Professional Documents
Culture Documents
Section II B Structure
2B-1 General
This section describes the technical specifications and measurements and payment for
structure works for canals and inspection roads that must be carried out in accordance
with working drawings or PPK orders.
If any, the structures to be constructed or rehabilitated are:
- Division/Off-take Structures,
- Tertiary Box,
- Pipe/box culverts,
- Flume concrete / masonry,
- Overflow Structure,
- Cross drainage culverts,
- People's bridge/bridge,
- Gutters,
- Waterfall Structure,
- Wash Ladder, and
- Concrete lining and masonry, slope protection, etc.
2B-2 Earthworks
2B-2.1 Excavation
Excavation work for structures must be carried out in accordance with the provisions of
Article B-3.2.
Excavations for canal lining, side spillways and box culverts must be carried out at the
same time as canal excavation work. The volume of excavation work for the above
structures must be calculated as canal excavation work.
Excavation work for drainage culverts, bridge foundations, except for bridges that cross
canal excavations, must be carried out before carrying out canal excavation work.
Measurement of excavation work must be carried out based on the original ground surface
as shown in the drawing or PPK order.
Excavation work for structures other than those mentioned above is carried out after the
excavation work and/or canal embankment has been completed. In this case the volume of
excavation work for the structure must be measured starting from the surface of the
excavation or canal embankment according to the dimensions shown in the drawings.
ST. IIB - 1
TECHNICAL SPECIFICATION Section II B - Structure
ST. IIB - 2
TECHNICAL SPECIFICATION Section II B - Structure
ST. IIB - 3
TECHNICAL SPECIFICATION Section II B - Structure
required for the completion of this work in accordance with the provisions in Sub-Article
G.
ST. IIB - 4
TECHNICAL SPECIFICATION Section II B - Structure
The provisions in Article H-8 or the PPK order regarding weep holes that are installed on
parapet walls and flap valves needed on flume floors must be followed and carried out in
drain work.
All costs for constructing temporary works required for the implementation of flume
works, for example temporary parapet walls, drying and others, including costs for
maintenance, demolition and cleaning, are calculated and included in the lump-sum cost
of temporary works listed in the Quantity and Price List.
If the items of work/lump-sum costs above are not listed in the Quantity and Price List, all
costs incurred for these activities which are necessary for the ease and smoothness of the
implementation of the main/permanent work, are considered included in the contract price
and are the full responsibility of the Provider..
ST. IIB - 5
TECHNICAL SPECIFICATION Section II B - Structure
must be carried out by the Provider after the proposed work plan and method have been
approved by the PPK.
Costs for all temporary works and supporting works above including costs for labour,
materials and equipment are considered to have been calculated in the lump-sum cost for
temporary works listed in the Quantity and Price List.
If the items of work/lump-sum costs above are not listed in the Quantity and Price List, all
costs incurred for these activities which are necessary for the ease and smoothness of the
implementation of the main/permanent work, are considered included in the contract price
and are the full responsibility of the Provider.
2B-12 Bridge
2B-12.1 General
Traffic bridges and bridges for pedestrians with long spans must be constructed with
reinforced concrete T-beam construction Type Class I to Class III of the Bina Marga
standard depending on the road class, while bridges with short spans are built with
reinforced concrete floor construction, supported by head and pillars of the bridge.
ST. IIB - 6
TECHNICAL SPECIFICATION Section II B - Structure
The costs required for the construction, maintenance and demolition of the temporary
facilities mentioned above including costs for workers' wages, materials and equipment
are considered to have been calculated in the lump-sum cost for temporary works listed in
the Quantity and Price List.
If the items of work/lump-sum costs above are not listed in the Quantity and Price List, all
costs incurred for these activities which are necessary for the ease and smoothness of the
implementation of the main/permanent work, are considered included in the contract price
and are the full responsibility of the Provider.
ST. IIB - 7
TECHNICAL SPECIFICATION Section II B - Structure
ST. IIB - 8
TECHNICAL SPECIFICATION Section II B - Structure
a) The slope/talud of the old canal must be excavated in stages as a foundation for
backfill/backfill to be done, payment for this work will be made separately in
accordance with the provisions of Article B-3.4 in Part-I.
b) The embankment on the excavated slope must be carried out layer by layer and
compacted using a tamping rammer or stamper in accordance with the conditions
of the work site following the terms and conditions of Article B-4 (Landfill) and
added sufficiently with extra embankment exceeding the slope line indicated in
the Picture. Payment for this embankment work is made based on the provisions
of Article B-4.3 in Part-I.
c) The extra embankment is cut up to the slope line which is determined as the
foundation of the canal lining, must be carried out in accordance with the
provisions of Article C-3.4.2 in Part-I.
- Pouring of concrete for canal linings must be carried out in accordance with the
provisions in Article C-3.4 (Pouring of Concrete Mixture) including the use of air-
entraining admixture and C-4.2 (Concrete for Lining of Canals).
- To avoid the formation of joints or cold joints in one segment of the concrete lining,
use an appropriate liquid retarder with PPK approval.
- To accelerate the hardening/strength of the concrete layer, use an appropriate liquid
(admixture) or fast-setting cement with PPK approval.
- Tolerances for concrete lining work must comply with the provisions in Article C-8
(Tolerances for Concrete Work)
- Concrete curing carried out according to the requirements specified in C-5 (Concrete
Curing) and curing materials according to the requirements in Sub-section C-5.3 and
approved by PPK shall be used for the curing of concrete layers as specified in Sub-
section C-5.1.
- At the joints between the new concrete lining panels or with the old concrete lining, a
joint sealant must be installed in accordance with the provisions in Article H-5 Part-I
or in accordance with PPK orders.
- Unless specified in the drawings or by the PPK, the provider must use molds/slip-
forms for coating concrete in such a way that the casting can be carried out
continuously and allows the compression and formation/setting of surface coatings.
This italic mold before being used in the field must first be proposed by the Provider
to the PPK for approval. The pouring concrete layer for the inclined molds shall be
started from the bottom of the chute upwards by electrically sliding the forms or other
suitable method.
- The lining concrete used is the result of batching plant production in accordance with
Sub-articles C-2 and C-9 and is approved by PPK.
- Underdrain, which consists of graded sand and gravel in accordance with Article D-8
which is placed on top of a Type-1 geo-textile layer in accordance with Article H-17
must be sufficiently compacted.
- Basically producing concrete for lining must use a batching plant based on Articles C-
2 and C-9 as well as PPK approval.
- For bottom bunds in canal linings, the graded sand and gravel filters as specified in
Article D-8 shall be used based on the Type-1 geo-textile filter specified in Sub-
section H-16.3 with sufficient compaction.
ST. IIB - 9
TECHNICAL SPECIFICATION Section II B - Structure
- For underdrain standards as shown in the drawing, if springs are found on the slope of
the foundation lining, adjustments to the direction and/or design of the underfloor
drainage must be made with the approval of the PPK.
Measurements for payment for canal linings made of concrete and stone masonry are
carried out based on the relevant work unit price per cubic meter listed in the List of
Quantities and Prices and are considered to include costs for wages, materials, equipment
and construction installation needed to complete this work, including the procurement of
cement. , aggregates, admixture (if used), mixing, pouring and grouting of concrete,
construction joints and other works. Measurements for payment for laying of masonry
linings are carried out separately at the unit price per square meter contained in the
Quantity and Price List. Measurement and payment for reinforcing bars, joint filler,
subfloor fittings and infiltration pipes are carried out separately based on the relevant
article in Part-I. Payment for fabrication and procurement of molds is made at the unit
price in question in the Quantity and Price List. The payment is total compensation for the
fabrication, transportation, storage, repair, materials, tools, equipment and other things to
prepare the oblique moulds,
2B-17 Km and Hm
The km and hm markers shall be made and installed along the canal by the Provider to
indicate the cumulative length of the canal measured from the intake structure or the canal
start point. The stakes must be made of concrete with a size of 30 cm x 30 cm x 1.5 m for
km stakes and a size of 10 cm x 10 cm x 1.0 m for hm stakes which must be installed
along the inspection road or according to PPK orders with painted letters and numbers and
clear.
ST. IIB - 10
TECHNICAL SPECIFICATION Section II B - Structure
Article B- 1 and B-2 unless the location of the structure is located on the clearing,
grubbing and stripping lines for the canal.
2B-19.2 Excavation
Measurements for structure excavations are carried out based on Article B-3.4. Payment
for structure excavation will be carried out in accordance with the unit price per cubic
meter listed in the Quantity and Price List in accordance with Article B-3.4.
2B-19.3 Backfill
Measurements must be carried out in accordance with Article B-5 and payments will be
made based on the unit price per cubic meter listed in the Quantity and Price List.
ST. IIB - 11
TECHNICAL SPECIFICATION Section II B - Structure
ST. IIB - 12