the request Variation is Rejected due to:

1- to provide the actual location for all isolators than mentioned in BoQ Bill 16/2 for
100 A,63 A,32 A ,20A and 16A industrial as there is omission shall be.
2- the Rate you submitted is rejected as it included the manpower hours
and to submit the breakdown for pricing as per BoQ
3- the overhead &profit is rejected
4- to provide the support documents for that additional

12/1/2016
rejected

the request Variation is Rejected due to:


1- to provide the actual location for all isolators than mentioned in BoQ Bill 16/2 for
100 A,63 A,32 A ,20A and 16A industrial as there is omission shall be.
2- the Rate you submitted is rejected as it included the manpower hours
and to submit the breakdown for pricing as per BoQ
3- the overhead &profit is rejected
4- to provide the support documents for that additional

12/1/2016
??

rejected

12/1/2016
rejected

rejected
rejected