CONSTRUCTION COST
PROJECT COST DERIVATION
AND
UNIT COST DERIVATION
TOTAL CONSTRUCTION PROJECT COST
1. BY ITEM OF WORKS
works are divided into major components of works
-CONCRETING, FORMWORKS, STEELWORKS
2. BY STRUCTURAL MEMBERS
works are divided into major structures of the project
- footings, column pedestals
Two main Types of Cost in Construction
Project
Types of Cost Construction Project Costs
BILL OF QUANTITIES
UNIT PRICE AMOUNT
ITEM NO. DESCRIPTION UNIT QTY.
(Pesos) (Pesos)
804(1)b Embankment (from Common Borrow) cu.m 890.50 -
804(4) Gravel Fill cu.m 80.42 -
CIVIL, MECHANICAL, ELECTRICAL AND
PART II
SANITARY/PLUMBING WORKS
PART B PLAIN AND REINFORCED CONCRETE WORKS
900(1)c1 Structural Concrete (Class A, 28days) cu.m 195.95 16,454.76 3,224,309.76
UNIT COST DERIVATION
UNIT COST DERIVATION
- in finding the unit cost of every pay item of works stated in
the bill of quantities, you need to compute the direct cost
first.
- compute and add the indirect cost and divide with the
given quantity of the item.
UNIT COST ANALYSIS OF CONCRETING
WORKS
Contract ID: 22GO0095
Contract
Name: Construction of Multi-Purpose Building, Bacolod City Police Office, Negros Occidental
Location of
the
Contract: Bacolod City, Negros Occidental
BILL OF QUANTITIES
UNIT PRICE AMOUNT
ITEM NO. DESCRIPTION UNIT QTY.
(Pesos) (Pesos)
TRANSIT
MIXER 2 4 10,500.00 84,000.00