Professional Documents
Culture Documents
ABSTRACT
Cameron-Clarke, I.S. and Budavari, S., 1981. Correlation of rock mass classification
parameters obtained from borecore and in-situ observations. Eng. Geol., 17: 19--53.
INTRODUCTION
The three tunnels from which data were obtained for this investigation are:
the Bushkoppies Tunnel, situated approximately 15 km to the south of
Johannesburg; the Delvers Street Tunnel, located in the central city area of
Johannesburg; and the Du Toitskloof Pilot Tunnel, situated approximately
60 km northeast of Cape Town. The locations of the three tunnels are shown
on the appropriate regional geological maps in Figs. 1 and 2. The Bushkoppies
Tunnel is to be used for the conveyance of sewage, and the Delvers Street
+ + + .~.
!. ''" (
o lo 20 3o km
LEGEND
Karroo Supergroup
Transvaal Supergroup
V Ventersdorp Supergroup
Upper
~- Witwatersrand Supergroup
Lower_J
Ancient Granite 8, schist remnants
/f Fault
Regional dip direction
Delvers Tunnel
LEGEND
* Tertiary to Quaternary
; Cape Supergroup
[~ KlipheuwelFormation
~i Cape Granite
Malmesbury Beds
f Fault
D0 Du Toitskloof Tunnel
Fig.2. Regional geological map of the Cape Peninsula area showing the location of the Du
Toitskloof Pilot Tunnel.
Tunnel was planned to house feeder and distribution cables for a new central
electricity substation. The Du Toitskloof Pilot Tunnel forms part o f the in-
vestigation for a major highway tunnel between Paarl and Worcester. The
ultimate aim of the scheme is to have two tunnels, 36 m apart, each carrying
unidirectional traffic. All three tunnels have inverted "U" shaped cross-
sections with equal horizontal and vertical excavated dimensions o f about 3 m.
23
The Bushkoppies Tunnel has a total length of a b o u t 6.5 km and the depth
of cover over the tunnel varies from 5 m to 65 m, Fig.3. It follows an approxi-
mate northwest--southeast route through the lavas o f the Ventersdorp Super-
group which display a general east--west strike direction and dip at a low
angle to the south. The rocks are variable from soft, completely weathered
and closely jointed material at the east portal, to very hard almost massive
rock in other sections along the tunnel. Most o f the tunnel was excavated in
hard, widely to closely jointed rock with three or more joint sets and occasional
clay-filled faults and fault zones. Tests on intact rock specimens, obtained
from these rocks yielded a mean uniaxial compressive strength of 367 MPa
(Brink and Associates, 1974). The twelve sample sites studied in this tunnel
are shown in Fig.3.
According to the nature o f the prevailing geological conditions, the tunnel
was divided into four broad sections: (a) from the east portal at 150 m to
624 m; (b) from 624 m to 3500 m and 4000 m to 5150 m; (c) from 3500 m
to 4000 m; and (d) from 5150 m to 6688 m. These sections can be described
qualitatively as follows.
Section (a)
The weathered rock exposed at the east portal was typical of the rock
encountered along the first 100--150 m length of the tunnel and is due to
normal weathering processes apparent to a b o u t 10 m below the ground surface.
Fresher rock was encountered as the excavation advanced, b u t the presence
of numerous clay-filled joints contributed to the generally unstable rock mass
condition. Partially weathered, closely jointed rock, apparently related to a
fairly extensive fault zone, was encountered near the end of this section.
Heavy support was o f t e n required throughout this part of the tunnel and
mesh-reinforced shotcrete, together with steel arches, were used.
Section (b )
This section o f the tunnel typified the most characteristic rock conditions
encountered. With the exception of localized unstable zones caused b y the
presence o f minor faults, the rock was hard and widely jointed with closed
or cemented joints. Minor water flows were noted from some of the faults.
No systematic support was needed, however, spot bolting was o f t e n carried
out.
Section (c)
The rock along this section was hard, unweathered and widely jointed, but
had a more blocky appearance than was noted in section (b). Several major
fault zones, containing quite badly sheared rock, from which moderate flows
of'water were noted, occurred within this section. Systematic rock-bolting at
1-m to 1.5-m intervalswas used for support, Along one short section, in
addition to rock bolts, wire mesh was introduced to prevent the fall-outof
small blocks from the roof.
t~
o i o
n~ t~ nn 0 •
• , M tl M .
; ! , =, . ,. ,. , . ~., ~ , , ,..~ ~ ,~n . , , ._-_ ". 0J
6000 SO00 4000 3000 ""'20'00 1000 150
il
LEGEND 0 , 1000rn
Scale
V e n t e r s d o r p Lav~.
Diabas.e
S h e a r Zones
BUSHKOPPIES TUNNEL
Section (d)
This section was characterized b y numerous intersecting clay filled joints
and a number o f quite major faults. The rock was hard and widely to closely
jointed. Weathering, particularly adjacent to the larger joints and minor
faults, became more pronounced as the depth of cover decreased westwards.
Moderate water flows were n o t e d in places. Owing to the tendency for the
rock mass to loosen as a result of the clay joint fillings, it was often neces-
s a l t to install quite closely spaced rock bolts (0.5 m in places). Along
particularly bad sections shotcrete and steel arches were used.
The Delvers Street Tunnel has a total length of a b o u t 1.2 km and the
cover depth to its crown varies from 2.5 m to 11 m (Fig.4). The tunnel
passed through alternating arenaceous and argillaceous strata of the Govern-
ment Reef and J e p p e s t o w n Formations of the Witwatersrand Supergrnup and,
at its northern end, through a sheared fault zone. The regional strike direction
of the strata is east--west and dips are vertical or very steep towards the
south. The tunnel was divided into three sections based on differences in the
general rock mass properties with respect to the tunnel, the excavation
method, and the distance behind the face at which the initial steel arches
were installed. These are: (a) from the north end of the tunnel to 350 m;
(b) from 350 m to 850 m; (c) from 850 m to 1180 m.
Section (a )
This section of the tunnel was orientated parallel to the regional strike
and dominant joint directions, and was excavated in the vicinity of the
sheared fault zone mentioned above. The steep dip, and chlorite and clay
coated joint surfaces resulted in unstable sidewall conditions. The excavation
method consisted of drilling and blasting, and the steel arches were installed
within a metre o f the face.
Section (b )
The strike of the dominant structures was perpendicular to the tunnel
axis along this section, resulting in more stable rock conditions. The excava-
tion m e t h o d was the same as in the previous section and the arches were
installed approximately 3--5 m behind the face.
Section (c)
This section was located in colluvium and residual soils derived from the
various geological horizons intersected. Hand-held pneumatic diggers were
used for Iexcavating this section and arches were installed within a metre of
the face. In places, unstable sandy material necessitated the instaUation o f
continuous Lagging in the roof.
t~
O~
e~ r,~ co ~t
Kruis Sma{
t
Yon Wetlig h "u~ Jeppe K~rk Pritchard I I
st. st. st. • ''1 I st. st. I st President L (
| I ~ ~ I ~'~" ~ Market
I / [11. I~ I , ~ Commissioner~ 20
LO 0-~
LEGEND
CoUuvium
Quartzite
Sandy Quartzite
,o lOO 2oo=
Argillaceous Quartzite with Shale & Sandstone
Scale
Arenaceous Shale Weathered
Shale
Diabase
The methods used to obtain and evaluate the parameters required b y the
Geomechanics and Q Classification Systems were adapted from existing
techniques. The main consideration was to obtain the relevant information
as simply and accurately as possible w i t h o u t unnecessary duplication of
effort. Since a number of the parameters required for both classification
systems are related to the jointing in the rock, a m e t h o d o f joint survey had
to be adopted. Scan line surveys, which record information a b o u t joints
intersecting a specific line, were suitable for both borecore and in-situ
t~
(2O
..%
-12 c~ 12
•11 ~ _ o_.a 117-
-10 ................... 10-
.9 _ ~ ~E~E! E~E ~'~ ~E ;E .-:'~._ c~ -~ 9-
"8 "~ ~ , ============================== 8-
7 o .,,,.j~. ~. , + ~ o
7-
6-
, , • T T -, ~ t t + \
LEGEND
Talus
0 1000m
Table Mountain Sandstone I i I
Fautt breccia
Borecore measurements
The method used to record the borecore data was based on those
suggested by Franklin et al. (1970), Rankilor (1974) and the South African
Section of the Association of Engineering Geologists (1976). The underlying
principle considered when selecting the method was, that the core log should
present, as closely as possible, a true picture of the rock core with a minimum
amount of description and interpretation being used. The object was to
enable the rock mass to be classified by anybody from the core log alone,
without their judgement being affected by the unintentional bias of the
original compiler of the log.
This method of logging was used only for selected sections of cores. In
most situations it would only be necessary to undertake a detailed assess-
ment of the jointing in the core for a limited distance above and below the
planned excavation. The remainder of the core could be recorded in more
general terms. The Point Load Strength Index, determined by using an
Engineering Laboratory Equipment test machine, was used to assess the
strength characteristics of the cores.
In most cases the available cores were in reasonably good condition. At
some of the sites in the Bushkoppies Tunnel, however, a suitable core length
could not be obtained from the roof strata owing to losses during storage. It
was therefore assumed that the available core was representative of the rock
mass at the particular site. This was considered to be a reasonable assumption
in view of the generally homogeneous nature of the rock mass at this
tunnel.
In-situ m e a s u r e m e n t s
The in-situ data were obtained using a line joint survey method adapted
from that proposed by Piteau (1970) and the information was recorded on
joint survey data sheets. The in-situ measurements were carried out as close
to the underground positions of the relevant boreholes as possible. At the
Bushkoppies and Delvers Street Tunnels, the boreholes were drilled from
surface along and adjacent to the centre lines of the planned excavations. At
the Du Toitskloof Tunnel, the holes were drilled from within the tunnel.
The detail line joint survey method was used only at the Bushkoppies and
Du Toitskloof Tunnels. In the former tunnel the survey lines were a standard
length of 10 m, centred as closely to the intersection points of the various
30
The procedure listed below was used to assign values to the various param-
eters specified by the Geomechanics and Q Classification Systems.
(1) The number of joints with similar inclination angles with respect to the
core axis were recorded and corrected for orientational bias.
(2) The results of step (1) were plotted as histograms and the numbers of
joint sets estimated for the rock mass at each borehole.
(3) The average spacing of the joints in each set was estimated.
(4) The number of joints in each set with similar surface roughness and
alteration characteristics were recorded.
(5) The most typical surface roughness and alteration characteristics of
each joint set was estimated.
(6) Data forms were compiled for each classification system, showing the
conditions considered to be representative of the rock mass at each borehole
location.
(7) Calculation sheets were compiled and "rock mass rating" (RMR) and
Q values were evaluated.
A similar approach to the one described above was used to evaluate the
in-situ joint survey data. The steps followed are listed below.
(1) The number of joint sets were estimated with the aid of a stereogzaphic
projection.
(2) The field survey data was then grouped into the respective sets as
estimated in step (1).
(3) The intersection angles between the survey line and the strike direction
of each joint set were determined and the true joint spacings calculated
after correcting for orientational bias (Terzaghi, 1965). The RQD values
were also determined.
31
(4) The influence of each joint set on the tunnel stability was estimated.
(5--8) Data forms and calculation sheets were compiled for each classifi-
cation system, as for the borecore data.
PRESENTATION OF RESULTS
The results derived from the borecore and in-situ observations and
presented in Tables I and II are the net output for each classification
system. For the Geomechanics System these are the RMR-value, rock class,
stand-up time and active unsupported span of each sample site. The latter
two values were estimated from the diagram presented by Bieniawski (1976a).
Owing to the scatter of data shown on this diagram, a median line was
constructed through the zone representing the limits of South African ex-
perience (Fig.6). The support recommendations for each site are also given.
The results for the Q System are the Q value, limiting span, stand-up time,
and support categories for each site. The limiting span was calculated from
TABLE I
TABLE H
Bos 1 Lava 0.07 34 1 day--1 wk. 1.1 0.14 29 1 wk.--I mth. 1.5
Bos 2 Lava 2.38 21 I0 yr. 4.5 6.06 17 I0 yrs. 6.6
Bos 3 Lava, 0.02 34 1 h 0.7 1.23 21 5---10 y r s . 3.5
dlabase
Bos 4 Diabase 26.67 13 10 yrs. 11.9 11.08 13 10 yrs. 8.4
Bos 5 Lava 6.26 17 10 yrs. 6.7 32.82 13 10 yrs. 12.9
Bos 6 Lava 0.33 29 1--6 mths. 2.1 6.66 17 I0 yrs. 6.8
Bos 7 Lava 0.13 29 Iwk.--Imth. 1.4 0.98 25 5--10yrs. 3.2
Bos 8 Lava 0.80 25 6 . 1 0 yrs. 2.9 2.91 21 I0 yrs. 4.9
Bos 9 Lava 200.00 5 10 yrs. 26.6 16.66 13 10 yrs. 9.9 ~
Bos 10 Lava 0.63 25 1--5 yrs. 2.7 0.83 25 5-10 yrs. 3.0
Bos 11 Lava 0.13 29 1 wk.--1 mth. 1.4 0.44 25 6.12 mths. 2.3
Bos 12 Lava 2.67 21 10 yrs. 4.7 2.0 21 10 yrs. 4.2
Del 1 Argill. 0.08 33 1 day--I wk. 1.2 0.58 25 1--2 yrs. 2.6
quartzite
De| 2 Argill. 0.16 29 1 wk.--I mth. 1.6 2.05 21 I0 yrs.
quartzite 4.3
Quartzite
Del 3 with 0.32 29 1--6 mths. 2.0 2.99 21 10 yrs. 5.0
argill, h o L
Del 4 Quartzite 1.76 21 I0 yrs. 4.0 4.75 17 I0 yrs. 6.0
Quartzite
Del 5 s h a l e and 0.012 33 1 h 0.5 1.02 21 5-10 yrs. 3.2
siltstone
Quartzite
Del 6 s h a l e and 0.27 29 1--6 mths. 1.9 0.22 29 1 wk.--1 mth. 1.7
siltstone
Dut 1-H ~aartzitic 1.20 21 5 - 1 0 yrs. 3.4
sandstone 1.20 21 5-10 yrs. S.4
D u t 1-V Quartzittc 0.90 25 5--10 yrs. 3.1
sandstone
Dut 2-H Quartzitie 2.04 21 10 y r s . 4.3
sandstone
1.09 21 5 - 1 0 yrs. 3.3
D u t 2-V Quartzitic 0.41 25 6 - 1 2 mths. 2.2
sandstone
Quartzitic
sandstone
D u t 3-V 1.1 21 5--10 yrs. 3.3 1.02 21 5--10 yrs. 3.2
w e a t h , and
brecc.
Granite
D u t 4-H 1.7 21 10 yrs. 4.0
sheared
0.47 25 6--12 mths. 2.4
Granite
Dut 4-V 0.09 33 1 day--1 wk. 1.2
sheared
D u t 5-H Granite 7.70 17 10 yrs. 7.2 9.74 17 10 yrs. 8.0
Dut 6-H Granite 89.70 9 10 y r s . 19.3
33,32 13 I0 yrs. 13.0
D u t 6-V Granite 33.20 13 10 yrs. 13.0
6 4 t n -6
5 ~ ~ , i , ~0 ,.~ -5
"" 80
3 -3
2 2o~ 1.2
£~~ ¢ I 1,1
o,.= .q5
1 10 10' D3 1
Joint spacing
The limits selected for this parameter, as well as for the other parameters
for the Geomechanics Classification System, were based on the minimum
t00
go
//~
80
/" A /"
/
70
~ 60
m
~ so
40
20 / ~+~ / A Bos
10 ® Dut
t=1
14.
75%
50%
S=/o
-3 -2 -1 0 1 2 3
[~IFFERENCE BETWEEN INS 8, BC ROCK CLASSES
Fig.8. Oeomechanics Classification System; histogram showing the frequency of rock class
differences between the l~recore and i.-situ ~ values.
difference between the ratings for each category. This approach was used
because the difference between the ratings for the various categories is not
always constant for a particular parameter, and it is important to assess the
borecore and in-situ ratings for all rock conditions.
The in-situ and borecore ratings for the joint spacing are presented in
Fig.9. 71% of the points lie within the selected limits. When considering all
the points with respect to the ideal line, there is a tendency for the borecore
ratings to be lower than the in-situ ratings. 64% of the points lie below the
ideal line, 25% plot above it and 11% fall on it.
30 //~
J ~ Q // /- / / / "
20 "1- 20
C " o
C J:/. j j:
10 ,,, ,," ,-// 0 A BOS ~ ' "
.," -I- D e l ,'" -I- ,,'" -I- Del
," ~ , o Dut 6 " Dut
~ // (BC =,~(i NS) * 5
/ 0 t:
5 lo 2'o 2's 3'o 6 ~ 2"o ~s
Rating (INS) Rating (INS)
Fig.9. Geomechanlcs Cla~fication System; borecore and in-situ joint spacing rating
values.
Fig. 10. Geomechanics Classification System; borecore and in-situ joint condition rating
values.
36
Joint condition
The ratings for this parameter are presented in Fig.10. 75% of the points
fall within the selected limits and 29% plot on the ideal line. 21 and 50%
lie above and below this line, respectively. These results suggest a slightly
better correlation between the borecore and in-situ ratings. A tendency for
the borecore ratings to be lower than the in-situ ratings is again apparent.
Q ClassificationSystem
Q values
The borecore and in-situQ values are plotted in Fig.12. Owing to the
logarithmic intervalsdefining the rock classes for this classificationsystem,
it was not feasible to use a constant value for the limits as was done for the
Geomechanics System, and some other method of selectinglimits was neces-
sary. One way was to combine appropriate rock classes,according to simil-
aritiesbetween their given support recommendations, in order to obtain a
constant class interval.
Barton et al. (1974) related their support categories to the Q value, and to
the equivalent dimension of an underground excavation. The latterwas
-12 I000- ~ / ~ //
// /'"/"// , /'
-I0 100- ,/ ® /
[OgO(eC}=log O(INS)±1
Um 10- ,, " A ,'"
//G Q ,
C5
~-s
..'" ~../~.~.+ A Bo,
," ~'7" -- ," + Del
/" ~ .,'" A Bos ," cS'~ /,'" A Q Dut
-2 .. / \..,- +_De, o,ol. " ~ , , . / " + ....
0,001 Ir /
-2 -~ -io 42 o,ool o.m o~ i ib ~6o 10b0
Rating (INS) O. (INSI
Fig.11. Geomechanics Classification System; borecore and in-situ joint orientation rating
values.
Fig.12. Q Classification System; borecore and in-situ Q values.
37
75°/o
d
Lt.I
U_
.50°/o
-3 -2 -1 0 1 2 3
DIFFERENCE BETWEEN INS & BC ROCK CLASSES
Fig.13. Q Classification System; histogram showing the frequency of rock class differences
between the borecore and in-situ Q values.
38
Joint roughness
For this parameter, higher ratings are related to more stable rock mass
conditions. The limits selected were based on the generalized m e t h o d Osed
to assess the joint roughness characteristics. The results presented in Fig.15
show that 71% of the points plot within the selected limits, while 39% plot
on the ideal line, and 47 and 14% lie above and below it, respectively. The
results suggest that there was a tendency for the borecore estimates of the
joint roughness to indicate better rock mass conditions than the in-situ
estimates.
Joint alteration
The limits selected for this parameter were the most c o m m o n rating
difference for the range of conditions encountered. Larger rating differences
asl 2 3 a 6 9 lz is 2o
Jr (INS}
Jn (INS)
Fig.14. Q Classification System; borecore and in-aitu joint set number rating values.
Fig.15. Q Classification System; borecore and in-situ joint roughness rating values.
39
are generally associated with higher rating values related to more intense
alteration conditions, and wider limits would therefore probably be m o r e
appropriate for such cases.
The results, presented in Fig.16, show that 64% of the points lie within
the selected limits while 36% plot on the ideal line. 43 and 21% plot above
and below the line, respectively. The borecore and in-situ results for this
parameter correlated quite well with the ideal relationship although there was
a slight tendency for the borecore estimates to indicate poorer joint alter-
ation conditions that were noted in-situ.
2°1
15
/-" ~
SRF(BC)=SRF~N~*-2,1~*_2,////~
Fig.16. Q Classification System; borecore and in-situ joint alteration rating values.
Fig.17. Q Classification System; borecore and in..situ stress reduction factor rating values.
40
60-
RaDISC):ROmI~=Z~ f / ®///'"+
/ "";"
/// / A
• /
-/•//~"
0
~,~ ~,0~ / /" + -t-
o
20" ® ® A
i0
A-I=CI-&
¢/
io io 8'0 16o
ROD °/o (INS)
Fig.18. Rock quality designation; borecore and in-situ values.
90
8O f
A
90"/, confidence timit~ ~ ~' "¢=
7O
I
I
b--£ ~o I
-90°/° confidence limit
~ so
~0 In situ rel=tionship ~ 1 ..=-"
30
A Bos
20 ~ ,,-,-" ~ , I " 4- Del
e Dut
10 ~ =~"
=-~ ~iemawski'$ relationship
0 .t
o,ooi ooi 0,1 1o 100 1000
Q(BC)
Fig.19. Comparison between the borecore RMR and Q values.
41
100 ~.
90 f A //--~.+/
~ieniowski ~ r elot ior+sl+iJ~
80 I"
--Borecore retQl[on+hip
60
I
t
Z 50 t
"*r . . . . - +% I ~
40
I3d
30
~ ~ ~ - -9O=/o ¢onfiaence limit A Bos
20 • "f -t- Del
o Dut
Q (INS)
Fig.20. Comparison between the in-situ RMR and Q values.
The 90% confidence limits, calculated from the standard errors o f estimate
about these regression lines, were +18.6 for the borecore results, and +26.8
for the in-situ results. The relationship between RMR and Q, after Bieniawski
(1976), is also shown on each diagram.
The scatter of points about the regression lines is greater for the in-situ
values than for the borecore values. In both cases, however, it is probably
t o o great to indicate any meaningful correlation between the two classifica-
tion systems. It is nevertheless interesting to note that the respective bore-
core and in-situ regression lines are similar.
DISCUSSION
as much scatter as the low values. This may be due to the relatively small
number o f observations as well as to the limited range o f rock classes
examined.
The R M R values correlated reasonably well with the various lithologies
studied. The hard lavas from the Bushkoppies Tunnel generally gave high
R M R values, whilst lower values were obtained from the weathered sediments
in the Delvers Street Tunnel. The RMR values from the granite in the Du
Toitsldoof Tunnel were similar to those obtained from the lavas. The quartz-
itic sandstones and the faulted and sheared rocks associated with the Du
Toitskloof Fault all gave low values.
Joint spacing
The borecore evaluation of the joint spacing generally indicated more
closely jointed rock conditions than were actually found in-situ. The results
from the Delvers Street and Du Toitskloof Tunnels deviated most signifi-
cantly from the ideal relationship. No satisfactory explanation can be given
for this because, for example, results from the Delvers Street Tunnel, which
represented similar sheared and closely jointed rock mass conditions,
displayed approximately equal b u t opposite deviations from the ideal
relationship. Widely jointed quartzite from the same tunnel, also gave a
similar deviation. The largest discrepancy at the Du Toitskloof Tunnel was
from relatively widely jointed rock with an average joint spacing o f 1--3 m,
which appeared to be more closely jointed in the borecore, where average
spacings of 5 0 - - 3 0 O m m and 0.4--I m were indicated.
The average joint spacing in a rock mass is a function of both t h e spacing
of each joint set as well as the number of joint sets present. If all the joint
sets can be observed and measured, a good estimate o f the average spacing
should be possible. If they are n o t all intersected, as may occur in a bore-
core, an incorrect estimate would be obtained. The error would, however, be
Opposite to that noted for the present results, i.e. wider joint spacings would
be indicated from the borecores. This suggests that the core recovery is an
important factor to consider when evaluating this parameter.
No results were obtained from joint sets with spacing values within the
two lower spacing categories and no meaningful c o m m e n t can therefore be
made concerning the correlation between the in-situ and borecore ratings for
all the categories. Regarding the various lithologies, the lavas were generally
more widely jointed than the weathered and sheared sediments. The Du
Toitskloof Tunnel results, particularly from the quartzite sandstones and
sheared rocks, display more scatter.
The joint spacing rating values contribute to the low borecore R M R
values. The discrepancy noted between the borecore and in-situ resttlts is
apparently related mainly to the core quality. Better quality core would
probably improve their correlation with respect to the ideal relationship. In
reality one would expect to obtain good quality core recovery from widely
jointed rocks, deteriorating with an increase in the degree of jointing. This
is evidently n o t always the case, however, and may be due to other factors,
43
Joint condition
The reasonably good correlation between the borecore and in-situ results
is surprising, considering that the joint continuity cannot be assessed at all
from the borecore. In p o o r quality rock, the joint separation is also very
difficult to determine. The results from the Bushkoppies Tunnel displayed
the largest deviation from the ideal relationship. These were due mainly to
incorrect joint separation estimates or, as at the Du Toitskloof Tunnel, an
incorrect assessment of the joint roughness.
It is suspected that the joint condition estimates for a particular borecore
do n o t necessarily give a true indication of the in-situ conditions at that
particular site. Nevertheless, the generally fair correlation is possibly due to a
tendency for one to select an average rating value for a parameter which
cannot easily be assessed. The overall trend towards low borecore ratings
could be indicative of a tendency to err on the conservative side, in a similar
situation,
Joint orientation
Although there is no real correlation between the borecore and in-situ
ratings for this parameter, there is a tendency for them to contribute towards
the low borecore R M R values. Owing to the lack o f information regarding
the strike and dip directions of joints in borecores, the joint orientation -was
generally assumed to be "fair" with respect to the tunnel axis.
The problems involved in correctly evaluating this parameter from a bore-
core are n o t related to core recovery, b u t rather to the physical difficulties
o f orientating the core. Some form of core orientation technique, for
example, could greatly assist in obtaining a better correlation. A good knowl-
edge of the local geology would also be of great value in obtaining a picture
of the regional joint orientations.
Q Values
The results for the Q Classification System also suggest that borecore
measurements tend to indicate poorer rock mass conditions than in.situ
measurements. 82% o f the borecore and in-situ results plotted within the
limits selected for this system. As noted previously, however, these limits
excluded borecore and in-situ Q values differing b y more than a factor of
10, b u t b y no more than one rock class.
Similarly to the Geomechanics Classification System, the histogram evalua-
tion o f the Q values yielded a higher percentage, with up to one rock class
difference, than did the evaluation with respect to the selected limits. Results
showing no class differences were most c o m m o n for this system. The
remaining results showed a tendency for t h e borecore rock class to be lower
than the in-situ rock class.
44
The majority of Q values obtained during this study varied between 0.I
and 10.0 and did not, therefore, cover a sufficiently large range to assess the
correlation of borecore and in-situQ values over the entire range possible.
One would expect, however, that a better agreement between the results
would be obtained from better quality rock.
The results obtained from the lavas of the Bushkoppies Tunnel suggest that
the Q values reflect the rock mass conditions rather than the lithological
characteristics of the rock. This view is supported, to some extent, by the
results from the D u Toitskloof Tunnel where the sheared granite and porphy-
ritic granite displayed different Q values, whilst the former rock type gave
values similar to those obtained from the sheared argillaceous quartzite at the
Delvers Street Tunnel. Houghton (1975), also, found very littlelithological
differentiation between Q values calculated for sandstone, mudstone and
l~mestone at the Kielder Experimental Tunnel in England.
Joint set n u m b e r
The confidence with which the number of joint sets present in a rock mass
can be estimated, is related to the method used to record the joints. In the
case of a borecore or in-situ survey, the estimated number of joint sets will
be a function of the orientation and spacing of each set with respect to the
orientation and length, respectively, of the borecore or in-situ survey line.
The method used to estimate the number of joint sets from the borecores, in
this study, assumed that all joints with similar dip angles (inclination angles
with respect to the core axes) also had similar dip directions. Obviously, this
was n o t necessarily correct and could have resulted in underestimates of
the n u m b e r of joint sets present. The results obtained from the present study
are consistent with this expected trend. This parameter tended, therefore, to
contribute to a better borecore estimate of the rock mass condition than
was noted in-situ.
The points which plotted outside the limits selected for this parameter
were not always related to sites with poor rock mass conditions. Examples of
good rock mass quality, where all the joint sets present were not intersected
by the borecore, were noted at both the Bushkoppies and Du Toitskloof
Tunnels.
Joint roughness
The borecore evaluation of this parameter generally indicated similar or
better roughness conditions than the in-situ evaluation. This is contrary to
what might be expected since it implies that planar joint surfaces, for
example, were classified as undulating. One would in fact expect the opposite
error to be more likely. A possible reason for this c o u l d be that the larger
asperities on planar surfaces were assumed to be undulations.
Considering the small joint surface area exposed in a rock core, the
correlation between the borecore a n d in-situ ratings is quite good. This is
probably due to the simple classification adopted during the present investi-
gation. With respect to the final Q values, this parameter does n o t contribute
to the lower borecore than in-situ values.
45
Joint alteration
The reliability of borecore joint alteration estimates is related to the
quality of the drilling operation, and the care taken by the drill operator to
record changes in the colour of the flushing water and bit penetration rate.
This latter information can indicate zones o f soft clay which may be totally
or partially lost during drilling, b u t which are important to the strength
characteristics of the rock mass. A general knowledge of the geology can also
be a great assistance in providing some indications of the possible alteration
conditions which m a y be expected.
No drilling information was available to supplement the borecore obser-
vations for the present investigation. Although there appeared to be a slight
tendency for the borecore results to indicate more advanced joint alteration
than the in-situ results, the general correlation was good. The range of alter-
ation conditions examined was limited, however, and it is likely that the
correlation would be significantly poorer for joints with no direct wall rock
contact.
Observations at only t w o sites from the Bushkoppies and Du Toitskloof
Tunnels deviated significantly from the ideal line. At the former tunnel, thick
clay gouge, which had evidently been washed away during drilling, was
revealed b y the in-situ survey. At the Du Toitskloof Tunnel, a borecore
intersected several zones of clayey grit above the tunnel, which were n o t
present at the tunnel level.
gives the Q System a slight advantage in this respect. Minor difficulties were
found with both systems for in-sltu rock classification, with the RQD esti-
mates being the most problematical.
In view of the fact that one of the main objectives of the rock mass
classification systems used in this investigation is to indicate the support
requirements in underground excavations, some comments on the correlation
between the predicted supports and those actually adopted is appropriate.
Owing to differing approaches to support problems by the contractors at
each tunnel, however, it is difficult to be general in this regard. The support
measures predicted from the borecore and in-situ results respectively,
together with those actually installed at each site, are presented in Tables III
and IV.
For the Q Classification System, the limiting span and stand-up time were
used to decide whether or n o t support was required. When the limiting span
exceeded the tunnel dimension and was associated with a stand-up time of
10 years, it was assumed that the rock mass could remain permanently unsup-
ported. For the Geomechanics System, the stand.up time never greatly
exceeded one year even if the unsupported span was significantly larger than
the span of the tunnel. In these cases it was therefore n o t possible to decide
whether the rock mass could permanently remain unsupported.
At the Bushkoppies Tunnel, the in-situ support predictions, based on the
Q Classification System, compared favourably with the supports actually
installed. The agreement is n o t as good for the borecore predictions, although
general similarities can be noted. The comparison between the installed
supports and predictions from the Geomechanics borecore and in-situ results
was n o t good, however.
At the Du Toitskloof Tunnel, the correlation was again better for the Q
System than for the Geomechanics System. For the latter the predicted
supports were generally more conservative than those installed. The Delvers
Street Tunnel results were n o t amenable to a comparison of this nature,
because, with minor variations in spacing, steel arches, and lagging when
necessary, were used throughout the entire tunnel. A 300 mm thick concrete
lining was also installed soon after excavation of the face.
CONCLUSIONS
TABLE III
TABLE IV
measurements. The borecore and in-situ classification values were then com-
pared. In general, it m a y be concluded that for both classification systems,
borecores can be used to classify rock masses for engineering purposes. Bore-
core measurements, however, tend to indicate poorer rock mass conditions
than in-situ measurements.
The tendency for lower borecore than in-situ classification values is
opposite to t h a t indicated by results presented by Barton (1976a) from a
similar type of investigation. Barton's borecore Q values were about twice
his in-situ values. This discrepancy appears to be related to the different rock
conditions examined in each case. The present results are based on measure-
ments from a variety of geological environments which included jointed rocks
predominantly, although massive rocks were also examined. Barton's data
were obtained from "quite massive biotite gneiss" only. This suggests that
the relationship between the borecore and in-situ classification values may be
linked to the rock mass condition, with lower borecore than in-situ values
being associated with jointed rocks, and the opposite being the case in more
massive varieties.
With regard to site investigations for underground excavations in rock,
both the Geomechanics and Q Classification Systems can be most useful.
Their value must be seen in perspective and their limitations always recognized.
Their best application would seem to be towards providing a general picture
of the anticipated rock conditions, and an initial assessment of the likely
51
The Q ClassificationSystem
The results obtained from the Q Classification System indicate that bore-
core data m a y be used with some certainty to classifyrock masses with Q
values exceeding approximately 0.1. Values significantly lower than this were
seldom encountered during the present study. With respect to selected limits,
the results suggest that there is approximately an 8(Wo probability of the
borecore and in-situ Q values being within one rock class of each other. The
borec0re and in-situlimiting spans and stand-up times were also generally
similar.
A tendency toward lower borecore than in-situ Q values was also noted
for this system. The borecore assessment of the individual classificationpar-
ameters correlated reasonably well with the in-situratings. The joint set
number and joint roughness parameters indicated better rock conditions
from borecore measurements than from in-situmeasurements, whilst the
joint alteration parameter and stress reduction factor displayed an opposite
52
trend. The rock quality designation probably influenced the present results
most significantly with a marked tendency to lower borecore than in-situ
values.
The Q ClassificationSystem was found simple to apply for both borecore
and in-siturock classification.The joint roughness parameter is possibly the
most difficultparameter to assessaccurately from a borecore, and the joint
alteration parameter could prove problematical in cases of advanced joint
alteration.
The correlation between the borecore and in-situ rock classes was found
to be better for the Q System than for the Geomechanics System. A similar
result was obtained for the unsupported or limiting spans, and stand-up times,
calculated from the classification values.
Neither classification system showed a good correlation between the bore-
core and in-situ support predictions, although a slightly better result was
again obtained for the Q System. This result appears to be due, to some
extent, to the greater number of support categories, and more detailed
support recommendations for this system, together with the fact that some
allowance can be made for excavation dimensions.
ACKNOWLEDGEMENTS
REFERENCES
Barton, N., 1976a. Recent experiences with the Q System in tunnel support design.In:
Z.T. Bieniawski (Editor),Proceedings of the Symposium on Exploration for Rock
Engineering. Johannesburg, Vol.1, pp.107--115.
53
Barton, N., 1976b. Unsupported ground openings. In: Rock Mechanics Meeting, Swedish
Rock Mechanics Research Foundation, Stockholm, pp.61--94.
Barton, N., 1976c. Session report on rock mass classifications. In: Z.T. Bieniawski
(Editor), Proceedings of the Symposium on Exploration for Rock Engineering.
Johannesburg, Vol.2, pp.167--172.
Barton, N., Lien, R. and Lunde, J., 1974. Engineering classification of rock masses for
the design of tunnel support. Rock Mech., 6: 189--236.
Bergrnan, M., 1974. Rock mass investigation in depth. Reliability of different methods
for drill hole investigations. In: Advances in Rock Mechanics, Proc. Congr., Int.
Soc. Rock Mech., 3~1, Denver, Colo., Vol.2, Pt.4, pp.15--20.
Bieniawski, Z.T., 1976a. Rock mass classification in rock engineering. In: Z.T. Bieniawski
(Editor), Proceedings of the Symposium on Exploration for Rock Engineering.
Johannesburg, Vol.1, pp.97--106.
Bieniawski, Z.T., 1976b. Session report on rock mass classifications. In: Z.T. Bieniawski
(Editor), Proceedings of the Symposium on Exploration for Rock Engineering.
Johannesburg, Vol.2, pp.167--172.
Brink, A.B.A. and Associates, 1974. Geotechnical Report, Borehole Profiles and Geo-
logical Map of the Bushkoppics Outfall Sewer Tunnel, Phase 1, Vol.4, City of
Johannesburg, Contr. No.3450.
Cockcroft, T.N. and Loudon, P.A., 1976. The Du Toitskloof T u n n e l - A case history of
the geotechnical investigations. Proc. Sym. Expl. Rock Eng., pp.301--312.
Franklin, J.A., Broch, E. and Walter, G., 1970. Logging the Mechanical Character of Rock
Imperial CoIl. Rock Mech. Res. Rept., No.D14, London.
Houghton, D.A., 1975. The Assessment of Rock Masses and the Role of Rock Quality
Indices in Engineering Geology with Reference to Hard Rock. M.Sci. Thesis, Imperial
College, London.
Payne, T.G., 1976. Assessment of the Use of Rock Classification Systems in Practice.
M.Sci. Thesis, Imperial College, London.
Piteau, D.R., 1979. Geological Factors Significant to the Stability of Slopes Cut in Rock.
In: Planning Open Pit Mines. South A_rTicanInstitute of Mining and Metallurgy,
pp.33--54.
Priest, S.D. and Hudson, J.A., 1976. Discontinuity spacings in rock. Int. J. Rock Mech.
Mining Sei., 13: 135--148.
Rankilor, P.R., 1974. A suggested field system for logging cores for engineering purposes.
Bull. Assoc. Eng. Geol., XI (3): 247--258.
Rocha, M., 1971. A method of integral sampling of rock masses. Rock Mech., 3: 1--12.
South African Section of the Association of Engineering Geologists (Core Logging
Committee), 1976. A guide to core logging for rock engineering. In: Z.T. Bieniawski
(Editor), Proceedings of the Symposium on Exploration for Rock Engineering.
Johannesburg, Vol.1, pp.71--86.
Terzaghi, R.D., 1965. Sources of errors in joint surveys. Geotechnique, 15: 287--304.
Van Niekerk, Kleyn and Edwards and P.A. de Villiers in association with Electro-Watt
Engineering Services Limited, Ziirich, 1978. Du Toitskloof Tunnel Pilot Bore;
Unpublished Test Results and Geological Data.