Professional Documents
Culture Documents
Summary of Work Accomplished de
Summary of Work Accomplished de
Period Covered:
Second (2nd) and Final Progress Payment From June 13, 2022 to July 25, 2022
ACCOMPLISHMENT
DESCRIPTION UNIT QTY. UNIT COST WT (%) COST PREVIOUS THIS PERIOD TO DATE
QTY. AMOUNT %WT QTY. AMOUNT %WT QTY. AMOUNT %WT
A. BOUNDARY SURVEY lot 1.00 50,000.00 4.95% 50,000.00 1.00 50,000.00 4.95% 50,000.00 50,000.00 4.95%
B. STRUCTURAL SURVEY l.s. 1.00 240,000.00 23.76% 240,000.00 1.00 240,000.00 23.76% 240,000.00 240,000.00 23.76%
C. SUBDIVISION SURVEY lot 160.00 3,875.00 61.39% 620,000.00 160.00 620,000.00 61.39% 620,000.00 620,000.00 61.39%
Page 1
OFFICE OF THE PRESIDENT
NATIONAL HOUSING AUTHORITY Annex A1
For Regional Offices:
Elliptical Road, Quezon City
Projects P50M and Below
Region: NCR East Sector District: QCDOI
PROJECT NAME: Survey Works and Individual Lot Titling of the Portion of Camp Atienza CONTRACT DURATION: 120 Calendar Days
LOCATION: Brgy. Libis, Quezon City DATE STARTED: June 13, 2022
CONTRACTOR: Dimaculangan Land Surveying Services COMPLETION DATE (ORIGINAL): October 10, 2022
ORIGINAL CONTRACT COST: ₱997,000.00
ACCOMPLISHMENT
DESCRIPTION UNIT QTY. UNIT COST WT (%) COST PREVIOUS THIS PERIOD TO DATE
QTY. AMOUNT %WT QTY. AMOUNT %WT QTY. AMOUNT %WT
A. BOUNDARY SURVEY lot 1.00 50,000.00 5.02% 50,000.00 1.00 50,000.00 5.02% 50,000.00 50,000.00 5.02%
B. TOPOGRAPHIC SURVEY lot 1.00 50,000.00 5.02% 50,000.00 1.00 50,000.00 5.02% 50,000.00 50,000.00 5.02%
C. STRUCTURAL SURVEY units 154.00 500.00 7.72% 77,000.00 154.00 77,000.00 7.72% 77,000.00 77,000.00 7.72%
Conforme: Prepared By: Checked and Reviewed by: Recommending Approval Approved by:
ENGR. DIOKNO M. DIMACULANGAN ENGR. BYRNE JOBIE B. FERRERAS ENGR. ROSE MICHELLE P. MAHAMUD ENGR MAURA D. AGGARAO ATTY. PARINA R. JABINAL
Sole Proprietor Senior Engineer A Officer-In-Charge Officer-In-Charge Acting Group Manager
QCDO NCR-East Sector QCDO NCR-East Sector NCR - East Sector Financial Services Group
Dimaculangan Land Surveying Services
Page 2