Professional Documents
Culture Documents
CPM / PERT
Need to add the footer with Dr.
Bhattachara to all slides
• QFD
2
Dr. Tapas Bhattacharya, Amity Business School
MBA (M&S), 2 Semester, Batch 2024
What is PERT?
• Prediction of deliverables
• Planning and controlling resources requirement
• Determination of activities and evaluation of activities
• Elimination of risks in a complex activities
• Reduction in cost and savings in time
• Internal program review and performance evaluation
4
Dr. Tapas Bhattacharya, Amity Business School
MBA (M&S), 2 Semester, Batch 2024
Probabilistic Time Estimates
• Reflect uncertainty of activity times
• Beta distribution is used in PERT
Optimistic Time : (to) Most Likely Time : (tm) Pessimistic Time : (tp)
the minimum time in which the best estimate of time in the maximum time in which
activity can be completed which the activity can be the activity can be completed
accomplished against all odds
Z = x - μ Standard deviation,
σ
Where,
σ = √ σ2 = √ tp−to 2
8
Dr. Tapas Bhattacharya, Amity Business School
MBA (M&S), 2 Semester, Batch 2024
Advantages of PERT
• Identifies the most critical elements in the plan, thus focusing
management attention ie. Constraining on the schedule
• This method can get very complex and tedious - there can be potentially
hundreds of activities and individual dependency relationships
10
Dr. Tapas Bhattacharya, Amity Business School
MBA (M&S), 2 Semester, Batch 2024
Process Flow in a PERT
11
Dr. Tapas Bhattacharya, Amity Business School
MBA (M&S), 2 Semester, Batch 2024
Differences between PERT and CPM
PERT CPM
12
Dr. Tapas Bhattacharya, Amity Business School
MBA (M&S), 2 Semester, Batch 2024
PERT Example 1
For the given activities determine:
ACTIVITY to tm tp
1-2 6 9 12
1-3 3 4 11
2-4 2 5 14
3-4 4 6 8
3-5 1 1.5 5
2-6 5 6 7
4-6 7 8 15
5-6 1 2 3
13
Dr. Tapas Bhattacharya, Amity Business School
MBA (M&S), 2 Semester, Batch 2024
PERT Example 1
Solution: First of all draw the network diagram for given data as shown below
by calculating Expected times (te):
2 6
9 6 6
9
1 4
6 2
5
3 5
2
TOTAL
ACTIVITY DURATION EST EFT LST LFT
FLOAT
1-2 9 0
1-3 5 0
2-4 6 9
3-4 6 5
3-5 2 5
2-6 6 9
4-6 9 15
5-6 2 7 15
Dr. Tapas Bhattacharya, Amity Business School
MBA (M&S), 2 Semester, Batch 2024
Quick CPM recap
2 6
9 6 6
9
1 4
6 2
5
3 5
2
TOTAL
ACTIVITY DURATION EST EFT LST LFT
FLOAT
1-2 9 0 9 9
1-3 5 0 5 20
2-4 6 9 15 15
3-4 6 5 11 15
3-5 2 5 7 22
2-6 6 9 15 24
4-6 9 15 24 24
5-6 2 7 9 24 17
Dr. Tapas Bhattacharya, Amity Business School
MBA (M&S), 2 Semester, Batch 2024
Quick CPM recap
2 6
9 6 6
9
1 4
6 2
5
3 5
2
LST = TOTAL
ACTIVITY DURATION EST EFT LFT
LFT - D FLOAT
1-2 9 0 9 0 9
1-3 5 0 5 15 20
2-4 6 9 15 9 15
3-4 6 5 11 9 15
3-5 2 5 7 20 22
2-6 6 9 15 18 24
4-6 9 15 24 15 24
5-6 2 7 9 22 24 18
Dr. Tapas Bhattacharya, Amity Business School
MBA (M&S), 2 Semester, Batch 2024
Quick CPM recap
2 6
9 6 6
9
1 4
6 2
5
3 5
2
TF = (LFT-
EST-D)
TOTAL
ACTIVITY DURATION EST EFT LST LFT
FLOAT
1-2 9 0 9 0 9 0
1-3 5 0 5 4 20 15
2-4 6 9 15 9 15 0
3-4 6 5 11 9 15 4
3-5 2 5 7 20 22 15
2-6 6 9 15 18 24 11
4-6 9 15 24 15 24 0
5-6 2 7 9 22 24 15 19
Dr. Tapas Bhattacharya, Amity Business School
MBA (M&S), 2 Semester, Batch 2024
Now let’s use PERT method
1 Critical path
Here the critical path is along the activities 1-2, 2-4, 4-6.
So the critical path is 1-2-4-6.
Following diagram is prepared to show critical path along with EST and LFT.
9
2 6 24
9 9 6 6
15 24
0 9
1 4
0 6 15 2
5
3 5
2
TOTAL
ACTIVITY DURATION EST EFT LST LFT
FLOAT
1-2 9 0 9 0 9 0
2-4 6 9 15 9 15 0
4-6 9 15 24 15 24 0
2 6
9 6 6
9
1 4
6 2
5
3 5
2
Here the time for completion of activities are probabilistic. So, using given
values of time we will find the expected time to completion the activities and
variance.
Variance V = tp−to 2
21
Dr. Tapas Bhattacharya, Amity Business School
MBA (M&S), 2 Semester, Batch 2024
6
PERT Example 1
2 Standard deviation & variance
2 6
9 6 6
9
1 4
6 2
5
3 5
2
2 6
9 6 6
9
1 4
6 2
5
3 5
2
te= Variance
ACTIVITY to tm tp
(to+4tm+tp)/6 V = [tp – to /6]2
1-2 6 9 12 (6+36+12)/6 = 9 (12 – 6 /6)2 = 1.00
1-3 3 4 11 5 1.778
2-4 2 5 14 6 4.000
3-4 4 6 8 6 0.444
3-5 1 1.5 5 2 0.444
2-6 5 6 7 6 0.111
4-6 7 8 15 9 1.778
5-6 1 2 3 2 0.11 23
Dr. Tapas Bhattacharya, Amity Business School
MBA (M&S), 2 Semester, Batch 2024
PERT Example 1
2 Standard deviation & variance
ACTIVITY to tm tp Te Variance
1-2 6 9 12 9 1.00
1-3 3 4 11 5 1.778
2-4 2 5 14 6 4.000 σc = √ V1+V2+V3
3-4 4 6 8 6 0.444
3-5 1 1.5 5 2 0.444 σc = √ 1+4+1.778 = 2.6034
2-6 5 6 7 6 0.111
4-6 7 8 15 9 1.778
5-6 1 2 3 2 0.11
Using the Standard Normal Table, we can look up the corresponding probability
26
STANDARD NORMAL TABLE
3 Probability: 26 days completion
Z = 0.7682
Therefore, the probability of completion of project in given time (t) of 26 days is 77.8%
27
Dr. Tapas Bhattacharya, Amity Business School
MBA (M&S), 2 Semester, Batch 2024
Project Crashing
29
Dr. Tapas Bhattacharya, Amity Business School
MBA (M&S), 2 Semester, Batch 2024
ASSIGNMENT QUESTION
30
Questions