Professional Documents
Culture Documents
Sub-section B Earthwork
An explanation regarding the above will be provided by the PPK based on the
conditions of the work location.
If the land within the boundaries of the demarcation line is dominated by plants
with a height of less than 2.0 m or plants with a diameter at breast height (DSD) of
less than 10 cm, land clearing and clearing in that area cannot be categorized as
"cutting and clearing of shrubs". ” in this Technical Specification, but as a stripping
work in accordance with the provisions in Article 2 is the stripping of organic soil:
layers of grass, topsoil, roots and non-organic materials, namely the remains of
structures, foundations and others and removing them from the work location .
ST.B-1
TECHNICAL SPECIFICATIONS Sub-section B - Earthworks
B-3 Excavation
B-3.1 General
Excavation work in question is excavation of sedimentary soil, ordinary soil and rock
excavation including other related work, for example treatment efforts, access roads and
supporting structures (separator, relocation, safety structures and others) as needed and
transportation of excavated materials to the location where necessary. agreed for a final
disposal site or temporary stockpiling (stock piling) prior to further utilization.
The provider is required to submit the results of laboratory tests of the soil to be
excavated, the working method of the excavation work including the equipment used,
transportation to the final disposal site or temporary storage prior to utilization for
stockpiling materials, no later than 30 (thirty) days before the excavation work is carried
out.
The provider is obliged to carry out the measurement and marking work with the PPK
after the cutting and clearing of shrubs has been completed or at other times in accordance
with the PPK's instructions, the results of which are pictures of measurement results
showing the elevation of the ground surface, longitudinal and transverse sections must be
submitted to the PPK for approval. The pictures of the results of pre-construction
measurements above will be used as a reference and basis for calculating the quantity of
excavation work.
The Provider is obligated to prevent damage to and protect the soil below the elevation of
the permanent work excavation: channels and structures to keep them in good condition,
ST.B-2
TECHNICAL SPECIFICATIONS Sub-section B - Earthworks
soil damage to the foundation soil caused by the Provider's fault must be repaired
immediately at his own expense.
In the event that the excavation work exceeds the limit specified in the working drawings
(drawings of pre-construction measurements) the Provider, at his own expense, must
backfill that part with fill materials approved by the PPK.
The provider must notify the PPK when excavation work has been completed to carry out
an inspection for approval before further work/irrigation structures or concrete casting is
carried out. The use of stockpiling and disposal of excavated soil must comply with
Article B-3.3
ST.B-3
TECHNICAL SPECIFICATIONS Sub-section B - Earthworks
ST.B-4
TECHNICAL SPECIFICATIONS Sub-section B - Earthworks
All costs incurred by the Provider to carry out all of the above activities in the
procurement of land for stockpiling materials, are considered to have been included
in the unit price of landfill work in the List of Quantities and Prices.
ST.B-5
TECHNICAL SPECIFICATIONS Sub-section B - Earthworks
ST.B-6
TECHNICAL SPECIFICATIONS Sub-section B - Earthworks
ST.B-7
TECHNICAL SPECIFICATIONS Sub-section B - Earthworks
This price is considered to include all costs for labor, equipment, materials, measuring,
excavation, transportation and disposal, fire and cliff avalanche prevention and other
efforts unless specified in the List of Quantities and Prices, for example temporary access
roads, canal relocation and avoidance structures. /safety, draining/pumping, partition and
others.
The unit price for excavationing hard rock includes costs for rock blasting and other
efforts required for smooth implementation.
ST.B-8
TECHNICAL SPECIFICATIONS Sub-section B - Earthworks
ST.B-9
TECHNICAL SPECIFICATIONS Sub-section B - Earthworks
Specification, the trial embankment must be unloaded by the Contractor from the work
location.
(2) Type-D
For embankment work with soft foundation soil and high groundwater level, after
the treatment of the foundation soil surface has been completed as described in
Article B-4.2.2.(1), efforts to drain it with a water pump need to be carried out at
least 2 (two) times. ) hours before the backfill work is done.
While the embankment is being carried out, the groundwater level must be
maintained at least 30 cm below the embankment surface, and if the soil surface is
flooded, the soil surface must be stripped to a thickness of at least 5 cm or according
to PPK instructions and then hoeed/plowed as deep as 15 cm as described in Article
B-4.2.2.(1).
(2) The groundwater content of the landfilld material must be at keep it around the
optimum water content with a tolerance of + 3% to -5% of the optimum water
content based on laboratory tests or other provisions based on PPK orders based on
the soil properties of the soil.
Compaction must be carried out until the density of the embankment reaches 95%
of the maximum dry density for normal compaction and 85% for light compaction
in accordance with the provisions in Article B-4.1.(2).
ST.B-10
TECHNICAL SPECIFICATIONS Sub-section B - Earthworks
For embankment slopes that will be reinforced with a layer/concrete girder, before
the concrete girder is installed/casted, the embankment slope must first be trimmed
and compacted with a tamping-rammer or other tool approved by PPK in
accordance with the dimensions shown in the working drawings.
B-4.3.1 Measurement
Measurements for payment for Type-A1, A2, B1, B2, C1, C2 and D embankments are
carried out in cubic meters (m3) of dense embankments measured based on the
longitudinal section, cross section, elevation, slope, and distance according to the
drawings the agreed work and the results of the latest work performance measurement
including Type-D embankment, taking into account the settlement and subsidence of the
foundation soil which is still ongoing.
B-4.3.2 Payment
(a) Type-A1 and Type-A2
Payment is made based on the unit price in the Quantity and Price List including
costs for wages, materials, equipment and all costs incurred by the Provider for the
smoothness and ease of carrying out work, including: temporary storage, heavy
equipment platforms on soft soil, control of moisture content and compaction ,
formation and hearth of heaps and others.
(b) Type-B1 and Type-B2
Payment is made based on the unit price in the Quantity and Price List including
costs for providing borrow-pit, transportation, disposal, temporary storage, heavy
equipment platforms on soft soil, spreading, controlling moisture content and
compaction, forming and embankment fireplaces and all costs incurred Providers
for the smoothness and ease of carrying out work including costs for wages,
materials, equipment, permits, royalties and others.
(c) Type-C1 and Type-C2
Payment is made based on the unit price in the Quantity and Price List including
costs for borrow-pit provision, transportation, payment, temporary storage, heavy
equipment platforms on soft soil, spreading, controlling moisture content and
compaction, forming and embankment fireplaces and all costs incurred Providers
for the smoothness and ease of carrying out work including wages, materials,
equipment, permits, royalties and others.
(d) Type-D
Payment is made based on the unit price of the List of Quantities and Prices
including costs for borrow-pit provision, transportation, disposal, temporary storage,
platforms for heavy equipment on soft soil, paving, controlling moisture content and
compaction, forming and embankment fireplaces and all costs incurred by the
Provider. for the smoothness and ease of carrying out work including wages,
materials, equipment, permits, royalties and others.
B-5 Landfills/Backfill
Backfill work must be carried out in accordance with the agreed work drawings or on the
order of the PPK, based on the purpose of backfill being classified into 2 (two) types,
namely:
ST.B-11
TECHNICAL SPECIFICATIONS Sub-section B - Earthworks
Type-A : backfill for structures: weirs, irrigation canals and drainage and in other
locations in accordance with PPK instructions with normal/ordinary
compaction as described in Article B-4.1.2). (a) This Technical
Specification.
Type-B : backfill without strict compaction control, intended for temporary bypass
canals and other locations designated by KDP.
The provider is obliged to convey the work methods, materials and equipment planned to
be used, to the PPK for approval before the backfill work is carried out:
Type-A : - soil backfill material must come from excavated soil or from borrow-
pitwhich meets the requirements as landfill material based on the results
of laboratory tests and on the approval/order of the PPK.
- Done at least 14 (fourteen) days after the concrete work for the structure
has been completed.
- worked layer by layer with layer thickness based on test results
depending on the material/soil for the landfill, the equipment used and
the number of passes.
- In general, the thickness of the compacted backfill layer should not
exceed 15 cm.
- the soil water content of the embankment material ranges from +3% to -
5% of the optimum water content based on laboratory test results with a
density level of 95% maximum dry density in accordance with ASTM
D-968 criteria.
- Compaction by usingvibro-rolleron the top of the structure up to a
distance of 0.50 m above the structure is not permitted unless it has
obtained PPK approval.
Type-B : landfill material originating from land resulting from excavation work at a
structure site or other location in accordance with PPK approval.
Measurement for Type-A backfill work is carried out in cubic meters (m3), namely the
volume measured starting from the boundary line of the excavation work and the outer
wall/surface of the structure or a predetermined elevation that does not exceed the original
ground level elevation or based on measurement data before and immediately after
backfill work is completed on soft soil foundations where settlement and land subsidence
are still continuing or according to PPK orders.
Unless otherwise stipulated by the PPK, costs for Type-B backfill are included in the
Lump Sum price in the Quantity and Price List. However, if based on a PPK order,
payment for Type-B backfill work must be made based on the unit price, then the payment
will be made based on the volume of work obtained from measurement data before and
after the completion of work that is satisfactory to PPK.
Payment for backfill work is carried out based on the price listed in the Quantity and Price
List which includes costs for: excavation, transportation, re-handling, spreading,
controlling moisture content, compaction, fireplace and other costs including, wages,
materials, equipment and supporting work described in Sub-section A.
ST.B-12
TECHNICAL SPECIFICATIONS Sub-section B - Earthworks
The technical specifications for road pavement work are described/specified in Article D-
6, Stone Works of this specification.
ST.B-13
TECHNICAL SPECIFICATIONS Sub-section B - Earthworks
ST.B-14
TECHNICAL SPECIFICATIONS Sub-section B - Earthworks
(b) Road
- road surface : - 0 cm, + 5 cm
- road width : - 0 cm, + 10 cm
- line : ± 5 cm
(c) Structure excavation
- bottom of excavation : + 0 cm, - 5 cm
Moisture/Density
ASTM D2216 -
Relationship
Unconfined
JIS 1216 -
Compression Test
According to the Engineer's
Permeability test
instructions
1. Every 10 km length of
subgrade or each section of
road length.
California Bearing Ratio For pavement
AASHTO T193 2. Pavement:
(CBR) 30% minimum
(i) for each new source of
material
(ii) at least once a month.
ST.B-15
TECHNICAL SPECIFICATIONS Sub-section B - Earthworks
value that
Laboratory Test Standard Method Laboratory Test Frequency
required
At each excavation base for
Cone Penetration Test AASHTO T206 -
structures
*2 times a day (morning,
Field Density Test ASTM D1556 > 95% MDD evening) at each work
location, or
*every 250 m³ of canal
Field Moisture Test ASTM D2216 OMC +3%, -5% rehabilitation works, or
*according to PPK orders
ST.B-16