REVISED SCHEDULE OF RATES DUE TO FINAL QUANTIFICATION

Contract Duration
Project: Original Contract Cost
Location: Original Completion Date
Contractor: Revised Completion Date due to CTE No. 1
Revised Completion Date due to CTE No. 2

ORIGINAL ADDITIVE DEDUCTIVE FINAL QUANTIFICATION


DESCRIPTION UNIT UNIT COST
QTY. AMOUNT QTY. AMOUNT QTY. AMOUNT QTY. AMOUNT

A. Boundary Survey lot 50,000.00 1.00 50,000.00 1.00 50,000.00

B. Structural Survey l.s. 240,000.00 1.00 240,000.00 1.00 240,000.00

C. Subdivision Survey lot 3,875.00 160.00 620,000.00 26.00 (100,750.00) 134.00 519,250.00

D. Topographic Survey ha. 100,000.00 1.00 100,000.00 1.00 100,000.00

REVISED PROJECT COST DUE TO FINAL


1,010,000.00 (100,750.00) 909,250.00
QUANTIFICATION
DETAILED COST COMPUTATION

C. SUBDIVISION SURVEY

Quantities in the contract


DESCRIPTION QTY. UNIT COST TOTAL
B. Subdivision Survey 160.00 ₱ 3,875.00 ₱ 620,000.00
TOTAL COST ₱ 620,000.00

Quantites due to Final Quantification


DESCRIPTION QTY. UNIT COST TOTAL
B. Subdivision Survey 134.00 ₱ 3,875.00 ₱ 519,250.00
TOTAL COST ₱ 519,250.00

Deductive Amount -₱ 100,750.00

Prepared by:

BYRNE JOBIE B. FERRERAS


Senior Engineer A, QCDO