Type Line Spiral-Curve-Spiral Spiral-Curve-Spiral Spiral-Curve-Spiral Line


Length 0.001m 50.000m 91.370m 50.000m 0.001m
Radius 89.999m
Start Point 925.3788m,1911.0699m 925.3794m,1911.0706m 960.7987m,1946.1188m 1047.9621m,1953.7446m 1088.9294m,1925.3794m
Xc 49.616m 49.616m
Tc 16.790m 16.790m
P 1.154m 1.154m
K 24.936m 24.936m
Pass Throught
1000.0000m,2000.0000m 1088.9301m,1925.3788m
Point 2
Pass Through
925.3788m,1911.0699m 1000.0000m,2000.0000m
Point1
Deflexión 90.0000 (d)
Direction N40° 00' 00"E S50° 00' 00"E
Start Station 1+142.14m 1+142.14m 1+192.14m 1+283.51m 1+333.51m
End Point 925.3794m,1911.0706m 960.7987m,1946.1188m 1047.9621m,1953.7446m 1088.9294m,1925.3794m 1088.9301m,1925.3788m
Yc 4.604m 4.604m
TL 33.469m 33.469m
End Station 1+142.14m 1+192.14m 1+283.51m 1+333.51m 1+333.51m
Delta angle 15.9157 (d) 58.1687 (d) 15.9157 (d)
Spiral_PI Northing 1936.7094m 1946.8929m
Radial Point Northing 1871.5804m 1871.5804m