE Plan
6
During PAT
7
NOTE ON RE-PAT
• Submit picture of rectification to
trigger request for re-PAT RE-PAT- A
• GT will assess if there is a need to
check on field or picture is enough
to close the PAT.
• Should follow SLA for Rectification NO
“maximum 15days”
8
specific projects of Globe
6. OSPMS - UAT
CRFS TO FAT
QA Team will
monitor status of QA
sites until it reaches Requests FAT
FAN Secured GT for FAT
9
FTTH OVERVIEW
10
FTTH ARCHITECTURE
Typical Architecture – FTTH Horizontal
Double Splitter
NAPs 1:8
OLT Subscriber
Line
NAP1 Splitter
Installation
1:8
ODF Splitter
1:8
Splitter
NAP2
1:4
1:8
Splitter
Splitter
11
SUBSCRIBER LINE INSTALLATION
Usual SLI Trouble
Fiber Drop
Network
Access
NAP1 (Outdoor)
Point
Field
Access
Terminal
Access
Terminal
Box Fiber Drop
(Indoor)
Optical
Network Patch Cord
Unit
12
Basic ODN Product Family
ODF/FDC Joint Closures Splitters FDP/FTB Accessories
Rack Series
Pigtail & Patch
cord
In-line type
ODF rack
Modular Series
FDPFDP
Adapter
FDC rack
FTB FTB
Micro- encapsulation
Dome type FASC / BIPC
ODF Unit
13
Optical Distribution Frames
14
High Density Optical Distribution Frames
15
Rack Mount Optical Distribution Frames
16
Fiber Optic Splice Closures / LCP
Features
Cable connection and branch without cutting the
cable
IP68 rating
72, 144 and 288 capacity
Polypropylene Material PP
Single splice slot with 2 Splitter slots per
tray
Structure
Heat shrinkable sealing dome
closure
Mechanical sealing dome closure
Horizontal closure
Application
Aerial/ duct/ buried application
Suitable for FTTH underground
Multiple duct drop cable available
17
NAP 410-E
18
Pedestal NAP
19
MDU Fiber Distribution Cabinet 410-E
Application
The FDP410E series are suitable for the application both on LCP
or NAP in a centralized split or a distributed split PON architecture
for MDU and high density areas
20
MDU Fiber Distribution Cabinet 460-C
21
MDU Fiber Distribution Box 410-B
22
Optical Micro PLC Splitters
Features
• Compliant with GR-1209-CORE and GR-1221-CORE.
• 1x4 to 1x64 PLC splitter (single chip)
• Wideband performance
• Low insertion loss
• Low back reflection
• Low PDL (Polarization Dependent Loss)
• Low WDL (Wavelength Dependent Loss)
• Low TDL (Temperature Dependent Loss)
• High output uniformity
• Stable optical performance
• Abundant encapsulation models, flexible ODN
application.
• All materials are RoHS approved.
• Work Temperature: –40 to +85ºC
23
FAT - Field Access Terminal
Features
24
ATB Access Terminal Box
Features
25
Patch Cords SC APC – SC APC
Features
5mm bending radius
High tensile strength
High crush strength
Bend insensitive fiber of G.657
Can be flexibly twisted, folded, bended
Automatic mechanical shutter.
Easy & simple installation
Operation
-40 to +85℃
Temperature
26
Field Assembly Connectors
Field assembly on the cable sheath to eliminate bare
fiber storage
Easy assembly, no special tools required
Low insertion loss
High assembly success rate
Re-assembly available
Compatible with cables of various sizes
Figure 8 flat drop cable
2.0~3.0mm round cable
Insertion Loss(dB) Avg.<0.25dB;Max.≤0.50dB
Optical fiber diameter 250μm or 900μm
Return Loss(dB) Avg.≥45dB, Min.≥40dB
27
GT Standards for
AERIAL INSTALLATIONS
28
POLE
Pole Installation
29
LCP & NAP INSTALLATION
Closure Not Allowed Or Not Feasible For Direct Attach
TILTED
0.4m
0.3m
Length of FOC:
7.5m LCP
7.5m NAP
Length of FOC:
100mm
7.5m LCP
7.5m NAP
0.4m
100mm
35
FOC STUB or J-LOOP INSTALLATION
38
BRIDLE RING INSTALLATION
44
Cable Run Pole-to-Pole
AER_4.4 With cable ID, should conform to approved engineering standard.
• Format:
• PLA ID Site A – PLA ID Site B < > #of cores < > Project Name < > Year Installed
ODN deployment
45
Cable Run Pole-to-Pole
AER_4.4 With cable ID, should conform to approved engineering standard.
46
Cable Run Pole-to-Pole
AER_4.4 With cable ID, should conform to approved engineering
standard.
47
Cable Run Pole-to-Pole
AER_4.4 With cable ID, should conform to approved engineering
standard.
48
NAP STENCIL
49
Cable Run Pole-to-Pole
• AER_4.1 Installation of aerial FOC cables should be able to conform with standard
installation practice including handling and laying of the cable.
50
Globe Fiber Optic Cable
51
Cable Run Pole-to-Pole
AER_4.1 Installation of aerial FOC cables should be able to conform with standard installation practice
including handling and laying of the cable.
FOC Transport:
-can be transported in a reel on
the truck.
52
Cable Run Pole-to-Pole
• FOC Handling
53
Cable Run Pole-to-Pole
AER_4.2 Lashed properly according to plan either on new or to existing
messenger strand.
54
AER_4.2 Lashed properly according to plan either on new or to existing messenger strand.
55
Cable Run Pole-to-Pole
AER_4.5 Cable clearance at mid-span should not be below minimum height as described for vertical
clearances.
• 18-21ft (5.5 - 6.4m) - clearance from ground level. (along the road)
• 23-24ft (7.0 – 7.3m) - clearance from ground level. (on road crossings)
Other provisions:
• Diagonal road crossing shall be avoided at all lines.
• The following alterative engineering solutions shall be considered at road crossing if the standard seven (7) meters clearance
between the lowest section of the FOC and the existing road level is not achieved due to overhead constructions:
• Underground installation by open trench;
• Underground installation by HDD;
• Routing of FOC route if possible.
• Diagonal road crossing shall be avoided at all lines.
• Aerial cable distance shall be 70 meters (maximum) length pole to pole spans with the range of 5.5 – 6.4 meter
clearance from ground level, while for road crossings, clearance from ground level shall be 7 meters minimum
• Vertical Clearance of 5.5m cable crossing permissible when crossing area has nearby overpass usually 4.27 vertical clearance
56
Cable Run Pole-to-Pole
AER_4.5 Cable clearance at mid-span should not be below minimum height as described for vertical
clearances.
Standard Aerial FOC installation at road crossings
57
Cable Run Pole-to-Pole
AER_4.6 Cable clearance from power lines or transformers
34kV
3m or
(9.8ft)
0.5m
58
Cable Run Pole-to-Pole
AER_4.7 Cable should not cross inside property line
• Cables should not be crossing private property
• Cables crossing private property is substandard for aerial installation and will only be allowed if all options
• are already exhausted. Even with lot owner consent we still need to assess the security of the cable facilities
59
Cable Run Pole-to-Pole
AER_4.8 Check proper Bonding of Strand and Cables especially at pull-off, cross-over and
dead end installation
• All dead end installation of messenger should be properly bonded.
• All special strand construction such as pull-off, cross over should be bonded together
60
Cable Run Pole-to-Pole
AER_4.9 Check Aerial installation fixture for material defects and substandard installation:
Alley arms, pull-off and cross-over construction, Pole Clamp, Suspension clamps, etc.
• SUSPENSION CLAMP which is bolted up against the underside of two angles by a 5/8" (16mm) Machine Bolt. This Machine Bolt is fitted between the legs of the two
angle and can be adjusted for proper extension from the pole.
• Mounting is accomplished by a 5/8" or 3/4" Inch Machine Bolt at the upper position and two 1/2" Inch Lag Screw at the lower.
• CABLE EXTENSION ARMS furnish with two (2) M.Bolts 3/4" x 3" full thread with nuts and two (2) G.I. Spacer 3/4" X 20mm L.
• 26" 750mm
• 44 ½” 1200mm
• MATERAILS:
• FINISH:
• Hot Dip Galvanize as per ASTM A 123 Min. Coating 0.099314mm Thick.
62
Cable Run Pole-to-Pole
AER_4.11 Spiral sleeves should be provided as cable protection:
• Cable touches tree or any hard object that may cause breakage
• Cable comes into contact with secondary power lines or near any power facilities
• Other special installation cases that needs extra cable protection
63
Cable Run Pole-to-Pole
AER_4.12 Cable support with cable spacers
• All cable attachment on pole must have cable support and
spacer.
10 in 10 in
4 inches
dist. From Cable sup
to lashing clamp
6 inches
64
Cable Run Pole-to-Pole
AER_4.12 Cable support with cable spacers
65
Cable Run Pole-to-Pole
AER_4.13 Maintenance loop provided
66
Cable Run Pole-to-Pole
AER_4.13 Maintenance loop provided
67
Cable Run Pole-to-Pole
• Refer to RTA
• Slot positioning of
attachment as indicated in
RTA document.
(Ex. Meralco)
68
• AER_5.1 Ground line within ground level
POLE
• GL mark of the pole should be within or under ground level
69
POLE
AER_5.2 Pole Depth Setting Based on the design requirements
• In case we cannot meet the requirements, concrete encasement can be implemented.
70
POLE
AER_5.2 Pole Depth Setting Based on the design requirements
71
POLE
AER_5.3 Pole Setting Excavation and Backfilling
• The hole of pole should be tamp, backfill and restored to each original state of pavement.
72
POLE Linearity and Verticality
AER_5.4
• Acceptable verticality for newly installed poles.
• Installed Pole should have linearity to existing pole lines
73
Aerial Grounding
AER_6.4 Ground rod properly embedded in ground
• By standard it should be embedded ground level.
• Tolerance of 4 inches above ground
74
Aerial Grounding
• AER_6.1 Ground wire provided
75
Aerial Grounding
AER_6.5 Strand Ground Clamp provided
• Strand ground clamp should be provided and properly terminated.
• Used to bond the cable sheath to the messenger strand. The clamp body is made
of 1-3/4 X 3/16"-inch steel with a keeper inside riding on the end of the bolt. The
2"-inch bolt can be removed to place the clamp over the messenger wire.
76
Aerial Grounding
AER_6.2 HDPE conduit provided to cover the ground wire
• Check grounding protector - 3m 1/2" diameter HDPE
77
Aerial Grounding
AER_6.6 Ground Rod provided
78
Aerial Grounding
AER_6.7 Ground resistance not to exceed 25ohms
• Every grounding system located at pole should be less than 25 ohms.
• Refer to the results as indicated in the IC grounding resistance test form
• Every 300 meter should have a grounding system based on approved detailed design drawing with
a grounding resistance of 25 ohms.
79
Aerial Grounding Guying
• AER_7.1 Installed according to plan & guying standard; if not, Site Instruction
should be provided or if ROW problem.
• Check SLD/AFI for the location of guy, it should correspond to the actual location.
• If possible base/height ratio should be 1, if not ratio cannot be less than 1/2. in most cases
base/ratio are 1, 3/4, 3/5, 1/2
80
Aerial Grounding
AER_7.2 Properly Tension
• Check tension of guy wire by simply pushing the wire, it should be sturdy.
81
Aerial Grounding
AER_7.3 Complete installation of guying accessories i.e. Guy grip, strain insulator, guy wire,
guy protector, anchor rod, etc.
• Guying fixture should conform with standard design and aerial installation practices.
82
Types of Guying
83
84
85
86
87
88
Do Things Right the First Time.
89