MEMORANDUM
PRODUCTION DEPARTMENT
ENGRO FERTILIZERS LIMITED
DAHARKI, PAKISTAN
TO : SID,MAJ,BAf
CC : SNH, AlQ,MIK, KBM
FROM : WI
1
PRODUCTION DEPARTMENT
ENGRO FERTILIZERS LIMITED
BACKGROUND
One of the biggest hurdle faced by interfaces today in maintenance of machinery is lack
of synergy amongst operations, maintenance & I&E. This is primarily due unavailability
of methodical PM & CM regimes. Operations is responsible for handing over an
equipment for PM & breakdown maintenance when demanded by the interface. But one
equipment has to undergo several PMs, involving more than one interface. For this
Operations has to handover one equipment multiple times for PM performed by different
interfaces.
In order to streamline this routine activity & reduce downtime of equipment, operations
has come with a plotted plan to eliminate discrepancies in PM & CM regimes. This will
not only reduce workload of operations team but also add to the health of equipment by
reducing multiple shut-downs & start-ups.
PROPOSAL
A plan or Job card is be developed so that for every critical machine job handover Ur-2
OPS & FM are on single page wrt to their preparedness and Job planning
ATTACHMENTS
2
Attachment-I: C-2C/D/E Job Package:
Job
Last Calibration Calibration Due Waiver
Sr # C-2C Job List Completed Remarks Resp
Date Date Status
Signature
1 C-2C overhauling FM
2 Power End & fluid end inspection FM
3 Main Packing & wiper packing leakage FM
4 E-33C tube cleaning FM
5 E-27C1/2 E-28C1/2 ,E-29C1/C2 ,E-20C1/2/3 CW side cleaning FM
6 PRV adjustment of FF lubricator FM
7 PSV inspection which are have planned inspection or on waiver FM
PSV-33___ FM
PSV-34___ FM
PSV-35___ FM
PSV-36___ FM
PSV-37___ FM
PSV-38___ FM
8 P-14C discharge C/V's inspection FM
9 5th discharge C/V inspection. FM
10 FIL-2C cleaning FM
11 Crank case cover leakages to minimize oil replenishment FM
12 C-2C all stages suc/dich valve inspection FM
13 Auto drainer fault rectification & inspection FM
14 Jacket water leakage removal FM
15 All knck out drums & pulsation bottles inspection FM
16 MP-14C & MP-16C field servicing & its breaker feeder servicing. I&E
17 C-2C all control valve PM job I&E
18 All tripping securities PM job. I&E
PLCO-87 A I&E
PLCO-90 A I&E
DPSH 100 A I&E
3
PLCO-86 A I&E
PHCO-82 A I&E
PHCO-83 A I&E
VHCO-12C I&E
VHCO-14C I&E
LHCO-23 C I&E
19 Green List Jobs FM/I&E
20 Lube oil filters cleaning FM
21 Sump cleaning & decanting & cleaning of C-2C OPS
4
Last Job
Calibration Waiver
Calibration Completed Remarks
Due Date Status
Sr # C-2D Job List Date Signature Resp
1 C-2D overhauling FM
2 Power End & fluid end inspection FM
3 Any Jacket water leakage or wiper packing leakage FM
4 E-33 D tube cleaning FM
5 E-27D1/2 E-28D1/2 ,E-29D1/C2 ,E-20D 1/2/3 CW side cleaning FM
6 PRV adjustment of FF lubricator FM
7 PSV inspection which are have planned inspection or on waiver FM
PSV-33___ FM
PSV-34___ FM
PSV-35___ FM
PSV-36___ FM
PSV-37___ FM
PSV-38___ FM
8 P-14D discharge C/V inspection FM
9 5th discharge C/V inspection. FM
10 FIL-2D cleaning FM
11 Crank case cover leakages to minimize oil replinshment FM
12 C-2D all stages suc/dich valve inspection FM
13 Auto drainer fault rectification & inspection FM
14 jacket water leakage removal FM
15 All knck out drums & pulsation bottles inspection FM
16 MP-14D & MP-16D field servicing & its breaker feeder servicing. I&E
17 C-2D all control valve PM job I&E
18 All tripping securities PM job. I&E
PLCO-87 B I&E
PLCO-90 B I&E
DPSH 100 B I&E
PLCO-86 B I&E
5
PHCO-82 B I&E
PHCO-83 B I&E
VHCO-12D I&E
VHCO-14D I&E
LHCO-23 D I&E
19 Green List Jobs FM/I&E
20 Lube oil filters cleaning FM
21 Sump cleaning & decanting of C-2D OPS
6
Sr # C-2E Job List Last Calibration Waiver Job Remarks Resp
Calibration Due Date Status Completed
Date Signature
1 C-2E overhauling FM
2 Power End & fluid end inspection FM
3 Mian packing & wiper packing leakage FM
4 E-33E tube cleaning FM
5 E-27E/28E29E/30E cw side cleaning. FM
6 PRV adjustment of FF lubricator FM
7 PSV inspection which are have planned inspection or on waiver FM
PSV-33___ FM
PSV-34___ FM
PSV-35___ FM
PSV-36___ FM
PSV-37___ FM
PRV-72 __ FM
8 P-14E discharge C/V's inspection FM
9 P-16E discharge C/V's inspection FM
10 5th discharge C/V inspection. FM
11 FIL-2E cleaning FM
12 C-2E cono filter cleaning FM
13 Crank case cover leakages to minimize oil replenishment FM
14 C-2E all stages suc/dich; valve inspection FM
15 MP-14E & MP-16E field servicing & its breaker feeder servicing. FM
16 C-2E all control valve PM job. FM
17 C-2E motor filter cleaning. FM
18 All tripping securities PM job I&E
PSL 101/6 I&E
PHCO-83E I&E
PI - 900-8 I&E
PDAH-900-10 I&E
7
TE-900-22 H I&E
TE-900-23 HH I&E
TAH-900-20 I&E
TE-900/21A I&E
TE-900/21B I&E
TE-900/21C I&E
TE-900-13 I&E
TAH-900-16 I&E
VSH-900-19/19A I&E
LHCO-23E I&E
TE-900-17-1A/1B/2A/2B/3A/3B/4A/4B/5A/5B/6A/6B/7A/7B I&E
19 C-2E motor PM job & its winding cleaning I&E
20 Green List Jobs FM/I&E
21 Sump cleaning & decanting of C-2E OPS
8
ENGRO FERTILIZERS LIMITED
MANUFACTURING DIVISION, DAHARKI
Document Type: Special Operating Originated by : WI/Mukhtiar Ali In : FEB 2020
Procedures Revision No: 0
C-2C/D/E CRANK Issue No. 1 : WI/Mukhtiar Ali In : May 2020
CASE OIL LEVEL Reviewed by : SNH In : May 2020
Document No.: PR-UR2-P4-18 Approved by : KBM In : May 2020
DRAINING & Updation due: In : May 2023
9
ENGRO FERTILIZERS LIMITED
MANUFACTURING DIVISION, DAHARKI
Document Type: Special Operating Originated by : WI/Mukhtiar Ali In : FEB 2020
Procedures Revision No: 0
C-2C/D/E CRANK Issue No. 1 : WI/Mukhtiar Ali In : May 2020
CASE OIL LEVEL Reviewed by : SNH In : May 2020
Document No.: PR-UR2-P4-18 Approved by : KBM In : May 2020
DRAINING & Updation due: In : May 2023
18.1 PPE’S:
1. Mandatory PPE’s.
2. Cotton Gloves.
18.2 PREPARATION:
1. Arrange 12 cleaned & same oil grade oil drums.
2. Arrange foam of dimension (20cm*8cm) for sump cleaning of C-2C/D/E
3. Arrange a potable water hose having a Chicago coupling at one end & other
end is open.
4. Arrange a spare SYNCOM area operator for this activity.
18.3 HAZARDS AND CONSEQUENCES:
1. Oil may contaminate so collect oil in clean & same oil grade oil drums.
2. Oil may spill, therefore must take care to avoid slippage.
3. Explosion may occur if welding job to be done nearby.
4. P-16C/D/E1/E2 may damage if Crank Case become empty/low oil level.
5. Oil may drained while recharge in crank case so make sure that all drains &
bleeders are properly closed.
6. Oil drum may fall so special care must be required during oil charging & drums
shifting.
18.4 PRE-CHECKS:
1. Ensure oil drums are neat & clean.
2. Ensure oil drums are being used having the same oil grade.
3. Ensure all drums are properly covered & secured after oil filling in drums.
4. Caution board is used to avoid any misunderstanding.
5. Entry is restricted at the oil drums location.
6. Hose which is to be used is cleaned & physically OK.
7. Area should be cordon off before start the activity.
8. Make sure that load testing tag is installed at belts are being used for oil drums
shifting.
18.5 OIL DRAINING:
1. For C-2C/D install hose at P-16C/D discharge line Chicago coupling bleeder &
insert other end of hose in empty oil drum.
2. For C-2E install hose at P-16E1/E2 discharge line Chicago coupling bleeder &
insert other end of hose in empty oil drum.
3. Crack open the drain valve & fill the drum at about 90% by starting P-16C/D/E.
10
ENGRO FERTILIZERS LIMITED
MANUFACTURING DIVISION, DAHARKI
Document Type: Special Operating Originated by : WI/Mukhtiar Ali In : FEB 2020
Procedures Revision No: 0
C-2C/D/E CRANK Issue No. 1 : WI/Mukhtiar Ali In : May 2020
CASE OIL LEVEL Reviewed by : SNH In : May 2020
Document No.: PR-UR2-P4-18 Approved by : KBM In : May 2020
DRAINING & Updation due: In : May 2023
4. Close the drain valve after oil drum filling & capped the drum.
5. Shift maximum oil from crank case in drums by keep an close eye on P-16C/D/E
discharge pressure.
6. For C-2D Remove hose from P-16C/D discharge bleeder & installed at suction
bleeder of P-16C/D
7. For C-2E Remove hose from P-16E1/E2 discharge bleeder & installed at suction
bleeder near E-30E for complete oil draining.
8. Marked the drums clearly.
18.6 SUMP CLEANING FOR C-2E
1. Ensure C-2E is LOTO
2. Ensure Vessel Entry prerequisite is done for Confine space permit Requirements
3. During lube oi removal from crank case use pack of foam sponge to soak the
residual of oil to empty out crank case & squeeze the sponge in tray OR bucket.
11
Attachment-II:P-201’s Job Package
Last Job
Calibration Calibration Waiver Completed Remarks
Sr # P-201B/C/E/F s Job List Date Due Date Status Signature Resp
1 P-201's crank case Overhauling (if required) FM
2 P-201's packing/manifolds replacement (if required) FM
3 Crank case & gear box lube oil cooler cleaning FM
P-201's suction , discharge ,casing & Lube oil PSV's
4 inspection FM
P-201 B PSV's FM
PSV-204___ FM
PSV-269___ FM
PSV-204___ FM
PSV-201___ FM
5 P-201's suction & discharge pulsation bottle inspection FM
6 P-201's gear box inspection or replacement (if required) FM
7 P-201's oil filter cleaning. FM
8 All instrumentation PM job FM
Instrumentation Inst
PTX/PHCO-419___ Inst
TAH/THCO-419___ Inst
PSL-423___ Inst
PLCO-427___ Inst
9 Lube oil motor PM job Inst
10 P-201,s flushing BFW FI's fault rectification. Inst
11 Motor field servicing & breaker feeder servicing Elec
12 Green List Jobs FM/I&E
12
Requirement of FM team in Handing over of P-201’s
1. P-201’s Suction hogger installation for removal of trapped ammonia
2. P-201’s suction blind installation
3. N2 connection while pressurization of Uraca
4. Presence of FM team while pressurizing Uraca’s with Ammonia
13
Attachment-III:P-202’s & SC-241 Job Package
Sr # P-202G's Job List Waiver Status Job Completed Remarks Resp
Signature
1 L.O filter replacement/cleaning. FM
2 BFWstrainers are cleaned . FM
3 Gear box inspection FM
4 Check Free Shaft Rotation FM
5 E-208 G1/G2 Lube oil exchangers cleaning FM
6 Safety Critical Securities PM I&E
PHCO-125G I&E
PSLL-122G I&E
PT-122G I&E
THCO-126G I&E
TE-137G I&E
FSLL-121G I&E
FSLL-122G I&E
VHCO-121G/GA I&E
VHCO-122G/GA I&E
VHCO-123G/GA I&E
7 Main & aux. motors servicing (Field/breakers) I&E
8 Temperature Indication PM I&E
TE-126G I&E
TI-136G I&E
TE-117 G I&E
TE-118 G I&E
TE-119 G I&E
TE-120 G I&E
TE-125 G I&E
TE-126 G I&E
TE-121G I&E
TE-123G I&E
TE-124 G I&E
14
(TE-1/2/3/4/5/6) I&E
9 PLC check up I&E
15
Attachment-IV: List of Breathers
16
Attachment-V Urea-2 Pump change over Matrix
17
Urea-2 STAND BY PUMPS OPERATION CHECK UP MATRIX 2Q-2020
Month April May June Remarks
Week 1w 2w 3w 4w 1w 2w 3w 4w 1w 2w 3w 4w
Category-1: Pump change over on quarterly basis
P-266B
P-265A
P-280C
P-16E2
P-205B
P-255A
P-263A
P-280 A
P-274B
P-243D
P-244C
P-11D
P-274A
P-202B
P-241A
P-267B
P-262A
P-243A
P-243C
18
Urea-2 STAND BY PUMPS OPERATION CHECK UP MATRIX 2Q-2020
Month April May June Remarks
Week 1w 2w 3w 4w 1w 2w 3w 4w 1w 2w 3w 4w
Category-1: Pump change over on quarterly basis
P-256A
P-242 A
P-255
P-202C
P-263B
P-243B
P-247B
P-242B
Category-2 Pump operation will be checked on half yearly basis or Standby pump to be put in operation
in case of Startup/Shutdown
Month Jan Feb March April May June July Aug Sept Oct Nov Dec
Week 3w 3w 3w 3w 3w 3w 3w 3w 3w 3w 3w 3w
P-254A/B
P-254C/D
Guidelines:
1. P-202 F to be start on 1st Wednesday of each Quarter (Jan, April,July,October)
2. Tuesday morning shift SS to ensure standby pump operation checkup as per matrix and sign the matrix
19
3. Category-1 pump operation will be checked and line up in system on quarterly basis as per scheduled matrix.
4. Category-2 pump operation will be checked on half yearly basis or Standby pump to be put in operation in case of Plant
startup/Shutdown. This category Pump has to be started on Tuesday (Working day)
5. In case the pump changeover is not possible pen down the reason on the pump matrix
20
Attachment-VI PRESERVATION OF ROTORY MACHINES
Engro Fertilizer Ltd.
Effective by : March 2020 Urea-2 plant
Prepared by : Asad Saifullah Lube Oil Circulation Checklist
Reviewed by :WI (Applicable when plant is shut down for
more than 1 month) Revision No : 2
Approved by : SNH Updated On:
Com pressor post checklist to be filled in Morning Shift and Synthesis post checklist to be filled
in Evening Shift on 15th of Every m onth
Date:__________________
OPERATOR:_________________________
21
Engro Fertilizer Ltd.
UREA-2 plant
Effective by : March 2020
Oil Cup Monitoring Checklist
Prepared by : Asad Saifullah
Reviewed by : RdA
(Applicable when plant is shut down for more Revision No : 2
Approved by :SNH than 1 month) Updated on:
Date:__________________
Check for presence of water in oil cup and replace lube oil if required. This audit to be carried out on
15th of every month in Night Shift.
SYNTHESIS
P - 263 C q q
P-204 q q
P-298 A / B q q
P-267 A/ C q Bearing hosing oil level
B-221 q q Bearing hosing oil level
P-280 A/ C q q Bearing hosing oil level
22
Attachment-VII: Compressors/Pump Startup checklist
Engro Fertilizers Ltd.
1 Ask Supervisor to initiate electrical supervisor / engineer call out through URUT-1
2 All maintenance jobs completed and work permits returned, house keeping carried out.
3 Ensure following utilities are available
Ensure all alarms and tripping securities isolation is removed and are in service at local panel
6
PSLL86____, LHCO23____, PSHH82____, PHCO83____, PSLL87____, PSLL-90____
7 Check c.water pressure is normal ( 40# - 45# ) and is in service to all coolers.
TK-5A level is 1-2 glass of the GLG, start P-11____ check auto cut in and line up jacket water to
9
all cylinders jacket.
Crank case oil level is 50% of high low mark at the side glass, lube oil pump (P-16____) is
10
running and oil pressure is normal (35-40 psig)
12 Ensure 2nd, 3rd, 5th stage vent valves are fully open.
13 5th stage both discharge valves and cross over valve are fully closed.
14 All pulsation bottles and K.O drums drain valves are crack open.
18 CO2 from NH3-2 is available, PIC-43C is open 40% with 7# S.P. and PIC-45____ with 3# S.P.
19 Start P-14____, check FF.Lubricator drops & bar over the compressor for 15min. then stop P-14____
Start P-14____, before starting compressor and check process trips healthy indication is 'ON' at
20
local panel.
21 Inform to Ur-2 Boardman, Amm-2, UR-1 control room and start the compressor.
22 After startup check the compressor for any abnormality at any stage and pressurize the compressor.
NOTE: During pressurizing the compressor, ensure that E-30's gas outlet temperature is above 120°F, before 4th discharge pressure increases beyond 800#.
NOTE: Ensure C-2____ motor anti condensate heater and cylinder lube oil heater are off.
23
Engro Fertilizers Ltd.
Date: Time:
1 Make sure that all maintenance job are complete & all work permit have been returned.
2 Housekeeping has been carried out in comp. hall & surrounding area.
3 Ensure C-2E local panel and excitation panels are energized in ASGR
4 CB-10 at MSGR for C-2E is ON, Rack in and Put on Trip position
7 Ensure lube oil pump A/B select A=hand, B=Auto (local panel).
Ensure Lube oil pressure is more than 50 Psig, on lube oil header end PI. If lube oil pressure is
9
less than 50 Psig then Oil sump inlet filter to be cleaned by FM.
10 Ensure 1st stage (both cylinder), 2nd, 3rd, 4th, and 5th stage cylinder all capacities are unloaded.
13 Check all bulbs on local panel lights and alarms are OK and no bulbs are fused.
Check crank case oil level is normal, start lube oil pump (P-16E1, E2) & standby pump is "on auto
17
cut in". Ensure that lube oil circuit pressure is more than 35#. (set pressure of cutout is = 15#).
Start JW pump (P-11C/D) & standby pump is "on auto cut in". Open JWS & JWR v/v to C-2E
18 each stage & Check visible JWR flow in sight glasses. TK-5A JW tank level is normal (02
glasses).
19 Ensure that PIC-37V and its u/s isolating valve is open and reset its solenoid valve.
21 Ensure CO2 is available from Amm-2 and PIC-43C is 70% open with set point of 7.1psig
24 Ensure both 5th discharge block valves & FIL-2E bypass valve are closed.
25 Ensure that 1" vent valves of 2nd, 3rd & 4th stages are open .
26 All suction / discharge pulsation bottles & K.O. drum drain valves are crack open.
28 Start F.F lubricator pump & check lubricator drops as per list.
Engage pneumatic barring gear machine by maintenance person & start barring over the
29
compressor for 15 minutes. Disengage the barring gear.
Check ready to start indication in ON on local panel & no flag is appearing (Now start the main
31
motor of comp.) by pushing both button simultaneously.
32 Check thoroughly abnormal sounds from any stage & see that all F.F lubricator are working properly.
NOTE: 1) 2nd, 3rd, 4th and 5th stages capacities to be loaded when their discharge temp. increased.
2) If any inter stage temperature rised to 300°F then first unload the stage otherwise trip the compressor.
3) Ensure cylinder lube oil heater breaker is off. 4) If the machine does not start immediately initiate trip signal, rectify the cause.
24
Engro Fertilizers Ltd.
Effective on : June 2019 CARBAMATE RECYCLE PUMPS Document No : 110-Chk
Prepared by : Asghar Ali Kanju JSW (P-202 B / C / E) Issue No : 012
Reviewed by : ZuA/AA STARTUP CHECKLIST Revision No : 00
Approved by : BQ Updation Due : June 2022
Check crankcase oil level is normal & lube oil pump is running with discharge
6
pressure of 60 psig. Lube oil filters are clean and one is on stand by.
7 Check cooling water for lube oil cooler & Tarque convertor are in service.
8 Check gear box oil level is 50% of the glass.
9 Check oil flow in sight glass by priming auxiliary gear pump.
Check torque convertor oil level is 50% of the low high mark at dip-stick and its
10
cooler is in service.
11 Check HP lubricator oil pump is running and F.F lubricators are giving drops.
12 Check LP lubricator oil pump is running and F.F lubricators are giving drops.
Check flushing water for plungers is in service and flow through return line
13
sight glass is visible.
14 Check isolating valve of PHCO is open.
15 Check isolating valve of discharge PI is open.
16 Check stroking of SIC control valve on torque convertor.
17 Check no oil slippage.
18 Check that discharge drain valve is open.
19 Check Main motor breaker is racked-in in MCC Room.
25
Engro Fertilizers Ltd.
Date: Time:
Sr. No. DESCRIPTION YES NO REMARKS
1 Check that all maintenance jobs are completed and work permit returned.
4 Check that 48V power supply for tripping securities is 'ON' in auxiliary switch gear room.
5 Check that power supply of breaker for local control panel is 'ON' in auxiliary switch gear room.
6 Check that local control panel is energized and all indication bulbs are available and working 'OK'.
Check cooling water in lube oil cooler is in service. Both strainers on cooling water lines are clean
7
& one is standby.
9 Check auxiliary lube oil pump is on line on auto cut-in mode with oil pressure of 40 psig.
10 Check bursting discs on glands seal flushing lines are not ruptured.
13 Check stroking of HIC-221V & FIC-222V checked from local panel & is 'OK'.
14 Check isolating valve of discharge and suction lines PI's are open.
Check oil level in menzel oil pump is full and pump is running normal to feed oil to suction and
15
discharge PI's.
Check low pressure oil cutout switches (PA-122) & low pressure auxiliary oil pump cutin switch
18
(PA-131) are in service.
i- Suction line I/V. ii- FIC-222V down stream I/V. iii- P-202F discharge line I/V to ACES.
Open seal flush water for 1st stage to maximum and check water is coming out from discharge
23
line drain.
Open seal flush water for 2nd stage to maximum and check water is coming out from discharge
25
line drain.
Open FIC-222V 80% on manual. Flow indication from FIC-222 will show flow has established
36
through the pump towards E-261 recycle line & line d/s of FIC-222V is clear.
38 Put main motor breaker on remote and reset in MSGR-1. Pump is ready to start now.
NOTE: 1) Reset diagnostic switch after main drive started. 2) Check for any leakage
26
Engro Fertilizers Ltd.
Date: Time:
27
Engro Fertilizers Ltd.
Effective on :Feb 2020 Document No : 109-Chk
P-261,s
Prepared by : Abid Ali Issue No : 01
STARTUP CHECKLIST
Reviewed by : WI Revision No : 00
Approved by :SNH Updation Due : July 2023
28
Engro Fertilizers Ltd.
Effective on :July 2020 Document No : 114-Chk
P-274 's
Prepared by : Abid Ali Issue No : 01
STARTUP CHECKLIST
Reviewed by : WI Revision No : 00
Approved by :SNH Updation Due : July 2023
1 Check that all maintenance jobs are completed & work permits returned.
2 Check all locks are removed,breaker is rack in & reset.
3 Check oil level in oil cup. It should be 50% min.
6 Check that RO is installed at seal water line option from P-274's discharge
7 Check that pump is flush and its suction , discharge lines are clear.
8 Check pump drain valve is closed.
9 Check that pump m/seal drain line valve is closed.
10 Check TW in pump suction is closed.
11 Check that LPA-A (E-262A) level is normal about 55% or more .
12 Check suction valve is open.
13 Check pump discharge valve is crack open.
Inform Boardmen & start the pump.Line up pump gradually by opening its
14
discharge valve
15 After pump started & linedup.Check for any abnormality.
29