Progress Report No.27 (Jan'23)
Progress Report No.27 (Jan'23)
27
PROJEK ANJUNG USAHAWAN SEMATAN 1st JANUARY 2023–
30th JANUARY 2023
Contents
PROJECT PARTICULAR............................................................................................................................3
Contract Particulars............................................................................................................................3
SCOPE OF WORK.................................................................................................................................4-5
SITE LOCATION.......................................................................................................................................8
PROJECT STATUS..................................................................................................................................10
Work Progress..................................................................................................................................11
Physical S-Curve...............................................................................................................................12
Financial S-Curve..............................................................................................................................13
Outstanding Activities......................................................................................................................14
Forecast Activities............................................................................................................................14
Machineries......................................................................................................................................18
PAYMENT STATUS...........................................................................................................................19-20
PROGRESS PHOTOGRAPH.........................................................................................................21-30
PROJECT PARTICULAR
General Project Works Description
The project site is located at Sematan in which the project involves theproposed Anjung
Usahawan Sematan, Kuching Division, Sarawak (Phase 1).
Contract Particulars
1. Contract Title : The Construction and Completion of the Proposed Anjung
Usahawan Sematan, Kuching Divison, Sarawak
EOT 1 – 14 days
14. Time Extension Approved : EOT 2 – 46 days
EOT 3 – 174 days
SCOPE OF WORK
A. Preliminaries & General
1. Contractual requirements
2. Insurances
3. SO/SOR’s requirements
4. Project requirements
5. Authorities’s requiremnets (occupational safety and health requirement)
6. Contractor’s requirements
7. Protection Works
8. Enviromental management plan
9. Maintenance
10. Survey
B. Piling works
1. 300 x 300mm Precast Reinforced Concrete piles
2. 200 x 200mm Precast Reinforced concrete piles
3. 150 x 150mm Precast Reinforced concrete piles
4. 80mm Belian Piles
C. Civil/External works
1. Site clearance
2. Earthworks
3. Road and carpark
4. Surface water drainage
5. 200mm thick RC crossover
6. Sewerage work
7. Water reticulation
8. Footpath
9. Spot Turfing
10. Fence and gate
D. Building Works for Anjung Usahawan Main Building Block
1. Foundation works
2. All structural frameworks
3. Roofing
4. Brick wall
5. All plastering works
6. Ceiling works
7. Door & windows including glazing
8. Painting works
9. Tiling works
10. Perforated alum screen works
11. Decorative panels works
12. All sanitary, plumbing including septic tanks works
13. Other works
E. Structural Works
1. Elevated R.C Water Storage Tank & all associated works
2. Alum louvre panels for Elevated R.C Water Storage Tank
3. Pump House
4. R.C Suction Tank
5. Covered Bin Centre
2. Mechanical Services
• Air-conditioning services
• Cold water services
• Fire fighting services
• Sanitary plumbing services
G. Provisional Sum
H. Contingency Sum
I. Other works
1. Termite treatment
2. Loose furniture
3. All signages as shown in drawings
4. Landscaping & turfing works
SITE LOCATION
Project Location : Lot 1300 Jalan Tun Hussien Onn, 94100 Sematan, Kuching
PROJECT STATUS
Work Progress
This is the Monthly Progress Report No.27 which covered from 1st January 2023 to 30th January
2023. The actual physical progress for this month is 31.54% and financial progress is 31.72% .
Original Schedule
- - -
Progress
Status Revised
-68.70% -68.46% -
Schedule Progress
(EOT 3)
Original Schedule -
- -
Progress
Status Revised
-68.38% -68.28% -
Schedule Progress
(EOT 3)
Outstanding Activities
Activities Remark
Earthworks
Pilling Works
Column 95%
Pump House
Column 100%
Roofing Sheet
Ceiling Finishes
RC Suction Tank
Slab 100%
RC Wall 100%
Waterproofing
Column 100%
Roof Finishes
Wall Finishes
Floor Finishes
Forecast Activities
- Upper Roof Beam at Anjung Usahawan Main Building
Machineries
PAYMENT STATUS
Interim Claim Date of Amount Payment Date of Issue Amount Date of Amount Remarks
Submission (RM) Certificate (RM) Receive (RM)
CLAIM NO.1 27 APRIL 2021 RM781,753.51 1(INTERIM) 4 JUNE 2021 RM769,378.88 7 JULY RM769,378.88
2021
CLAIM NO.2 15 SEPT 2021 RM87,305.87 2(INTERIM) 4 OCT 2021 RM78,180.80 30 NOV RM78,180.80
2021
CLAIM NO.3 16 NOV 2021 RM163,209.16 3(INTERIM) 30 NOV 2021 RM153,771.99 4 JAN RM153,771.99
2022
Interim Claim Date of Amount Payment Date of Issue Amount Date of Amount Remarks
Submission (RM) Certificate (RM) Receive (RM)
PROGRESS PHOTOGRAPH
Anjung Usahawan Main Building - Casting Concrete for Lower Roof Beam
Anjung Usahawan Main Building - Casting Concrete for Upper Roof Beam
Anjung Usahawan Main Building - Rebar and Formwork Installation for Upper
Column
Anjung Usahawan Main Building - Dismantle Formwork for Upper Roof Beam
STATUS OF SUBMISSIONS