The document is a budget plan for a landslide mitigation project in Cikereteg in 2023. It outlines 3 zones of work (Zones 1, 2, and 3) and itemizes 20 line items of work for Zones 1 and 2, such as excavation, bamboo installation, concrete work, and drainage. The total costs for the preparation work, Zone 1 work, and Zone 2 work are not included in the summary budget table.
The document is a budget plan for a landslide mitigation project in Cikereteg in 2023. It outlines 3 zones of work (Zones 1, 2, and 3) and itemizes 20 line items of work for Zones 1 and 2, such as excavation, bamboo installation, concrete work, and drainage. The total costs for the preparation work, Zone 1 work, and Zone 2 work are not included in the summary budget table.
The document is a budget plan for a landslide mitigation project in Cikereteg in 2023. It outlines 3 zones of work (Zones 1, 2, and 3) and itemizes 20 line items of work for Zones 1 and 2, such as excavation, bamboo installation, concrete work, and drainage. The total costs for the preparation work, Zone 1 work, and Zone 2 work are not included in the summary budget table.
No. Uraian Pekerjaan Spesifikasi Volume Satuan Harga Satuan Jumlah Harga
PEKERJAAN PENANGULANGAN LONGSOR
I. Pekerjaan Persiapan (3 Lokasi Penanganan) a. Pekerjaan mobilisasi material dan tenaga kerja 3.00 Lokasi - b. Pek. pengukuran & pembuatan gambar eksisting 1.00 Ls - c. Pekerjaan sondir 2 titik sondir / lokasi 1.00 Ls - d. Konsultan perencanaan 1.00 Ls - e. Pembersihan lokasi sebelum dan setelah pekerjaan 120.00 HOK - f. SMK3 3.00 Lokasi - g. Laporan dan dokumentasi pekerjaan 3.00 Lokasi -
Jumlah Pekerjaan Persiapan -
II. Pekerjaan Penanganan Zona 1 (Area Pintu gerbang) 1 Pemasangan bowplank 46.00 m' - 2 Galian tanah biasa untuk pondasi 55.44 m3 - 3 Pekerjaan cerucuk bambu Ø10 cm T=4.0 m 3,024.00 m' - 4 Pemasangan pondasi siklop Pas.Batu 1:4 46.00 m3 - 5 Pemasangan DPT batu belah Pas.Batu 1:4 248.40 m3 - 6 Pekerjaan kolom beton - - Pekerjaan bekisting 108.12 m2 - Pembesian 865.94 kg - Cor beton K-225 8.11 m3 7 Pekerjaan balok beton Uk 30/30 - - Pekerjaan bekisting 165.60 m2 - Pembesian 1,210.55 kg - Cor beton K-225 12.42 m3 8 Pemasangan sulingan Pipa Pvc Ø 2" + ijuk 184.00 m' - 9 Pekerjaan plester aci topian 46.00 m2 - 10 Pekerjaan urugan kembali sisa galian + perapihan 55.44 m3 - 11 Pekerjaan uruan tanah dari luar lokasi + pemadatan 299.88 m3 - 12 Pekerjaan saluran beton Uk.30/30 2.10 m3 - 13 Pekerjaan rabat beton Tb.10 Cm + Wiremesh m8 6.30 m3 - 14 Pekerjaan bak kontrol Uk.2x1 m 1.00 bh - 15 Pemasangan pipa outline bak kontrol termasuk dudukan & support 30.00 m' -
Jumlah Pekerjaan Penanganan Zona 1 -
III. Pekerjaan Penanganan Zona 2 (Area Pintu Air ) 1 Pekerjaan pembuatan kisdam dengan karung tanah 37.00 m' - 2 Pemasangan bowplank 46.00 m' - 3 Pekerjaan peninggian DPT sebelum pintu air - - Galian tanah biasa untuk pondasi 31.50 m3 - - Pasangan batu belah 40.95 m3 - - Urugan kembali sisa galian + perapihan 31.50 m3 - - Pekerjaan plesteran topi 10.50 m2 - 4 Pekerjaan sulingan Pipa Pvc Ø 2" + ijuk 42.00 m' - 5 Pekerjaan plesteran topi 10.50 m2 - 6 Pekerjaan bongkaran dan pemindahan pagar panel 10.50 m' - 7 Pekerjaan Bongkaran DPT yang tidak terbawa longsor 28.70 m3 - 8 Pekerjaan perbaikan rongga DPT seberang longsoran 19.00 m3 - 9 Pekerjaan galian tanah biasa sisa longsoran 196.88 m3 - 10 Pekerjaan galian tanah cadas untuk pondasi DPT 44.40 m3 - 11 Galian tanah straus pile Ø 40 cm 5.25 m3 - 12 Pekerjaan urugan tanah dan pemadatan 120.00 m3 - 13 Pengecoran beton straus pile - - Pembesian 958.04 kg - - Cor beton K-250 5.67 m3 - 14 Pekerjaan Beton DPT - - Pekerjaan bekisting 210.90 m2 - - Pembesian 6,077.15 kg - - Cor beton K-250 85.10 m3 - No. Uraian Pekerjaan Spesifikasi Volume Satuan Harga Satuan Jumlah Harga
15 Pekerjaan cerucuk bambu Ø10 cm T=4.0 m 496.00 m' -