Project Task Duration and Dependencies

The document outlines a project plan with 7 tasks labeled A through G, including task descriptions and durations in weeks. Critical tasks are highlighted in yellow, and the Coating task of 5 weeks duration has a total float of 3 weeks and free float of 13 weeks. A Gantt chart shows the schedule and dependencies between the tasks over a period of 21 weeks.

Uploaded by

Javed Choudhry
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views13 pages

Project Task Duration and Dependencies

The document outlines a project plan with 7 tasks labeled A through G, including task descriptions and durations in weeks. Critical tasks are highlighted in yellow, and the Coating task of 5 weeks duration has a total float of 3 weeks and free float of 13 weeks. A Gantt chart shows the schedule and dependencies between the tasks over a period of 21 weeks.

Uploaded by

Javed Choudhry
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Task Description of the task Duration (weeks) Predecessors

A General Design 7

B Opearatinal Design 3 A

C Design of building surface solutions 1 A

D Design of lighting 2 B

E Purchase of lighting 6 BD

F Coating 5 C

G Installation of lamps and furnitures 2 EF

Notes: Critical activities are highlighted in yellow.


Total float and free float of Coating Activity are highlighted in green
0
A
7
0
ES TF EF

ID
Activity name
D

LS FF LF

8 0 10
D
Design of lighting
2
8 0 10

7 0 10
B
Operational design
3
7 0 10

0 7
General Design

0 7

7 3 8
C Design of Building
1 Surface Solutions
10 0 11
10 0 16
E
Purchase of lighting
6
10 0 16

16 0 18
G Installation of
2 lamps/furnitures
16 0 18

8 3 13
F
Coating
5
11 3 16
Task Description of the task Duration (weeks) Predecessors

G Installation of lamps/furnitures 2 EF
Dependency type

FS

Gantt chart

1 2 3
A General Design
B Opearatinal Design
C Design of building surface solutions
D Design of lighting
E Purchase of lighting
F Coating
G Installation of lamps and furnitures
4 5 6 7 8 9 10 11 12
13 14 15 16 17 18
week 1 2 3 4 5 6 7 8
A 3 3 3 3 2 2 3 3
B 8 8 8 8
C 4 4 4 4
D 6 5 5
E
F
G
pwd 3 3 3 3 14 20 20 20

week 1 2 3 4 5 6 7 8
A 3 3 3 3 3 3 2 2
B 8 8 8 8
C 4 4 4 4
D 5 6 6
E
F
G
pwd 3 3 3 3 15 20 20 20
PART - a

9 10 11 12 13 14 15 16 17 18 19 20 21

8 8 8 8
4 4 4 4 4 4 4 4 5 5
8 4 4
4 4 3 3 3 3 3 3 4 4 4 4
5 8 8 8 8 7 6 6 6 5
5 5 4
20 20 20 20 15 15 15 15 15 15 15 15 13

PART - b

9 10 11 12 13 14 15 16 17 18 19 20 21

8 8 8 8 2 2
4 4 4 4 4 4 4 4 5 5
8 5 5 6 4 4 6
3 3 3 3 3 3 4 4 4 4 4 4
6 6 6 6 6 8 8 8 6 6
4 4 5
20 20 20 27 19 19 19 14 17 17 16 14 15
22 Workload pwd
22
64
58
32
42
5 72
4 18
9 308

22 Workload pwd
22
68
58
55
6 48
6 72
5 18
17 341