SECTION B2
B2- 1
Concrete structures general
10°C. When the temperature is below 10°C, the time of opening to traffic shall be
increased at the discretion of the Engineer's Representative.
Bridges with concrete decks shall not be opened to traffic without the approval of the
Engineer's Representative.
B2 04 Measurement
Measurement of the various items involved in the construction of "Concrete
Structures" shall be made in accordance with the specifications for the several items
involved.
B2 05 Payment
Payment for the various items involved in the construction of "Concrete Structures",
will be made in accordance with the Specification, at the price tendered in the Bill of
Quantities for the several items involved. Any item not included in the Bill of Quantities
which is shown on the Drawings or called for by the Specification shall be understood to
be included in the rates quoted for other items.
Payment shall include the furnishing of all materials, labor, equipment and all items
required to complete the work. The construction of weep holes and drains and the back-
filling with coarse gravel or rock as specified above, shall be included in the price
tendered in the Bill of Quantities per cubic meter for concrete in place.
B2- 2