TODO Before Site

1. Image of Tower – Deck configura�on


2. Founda�on

a. Theore�cal Eleva�on of Top of Founda�on = (Loaded Cable from DWG) 1232.525 – 2.225 (space) – 0.2
(beam U 200) – 6.616 (height of structure) = 1223.48
b. Theo Eleva�on of Botom of Founda�on = 1223.484 – 1.5 = 1221.98
3. Note Theore�cal Tension & Angle
a. Tension: 48.9 kN or 4.99 tons
i. SkyZip Sheets: Horizontal T = 48.93 kN.
OR 49.47 at point C and 48.94 at point D
ii. Skyline DWG = 48.9 kN
b. Angle
i. Point C: 8.45 degree
ii. Point D: 1.3 degree (downhill / very tout)
4. Note Theore�cal Cable Height along the profile
UNLOADED Cable

Start – Point C 0 1261.9


10 meters 10 1260.43
100 meters 100 1248.88
Mid Point 170 1241.94
Safety Net (4 m) 316.97 1233.22
Front Column (4 m) 320.97 1233.1
Back Column (14 m) 324.97 1232.98
10 meters 330 1232.83
End – Point D 338.97 1232.6
5. Note Tensioner Setup of how many meters each

a. Red = Enough for Jack


b. Green = at least 15 cm
c. Blue = example when no addi�onal tension adjustment
6. Es�mate Eleva�on of Ground Tower – Founda�on Tower – Tower Pla�orm – Tower Connec�on – Ground Offload
Deck -- Founda�on OD – OD Pla�orm – Unloaded Cable – Loaded Cable
a. C Top of Founda�on: 1256.5
b. C Cable atachment: 1261.9
c. D Top of Founda�on: 1255.1
d. D Cable atachment: 1232.6
e. Offload Deck Pla�orm: 1230.3 m
f. OD Loaded Cable [18 meters away]: 1232.525
g. OD Unloaded Cable [18 meters away]: 1233.1
h. OD Top of Founda�on: 1223.48
i. OD Botom of Founda�on: 1221.98
7. Theore�cal Elas�c Stretch
a. Elas�c Stretch for 70kN
i. Based on calcula�on: 0.33%
ii. Based on empirical benchmark: 0.34%
b. Structural Stretch
i. 0.5 – 1%
TODO On Site
1. Briefing & Review All Plan
2. Check readiness of Tower in point C and point D
a. Tensioner correctly installed
b. Cable installed on Tensioner
c. Hydraulic Jack can fit in Tensioner
3. Tensioning
a. Install Load Cell
b. Measure tension up to XX tonnes
c. Measure angle
d. Dismantle and repeat
4. Eleva�on of Cable Confirma�on
a. Measure unloaded eleva�on
b. Weight 120 kg & hang to 19 mm cable, where the horizontal distance is 18 meters away
c. Measure loaded cable eleva�on
d. Determine PRACTICAL pla�orm height by minus 2.225 meters
5. Marking of Socke�ng Posi�on
a. Ensure everything OK before finalizing socke�ng posi�on
i.e. Tension, Tensioner posi�on, Angle, Offload Deck Height Feasibility, Profile Obstruc�on
b. Mark Cable where the end of spelter socket should be

AFTER MAIN WORK DONE:

• Input & recheck everything on LAPTOP


• Remeasure and check profile along the cable
• Try Zip 1