CONTENTS
INTRODUCTION ....................................................................................................................................... 3
1. FIVE-YEAR PROJECTS PORTFOLIO PLANNING .................................................................................. 4
2. INITIAL PLANNING STAGE ................................................................................................................ 8
3. TENDER FOR DESIGN STAGE .......................................................................................................... 17
4. DESIGN STAGE ............................................................................................................................... 20
5. TENDER FOR CONSTRUCTION STAGE ............................................................................................ 30
6. CONSTRUCTION STAGE ................................................................................................................. 34
7. TESTING & COMMISSIONING STAGE............................................................................................. 47
8. HANDING OVER AND CLOSEOUT STAGE ....................................................................................... 50
9. APPENDIX 1: SUMMARY OF PMM SECTIONS ................................................................................ 53
2 of 52
PROJECT MANAGER HANDBOOK
INTRODUCTION
The Project Management Manual (PMM) is the detailed guide for managing NWC Capital Projects from
the inception and strategic planning up to handing over to operation & maintenance and closing out.
The PMM is structured according to project functions (knowledge areas). It contains 19 sections for
different project functions (knowledge areas). A summary of each Section’s processes and attachments
is provided in Appendix 1.
This handbook is developed to summarize and present the key processes, not all, of PMM in a simple,
easy and quick way. It is based on the project life cycle. Each stage of the life cycle is summarized and
connected to its processes, procedures, forms, templates and attachments with clear reference to the
main PMM and logical sequence.
The Main Stages of the Project Life Cycle as per the PMM are:
• Five years Projects Portfolio Planning
• Initial Planning Stage
• Tender for Design Stage
• Design Stage
• Tender for Construction Stage
• Construction Stage
• Testing and Commissioning stage
• Handing over and Closeout Stage
Each stage shall conclude with a Stage-Gate Process detailed in (Governance Section Page) which shall
allow the project to proceed to the next stage within the project life cycle.
3 of 52
PROJECT MANAGER HANDBOOK
These steps are detailed in PMM within the Five-Year Projects Portfolio Planning, Risk, Procurement,
Governance, Schedule, Cost as described below.
4 of 52
PROJECT MANAGER HANDBOOK
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Five-Year
Approve Cluster Local
PMM-004-FYP-020-090 Projects Portfolio 114 NA
Master Plan at Cluster
Planning
Five-Year
Approve Cluster Local
PMM-004-FYP-020-100 Projects Portfolio 115 NA
Master Plan at HQ
Planning
1.3. Establish Initial Project Scope, identify and analyze potential site location options
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Establish Initial Project
Five-Year
Scope and Identify
PMM-004-FYP-010-040 Projects Portfolio 106 PMF-004-FYP-003
Potential Site Location
Planning
Options
Five-Year
Undertake Pre-Concept
PMM-004-FYP-020-010 Projects Portfolio 108 NA
Site Options Testing
Planning
1.4. Prepare Initial Cost Estimate (Class 5) and initial project schedule (level 1)
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Five-Year
Prepare Initial Cost
PMM-004-FYP-020-020 Projects Portfolio 109 PMF-011-COS-005
Estimate (Class 5)
Planning
Five-Year
Prepare Initial Project
PMM-004-FYP-020-040 Projects Portfolio 111 NA
Schedule Level 1
Planning
1.5. Develop Cluster Initial Projects Portfolio
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Five-Year
Develop Cluster Initial PMF-004-FYP-005
PMM-004-FYP-020-130 Projects Portfolio 117
Projects Portfolio PMF-004-FYP-010
Planning
1.6. Perform project strategic and risk assessments
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Five-Year
Perform Project PMF-004-FYP-007
PMM-004-FYP-030-010 Projects Portfolio 124
Strategic Assessment PMF-004-FYP-008
Planning
Five-Year
Perform Project Risk
PMM-004-FYP-030-020 Projects Portfolio 125 PMF-007-FYP-021
Potential Assessment
Planning
5 of 52
PROJECT MANAGER HANDBOOK
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Approve Project
Five-Year
Strategic Assessment
PMM-004-FYP-030-025 Projects Portfolio 125 NA
and Project Risk
Planning
Potential Assessment
1.7. Assess project Cross-Sectoral Integration
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Five-Year
Assess Project Cross- PMF-004-FYP-013
PMM-004-FYP-030-030 Projects Portfolio 126
Sectoral Integration PMF-004-FYP-016
Planning
Approve Project Cross- Five-Year
Sectoral Integration PMM-004-FYP-030-035 Projects Portfolio 127 NA
Assessment Planning
1.8. Develop project Business Case
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Five-Year PMF-004-FYP-001
Develop Project
PMM-004-FYP-030-040 Projects Portfolio 128 PMF-004-FYP-004
Business Case
Planning PMF-004-FYP-018
Five-Year PMF-004-FYP-001
Approve Project
PMM-004-FYP-030-050 Projects Portfolio 129 PMF-004-FYP-004
Business Case at Cluster
Planning PMF-004-FYP-018
Five-Year PMF-004-FYP-001
Approve Project
PMM-004-FYP-030-055 Projects Portfolio 129 PMF-004-FYP-004
Business Case at HQ
Planning PMF-004-FYP-018
1.9. Prioritize projects
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Confirm Projects Five-Year
Suitable for Private PMM-004-FYP-030-060 Projects Portfolio 130 NA
Sector Participation Planning
Five-Year
Prepare Project PMF-004-FYP-010
PMM-004-FYP-030-070 Projects Portfolio 131
Prioritization PMF-004-FYP-019
Planning
1.10. Develop Draft FYPPP and Submit for Review
Page
Process Name Process No. Section Form/Guideline No.
No.
Five-Year
Develop Draft FYPPP
PMM-004-FYP-040 Projects Portfolio 131 PMF-004-FYP-005
and Submit for Review
Planning
6 of 52
PROJECT MANAGER HANDBOOK
7 of 52
PROJECT MANAGER HANDBOOK
8 of 52
PROJECT MANAGER HANDBOOK
9 of 52
PROJECT MANAGER HANDBOOK
10 of 52
PROJECT MANAGER HANDBOOK
11 of 52
PROJECT MANAGER HANDBOOK
12 of 52
PROJECT MANAGER HANDBOOK
13 of 52
PROJECT MANAGER HANDBOOK
14 of 52
PROJECT MANAGER HANDBOOK
Page
Process Name Process No. Section Form/Guideline No.
No.
Capture Lessons
PMF-007-INT-020
Learned for Future Risk PMM-015-RIS-080-040 Risk 607
PMF-007-INT-021
Management
2.11. Develop and approve the 30% Design Package
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Pre-design T&C
PMM-008-SCO-055-010 Scope 300 PMF-008-SCO-041
Activities
Analyze Business Case
PMF-007-INT-001
and Update Project PMM-008-SCO-030-010 Scope 280
PMF-008-SCO-037
Requirements
Identify Possible Project
Design Options and
PMM-008-SCO-030-020 Scope 281 PMF-008-SCO-037
Create the Design Basis
Report
Develop the 30% Design PMF-008-SCO-038
Package for EPC PMM-008-SCO-030-023 Scope 282 PMF-008-SCO-039
Projects PMF-008-SCO-040
Approve the 30% PMF-008-SCO-038
Design Package for EPC PMM-008-SCO-030-026 Scope 283 PMF-008-SCO-039
Projects PMF-008-SCO-040
Update the Scope
Management Plan PMF-008-SCO-037
PMM-008-SCO-030-030 Scope 283
Section of Project PMF-007-INT-001
Management Plan
2.12. Perform Environmental Impact Assessment when required
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Perform Environmental
PMM-017-HSE-015-010 HSE 686 PMF-017-HSE-231
Impact Assessment
Obtain NCEC Approval
on Environmental PMM-017-HSE-015-020 HSE 687 NA
Impact Assessment
2.13. Develop Class 3 Cost Estimate for EPC Projects
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Update Class 4 Cost
PMF-011-COS-001
Estimate for Design-Bid- PMM-011-COS-030-010 Cost 425
PMF-011-COS-002
Build Projects
15 of 52
PROJECT MANAGER HANDBOOK
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Develop Class 3 Cost
PMF-011-COS-001
Estimate for EPC PMM-011-COS-030-020 Cost 426
PMF-011-COS-002
Projects
Update the “Primavera
PMM-011-COS-030-030 Cost 427 NA
P6” Database
2.14. Conduct Value Engineering Study (for EPC Projects)
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
PMF-009-VEN-001
PMF-009-VEN-003
PMF-009-VEN-004
PMF-009-VEN-005
Conduct Value Value
PMM-009-VEN-020 369 PMF-009-VEN-012
Engineering Study Engineering
PMF-009-VEN-013
PMF-009-VEN-016
PMF-009-VEN-017
PMF-009-VEN-018
2.15. Define procurement activities and schedule
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Define the Procurement
PMM-010-SCH-020-010 Schedule 392 NA
Activities
Develop the
PMM-010-SCH-020-020 Schedule 393 NA
Procurement Schedule
16 of 52
PROJECT MANAGER HANDBOOK
These steps are detailed in PMM within the Risk, Schedule, Cost, Quality, Communication, HSE and
Procurement Sections as described below.
17 of 52
PROJECT MANAGER HANDBOOK
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Ensure Quality
Requirements and
PMM-012-QUA-010-
Technical Evaluation are Quality 465 NA
030
Included in the Design
Tender Documents
Ensure Communication
Requirements and
PMM-014-COM-010-
Technical Evaluation are Communication 418 NA
030
Included in the Design
Tender Documents
Ensure HSE
Requirements and
Technical Evaluation are PMM-017-HSE-010-040 HSE 684 NA
Included in the Design
Tender Documents
Ensure Integration
Requirements and
Technical Evaluation are PMM-007-INT-015-030 Integration 220 NA
Included in the Design
Tender Documents
Ensure Scope
Requirements and
Technical Evaluation are PMM-008-SCO-010-030 Scope 275 PMF-007-INT-001
Included in the Design
Tender Documents
Ensure Human
Resource Requirements
and Technical PMM-013-HUM-010-
Human Resource 496 PMF-007-INT-001
Evaluation are Included 030
in the Design Tender
Documents
Ensure Risk
Requirements and
Technical Evaluation are PMM-015-RIS-020-030 Risk 585 PMF-007-INT-001
Included in the Design
Tender Documents
Ensure Procurement
Requirements and
PMM-016-PRO-020-
Technical Evaluation are Procurement 624 PMF-007-INT-001
030
Included in the Design
Tender Documents
18 of 52
PROJECT MANAGER HANDBOOK
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Ensure Financial
Requirements and
Financial
Technical Evaluation are PMM-018-FIN-005-030 718 PMF-007-INT-001
Requirements
Included in the Design
Tender Documents
Ensure Claim
Requirements and
Technical Evaluation are PMM-019-CLA-005-030 Claim 734 PMF-007-INT-001
Included in the Design
Tender Documents
3.3. Update Level 1 Design Schedule and Include it in Tender for Design Documents and
Evaluation
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Update Level 1 Design
Schedule and Include it
in Tender for Design PMM-010-SCH-030-010 Schedule 398 NA
Documents and
Evaluation
3.4. Prepare and approve RFP and PR for Design Tender
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Prepare Tender PMF-016-PRO-008
PMM-016-PRO-030 Procurement 627
Documents PMF-016-PRO-039
3.5. Select and approve a bidder
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Select a bidder PMM-016-PRO-040 Procurement 634 PMF-016-PRO-012
19 of 52
PROJECT MANAGER HANDBOOK
4. DESIGN STAGE
The Design Stage starts after fulfilling all the requirements for the Tender for Design Stage and after
the Design Consultant contract award. During this stage, the detailed design for the project is prepared,
reviewed and approved including a Value Engineering study if applicable to the project.
The Design Stage includes the following steps:
1- Develop Design Management Plan
2- Develop and Approve the Design Management Plan
3- Develop and approve level 3 design schedule
4- Identify risks at Project Level
5- Qualitative and Quantitative Analysis at Project Level
6- Plan risk responses at Project Level
7- Implement and monitor risk responses at project level.
8- Develop and approve the 30% Design Package for Design-Bid-Build Projects
9- Develop Class 3 cost estimate at 30 % design Package
10- Perform Value Engineering Study
11- Develop the and approve the Design Submittals in Design & Build Projects
12- Develop and approve the 90% Design Package
13- Develop Class 2 Cost Estimate within 90% Design Package
14- Develop and approve the 100% Design Package
15- Design Performance Directing, monitoring, controlling and reporting.
16- Issue, receive, distribute correspondences, submittals, queries and NCRs
17- Carry out internal design reviews by design consultant
18- Review the Design packages
19- Review, Approve Design Consultant Invoice
20- Implementation of Value Engineering recommendations
21- Control Design Variations and Claims
22- Define and implement Corrective and Preventive Actions for Design Quality & HSE
observations and Non-Conformities.
23- Review and ensure Design Completion
These steps are detailed in PMM within the Integration, Cost, Quality, Communication, HSE, Schedule,
Risk, Procurement, Claim, Scope and Value Engineering Sections as described below.
20 of 52
PROJECT MANAGER HANDBOOK
21 of 52
PROJECT MANAGER HANDBOOK
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Develop Project Claim
Management Plan
Section in the Project PMM-019-CLA-005-040 Claim 734 PMF-007-INT-002
Design Management
Plan
4.2. Develop and approve the Design Management Plan
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Develop Design
PMM-007-INT-020-050 Integration 226 PMF-007-INT-002
Management Plan
Approve the Design PMF-007-INT-003
PMM-007-INT-020-060 Integration 226
Management Plan PMF-014-COM-004
4.3. Develop and approve level 3 Design schedule
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Develop and Submit
PMM-010-SCH-030-020 Schedule 399 NA
Level 3 Design Schedule
Approve Level 3 Design
PMM-010-SCH-030-030 Schedule 399 PMF-010-SCH-013
Schedule at Cluster
Approve Level 3 Design
PMM-010-SCH-030-033 Schedule 400 PMF-010-SCH-013
Schedule at HQ
Upload Level 3 Design
Schedule to ENJAZ PMM-010-SCH-030-036 Schedule 400 NA
System
4.4. Identify risks at Project Level
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Identify and Analyze
Objective, Issues,
PMM-015-RIS-030-010 Risk 589 NA
Constraints &
Assumptions
PMF-015-RIS-005
PMF-015-RIS-007
Stakeholder Mapping
PMM-015-RIS-030-020 Risk 590 PMF-015-RIS-008
and Positioning
PMF-015-RIS-016
PMF-015-RIS-019
PMF-015-RIS-001
PMF-015-RIS-004
Conduct Risk Workshop PMM-015-RIS-030-030 Risk 590
PMF-015-RIS-011
PMF-015-RIS-017
22 of 52
PROJECT MANAGER HANDBOOK
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Identify Risks PMM-015-RIS-030-050 Risk 593 NA
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Approve Class 3 Cost PMF-011-COS-001
PMM-011-COS-040-025 Cost 433
Estimate PMF-011-COS-002
4.10. Perform Value Engineering Study
Page
Process Name Process No. Section Form/Guideline No.
No.
PMF-009-VEN-005
Plan and Prepare for PMF-009-VEN-007
Value
Value Engineering PMM-009-VEN-010 365 PMF-009-VEN-008
Engineering
Study PMF-009-VEN-014
PMF-009-VEN-015
PMF-009-VEN-001
PMF-009-VEN-003
PMF-009-VEN-004
Conduct Value Value PMF-009-VEN-005
PMM-009-VEN-020 370
Engineering Study Engineering PMF-009-VEN-012
PMF-009-VEN-016
PMF-009-VEN-017
PMF-009-VEN-018
4.11. Develop and approve the Design Submittals in Design & Build Projects
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
PMF-008-SCO-037
Develop the Design
PMF-008-SCO-038
Submittals in Design & PMM-008-SCO-030-043 Scope 286
PMF-008-SCO-039
Build Projects
PMF-008-SCO-040
PMF-008-SCO-037
Approve the Design
PMF-008-SCO-038
Submittals in Design & PMM-008-SCO-030-046 Scope 287
PMF-008-SCO-039
Build Projects
PMF-008-SCO-040
4.12. Develop and approve the 90% Design Package
Process/Procedure Page
Process/Procedure No. Section Form/Guideline No.
Name No.
PMF-008-SCO-037
Develop the 90% PMF-008-SCO-038
PMM-008-SCO-030-048 Scope 288
Design Package PMF-008-SCO-039
PMF-008-SCO-040
PMF-008-SCO-037
Approve the 90% PMF-008-SCO-038
PMM-008-SCO-030-050 Scope 289
Design Package PMF-008-SCO-039
PMF-008-SCO-040
24 of 52
PROJECT MANAGER HANDBOOK
25 of 52
PROJECT MANAGER HANDBOOK
Process/Procedure Page
Process/Procedure No. Section Form/Guideline No.
Name No.
PMF-014-COM-017
PMF-014-COM-018
Perform Design PMF-014-COM-021
PMM-014-COM-120 Communication 558
Performance Reporting PMF-014-COM-022
PMF-014-COM-023
PMF-014-COM-024
Consultant /
PMF-010-SCH-003
Contractor
PMM-016-PRO-070-010 Procurement 643 PMF-014-COM-017
Performance Review
PMF-014-COM-018
and Reporting
Address HSE-Related
Issues in Technical
Reviews and Regular PMM-017-HSE-030-020 HSE 700 NA
Design Progress
Meetings
T&C Activities at
PMM-008-SCO-055-020 Scope 301 PMF-008-SCO-041
Design Stage
Update the Project
Scope Statement in the
PMM-008-SCO-030-080 Scope 292 NA
Project Management
Plan
4.16. Issue, receive, distribute correspondences, submittals, queries and NCRs
Process/Procedure Page
Process/Procedure No. Section Form/Guideline No.
Name No.
Distribute Confidential
Correspondence from
PMM-014-COM-020 Communication 520 PMF-014-COM-046
Consultant/Contractor
to NWC
Distribute Confidential
Correspondence from
PMM-014-COM-030 Communication 524 PMF-014-COM-046
NWC to
Consultant/Contractor
Distribute Non-
Confidential
PMM-014-COM-040 Communication 527 PMF-014-COM-046
Correspondence from
Consultant to NWC
Distribute Non-
Confidential
PMM-014-COM-060 Communication 533 PMF-014-COM-046
Correspondence from
NWC to Consultant
26 of 52
PROJECT MANAGER HANDBOOK
Process/Procedure Page
Process/Procedure No. Section Form/Guideline No.
Name No.
PMF-014-COM-005
PMF-014-COM-006
Distribute Submittals
PMM-014-COM-090 Communication 542 PMF-014-COM-011
for Approval
PMF-014-COM-012
PMF-014-COM-046
Distribute Non- PMF-014-COM-013
Conformance Report PMM-014-COM-100 Communication 546 PMF-014-COM-042
(NCR) PMF-014-COM-046
Distribute Request for PMF-014-COM-014
PMM-014-COM-110 Communication 552
Information (RFI) PMF-014-COM-046
4.17. Carry out internal design reviews by design consultant
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Carry Out the Quality-
Related Internal Design PMM-012-QUA-020-010 Quality 469 NA
Reviews
Review the Quality-
Related Internal Design PMM-012-QUA-020-020 Quality 470 NA
Review Report
4.18. Review the Design Packages
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Review the Compliance
of Design Packages to
PMM-012-QUA-030-010 Quality 477 PMF-012-QUA-006
Design Quality
Requirements
Carry Out and Submit
the Scheduled HSE- PMM-017-HSE-020-010 HSE 689 NA
Related Design Study
Approve the HSE-
Related Design Study PMM-017-HSE-020-020 HSE 690 NA
Documentation
Review the HSE
Aspects in Submitted
PMM-017-HSE-030-010 HSE 700 PMF-008-SCO-002
Design Review
Packages
Review
PMM-019-CLA-020-010 Claim 740 PMF-019-CLA-002
Constructability
27 of 52
PROJECT MANAGER HANDBOOK
28 of 52
PROJECT MANAGER HANDBOOK
4.21.2. Claim
Process/ Procedure Page
Process/Procedure No. Section Form/Guideline No.
Name No.
Identify Potential
Claims by
PMM-019-CLA-010 Claim 736 NA
Reviewing Contract
Documentation
Assess and Quantify
PMM-019-CLA-030 Claim 741 PMF-007-INT-010
Claim
4.22. Define and implement Corrective and Preventive Actions for Design Quality & HSE
observations and Non-Conformities.
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Carry Out Root Cause
Analysis for Design PMM-012-QUA-030-030 Quality 479 PMF-012-QUA-006
Quality Observations
Define Design
PMF-012-QUA-006
Corrective and PMM-012-QUA-030-040 Quality 379
PMF-014-COM-013
Preventive Actions
Carry Out Root Cause
Analysis for Design
PMM-017-HSE-030-030 HSE 701 PMF-017-HSE-012
Related HSE
Observations
Define Design Related
PMF-017-HSE-012
Corrective and PMM-017-HSE-030-040 HSE 701
PMF-014-COM-013
Preventive Actions
4.23. Review and ensure Design Completion
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Review
Implementation of the
Value Engineering
Value
Study PMM-009-VEN-040-010 375 NA
Engineering
Recommendations
through the next
Design Review
Ensure Relevant
External Stakeholders PMF-008-SCO-037
PMM-008-SCO-030-060 Scope 290
Approvals on the PMF-015-RIS-018
Project Scope
29 of 52
PROJECT MANAGER HANDBOOK
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Transfer Risks to
Design Consultant /
PMM-015-RIS-030-060 Risk 595 PMF-015-RIS-001
Contractor Through
the Tender Documents
5.2. Ensure schedule, cost, quality, HSE and communication requirements are included in tender
documentation and technical evaluation.
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Include Scheduling
Requirements and
Technical Evaluation in
PMM-010-SCH-020-030 Schedule 394 NA
the
Design/Construction
Tender Documents
30 of 52
PROJECT MANAGER HANDBOOK
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Ensure Quality
Requirements and
Technical Evaluation
PMM-012-QUA-010-060 Quality 466 NA
are Included in the
Construction Tender
Documents
Ensure Communication
Requirements and
Technical Evaluation
PMM-014-COM-010-050 Communication 519 NA
are Included in the
Construction Tender
Documents
Ensure HSE
Requirements and
Technical Evaluation
PMM-017-HSE-010-050 HSE 684 NA
are Included in the
Construction Tender
Documents
Ensure Integration
Requirements and
Technical Evaluation
PMM-007-INT-015-050 Integration 221 NA
are Included in the
Construction Tender
Documents
Ensure Scope
Requirements and
Technical Evaluation
PMM-008-SCO-010-050 Scope 276 NA
are Included in the
Construction Tender
Documents
Ensure Cost
Requirements and
Technical Evaluation
PMM-011-COS-020-050 Cost 423 NA
are Included in the
Construction Tender
Documents
Ensure Human
Resource
Requirements and
PMM-013-HUM-010-
Technical Evaluation Human Resource 497 NA
050
are Included in the
Construction Tender
Documents
31 of 52
PROJECT MANAGER HANDBOOK
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Ensure Risk
Requirements and
Technical Evaluation
PMM-015-RIS-020-050 Risk 586 NA
are Included in the
Construction Tender
Documents
Ensure Procurement
Requirements and
Technical Evaluation
PMM-016-PRO-020-050 Procurement 625 NA
are Included in the
Construction Tender
Documents
Ensure Financial
Requirements and
Technical Evaluation
PMM-018-FIN-005-050 Financial 719 NA
are Included in the
Construction Tender
Documents
Ensure Claim
Requirements and
Technical Evaluation
PMM-019-CLA-005-050 Claim 735 NA
are Included in the
Construction Tender
Documents
T&C Activities During
Tender for PMM-008-SCO-055-030 Scope 302 PMF-008-SCO-041
Construction Stage
5.3. Update Project Construction level 1 schedule and include it in tender documents and
Evaluation
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Update level 1
Construction Schedule
and Include it in
Tender for PMM-010-SCH-040-010 Schedule 404 NA
Construction
Documents and
Evaluation
32 of 52
PROJECT MANAGER HANDBOOK
5.4. Prepare and approve Pre-tender cost estimate, RFP and PR for Construction Tender
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Collect Tender Cost
Estimate (Class 2 /
PMF-011-COS-001
Class 3) from Design PMM-011-COS-050-010 Cost 438
PMF-011-COS-002
Package and Include in
RFP
Prepare Tender
PMM-016-PRO-030 Procurement 627 NA
Documents
5.5. Select and approve a bidder
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Select a bidder PMM-016-PRO-040 Procurement 634 NA
33 of 52
PROJECT MANAGER HANDBOOK
6. CONSTRUCTION STAGE
The Construction Stage starts after fulfilling all the requirements for the Tender for Construction Stage
and after contract award for the Construction Contractor. This Stage starts with the project site
handover and concludes with the initial acceptance and handover of the project deliverables to the
operation and maintenance department. During this stage, the deliverables of the project are being
constructed, inspected, verified and approved.
The Construction Stage includes the following steps:
1- Handing over the project site to the contractor
2- Conduct Kick-off meeting
3- Develop and approving Construction level 3 schedule
4- Develop and approve Project Construction Management Plan and early submissions
5- Develop and submit of first revised BOQ based on contractor review and surveys
6- Identify risks at Project Level
7- Qualitative and Quantitative Analysis at Project Level
8- Plan risk responses at Project Level
9- Implement and monitor risk responses scheduled at Project Level
10- Prepare, submit, review, and approve method statements, ITPs, risk assessments, permit to
work, T&C Preparatory Works and Documentations
11- Construction Performance Directing, monitoring, controlling, and reporting.
12- Issue, receive, distribute correspondences, submittals, queries, and NCRs
13- Calculate actual value improvement results and update database
14- Review, approve and process interim payment applications
15- Control Construction Variations and Claims and Budget and Cashflow
16- Define and implement Corrective and Preventive Actions for Construction Quality & HSE
observations and Non-Conformities.
17- Project Suspension (Special Case)
18- Project withdrawal (Special Case)
These steps are detailed in PMM within the Integration, Cost, Quality, Communication, HSE, Schedule,
Risk, Procurement, HR, Claim, Scope and Value Engineering Sections as described below.
34 of 52
PROJECT MANAGER HANDBOOK
35 of 52
PROJECT MANAGER HANDBOOK
6.4. Develop and approve Project Construction Management Plan and early submissions
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Develop the
Construction Scope
PMM-008-SCO-010-060 Scope 277 NA
Management Plan
Section
Develop the
Construction Schedule
PMM-010-SCH-010-060 Schedule 389 NA
Management Plan
Section
Develop the
Construction Cost
PMM-011-COS-020-060 Cost 424 NA
Management Plan
Section
Develop the
Construction
Integration PMM-007-INT-015-060 Integration 221 NA
Management Plan
Section
Develop the
Construction Human
Resource PMM-013-HUM-010-060 HR 498 NA
Management Plan
Section
Develop the
Construction
Communication PMM-014-COM-010-060 Communication 519 NA
Management Plan
Section
Develop the
Construction Risk
PMM-015-RIS-020-060 Risk 587 NA
Management Plan
Section
Develop the
Construction
Procurement PMM-016-PRO-020-060 Procurement 625 NA
Management Plan
Section
Develop the
Construction Quality PMM-012-QUA-010-080 Quality 467 PMF-012-QUA-121
Management Plan
Develop the
Construction HSE
PMM-017-HSE-010-060 HSE 685 PMF-017-HSE-232
Management Plan
Section
36 of 52
PROJECT MANAGER HANDBOOK
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Develop the
Construction Financial
PMM-018-FIN-005-060 Financial 719 NA
Management Plan
Section
Develop the
Construction Claim
PMM-019-CLA-005-060 Claim 735 NA
Management Plan
Section
Submit Construction
Management Plan PMM-007-INT-020-080 Integration 228 PMF-007-INT-004
and Early Deliverables
Approve the
Construction PMM-007-INT-020-090 Integration 229 PMF-007-INT-004
Management Plan
6.5. Develop and submit of first revised BOQ based on contractor review and surveys
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Develop and Submit
PMM-011-COS-060-010 Cost 441 PMF-011-COS-026
Revised BOQ
Approve Revised BOQ
Submitted by PMM-011-COS-060-020 Cost 442 PMF-011-COS-029
Contractor at Cluster
Approve Revised BOQ
Submitted by PMM-011-COS-060-030 Cost 443 PMF-011-COS-029
Contractor at HQ
6.6. Identify Risks at Project Level
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Identify and Analyze
Objective, Issues,
PMM-015-RIS-030-010 Risk 589 NA
Constraints &
Assumptions
PMF-015-RIS-005
Stakeholder Mapping PMF-015-RIS-007
PMM-015-RIS-030-020 Risk 590
and Positioning PMF-015-RIS-016
PMF-015-RIS-019
PMF-015-RIS-001
Conduct Risk PMF-015-RIS-004
PMM-015-RIS-030-030 Risk 590
Workshop PMF-015-RIS-011
PMF-015-RIS-017
Identify Risks PMM-015-RIS-030-050 Risk 593 NA
37 of 52
PROJECT MANAGER HANDBOOK
38 of 52
PROJECT MANAGER HANDBOOK
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
PMF-012-QUA-007
PMF-012-QUA-071
Develop and
PMF-012-QUA-061
Submit the
PMM-012-QUA-020-050 Quality 472 PMF-012-QUA-051
Inspection and
PMF-012-QUA-081
Testing Plan (ITP)
PMF-012-QUA-021
PMF-012-QUA-031
Approve the
PMM-012-QUA-020-060 Quality 473 Same as above
Submitted ITP
6.10.2. HSE
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Carry out an HSE
PMF-017-HSE-006
Risk Assessment PMM-017-HSE-020-030 HSE 691
PMF-017-HSE-007
for PTW
Approve the
Submitted HSE PMM-017-HSE-020-040 HSE 691 PMF-017-HSE-006
Risk Assessment
Draft and Submit
a Permit-to-Work
for an PMM-017-HSE-020-050 HSE 692 PMF-017-HSE-005
Area/Section of
the Project
Approve the
Submitted PTW PMM-017-HSE-020-060 HSE 694 PMF-017-HSE-005
Request
6.10.3. T&C
Page
Process Name Process No. Section Form/Guideline No.
No.
T&C Preparatory
Works and
PMM-008-SCO-055-040 Scope 302 PMF-008-SCO-041
Preparation of T&C
Documentations
Supervision and
Approval of
Preparatory Works PMM-008-SCO-055-050 Scope 304 PMF-008-SCO-041
and
Documentations
39 of 52
PROJECT MANAGER HANDBOOK
40 of 52
PROJECT MANAGER HANDBOOK
6.11.4. HSE
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Supervise the
Implementation of
PMM-017-HSE-030-050 HSE 702 PMF-012-QUA-004
Documented HSE
Mitigation Actions
Carry out HSE PMF-017-HSE-011
Inspections and PMF-017-HSE-012
PMM-017-HSE-020-070 HSE 695
Audits Recommend PMF-014-COM-013
Penalties PMF-017-HSE-015
Address HSE-Related
Issues in Regular Site PMM-017-HSE-030-080 HSE 704 NA
Meetings
Request Closure of
PMM-017-HSE-020-080 HSE 696 PMF-017-HSE-005
the PTW
Agree Closure of the
PMM-017-HSE-020-090 HSE 697 PMF-017-HSE-005
PTW
6.11.5. Communication
Process/ Procedure Page
Process/Procedure No. Section Form/Guideline No.
Name No.
PMF-014-COM-018
PMF-011-COS-019
PMF-011-COS-020
PMF-014-COM-021
PMF-014-COM-022
Perform PMF-014-COM-023
Construction PMF-014-COM-024
PMM-014-COM-130 Communication 562
Performance PMF-014-COM-047
Reporting PMF-014-COM-049
PMF-014-COM-050
PMF-014-COM-051
PMF-014-COM-056
PMF-012-QUA-114
PMF-017-HSE-014
Design Consultant /
Contractor PMM-016-PRO-070- PMF-010-SCH-003
Procurement 643
Performance Review 010 PMF-014-COM-018
and Reporting
6.11.6. HR
Page
Process Name Process No. Section Form/Guideline No.
No.
Manage the Project
PMM-013-HUM-040 HR 507 NA
Team
41 of 52
PROJECT MANAGER HANDBOOK
6.11.7. T&C
Page
Process Name Process No. Section Form/Guideline No.
No.
Ensuring the Pass of
PMM-008-SCO-055-060 Scope 305 PMF-008-SCO-043
Construction Tests
6.12. Issue, receive, distribute correspondences, submittals, queries, and NCRs
6.12.1. Communication
Process/ Procedure Page
Process/Procedure No. Section Form/Guideline No.
Name No.
Distribute
Confidential
Correspondence
PMM-014-COM-020 Communication 520 PMF-014-COM-046
from
Consultant/Contract
or to NWC
Distribute
Confidential
Correspondence
PMM-014-COM-030 Communication 524 PMF-014-COM-046
from NWC to
Consultant/Contract
or
Distribute Non-
Confidential
Correspondence PMM-014-COM-050 Communication 530 PMF-014-COM-046
from Contractor to
NWC
Distribute Non-
Confidential
Correspondence PMM-014-COM-070 Communication 536 PMF-014-COM-046
from NWC to
Contractor
Distribute Non-
Confidential
Correspondence
PMM-014-COM-080 Communication 539 PMF-014-COM-046
from Supervising
Consultant to
Contractor
PMF-014-COM-005
PMF-014-COM-006
PMF-014-COM-009
Distribute Submittals
PMM-014-COM-090 Communication 542 PMF-014-COM-010
for Approval
PMF-014-COM-043
PMF-014-COM-044
PMF-014-COM-046
42 of 52
PROJECT MANAGER HANDBOOK
43 of 52
PROJECT MANAGER HANDBOOK
44 of 52
PROJECT MANAGER HANDBOOK
6.16. Define and implement Corrective and Preventive Actions for Construction Quality & HSE
observations and Non-Conformities.
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Carry Out Root Cause
Analysis for
PMM-012-QUA-030-
Construction Quality Quality 483 NA
070
Observations and Non-
Conformities
Define Construction
PMM-012-QUA-030- PMF-012-QUA-006
Corrective and Quality 484
090 PMF-014-COM-013
Preventive Actions
Carry Out Root Cause
Analysis for
PMM-017-HSE-030-070 HSE 704 PMF-017-HSE-012
Construction Related
HSE Observations
Investigate Reported PMF-017-HSE-009
PMM-017-HSE-030-090 HSE 705
Incidents and Accidents PMF-017-HSE-010
Define Construction
PMF-017-HSE-012
HSE-Related Corrective PMM-017-HSE-030-100 HSE 705
PMF-014-COM-013
and Preventive Actions
6.17. Project Suspension (Special Case)
Page
Process Name Process No. Section Form/Guideline No.
No.
PMF-016-PRO-007
PMF-016-PRO-009
PMF-016-PRO-022
PMF-016-PRO-026
Suspend and Resume
PMM-016-PRO-080 Procurement 646 PMF-016-PRO-034
Project
PMF-016-PRO-042
PMF-016-PRO-044
PMF-016-PRO-045
PMF-016-PRO-046
45 of 52
PROJECT MANAGER HANDBOOK
46 of 52
PROJECT MANAGER HANDBOOK
47 of 52
PROJECT MANAGER HANDBOOK
48 of 52
PROJECT MANAGER HANDBOOK
Page
Process Name Process No. Section Form/Guideline No.
No.
Form T&C Working
PMM-008-SCO-055-100 Scope 307 NA
Group
Pre-commissioning
Activities at Testing & PMM-008-SCO-055-110 Scope 308 PMF-008-SCO-041
Commissioning Stage
Perform Commissioning
PMM-008-SCO-055-120 Scope 309 PMF-008-SCO-041
Activities
7.7. Prepare T&C Working Group Report and T&C Report
Page
Process Name Process No. Section Form/Guideline No.
No.
Issue T&C Working
Group Report and T&C PMM-008-SCO-055-130 Scope 310 PMF-008-SCO-044
Report
49 of 52
PROJECT MANAGER HANDBOOK
51 of 52
PROJECT MANAGER HANDBOOK
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Review the Report and
PMF-007-INT-020
Publish the Applicable PMM-007-INT-040-040 Integration 246
PMF-007-INT-021
Lessons Learned
Capture Lessons
PMF-007-INT-020
Learned for Future Risk PMM-015-RIS-080-040 Risk 607
PMF-007-INT-021
Management
8.7. Review, approve and Process Final Payment
Page
Procedure Name Procedure No. Section Form/Guideline No.
No.
Approve Contractor PMF-011-COS-021
PMM-011-COS-070-020 Cost 448
Invoices PMF-011-COS-024
PMF-016-PRO-004
Audit the Contract PMM-016-PRO-100-
Procurement 670 PMF-011-COS-021
Closeout 010
PMF-016-PRO-032
8.8. Close the project team
Page
Process Name Process No. Section Form/Guideline No.
No.
Close the Project Team PMM-013-HUM-050 HR 507 NA
52 of 52
APPENDIX 1
SUMMARY OF PMM SECTIONS
SUMMARY OF PMM SECTIONS
CONTENTS
1. INTRODUCTION (Section 1 in PMM)........................................................................................... 3
2. GLOSSARY (Section 2 in PMM) ................................................................................................... 3
3. PROJECT LIFECYCLE AND STAGE GATE PROCESS (Section 3 in PMM) ........................................ 3
4. FIVE - YEAR PROJECTS PORTFOLIO PLANNING (Section 4 in PMM) ........................................... 4
5. PROJECT TEAM MANAGEMENT (Section 5 in PMM).................................................................. 5
6. PROJECT GOVERNANCE MANAGEMENT (Section 6 in PMM) .................................................... 5
7. PROJECT INTEGRATION MANAGEMENT (Section 7 in PMM) .................................................... 7
8. PROJECT SCOPE MANAGEMENT (Section 8 in PMM)................................................................. 8
9. PROJECT VALUE ENGINEERING MANAGEMENT (Section 9 in PMM) ....................................... 10
10. PROJECT SCHEDULE MANAGEMENT (Section 10 in PMM) ...................................................... 11
11. PROJECT COST MANAGEMENT (Section 11 in PMM) ............................................................... 12
12. PROJECT QUALITY MANAGEMENT (Section 12 in PMM) ......................................................... 13
13. PROJECT HUMAN RESOURCE MANAGEMENT (Section 13 in PMM) ....................................... 14
14. PROJECT COMMUNICATION MANAGEMENT (Section 14 in PMM) ......................................... 15
15. PROJECT RISK MANAGEMENT (Section 15 in PMM) ................................................................ 16
16. PROJECT PROCUREMENT MANAGEMENT (Section 16 in PMM).............................................. 17
17. PROJECT HEALTH, SAFETY AND ENVIRONMENTAL MANAGEMENT (Section 17 in PMM) ...... 19
18. PROJECT FINANCIAL MANAGEMENT (Section 18 in PMM) ...................................................... 20
19. PROJECT CLAIM MANAGEMENT (Section 19 in PMM) ............................................................. 20
2 of 20
SUMMARY OF PMM SECTIONS
3 of 20
SUMMARY OF PMM SECTIONS
• Five-Year Projects Portfolio Planning section attachments include but are not limited to:
o Templates & Forms for:
▪ Business Case, Strategic Assessment Template, Risk Potential Assessment Template, Project
Prioritization Template, Inter-Dependency Matrix Template, Business Case Approval Form,
Initial Project Scope Outline Form, FYPP Variation Request Approval Form (Clusters).
o Check Lists for:
▪ Draft Five-Year Projects Portfolio Plan Checklist, Final Five-Year Projects Portfolio Plan Checklist,
Cross-Sector Integration Checklist, Business Case Checklist, Strategic Assessment Checklist.
4 of 20
SUMMARY OF PMM SECTIONS
5 of 20
SUMMARY OF PMM SECTIONS
• The eighth process (Management Review): Describes the process of compiling a briefing paper and
agenda and sending an invitation for a management review meeting, attending the management review
meeting and implementing the agreed action plan.
• The ninth process (Human Resources Centralization): Describes the process of maintaining a centralized
register of project team members’ history and inductions and training, reviewing performance appraisal
records for continual improvement opportunities.
• The tenth process (Infrastructure): Describes the process of keeping local infrastructure requirements
under review, ensuring suppliers are qualified to the approved supplier’s list.
• The eleventh process (Work Environment): Describes the process of keeping the local work environment
under review.
• The twelfth process (PMM User Feedback): Describes the process of running online semi-annual PMM
surveys, submitting PMM users’ feedback, registering and analyzing the PMM user’s feedback.
• The thirteenth process (PMM Internal Audit): Describes the process of developing cluster internal audit
schedule, preparing and carrying out the internal audit, agreeing on the audit findings and
recommendations and issuing the final report.
• The fourteenth process (Monitoring Application of PMM Processes): Describes the process of applying
appropriate resources to gather PMM process data, developing the KPI report at the cluster level,
consolidating all cluster reports into a single report, escalating issues and publishing the final KPI report.
• The fifteenth process (Stage Gate Review): Describes the process of notifying the cluster projects GM by
project stage completions before two months, compiling objective evidence of stage completion,
compiling an agenda and sending a meeting notification for the stage-gate review meeting, conducting
the meeting and compile minutes for the stage-gate review meeting, acknowledge the minutes and
initiate actions by the due date, formally approve the project stage completion.
• The sixteenth process (Project Management Data Analysis): Describes the process of reviewing the
project management registers and KPI reports, reviewing external factors for opportunities and threats.
• The Project Governance Management Section attachments include but are not limited to:
o Templates & Forms for:
▪ KPI Report, PMM Management Review Meeting Agenda, PMM Management Review
Meeting Minutes, PMM Internal Audit Schedule, PMM Audit Report, Archival Instruction,
Local Work Instruction, PMM Improvement Request, PMM User Feedback Record, Record of
Delegation of Authority.
o Check Lists for:
▪ PMM Review Checklist, Stage-Gate Review Checklist, PMM Audit Checklist.
o Guidelines for:
▪ Document Filing Index
o Registers for:
▪ External Requirements Tracking Register, Archival Instruction Register, Local Work
Instruction Register, PMM NCRs Register, Stage-Gate Review Register, PMM Improvement
Register, PMM Corrective and Preventive Action Register, PMM Auditors Register, PMM User
Feedback Register.
6 of 20
SUMMARY OF PMM SECTIONS
7 of 20
SUMMARY OF PMM SECTIONS
on the variation request, forward approved variation to negotiation & award (N&A) / department bid
examination committee (BEC), negotiating and agree on the variation settlement, issuing variation order
to the second party, updating the project documents and plans.
• The tenth process (Close the Project): Describes the process of ensuring completeness and properness
of initial and final acceptance and handover, confirming the status of contracts, developing project
closeout report, closing the project and informing key stakeholders.
• The Project Integration Management Section attachments include but are not limited to:
o Templates & Forms for:
▪ Project Charter, Project Management Plan, Construction Management Plan, Design
Management Plan, Lessons Learned Report, Project Closeout Report, Variation Notice
Template, Variation Report, Variation Request Approval Form, Land Acquisition Strategy
Form, Lessons Learned From.
o Check Lists for:
▪ Design Management Plan Review Checklist, Construction Management Plan Review
Checklist, Initial Handover Check List, Final Handover Check List, Project Closure Checklist,
Variation Notice Checklist.
o Guidelines for:
▪ Land Acquisition Strategy Guidelines, Variation Request Preparation Guideline.
o Registers for:
▪ Project Variation Register, Lessons Learned Register.
8 of 20
SUMMARY OF PMM SECTIONS
• The fourth process (Control Scope): Describes the process of drafting a scope change, performing
engineering team peer review for the draft scope change, performing impact analysis for the draft scope
change, finalizing updates of the draft scope change, process the change through the variation control
process, updating the project management plan as per approved variation.
• The fifth process (Testing & Commissioning): Describes the process of pre-design T&C activities, T&C
activities at the design stage, T&C activities during the tender for construction stage, T&C preparatory
works and preparation of T&C documentations, supervising and approving of preparatory works and
documents, ensuring the pass of construction tests, finalizing T&C plan and T&C method statement and
submitting for approval, approving T&C plan and T&C method statement, requesting for testing &
commissioning project works, form T&C working group, pre-commissioning activities at testing &
commissioning stage, performing commissioning activities, issuing T&C working group report and T&C
report, post-acceptance T&C work.
• The sixth process (Total Initial Acceptance and Handover of Project Scope): Describes the process of
reservation and review the initial acceptance request, request forming an initial acceptance committee,
forming initial acceptance committee, performing initial acceptance inspection, preparing and issue initial
acceptance and handover certificate/rejection report/inventory report, actions to recoup inability to
handover for less than six months, actions to recoup inability to handover for more than six month, issuing
warning letter due to not request for inspection for snag list rectification, rectifying the snag list items by
another contractor on main contractor expense, inspecting snag list fulfillment, issuing warning letter due
to incomplete snag list rectification, re-inspecting snag list fulfillment after 15 days from a warning letter,
inspecting IA&HO rectified snag list by another contractor at contractor’s expense.
• The seventh process (Partial Initial Acceptance and Handover of Project Scope): Describes the process
of receiving and reviewing the partial initial acceptance request, request forming a partial initial
acceptance committee, forming partial initial acceptance committee, performing partial initial acceptance
inspection, preparing and issue partial initial acceptance and handover certificate/rejection
report/inventory report, issuing warning letter due to not request for inspection for snag list rectification,
rectifying the snag list items by another contractor on main contractor expense, inspecting snag list
fulfillment, issuing warning letter due to incomplete snag list rectification, re-inspecting snag list
fulfillment after 15 days from a warning letter, inspecting rectified snag list by another contractor at
contractor’s expense.
• The eighth process (Final Acceptance of Project Scope): Describes the process of receiving and reviewing
the final acceptance request, issuing warning letter due to not requesting for final acceptance and
handover, request forming a final acceptance committee, performing final acceptance inspection, issuing
snag list, issuing warning letter due to not request for inspection for snag list rectification, inspecting snag
list items fulfillment, issuing warning letter due to not complete snag list rectification, re-inspecting snag
list fulfillment after 15 days from a warning letter, inspecting FA&HO rectified snag list by another
contractor at contractor’s expense, issuing final acceptance and handover certificate.
• The Project Scope Management Section attachments include but are not limited to:
o Templates & Forms for:
▪ Spare Parts Record (SPR) Template, Snag List Template, Initial Acceptance and Handover
Certificate, Initial Handover Rejection Report, Final Acceptance and Handover Certificate,
Initial Acceptance Committee Forming Request, Final Acceptance Committee Forming
Request, Initial Acceptance Committee Forming Request, Contractor Initial Acceptance
Request letter, Partial Initial Acceptance and Handover Certificate, Partial Final Acceptance
and Handover Certificate.
o Guidelines Lists for: Design Review Guidelines, Project Testing and Commissioning Guideline.
9 of 20
SUMMARY OF PMM SECTIONS
10 of 20
SUMMARY OF PMM SECTIONS
11 of 20
SUMMARY OF PMM SECTIONS
• The Project Cost Management Section attachments include but are not limited to:
o Templates & Forms for:
▪ CAPEX Forms, Cost Estimate Form, Monthly Cluster Cost Report Template, Revised BOQ
Form, Advance Payment Request, Advance Payment Approval Form.
o Guidelines for:
▪ Cost Estimating Guidelines, Cost Budgeting, Trending and Forecast Guidelines, Cost Database
Guidance Notes, Cost Control Reporting Guidelines.
12 of 20
SUMMARY OF PMM SECTIONS
• The Project Quality Management attachments include but are not limited to:
o Templates & Forms for:
▪ Quality Reports, Method Statements, ITPs, Sectional Acceptance Certificates, Inspection
Requests, Material Approvals, NCR, Quality Observation, Leak Tests, Existing Manhole
Handing Over.
o Check Lists for:
▪ Inspection Checklist for various activities, Audit Checklists, Handover Package, Non-
Disruptive Method NDM Acceptance Checklist for various activities.
o Guidelines for:
▪ Construction Sites (General) for various construction activities.
13 of 20
SUMMARY OF PMM SECTIONS
14 of 20
SUMMARY OF PMM SECTIONS
15 of 20
SUMMARY OF PMM SECTIONS
• The Project Communication Management attachments include but are not limited to:
o Templates for:
▪ Project Document Distribution Matrix Template, Monthly Progress Report, Stakeholder
Communication Plan Template, Weekly Construction Progress Report, Daily Construction
Report, Weekly Meeting Minutes, Monthly Progress Meeting Minutes, Weekly and Monthly
Meetings Agendas.
o Check Lists for:
▪ Progress Evaluation Checklist, Performance Report Checklist.
o Forms for:
▪ Document Approval Form, Document Submittal Form, Non-Conformance Report, Drawing
Submittal Form, Request for Information, Shop Drawing Submittal Form.
o Registers for:
▪ Document Submittals Register, Drawing Submittals Register, Non-Conformance Register,
Shop Drawing Submittals Register.
16 of 20
SUMMARY OF PMM SECTIONS
• The eighth process (Monitor Risk Responses at Project Level): Describes the process of monitoring
project risks, risk review through the stage-gate review process, closing the risk register, capturing lessons
learned for future risk management.
• The Project Risk Management attachments include but are not limited to:
o Check Lists for:
▪ Risk Register Review Checklist, Risk Elements Checklist.
o Registers for:
▪ Project Risk Register, Portfolio Risk Register, Stakeholders Register.
o Guidelines for:
▪ RM Workshop Report Example, Project Stakeholder Mapping Guidelines, Stakeholder Map
Example, Stakeholder Positioning Analysis, RM Workshop Preparation Handbook, Guide to
Hierarchical Sources of Risk, Examples of Risk Management Tools and Techniques, List of
Potential Stakeholder.
17 of 20
SUMMARY OF PMM SECTIONS
• The sixth process (Contract Administration): Describes the process of design consultant/contractor
performance review and reporting, managing payments system, carrying out inspections and audits,
project documentation and records management.
• The seventh process (Suspend and Resume Project): Describes the process of reviewing the suspension
justifications, approving suspension requests at the cluster, approving total / partial project suspension
for more than 50 % of remaining works at HQ, issuing a formal letter for complete/partial project
suspension, issuing resumption recommendation, issuing a formal letter to resume the work.
• The eighth process (Change Project Status from Partial Suspension to Total Suspension): Describes the
process of receiving a report of changing project status from partial suspension to total suspension, raising
a request for changing the project status from partial suspension to total suspension, approving changing
to total project suspension, issuing a formal letter for total project suspension.
• The ninth process (Withdraw Project): describes the process of issuing urge letter to design consultant /
contractor, issuing 1st warning letter to design consultant / contractor, issuing final warning letter to
design consultant / contractor, developing and submit a project status report and initiate withdraw
approval form, developing a project works inventory and status report at the project end date, developing
project status report at 20% time overrun and recommend withdrawal / grace period, approving
withdrawal / grace period recommendation, reviewing the project status / supervision consultant’s report
and recommendation and approve the withdraw approval form, approving the project withdrawal at
cluster and HQ, final approval on the project withdrawal at HQ, issuing withdraw letter to design
consultant / contractor, updating the project status in ENJAZ system and secure the site, performing
inventory on actual executed and remaining works, requesting for assigning another design consultant /
contractor to complete the contract scope.
• The tenth process (Contract Closure): Describes the process of auditing the contract closeout, issuing the
contract closure notification.
• The Project Procurement Management attachments include but are not limited to:
o Templates for:
▪ Project Procurement Strategy, Tender Status Report Template, Warning Letters, Urge Letter,
Withdraw Letter, Resumption Letter, Suspension Letter, Withdraw or Grace
Recommendation Report, Total & Partial Suspension Request Report.
o Checklists for:
▪ Contract Closeout Checklist.
o Forms for:
▪ PR Approval Form, Resumption Request Approval Form, RFP Approval Package, Contractor
Technical Bid Evaluation Form, Withdraw Approval Form, Consultant Technical Bid
Evaluation Form.
o Guidelines for:
▪ Tender Status Report Guidelines, Project Procurement Strategy Guidelines, Procurement
Management Plan Guidelines.
o Registers for:
▪ Performance Guarantee and Bonds Register, Insurance Register, Warranty Register.
18 of 20
SUMMARY OF PMM SECTIONS
• The Project Health, Safety And Environmental Management attachments include but are not limited to:
o Templates & Forms for:
▪ Accident Incident Report, Monthly HSE Report, HSSE Project’s Plan Template, HSE Accident
Investigation Report, Permit to Work Form, HSE Observation Record, Confined Space Entry
Permit, Manual Handling Risk Assessment
o Checklists for:
▪ HSE Assessment Checklist for Method Statement, HSE Inspection Checklists
o Guidelines for:
▪ Project Pollution Control, Project Waste Management, Project Respiratory Protective
Equipment, Project Labor Accommodation Sanitation & Hygiene, Project Control of
Hazardous Materials, Project Heat Stress Management, Project General Safe Working
Requirements, Project Housekeeping Requirements, Project Elevated Work Platform.
o Registers for:
▪ Project HSE Register, Accident Incident Register
19 of 20
SUMMARY OF PMM SECTIONS
20 of 20