: SOP / PIS
PROJECT MANAGEMENT
PROCEDURE & GUIDELINES
REVISION RECORD
REVISION DESCRIPTION APPROVED DATE
FIRASAT PRIMA SDN. BHD. File no. : SOP / PIS
a. PROCEDURE
SOP : Project Implementation Strategy.
b. OBJECTIVE
To outline project strategy and implementation schedule upon receiving confirmation on
project execution.
c. SCOPES
The scopes at this level comprising but not limited to the following matters :
- Appointment of Project Consultants
- Appointment of Land Survey
- Appointment of Soil Investigation (S.I) Contractor
- Initial Meeting ( FPSB – Consultants )
- Finalization of concept design and site layout
- Issuance and approval for Planning Approval (KM)
- Issuance and approval for Building Plan (BP)
- Tender preparation
- Tender evaluation
- Tender award
- Construction stage
- Application and approval of CCC
- Project handover
d. REFERENCE / ATTACHMENT
Attachment 1 – Project Implementation Strategy Flow Chart.
e. REQUIRED INFORMATION
- Development scopes and project brief.
- Site visit report.
- Milestone date.
FIRASAT PRIMA SDN. BHD. File no. : SOP / PIS
f. PRODUCT
Approval from FPSB top management for the Project Implementation Strategy.
FIRASAT PRIMA SDN. BHD. File no. : SOP / PIS
Attachment 1
Project Implementation Strategy
Flow Chart
FIRASAT PRIMA SDN. BHD. File no. : SOP / PIS
START
Presentation of project
implementation strategy
( Strategy Paper ) to FPSB top
management for approval.
Compliance to
comments
NO
Approved ?
YES
FINISH
FIRASAT PRIMA SDN. BHD. File no. : SOP / PIS
Attachment 2
Sample of Strategy Paper
FIRASAT PRIMA SDN. BHD. File no. : SOP / PIS
1.0 OBJECTIVE
1.1 To obtain an approval from FPSB top management for the proposed Project
Implementation Strategy.
2.0 BACKGROUND
2.1 Description on Project Brief.
2.2 Description on Project Development scopes.
2.3 Description on Initial Budget ( development and construction ).
2.4 Description on Proposed Project Site ( Lot no., Land status, Land area etc. )
5.0 RECOMMENDATION
5.1 Based on the above report and justifications, it is recommended that FPSB top
management to approved the strategy paper to allow for the execution of activities as per
proposed strategy table at Item 4.2 .