Professional Documents
Culture Documents
Table of Content
1. Scope ............................................................................................................................................. 4
2. References .................................................................................................................................... 4
4. Abbreviations ................................................................................................................................. 5
5. Design ............................................................................................................................................ 5
7. Installation ...................................................................................................................................... 9
8. Commissioning ............................................................................................................................ 11
9. Marking ........................................................................................................................................ 11
1. Scope
This specification covers the m inim um requirements for the design, materials, construction,
2. References
Design, manufacture, performance and testing should be in compliance with the following
codes and standard, except where otherwise specified. The following documents should form
300.K/38/M.PE/1997
Geothermal Activity
Regulation
Safety Audit to Inspection, Equipment and Technique
06P/0746/M.PE/1991
used In Oil and Gas Mining and geothermal Activities.
Year 1979
Gas
Except where otherwise noted, the latest edition of the following codes and standards
should apply:
anodes
methodology
3. Definition of Terms
CONTRACTOR The party that carries out all or part of the design, engineering,
the CONTRACTOR.
4. Abbreviations
EN European Standard
5. Design
Pipeline shall be protected from subsea corrosion using a combination of external coatings and
cathodic protection. The design life of the cathodic protection shall cover the period from
For offshore pipeline operating at temperatures up to 50 °C, galvanic anode placed in the form
of bracelets (half shell or segmental) around the pipe is the preferred method. For high
operating temperature of the pipeline, anode bracelet installation on the pipeline may not
desirable.
U nless their perform ance is supported by appropriate test data to the contrary, zinc anode
should not be used at temperature exceeding 50 °C due to it can undergo a reduction in driving
potential.
For on-land pipeline, the impressed-current system is preferred. Alternatively, galvanic anodes
may be used. Unless their performance is supported by appropriate test data to the contrary,
zinc anode should not be used if resistivity of the electrolyte is higher than 30
Ω ⋅m and
magnesium anode should not be used if resistivity of the electrolyte is higher than 150 Ω ⋅m.
Depending on the pipeline installation method, the anodes can be susceptible to damage. This
concern is critical when the anodes pass over a stinger as the offshore pipeline leaves the lay
barge. For non-weight-coated pipelines, anodes with either tapered shoulders or taper cones
should be used to reduce the risk of the anodes catching on the stinger rollers. For weight-
coated pipelines, the thickness of anodes should match the thickness of the weight coating,
such that the anodes will roll smoothly over the stinger roller.
the systems used to protect the structures or installations to which they are connected.
Design calculation for the cathodic protection system shall demonstrate that the CP
gives current to the pipeline necessary to meet the current density requirements.
Unless otherwise stated, for offshore pipeline, all the requirements of the ISO 15589-2
applicable when they are not in conflict with ISO 15589-2. For on-land pipeline, all the
Calculation of cathodic protection system for offshore pipeline shall be conducted using
the procedure described in Annex A of ISO 15589-2 or equivalent. Where applicable, all
design parameters shall be in according with ISO 15589-2 as mentioned in Section 5.5.
The cathodic protection of the conventional riser shall be included in the cathodic
The spacing between anodes shall be determined once the number of anodes has been
calculated. The anode spacing shall be close enough to maintain an adequate protection
in the event of mechanical or electrical loss of a single anode. Anode spacing should not
The first and last pipeline length (about 50m , m easured from the respective bottom of
riser corrosion protection coating), anode spacing shall be half of that calculated using
design parameters and hence additional anodes shall be provided accordingly. For each
pipeline crossing, spool piece, branch connection or subsea flange, the anode spacing
shall also be half of that calculated using design parameters, up to a distance of 50m on
either side of those the possible interferences, and hence additional anodes shall be
provided accordingly.
F or sh ort pipelin es, ano des m ay be insta lled at e ach en d of th e pipe lin e, if it ca n be
achieved. Attenuation calculations shall be carried out for these installations to determine
whether it is feasible to protect the mid-point of the pipeline using anodes located at the
ends.
Retrofit system is used for pipelines with galvanic anode failures, excessive anode
consum ption, operation beyond original design life or excessive coating deterioration.
engineering CONTRACTOR.
certain modifications to the installation may be necessary to comply with the minimum
reliability e.g. evaluates impressed current, galvanic anode and hybrid solution.
Retrofit system may provide differ current density as one would for a new facility.
If the subsea protection structure is not conductively connected to the pipeline and it
requires its own cathodic protection, calculation of cathodic protection shall be conducted
Manufacturing, inspection and testing of galvanic anode for subsea protection structure
• Offshore pipeline
Electrical isolation may not need to be installed between the pipeline and the topside
piping. Clause 5.1 of ISO 15589-2 confirms electrical isolation is required where
different protection systems are used between the pipeline and the onshore or
• On-land pipeline:
possible. If the use of monobloc isolating joint is not practical, isolating flange kits may
be used. Isolating flange should be protected against ingress of dirt and moisture by
the use of flange protector or protective tape. Each isolating joint/isolating flange
should be provided with test facilities. The electrical resistance across isolating joints
should be more than 10 M Ω measured at 1000 V (dc) in dry air, before installation.
In areas w here there risk of high voltage e.g. caused by nearby pow er system or
lightning, the isolating joint or flange shall be protected using electrical earthing or
surge arrestor.
Some of design data can be assessed from ISO 15589-2 as the following:
shall be in accordance with Clause 8 and 9 of ISO 15589-2. The mass fraction of
anode material shall conform to the following Table 1 and 2 (reference is made
to T a b le 5 o f 1 5 5 8 9 -2 fo r a lu m in iu m a n o d e a n d T a b le 6 o f 1 5 5 8 9 -2 fo r zin c
COMPANY’s approval.
The mass fraction of anode material for on-land pipeline shall conform to Table 3
and 4 (reference is m ade to Table 2 of 15589-1 for zinc anode and Table 3 of
Slight alteration in mass fraction of anode material may be allowed but it shall be
Table 1-Mass fraction of aluminium anode Table 2-Mass fraction of zinc anode
Mass fraction
Mass fraction
Element
Element
Zn 2,5 5,75
Cu - 0,005
In 0,016 0,040
Al 0,10 0,50
Fe - 0,09
Fe - 0,005
Si - 0,12
Cd 0,025 0,07
Cu - 0,003
Pb - 0,006
Cd - 0,002
Zn Remainder
Others - 0,02
Al Remainder
anode
Mass fraction
Mass fraction
Element
Element
Cu - 0,005
Cu - 0,02
Al 0,10 0,50
Al 5,3 6,7
Fe - 0,005
Si - 0,1
Cd - 0,07
Fe - 0,003
Pb 0,006
Mn 0,15 -
Zn Remainder
Ni - 0,002
Other - 0,02
Zn 2,5 3,5
Mg Remainder
Other - 0,005
Anode core shall conform to Clause 8.3 of ISO 15589-2 with addition the
following requirement:
•
Steel core at least 6mm thick. Anode material shall surround the core.
•
Minimum main steel straps shall be of 2.
ascertain that all moulds, cores, casting equipment and other components are in
and/or a lim ited num ber of anodes, the extent of testing is subject to special
agreement.
6.2 Cabling
insulation 2.8 mm thick conform to ASTM D1248 type 1 class C category 5 grade E-4 or
E-5, i.e. HMW -PE (high molecular weight polyethylene) or equivalent. Surface printed
Cable for environment where halogen gases and/or particularly chlorine are evolved and
concentrated around the anode and cable shall be double insulated with ECTFE
Cable shall sufficient length to run with the acceptable voltage drop as specified by the
IEE regulation.
At least two cables per anode shall be installed. For half-shell anodes, two half-shells
The m onitoring and special facilities for on-land pipeline shall be in accordance w ith
7. Installation
follows:
Welders and welding procedures should be qualified for any applicable welding process
to a recognized standard.
For bracelet anodes mounted on pipe joints that are concrete weight-coated, electrical
contact between the concrete reinforcement and the anodes shall be avoided by
providing a gap, typically of 25 mm, at each end of the anode. Gaps between bracelet
anode half-shells and between half-shells and the concrete shall be filled with non-
Anode installation shall be carried out in such a way that damage to the coating is
minimized.
mechanical strength and electrical continuity and to prevent damage to the pipe at the
point of connection. The removal of the protective coating from the pipe should be kept
W elding of cable connections shall not be carried out on bends or within 200 mm from
pipeline welds.
For thermite welding of cables, the welding procedure shall be such that copper
penetration into the pipeline material shall be less than 1 mm and local pipeline hardness
Therm ite w eld charges should not be greater than 15 g. If cables larger than 16 m m
need to be attached, the cores shall be separated into a number of smaller strands each
less than 16 mm
and welded separately.
Alternative methods such as pin brazing, soft soldering, adhesive bonding or friction
welding may be used, provided that the detailed procedure and performance are reliable
All items to be protected by CP shall be electrically connected and should have a welded
or brazed connection to an anode. All bolted or clamped components with surface area
exceeding 1 m
shall have an all-welded or brazed connection to an anode. For all bolted
verified that the electric resistance is less than 0.10 Ω . Coating on contact surfaces shall
Cables should be copper-cored, and shall be insulated and sheathed to withstand the
prevailing chemical and mechanical conditions. The minimum conductor size for
If the contact is made by using current-carrying copper cables welded or brazed at each
to the cable shoe. At least two cables per anode shall be installed. For half-shell anodes,
Only in exceptional cases (e.g. the retrofit of a cathodic protection system or the use of
remote anode assemblies) should the underwater installation of anodes, utilizing either
Bolted connections with set screws or friction welding may be considered for the
For high strength materials (SMY > 550 MPa), welding of doubler plates for anode
connections shall be avoided, as this can cause local stress increase which can lead to
hydrogen embrittlement.
A separate impressed current system should be provided for each gate leaf. Each
system should consist of a rectifier supplying protective current to anodes, w hich w ill
distribute protective current to the gate structure. Cathodic protection should be installed
on those portions of the gates submerged at normal pool levels. The faces of the gates
should be protected to upper pool stages, except that the downstream face of the lower
gates should be protected to the lower pool. M eters should be provided as part of the
This navigation lock will be subject to flooding and floating debris; therefore, the cathodic
protection system should be designed to permit for removal during periods of high water,
and the anode cables and sausage-type anodes will require impact protection to prevent
Installation of impressed current system shall consider regular control and maintenance.
The voltage and current readings of the rectifiers shall can be observed, monitored, and
recorded daily. C onsideration shall also be given to the need of evaluation of annual
potential is the accepted method for determining the adequacy of corrosion protection
provided by the cathodic protection system. Reference cell data are evaluated based on
the design (anode locations), the voltage adjustm ents, and the adequacy of the test
locations. Adjustments to the rectifier output (e.g. up to 120% of design operating output)
can be made to improve the protective potentials applied to the gate leaves. Sometime
DC voltage and current data indicate that the rectifiers and cathodic protection system
are working but do not guarantee that the system is properly optimized.
8. Commissioning
For galvanic anode system of offshore pipeline, commissioning is generally not applicable. For
• measurement of adequate protection levels (in according with Annex C of ISO 15589-2)
For on-land pipeline, commissioning shall be in according with Clause 10 of ISO 15589-1.
Upon completion of installation and commissioning phase, project team shall close the activity
9. Marking
Galvanic anodes shall be marked with the type of material (e.g. tradename), anode mass and
melt number.
10. Documentation
•
drawings including detailed cathodic protection design, manufacturing/installation, anode
distribution.
•
inspection document (analysis certificates, electrochemical test certificates giving the
m ethod, the results and the m elt num ber in the casting operation, m ill certificates of the
steels used, net and gross weight of anodes, cable type/specification along with routine and
•
drawings of wiring system and type test certificate for monitoring panel of impressed-current
•
detailed technical study (hypotheses considered for the calculation including chosen type,
•
relevant design and installation manual including detailed calculation verifying that the
protection is assured for the pipeline and, if required, recommended means of anode
support and analytical information regarding the location of reference electrode (which has