In SAP Project system, you can schedule a project or part of the project with all the activities that
are assigned to project. You can use WBS element basic dates as basic dates to schedule the
activities.
When a network contains few activities that are not assigned to same WBS, they are treated as
external networks in system in project scheduling.
Step 1 − To define parameters for WBS scheduling, you can use T-code: OPTQ or you can
navigate to SPRO → IMG → Project System → Dates → Data Planning in WBS → Define
Parameter for WBS Scheduling.
Step 3 − In the next window, you have to enter the following field −
Start in Past − Enter number of past days when scheduling starts in past.
Scheduling Method − Select the scheduling method.
Step 5 − When you enter all the details, next is to save the configuration.