Professional Documents
Culture Documents
II-1
Workshop I
0 h1 h2 8760
Hours of Operation
P
Peaking
Capacity
I
Intermediate
Capacity
B
Baseload
Capacity
0 h1 h2 8760
Hours of Year
II-2
Workshop I
X + h1 x
Y
0 h1 h2 8760
Hours of Operation
0 h1 h2 8760
Hours of Year
II-3
Workshop I
X+ h 1 x
0 h1 h 8760
2
Hours of Operation
Added Intermediate I’
and Reduced
Peaking Capacity I
0 h1 h2 8760
Hours of Year
II-4
Workshop I
0 h h2 8760
1
Hours of Operation
I
Added Baseload
and Reduced B’
Intermediate B
Capacity
0 h1 h2 8760
Hours of Year
II-5
Workshop I
II-6
Workshop I
Competitive –
Need a forecast of
Energy-only or Electricity market
market prices
Energy + Capacity prices – Forces of
markets supply & demand set
prices
Non-competitive —
Vertically- Marginal running
integrated utility Use a production cost
cost (system lambda)
simulation model to
plus shortage cost —
estimate running costs
Customers reveal
value of unserved Estimate from
energy or utility consumer surveys or
assumes value in back into value based
setting reserve on reserve margin and
margin. cost of reserves.
II-7
Workshop I
II-8
Workshop I
II-9
Workshop I
II-10
Workshop I
r = (1-EFOR) x LOLH* x c
For example,
$40/kW 1
c= x = $19/kWh
0.9 2.4 hours
II-11
Workshop I
pi = mci = c x LOLHi
Substituting for c:
r LOLH LOLHi
mci = x x
1-EFOR LOLH* LOLH
Wrong:
LOLHi
mci = r x (1 + RM) x
LOLH
where RM = system reserve margin.
II-12
Workshop I
II-13
Workshop I
II-14
Workshop I
Approach Time-differentiation
Non-competitive market Relative loss–of–load
– vertically-integrated probability (in service
utility territory)
Pool with reserve margin Depends on Resource
requirements Adequacy rule:
• % of annual NCP
• % of annual CP
• some other formula
Usually requires some
estimation of relative
probability of peak
Competitive, single- Relative loss-of-load
market situation probability (LOLP)
II-15
Workshop I
▪ Capacity
▫ Peaker is least-cost capacity option
▫ Adjustment for excess capacity in near-term
▫ Assignment to hours based on relative loss-
of-load probability
▫ Adjustment for demand losses
▪ Energy
▫ Simulation of marginal running cost
▫ Adjustments for A&G, fuel stock, cash
working capital
▫ Application of marginal energy loss factors
II-16
Workshop I
Working Capital
(10) Material and Supplies (2) x 1.34% $7.31
(11) Prepayments (2) x 0.07% 0.38
(12) Cash Working Capital Allowance (8) x 1.00% 0.01
(13) Total Working Capital (10) + (11) + (12) 7.70
(14) Revenue Requirement for Working
Capital (13) x 13.53% $1.04
II-17
Workshop I
II-18
Workshop I
II-19
Workshop I
II-20
Workshop I
100
a ct
e i n contr
rgy charg
= ene
Slope
75
Dollars/kW
50
25 demand charge in
contract
0
0 1000 2000 3000 4000 5000 6000 7000 8000 9000
Hours
See Volume 1, Tab 8
Using Capacity Contracts and Energy
Saving to Estimate Marginal
Generation Capacity Costs
II-21
Workshop I
ice
p ot Pr
iv eS
ulat
Cu m
0
0 1000 2000 3000 4000 5000 6000 7000 8000 9000
See Volume 1, Tab 8 Hours Sorted in Descending Order of Energy Spot Price
Using Capacity Contracts and Energy
Saving to Estimate Marginal
Generation Capacity Costs
II-22
Workshop I
ct
ntra
st o f Co
100 o
u lat ive C
Cum
Slope of
short-term
contract line
equals contract
75 energy charge
Capacity value of contract
Dollars/kW
tra ct
Con
50 e) of
st (Slop Contract will be used in all
Co
able hours when its variable cost
Vari rice
S pot P is less than spot price.
ive
u mulat
C
25
hours contract
used
0
0 1000 2000 3000 4000 5000 6000 7000 8000 9000
Hours Sorted in Descending Order of Energy Spot Price
II-23
Workshop I
Time-differentiation of marginal
financial costs depends upon probability
of peak.
II-24
Workshop I
Each LSE submits a plan to meet its forecast generation capacity obligation on a
year-ahead basis. Forecast obligation is adjusted monthly to account for customer
migration. Deficiency penalties apply.
II-25
Workshop I
Capacity rule:
In every month, a utility must maintain sufficient accredited capacity
to cover its peak load in that month plus 16%.
Where:
II-26
Workshop I
II-27
Workshop I
frequency
Normalized
Peak Load **
II-28
Workshop I
II-29
Workshop I
II-30
Workshop I
Node Node
A B
If there is plenty
of transmission
linking load and
generation
nodes, the
market-clearing
price at every
location will be
the same
Node (except for
E Node
losses).
C
Node
D
Transmission constraints mean that some nodes will not have access to cheap
energy, and will have to be served by local generators with higher running
costs. In this case the market-clearing price will differ by node and there will
be “locational marginal prices” (LMPs).
II-31
Workshop I
Bilateral
WHOLESALE Contracts:
MARKET Î Negotiated
prices
Î
Bid-Based Markets:
Hourly Locational Marginal Prices (LMP) : Highest generator offer
price accepted in the market (may be limited by price caps)
Dispatch
II-32
Workshop I
▪ The ISO subtracts the hourly amount notified by the LSE day-
ahead from the hourly metered amount
II-33
Workshop I
II-34
Workshop I
Supply curve
Price
(Marginal Cost
of Pumping ) (X Efficiency
factor )
Demand curve
S
( Value of energy
dispatched on-peak )
q1
Quantity
II-35
Workshop I
A An A An A An
Peak Off-Peak Peak Off-Peak Peak Off-Peak
Hour Hour Hour Hour Hour Hour
(5) Cost of Fuel Stock per kWh 1.23 1.23 1.23 1.23 1.23 1.23
(8) Marginal Energy Cost (1)+(4)+(7) 19.22 15.91 17.03 17.49 18.61 16.17
II-36
Workshop I
RANGE NAME: VAROM
II-37
Workshop I
Percent Weighted
of Time Fuel Stock
Fuel Stock Fuel Stock Fuel is Cost
Plant Cost Generation Cost per kWh Marginal Per kWh
--------($)------- ----(GWh)----- -------(Mills)------- ------(%)------ ------(Mills)------
(1) /((2) x 1000) (1995-1999) (3)x(4)
(1) (2) (3) (4) (5)
(4) Fuel Stock Inventory Weighted by Percent of Time Fuel Type is on the Margin 1.227
Note: NA indicates not applicable as gas is not stored and stocks associated
with purchases are held by selling entity.
Source: Cols. (1)-(2): HPC document: "Historical Fuel Stock and Net
Generation Data," 1994 totals.
Col. (4): NERA worksheet HPC "Generation: Percent
Time on Margin by Type." (Range Name: FUELGEN)
II-38
Workshop I
Range Name: FUELGEN
Emergency
Year Coal Gas Purchases
II-39
Workshop I
NERA is conducting a separate study of this issue for RG&E, but has not
completed the analysis. In the interim, we have used as the basis for marginal energy
costs marginal running costs supplied by RG&E and based on data in Section 290.303 of
RG&E's 1982 PURPA 133 filing and data filed in Case 28313.
II-40
Workshop I
On Schedule 1, average marginal running costs and variable operation and maintenance
expenses for 1981 through 1986 in 1982 dollars were adjusted for administrative and general
(A&G) expenses and working capital allowances. Added to these costs were the marginal cost
of the water pollution tax and the foregone margin on sales to other utilities, weighted by the
likelihood that marginal growth will cause off-system sales to be reduced. These marginal
energy costs were then adjusted for marginal energy losses. The last adjustment translates the
cost at the generator into the cost that will be experienced at the customer's meter.
II-41
Workshop I
Average
1981 - 86 20.3 14.4 22.4 16.4 24.7 21.3
Escalated
1982 Dollars 22.7 16.1 25.1 18.4 27.7 23.9
1 1
Used in Study 22.7 16.1 25.1 18.4 32.3 28.5
II-42
Workshop I
Open Effective
Constraint Lines Margin Margin
1
See A.60 Case 28313
II-43
Workshop I
Overall return is estimated using the incremental capital structure and cost of capital supplied by RG&E.
The income tax component is estimated at 0.46/0.54 of the preferred and common equity components.
5 NERA estimate. (see II-202). II-44
Source: Lines (1), (6), and (9)-(11): Based on data supplied by RG&E
Workshop I
II-45
Workshop I
(2) Cash Working Capital (1) x 12.556% 0.92 0.70 0.48 0.65 0.53 0.34
(3) Revenue Requirements (2) x 7.950% 0.07 0.06 0.04 0.05 0.04 0.03
(4) Marginal Energy Cost (1) + (3) 7.39 5.63 3.88 5.25 4.24 2.76
II-46
Workshop I
II-47
Workshop I
II-48
Workshop I
II-49
Workshop I
II-50
Workshop I
Exercise
II-51