Professional Documents
Culture Documents
Distribution
Dedicated
feeder
Substation <24 kV
C&I Primary
Customer – Served (24,14.4,13.8,12.5,4.16 kV)
from dedicated
trunkline equivalent
Trunkline (3 phase Primary)
C&I Primary
customer
Services
(<600v)
C&I
Residential Secondary
Customer customer
V-1
Workshop I
Distribution Elements
And Planning Criteria
Trunkline Feeder
Secondary Line
V-2
Workshop I
Distribution Costs -
How Much Detail?
Overhead / underground
Radial / network
Soil type
Other
V-3
Workshop I
Residual
Minimum incremental
Minimum
NA investment
System/Residual System
divided by
incremental load
Incremental
Typical cost/kVa investment in
Distribution Typical meter for secondary trunkline primary
Facilities and service drop and some and substations
primary divided by
incremental load
Slope of time-
Typical meter
Regression NA series regression
and service drop
line
Outlay for new +
replacement
New Customer equipment + NA NA
customer-related
expenses
V-4
Workshop I
V-5
Workshop I
V-6
Workshop I
V-7
Workshop I
Sample Circuits
Weighted
Urban Suburban Rural Average
Circuit Cost per kVa assuming all
residential customers are:
V-8
Workshop I
Estimated Load:
Single Phase Commercial 86.2 kW
Three Phase Commercial 662.8 kW
Three Phase Industrial 5,576.1 kW
Single Phase Industrial 7,774.9 kW
Total 14,100.0 kW
V-9
Workshop I
Conceptually, most costing practitioners agree that the design of the distribution system is determined by
two major factors: (1) the number and location of customers and (2) their demands. Marginal cost studies have
traditionally attempted to identify a portion of distribution costs as customer-related and the remaining portion as
demand-related. This has led to semantics arguments about the definition of the customer-related and demand-
related components. In fact, for most distribution systems, there is no economic reason for separating the two
components. Distribution systems (up to the feeder coming from the distribution substation) are typically
designed using engineering design standards which take into consideration the number of customers and the
expected maximum loads of those customers. An area with all-electric homes has different design standards from
an area where the homes are not big electricity users. Distribution facilities for commercial and industrial
customers are generally designed on a case-by-case basis, given the expected peak load of the customer. In short,
the distribution system is designed based on the design load of the customers to be served, not specifically on the
Because these marginal distribution costs are incurred based on the design load of the customer, and do
not vary with the customer’s actual peak load from month to month, it makes sense to recover these marginal
distribution costs in a fixed monthly charge imposed on the customer’s design load (or actual peak in the past
twelve months as a possible proxy). Likewise, since these costs are not saved if a customer chooses to invest in a
demand-side management device or a more efficient appliance, it is important to keep these costs out of the
usage-sensitive components of marginal or avoided cost estimates. To avoid confusion, we refer to these costs as
marginal distribution facilities costs, since the costs are both customer- and (design) demand-related.
V-10
Workshop I
To estimate the cost of distribution facilities installed for customers of various types, we asked HPC to
study two sample circuits that represent the range of types of distribution design and customer mix on the HPC
system. We first asked HPC to identify the standard planning assumptions that are used for their typical sized
customers (for HPC small, medium and large residential customers). Next, distribution planners provided us with
two variants for each of two sample circuits, one as-built and the other assuming all residential customers on the
circuit are of the smallest size. The as-built first circuit, Arbor Lane, was all medium customers, while the second
circuit, Barrington Ridge, was a mix of small, medium and large customers. The planners then determined the
installed cost of the secondary and primary facilities in the original and redesigned circuits, and divided these costs
by the total design load on the facilities. We used the cost for the Arbor Lane all small customer circuit design to
get a unit cost for small customers and the Arbor Lane all medium customer circuit design to get a unit cost for
medium customers. We then used these small and medium unit costs, the number of small, medium and large
customers on the “as-built” Barrington Ridge circuit and the total cost of the “as-built” Barrington Ridge circuit to
calculate a unit cost for large customers. The final step was to weight the unit costs for the sample circuits to
estimate costs for industrial and commercial distribution customers. The results of these calculations are presented
in Schedule 6.
The marginal distribution facilities costs cover all distribution components between the meter and the
distribution substation. At HPC, substations are added or expanded based upon changes in actual loads, not based
on design loads. Therefore, the marginal distribution substation costs are most appropriately expressed in terms of
kilowatts of load growth and time-differentiated to indicate in which periods load growth is most likely to trigger
capacity additions.
(excluding replacements and expressed in 1995 dollars) by expected growth in the sum of noncoincident
substation peaks for the same period. This calculation is shown in Schedule 7.
We estimated marginal meter costs by having HPC supply the cost of a typical meter for each customer
category. This is the last component of the distribution marginal cost and these costs are shown on Schedule 8.
V-11
Workshop I
Sample Weighted
Customer Type Circuit Average
----------- (1995 Dollars) -----------
(1) (2)
Re side ntial
V-12
Workshop I
Total Cost
(4) 0.5 kVa customers 50,512.00 235,741.00 $126,711
(5) 2.0 kVa customers 48,864.00 $48,864
(6) 14.0 kVa customers $64,165
V-13
Workshop I
PRIMARY
Circuits
Arbor Lane Barrington Ridge
As Built 0.5kW size 0.5kW size As Built
(13) Number of Customers 0.5 kVa 90.00 400.00 215.00
(14) 2.0 kVa 90.00 90.00
(15) 14.0 kVa 95.00
Total Cost
(16) 0.5 KVa customers 61,745 304,650 163,749
(17) 2.0 KVa customer 78,305 78,305
(18) 14.0 KVa customer 420,100
V-14
Workshop I
Total Secondary and Primary Cost per kVa (at Customer's meters) ^4
Percent Weighted
Residential Average
Customers Cost/kVa
Primary
(33) medium and large $289
Source: HPC Table, "New Installed Cost of Distribution Facilities below the
Substation for Residential Areas."
V-15
WorkshopSchedule
I 7
V-16
Workshop I
Total Peak
Year Distribution Loads
--------(kW)--------
1990 1,717,974
1991 1,817,959
1992 NA
1993 1,676,158
1994 1,694,740
1995 1,736,483
1996 1,800,264
1997 1,863,833
1998 1,928,884
1999 1,994,784
V-17
Workshop I
Each type of distribution facility requires O&M. Because detailed O&M budgets are not available, we
used HPC’s average level of distribution O&M expenses in the recent past as a guide for estimating marginal
O&M costs. Meter and substation O&M costs, along with their associated overheads, were analyzed separately.
O&M costs for the remaining distribution facilities were separated into primary and secondary components. Each
type of O&M expense was unitized and converted to 1995 dollars. Substation O&M is presented on Schedule 9,
p. 1, distribution facilities O&M on Schedule 9, p. 2, and meter O&M on Schedule 9, pp. 3-4.
V-18
Range Name: SCHED9P3 Workshop I
(6) Estimated Annual Weighted Meter O&M Expense for the Planning Period (1995 Dollars) ^3 $10.53
^1 Total meter expenses are meter operation and maintenance expenses (Accounts 586 and 597) and
overheads allocated to meters. Operation overheads (Accounts 580 and 588) and maintenance
overheads (Accounts 590 and 598) were allocated to meters expense based on the relative
importance of these expenses to total distribution O&M (excluding overhead).
^2 Based on data supplied by HPC.
^3 Average of 1990-1993.
Col. (1): NERA worksheet HPC "Calculation of M eter O&M Expense, 1989-1993."
line (19). (Range Name: M ETERO&M )
Col. (2): NERA worksheet HPC "Average Number of Customers,
1989 - 1993." (Range Name: AVGCUST)
Col. (5): NERA worksheet HPC "Computation of Weighted Labor and
M aterial Cost Indexes, 1989-1995," Col. (8). (Range Name: LAB&M AT)
V-19
Workshop I
Annual
Weighting Meter Expense
Rate Class Factor Per Customer
(1995 Dollars)
(1) x $10.53
(1) (2)
(1) 811 Base 1.00 $10.53
V-20
Rang e Name: M ETERWGT Workshop I
Source: Col. (1): HPC worksheet "Development of Allocation Factor for Distribution
Meters (CO6)-- 12 months ended 12-31-92."
Col. (2): Col. (1) divided by Col. (1) for 811-Base, i.e., Col. (1) divided by 123.67 .
Col. (3): HPC worksheet "Development od Allocation Factor for Distribution
Meters (CO6)-- 12 months ended 12-31-92." Also FERC Form 1, 1992,
Page 310 for classes 832, 833, 835 and 836.
V-21
Workshop I
(1) Total Distribution Operation Expenses $11,598 $11,840 $12,583 $12,356 $12,064
(2) Operation Supervision and Engineering 2,413 2,305 2,158 2,440 2,652
(3) Miscellaneous Distribution Expenses 2,735 2,593 3,211 2,804 2,852
(4) Total Operation Overheads 5,148 4,898 5,369 5,244 5,504
MAINTENANCE
(10) Total Distribution Maintenance Expenses 12,704 12,806 12,382 12,559 11,813
(11) Maintenance Supervision and Engineering 1,397 1,274 1,132 1,092 1,154
(12) Maintenance of Miscell. Distribution Expenses 883 948 837 915 911
(13) Total M aintenance Overheads 2,280 2,222 1,969 2,007 2,065
V-22
Workshop I
Rang e Name: AVGCUST
Rate / Subgroup
Description 1989 ^1 1990 ^1 1991 ^1 1992 1993
(1) 811 Base 333,359.00 337,480.00 340,988.00 327,237.00 349,136.00
(2) 811 Spaceheating 17,619
(3) 821 Primary 37,081.00 37,666.00 37,950.00 22.00 38,789.00
(4) 821 Secondary 38,258
(5) 822 Secondary 312.00 296.00 287.00 274.00 247.00
(6) 823 Primary 3,020.00 3,108.00 3,641.00 21.00 3,155.00
(7) 823 Secondary 3,093
(8) 824 Transmission 453.00 483.00 495.00 17.00 484.00
(9) 824 Primary 119
(10) 824 Secondary 346
(11) 825 Primary 10.00 10.00 11.00 8.00 13.00
(12) 825 Secondary 4
(13) 826 Transmission 60.00 66.00 71.00 2.00 76.00
(14) 826 Primary 4
(15) 826 Secondary 69
(16) 832 Transmission
(17) 833 Transmission
(18) 834 Primary 0.00 1.00 1.00 1.00 1.00
(19) 835 Transmission
(20) 836 Transmission
(21) 841 Primary 535.00 532.00 11.00 4.00 551.00
(22) 841 Secondary 545
(23) Total 374,830.00 379,642.00 383,455.00 387,643.00 392,452.00
^1 For the FERC Form 1 entries: (1) sums rate schedules 811, 812 and 813; (3) sums 820
and 821(commercial and industrial (6) sums 823 commercial, industrial and OPA; (8)
sums 824 commercial and industrial, 824.1 and 824.2; (13) sums 826 commercial and 826
industrial; (17) sums 841 commercial and OPA.
Source: 1992: HPC table entitled "Development of Allocation Factor for Distribution
Meters (CO6) Twelve Months Ended 12-31-92."
1989-1991, 1993: FERC Form 1, Page 304a-c.
V-23
Workshop I
Substation Substation
Expenses Per Expenses Per
Total kW of Weighted kW of
Distribution Substation Substation Labor and Substation
Substation Noncoincident Noncoincident Materials Noncoincident
Year Expenses ^1 Peak Loads Peak Loads Cost Index Peak Loads
(Thousand (MW) (Dollars) (1995=1.0000) (1995 Dollars)
(Dollars)
(1) / (2) (3) / (4)
(1) (2) (3) (4) (5)
(6) Estimated Annual Distribution Substation O&M Expenses for the Planning Period ^2 $2.18
Source: Col. (1): NERA worksheet HPC "Calculation of Distribution Substation O&M
Expense, 1989-1993," line (19). (Range name: SUBO&M)
Col. (2): HPC table "Total Peak Distribution Loads." (File: PEAKLOAD.WK4,
dated 1/17/95)
Col. (4): NERA worksheet HPC "Computation of Weighted Labor and Material
Cost Indexes, 1989 - 1995," column (8). (Range name: LAB&MAT)
V-24
Workshop I
OPERATIONS
(1) Total Distribution Operations Expenses $11,598 $11,840 $12,583 $12,356 $12,064
Operation Overheads
(2) Operation Supervision and Engineering 2,413 2,305 2,158 2,440 2,652
(3) Miscellaneous Distribution Expenses 2,735 2,593 3,211 2,804 2,852
(4) Total Operation Overheads 5,148 4,898 5,369 5,244 5,504
(8) Operation Overheads Allocated to Station Ex 843 672 918 865 966
MAINTENANCE
(10) Total Distribution Maintenance Expenses 12,704 12,806 12,382 12,559 11,813
Maintenance Overheads
(11) Maintenance Supervision and Engineeri 1,397 1,274 1,132 1,092 1,154
(12) Maintenance of Miscellaneous Distribut 883 948 837 915 911
(13) Total Maintenance Overheads 2,280 2,222 1,969 2,007 2,065
(17) Maintenance Overheads Allocated to Station 266 266 210 218 196
(19) Total Station Expenses and Associated Overh 3,382 3,158 3,468 3,399 3,236
V-25
Workshop I
(6) Estimated Annual Distribution Facilities O&M Expenses for the Planning Period
(1995 Dollars / kVa) [Average of 1990, 1991 and 1993] $3.05 $3.05
(7) Loss Adjustment Factors to Adjust Expenses Per kVa as Measured at the Substation to Expenses
per kVa as Measured at the Customer Level 1.0158 1.0059
(8) Loss Adjusted Estimated Annual Distribution Facilities O&M Expenses for the Planning Period
Line (6) / Line (7) $3.00 $3.03
1 Distribution facilities expenses are total distribution O&M expenses excluding rents (Account 589), meter
expenses (Accounts 586 and 597), street lighting expenses (Accounts 585 and 596), substation expenses (Accounts
582 and 592), expense s re lated to subtransmission, and overheads allocated to meters and street lighting, substation
and subtransmission expenses. Opera tion overheads (Accounts 580 and 588) and maintenance overheads
(Accounts 590 and 598) were allocated to facilities expenses based on the relative importance of these expenses in
total operation and maintenance expenses (excluding overhea ds).
2 HPC provided ratio of Maximum demand at the meter to diversified demand: 1.8 for small, 1.5 for
medium and 1.3 for large customers. Weighted using proportion of customers from HPC file CUSTOMR1.WK4.
V-26
Workshop I
OPERATIONS
(1) Total Distribution Operation Expenses $11,598 $11,840 $12,583 $12,356 $12,064
Operation Overheads:
(2) Operation Supervision and Engineering 2,413 2,305 2,158 2,440 2,652
(3) Miscellaneous Distribution Expenses 2,735 2,593 3,211 2,804 2,852
(4) Total Operation Overheads 5,148 4,898 5,369 5,244 5,504
MAINTENANCE
(10) Total Distribution Maintenance Expenses 12,704 12,806 12,382 12,559 11,813
Maintenance Overheads:
(11) Maintenance Supervision and Engineering 1,397 1,274 1,132 1,092 1,154
(12) Maintenance of Miscellaneous Distribution Expe 883 948 837 915 911
(13) Total Maintenance Overheads 2,280 2,222 1,969 2,007 2,065
V-27
Workshop I
V-28
Workshop I
Minimum New
Cost Per x Customers
Customer
Customer-
Related
Non
Remove
Growth-
Related
Distribution
Budget
Budget
Residual
Demand-
Related
.
.
Budgeted
Load
Growth
=
Demand-
Related
Cost/kW
V-29
Workshop I
V-30
Workshop I
1982-1985
Source: Lines (1), (3) and (6): Based on data supplied by RG&E.
Line (2): Schedule 5, col. (3), line (2).
V-31
Workshop I
1982-1985
Source: Lines (1), (3) and (6): Based on data supplied by RG&E.
Line (2): Schedule 5, col. (3), line (2).
V-32
Workshop I
1977 $10,981 $6,589 287,133 22.95 $4,392 846 $5.19 0.68 $33.74 $7.64
1978 11,269 6,761 288,715 23.42 4,508 839 5.37 0.72 32.53 7.46
1979 11,857 7,114 290,096 24.52 4,743 854 5.55 0.79 31.04 7.03
1980 12,328 7,397 293,877 25.17 4,931 858 5.75 0.85 29.61 6.76
1981 13,195 7,917 296,843 26.67 5,278 881 5.99 0.93 28.68 6.44
1982 14,804 8,882 298,694 29.74 5,922 890 6.65 1.00 29.74 6.65
4
Estimated Annual Distribution O&M Expenses for the Planning Period (1982 Dollars) $29.34 $6.62
5
Estimated Annual Primary Distribution O&M Expenses for the Planning Period (1982 Dollars) $9.24 $5.58
5
Estimated Annual Secondary Distribution O&M Expenses for the Planning Period (1982 Dollars) $20.10 $1.59
1 Distribution expenses are total distribution O&M expenses excluding rents (Account 589), meter expenses (Accounts 586 and 597), street
lighting expenses (account 585 and 596) and overheads allocated to meter and street lighting expenses. Operation overheads (Account 580
and 588) and maintenance overheads (Accounts 590 and 598) were allocated to street lighting and meters based on the relative importance
of these expenses in total operation and maintenance expenses (excluding overhead), respectively.
2 Average number of customers excluding street lighting customers, transmission customers, sales for resale customers and including inactive
meters on customer premises.
3 The labor and materials cost indexes were weighted by the labor and materials expenses components, respectively, of total distribution O&M
expenses. RG&E labor costs and the Handy_Whitman total distribution index were used for labor and materials cost indexes, respectively.
4 Average of 1980-1982.
5 The demand-related O&M expenses of $6.62 were allocated to primary and secondary components based on their corresponding investment
and demands. The customer-related O&M expenses of $29.34 were allocated to primary and secondary components based on their
corresponding investments and average number of customers.
V-33
Workshop I
V-34
Workshop I
V-35
Workshop I
•
•
$ = ost
o pe tedc
sl l a
- re
and
• dem
•
customer-related
cost {
transformer capacity
NEGATIVE Y-INTERCEPT
st
p e = ted co
sl o a
rel
and-
dem
negative
customer-related transformer capacity (kVa)
cost
V-36
Workshop I
V-37
Workshop I
Regression Approach
V-38
Workshop I
Regression Approach to
Marginal Distribution Costs
Cumulative
investment
in distribution = f (cumulative distribution load growth)
plant
Cumulative
Investment
$
Problems:
Difficult to get good estimates of distribution load
going back many years.
V-39
Workshop I
V-40
Workshop I
Subtotal $500,000
Total $2,850,000
V-41
Workshop I
V-42
Workshop I
V-43
Workshop I
V-44
Workshop I
Distribution Cost
Time-Differentiation
V-45
Workshop I
Alternatives For
Time-Differentiating Distribution Substation
And Feeder Costs
V-46
Workshop I
Illustration of Demand-Related
Distribution Capacity Assignment
Factors Calculated From Substation Loadings
S h a re of
M o n th ly A nnual Sum
M on th 1 S u b -S ta tion P eak C a p a city 2 D ifferen ce R ecip ro ca l o f R ecip ro ca l
(4 ) - (3 ) 1 /(5) (6 )/0 .1 8
(1 ) (2) (3 ) (4 ) (5) (6) (7 )
1 A 80 90 10
B 80 80 0
C 60 70 10
20 1 /2 0 = 0.0 5 28%
2 A 90 90 0
B 70 80 10
C 70 70 0
10 1 /1 0 = 0.1 0 56%
3 A 80 90 10
B 70 80 10
C 50 70 20
40 1 /4 0 = 0.0 2 13%
4 A 70 90 20
B 60 80 20
C 40 70 30
70 1 /7 0 = 0.0 1 8%
T o tal 0 .1 8 10 0 %
1
A fo u r-m o n th y ear is assu m ed fo r th is ex am p le.
2
S o m etim es ap p ro x im ated b y an n u al p eak .
V-47
Workshop I
V-48
Workshop I
V-49
Workshop I
V-50
Workshop I
V-51
Workshop I
V-52