Professional Documents
Culture Documents
15
Document Details
Date: 21 October 2022
Reference: 1-D0136.15
Status: Detailed Design/ Consent
Prepared by
----------------------------------------
Bruce McClelland | Senior Fire Engineer
Reviewed by
----------------------------------------
Meng Lim | Senior Fire Protection Engineer
--------------------------------------
Seamus Slattery | Project Manager
Contents
1 Preliminary and General .............................................................................................................................................. 1
1.1 Extent of work ....................................................................................................................................................................... 1
1.2 Definitions and Abbreviations ................................................................................................................................. 1
1.3 Supplementary Standards and Regulations ............................................................................................. 2
1.4 Health and Safety ............................................................................................................................................................. 3
1.6 Materials and Work Not Specified but Required ................................................................................. 6
1.7 Equipment Installation ............................................................................................................................................... 6
1.8 Access to Equipment ................................................................................................................................................... 6
1.9 Seismic Restraints ........................................................................................................................................................... 6
1.10 Fixing to Structure ............................................................................................................................................................ 7
1.11 Safety Devices ...................................................................................................................................................................... 7
1.12 Uniformity ................................................................................................................................................................................ 7
1.13 Alternative equipment ................................................................................................................................................. 7
1.14 Samples and prototypes ............................................................................................................................................ 8
1.15 Protection of Works ........................................................................................................................................................ 8
1.16 Welding .................................................................................................................................................................................... 8
1.17 Corrosion Protection...................................................................................................................................................... 9
1.18 Identification of services............................................................................................................................................. 9
1.19 Painting .................................................................................................................................................................................. 10
1.20 Noise Levels ......................................................................................................................................................................... 10
1.21 Existing Services .............................................................................................................................................................. 10
1.22 Demolition and Salvage ............................................................................................................................................. 11
1.23 Builder's work ...................................................................................................................................................................... 11
1.24 Co-ordination and Liaison ........................................................................................................................................ 11
1.25 Holes in Structure ........................................................................................................................................................... 12
1.26 Ducts and Penetrations ............................................................................................................................................. 12
1.27 Programme of Work ..................................................................................................................................................... 13
1.28 Testing and commissioning .................................................................................................................................. 14
1.29 Practical Completion ................................................................................................................................................... 15
1.30 Operator Instruction ..................................................................................................................................................... 15
1.31 Drawing Information Required ........................................................................................................................... 15
1.32 Operational and Maintenance Manual ........................................................................................................ 17
1.33 Post practical completion and defects liability period ..................................................................19
2 Specific Scope of Works .......................................................................................................................................... 20
2.1 General ................................................................................................................................................................................... 20
2.2 Project Summary and Project and System Overview .................................................................... 20
2.3 Extent of Works................................................................................................................................................................. 21
2.4 Fire Alarm System.......................................................................................................................................................... 22
2.5 Fire Sprinkler System .................................................................................................................................................. 24
2.6 Fire Equipment ................................................................................................................................................................25
2.7 Authority Approvals......................................................................................................................................................25
2.8 Compliance ........................................................................................................................................................................ 26
2.9 Completion Documents ......................................................................................................................................... 26
2.10 Services interface works .......................................................................................................................................... 26
Revision Details
Revision Details
Abbreviation Description
AFASP Automatic Fire Alarm Service Provider
AHJ Authority Having Jurisdiction
AS Australian Standard
ASD Aspirating Smoke Detector
ATD Alarm Transmission Device (to remote receiving centre, e.g. ASE)
BC Building Consent
BHI Building Hydrant Inlet
BIM Building Information Modelling
BMS Building Management System
BPU Backflow Prevention Unit
COC Certificate of Compliance
DLP Defects Liability Period
Abbreviation Description
EWIS Emergency Warning and Intercommunication Systems
FAS Fire Alarm System
FACP Fire Alarm Control Panel/Unit
FAP Fire Alarm Panel
FBA Fire Brigade Alarm
FENZ Fire and Emergency New Zealand
FFCP Fire Fan Control Panel
FIP Fire alarm Indicating Panel
FM Factory Mutual
FRR Fire Resistance Rating
FSI Fire Sprinkler Inlet
GUI Graphics User Interface
HNZL Health New Zealand Lakes
HDPE High Density Polyethylene
HSC Hydrant System Certifier
HSSD High Sensitivity Smoke Detection
HVAC Heating, Ventilation and Air Conditioning
IL Importance Level
IRS In-rack Sprinklers
MCC Motor Control Centre
MCP Manual Call Point
MHOD Magnetic (door) Hold-Open Device
MJC Multiple Jet Control
NO / NC Normally Opened / Normally Closed
NZS New Zealand Standard
NZSEE New Zealand Society for Earthquake Engineering
PA Public Address
PAS Publicly Available Specification
PRV Pressure Reducing Valve
QR Quick Response
RDU Remote Display Unit (or Liquid Crystal Display repeater/mimic)
SCADA Supervisory Control and Data Acquisition
SNZ Standards New Zealand
SSC Sprinkler System Certifier
TA Territorial Authority
UL Underwriters Laboratories
WIP Warden Intercommunication Point
XAP Extended Alarm Protocol
1.3.2 Regulations
Comply with all statutory and regulatory requirements including:
(a) New Zealand Building Act 2004
(b) Fire and Emergency New Zealand Regulations 2018
(c) Health and Safety at Work Act 2015.
(d) Territorial Authority requirements.
(e) Electricity (Safety) Regulations 2010.
1.4.1 General
(a) Allow to carry out the responsibility required within the terms of the Health and Safety
at Work Act 2015.
(b) Allow to obtain a copy of the Principal’s Health and Safety Policy upon notice of
commencement of works.
(c) Take all reasonable steps on the site to ensure the safety of all concerned and to
exclude all unauthorised personnel.
1.4.2 Submission
Within 5 working days of the award of a contract, allow to submit:
(a) The safety plan appropriate to their section of work.
(b) A statement on staff selection criteria, training standards and induction courses.
(c) A statement on how compliance with the Act and their safety performance will be
monitored.
(d) A statement on their safety performance and injury record for the last 2 years.
(e) A statement of their safety rules.
(f) The operational safety guidelines for known or potential hazards.
(g) The name and contact telephone number of their Work Place Controller.
1.4.3 Reporting
During the duration of the contract, allow to report regularly in relation to:
(a) Review of safety performance and compliance with the Act.
(b) Action relating to breaches of safety requirements.
(c) Safety audits/reports/spot inspections carried out.
(d) Follow up on accidents.
(5) To obtain all Authority permits and certificates in a timely manner to allow the
progress of the work.
(6) To implement procedures to ensure that only competent tradesmen are used for
the works.
(7) To be cognisant of the role of all relevant parties during the construction phase of
the project and to assist them in the conduct of their duties wherever possible.
(8) To contribute, in the spirit of partnering, towards the successful execution of the
contract.
(9) To provide manufacturer’s and construction drawings.
(10) To provide samples and prototypes.
(11) To make final equipment selections to meet the requirements listed.
1.5.4 Installers Design Responsibilities
(a) The Contract documents depict a schematic intent of the services and are not fully
coordinated with the Architectural drawings or other services, and are in fact for a
performance-based design, document and install contract. The Installer shall be
responsible to fully develop the design in accordance with the requirements of the
brief and the contract documents, carry out computations, and attend meetings with
the Architect/Engineer, Head Installer and other trade Contractors. Design drawings
should to be prepared, which may be used for the purposes of shop/construction
drawings.
(b) The Installer shall be responsible for the development of design activities listed below,
in addition to those activities normally undertaken through the custom and practice of
the industry.
(c) The Installer shall be responsible for ensuring that the design which he undertakes is
fully co-ordinated and compatible with the remainder of the project design.
(d) The Installers design obligation shall include:
(i) Pipework routes and locations.
(ii) Bracket and support detailed design and locations.
(iii) Details of electrical wiring diagrams of all equipment supplied by the Installer
showing all interconnections between equipment to enable the necessary
wiring to be undertaken.
(iv) Details of all equipment component design and selection necessary insofar as
such items have been selected by the Installer for that item of equipment to
meet the engineering specification and performance indicated.
(v) Thermal expansion accommodation and anchorage, including provision of
bellows or bends.
(vi) Acoustic design or modification of equipment to meet with the noise levels
specified. Specified levels to be achieved with all plant operating.
(vii) Valve and access locations.
(viii) Determining water supply capacities.
(ix) Selection of all anti-vibration mountings to suit the particular pump
application of the mounts.
(x) Final locations of all installed components and other similar equipment that
make up the installation.
(xi) Fire protection systems design in accordance with the Fire Safety Engineering
Report.
1.5.5 Required Submissions
(e) Provide to the Superintendent, in good time to allow review without impediment to
the programme:
(i) Copies of correspondence with Authorities.
(ii) Certified schedule of compliance for all equipment, prior to placing orders.
(iii) Hydraulic Calculations for all systems installed, inclusive of results print-out,
drawings (noded, numbered, area of operation) and water supply curves
complete with system performance requirements.
(iv) Design calculation worksheets for battery capacity for EWIS and Fire Detection
and Alarm Systems equipment.
(v) Certified schedule of competency for all tradesmen intended to work on the
project.
(vi) Factory test results where applicable.
(vii) All product data, performance test and commissioning results required by this
specification.
(viii) Shop drawings for fabrication and installation of all equipment and items
supplied.
(ix) Inspection and test plans for every section of the works. Detail the procedure of
how to complete the task, the skill or competency of the person undertaking
the works, the review or testing procedure to assure satisfactory completion of
the task, the person within the installer’s organisation authorised to sign-off the
task as accepted.
(x) Client handover/training proposals.
(xi) Record and installation drawings: Record all changes to equipment and
services layouts, wiring and any other items during the construction period,
which may have been incorporated into these works.
(xii) Operating and Maintenance manuals.
(xiii) Certification for compliance with project specific Code/Design requirements of
the completed works.
(xiv) Maintenance and servicing during the defects liability period.
1.12 Uniformity
When a particular manufacturer or product range has been adopted for equipment or fittings, all
such fittings and components shall be uniform throughout the project.
(c) Quality, performance, and finish are equal to or better than that quoted. The following
(where appropriate) will be considered when making comparisons:
1.14.1 General
(a) Approved samples may be retained until completion of the work. All such materials
used in the work shall conform with the approved sample(s).
(b) Allow for the reasonable testing and/or analysing of samples of any materials brought
on to the site and intended for use at any time.
1.16 Welding
1.18.3 Labels
Labels for plant and equipment shall:
(a) Be black lettering on a white background unless indicated otherwise.
(b) Have lettering a minimum of 5 mm high unless indicated otherwise.
(c) Be permanent and rigid.
(d) Be attached by screws, chains or some other permanent method that shall be subject
to approval.
1.19 Painting
1.19.2 Finish
(a) Equipment supplied in a factory finished condition will be acceptable, provided that
the finish is of high standard, acceptable in colour, and does not require extensive
touching up. Otherwise factory finished equipment shall be cleaned, wire brushed
and painted on site with not less than two coats of approved finishing paint.
(b) Pipework in ceiling space shall be painted with one finish coat over the priming coat.
(c) The final coat of paint on each piping service shall constitute the basic identification
colour of the service as scheduled below.
(d) Normally bright metal parts of installation and all equipment identification plates shall
be polished.
(e) Galvanised coating shall have a minimum of 300 g/m2 zinc on both internal/external
surfaces.
(e) Services found during excavation which have not been previously located shall be
reported.
(f) Report immediately any services that are damaged.
(g) No excavating machine shall be used closer than 200 mm to any buried services.
(h) Any power cable or service that is found to be redundant shall first be proved safe to
cut before removal.
(i) Show exact locations of all underground ducts and services on as-built drawings giving
exact depths and dimensions from readily identifiable buildings or landmarks. These
shall include any underground services found during excavation not previously located.
(b) Examine work carried out by other Trades affecting services work such as finish and air
tightness of builders' work, air ducts, etc., and if unsatisfactory, notify the Contractor in
writing.
(c) All chases, ducts, recesses and penetrations in structural elements not shown on the
building and structural drawings shall be subject to approval before commencing
work.
1.26.3 Ducts
(a) Buried sections of wiring shall be installed within underground cable ducts of Class D
rigid PVC to NZS 7648 or (BS 3505), or reinforced fibre cement pipes with sleeved or
socket joints.
(b) Include access chambers/pits (with trafficable covers) at bends, and at intervals of 75
m.
(c) Bends in ducts to have an internal radius greater than 15 times the diameter of the
duct, or 400 mm, or as detailed.
(d) Clean out all ducts and penetrations etc. before the installation of cables, remove all
sharp edges. Fit draw wires/tape.
1.28.1 General
(d) Before any of the systems are put into service they shall be subjected to a testing and
commissioning procedure.
(e) All tests shall be conducted in accordance with the requirements of this specification,
the local authority, FENZ, and IANZ-accredited inspectors. Provide all associated
inspection reports.
(f) All tests shall be carefully pre-planned and scheduled to ensure that they are co-
ordinated with the work of other relevant trades involved and that they are carried out
in a safe and efficient manner with a minimum of inconvenience to owners and/or
management of the building who shall be advised regarding the nature of the tests
and the tests shall be coordinated with them to minimise any possible hazards or
inconvenience that may arise.
(g) In addition, the Engineer shall be notified at least seven days before the
commencement of commissioning so that a representative may attend as necessary.
Examples of such tests deemed to be mandatory include those that demonstrate
system performance meeting the specified functions beyond those required by the
respective standards; typically, these include multi-disciplinary integrated tests.
(h) Submit a complete Plant & Equipment Register and testing schedule prior to the
commissioning tests. Include a cause/effect matrix for the proposed integrated tests.
(i) All such commissioning and testing shall be completed prior to the certification of
Practical Completion.
(c) Fully co-ordinate detailed design for all Fire Protection systems, including fully co-
ordinated shop drawings in accordance with the specification.
(d) Provide full and comprehensive coordinated equipment layout to all areas of the
building. Co-ordinate the layout of plant and services with the building layout and
structure, and with other plant and services.
(e) Co-ordinate all aspects of the Fire Protection detailed design with the Architect,
Structural Engineer and all other parties.
(f) Check space requirements of equipment and services when indicated
diagrammatically in the Contract documents. Select equipment with dimensions to
suit the available space.
(g) Lay out equipment and services to be accessible for operation, maintenance and
replacement and so as not to interfere with access to other installations. Make offsets
as necessary.
(h) Neatly group services, with separate layers for crossing services.
(i) Include physical co-ordination of installation with other trades.
(j) Indicate electrical loads to be provided by electrical trade and compare with design
loads cable sizes and circuit protection devices, seeking design direction where
discrepancies occur.
(k) Include locations of alarm devices, ceiling fixtures, etc.
(l) Allow a minimum of two weeks for the review.
(m) Rejected drawings shall be revised and resubmitted until such time as the agreement
on the work to be done has been reached. No extension of time will be granted for
delays that can be attributed to the need to resubmit the shop drawings.
(n) The review of drawings shall not in any way relieve the Sub-contractor/ Contractor of
the responsibility for any errors and omissions, nor from the necessity to furnish such
workmanship and materials as may be required for the completion of the work.
(j) When the drawings have been prepared to an acceptable and approved standard of
accuracy and presentation, provide one set of prints reduced to A3 size (to be included
in each copy of the Maintenance Manual).
(k) A base set of clean contract drawings can be provided, at the Contractors expense.
Drawings will be provided in AutoCAD. The Contractor will submit two copies of the
completed “Drawings Supplied For As Built - Agreement” (Refer Section Error!
Reference source not found. at the end of this section). This agreement will include a
schedule of the drawings required.
(l) Schematic drawings, suitably laminated shall be provided and installed adjacent to
each control panel.
(m) The first draft of as-built documents must be supplied before practical completion.
1.32.1 General
(a) Prior to the issue of the Certificate of Practical Completion, submit electronic (PDF)
copies of Operational and Maintenance Manual.
(b) The Operational and Maintenance Manual and drawings incorporating comments will
be returned within two months of the receipt of the draft copies.
(c) Supply four copies of the approved draft Operational and Maintenance Manual within
four weeks of their provisional acceptance and prior to the issue of the Certificate of
Final Completion.
(d) If there is a failure to meet the above requirements, then the cost of producing the
Operational and Maintenance Manuals, by other parties, shall be deducted from the
Contract Sum.
1.32.2 Presentation
(a) Operational and Maintenance Manuals shall be bound in hard backed plastic ring
binders A4 size with embossed titles on the front and spine.
(b) The project identification and names of the Services Consultant, Sub Trade
contractor/Contractor and Principal shall be shown on the cover.
(c) A table of contents that schedules the contents of the manual. Include in the table,
section headings, sub-sections and the page number for each entry.
(d) An introduction that identifies:
Index of all sections and sub-divisions including lists of drawings, components and
equipment.
(b) Description
General description of the installation divided into sub-sections for each individual
system as appropriate.
(c) Equipment
Full operating instructions for each system and for groups of inter-related systems with
details of emergency procedures.
Operating conditions fluid flows, pressures, electrical data and other characteristics as
applicable for checking and adjustment of all systems and components.
(e) Maintenance
Include check-lists.
(f) Commissioning Records
Producer Statement/s for the entire installation, clearly citing the relevant standards,
noting any deviations and specific inclusions.
One set of bound-in reduced size prints to A3 size of the final as built and
maintenance drawings protected by a plastic lamination.
(i) Specific systems fail to achieve the desired outcomes after two attempts are
made to rectify the drawback. These specific systems include those that are fire
and life safety or business / mission critical to the Principal.
(ii) If there have been more than three (3) attempts to rectify the defect, in which
instance a further 12 months of monitoring will be required after the defect is
rectified to monitor that the desired outcomes are achieved without further
shortfalls.
Provision means the detailed design, obtaining design approval for, supply, delivery, installation,
testing, commissioning, obtaining certification for, documentation, defects liability, maintenance
and warranty of all materials and equipment and systems as required by this Contract, together
with auxiliary hardware necessary to complete the systems according to the Contract Documents.
The smoke detection will be a combination of point smoke detectors and aspirating systems. The
fire alarm panel will be analogue addressable with a mimic and at least two mini mimic panels
with provision for a third.
The Rotorua Hospital has mainly Ampac fire alarm panels and devices. The preference it that the
new Mauri Ora Unit has an Ampac FireFinder Plus panel to enable interface to site network with
other Ampac equipment. or a compatible approved panel. The new panel would need to be
connected the sitewide network via an RS485 loop cable. Allow provision to run a loop cabling
back to the main hospital panel located behind reception in the main building. A network
connection will enable the panel to be monitored from other locations on the Rotorua Hospital
Site.
We propose that the FENZ attendance point be at the front of the building on the eastern
elevation, adjacent to the sprinkler valve room. From the attendance point FENZ will have access
the main building entry and the inlets to the sprinkler system. Access to the attendance point is
from Rangiuru Street, via an existing internal road.
• Type 7 - Automatic sprinkler and fire alarm systems to NZS 4541:2020 & NZS 4512 :2021.
• Type 9 – Smoke control on air handing systems, the shutdown maybe either zonal or
complete shutdown. Detectors will be located on the supply side of the AHU’s. A sprinkler
or manual call point activation will mean a complete shut down, but with smoke detectors
zonal control is possible.
Building importance level shall be considered as IL3 for the purpose the determining the seismic
performance requirements of the system. Provide seismic resilience of all pipework in accordance
with the requirements of section 4.3.12.1 of NZS 4541:2020.
Where requirements here in Section 2 (Specific Scope of Works) are incompatible with those
described by Section 3 (General Scope and Technical Requirements), they shall take precedence
over those described by the latter.
(i) Alert
(ii) Action
(iii) Fire 1
(iv) Fire 2
(v) Flow Fault (system blockage)
(l) Provide evacuation low level speakers & strobes throughout patient areas in
accordance with NZS 4512.
(m) Dual strobes will be provided throughout, as per other parts of the site. ‘Amber’ strobes
will be used for Alert , with ‘Red’ strobe for evacuation. ”
(n) Provide evacuation speakers / strobes and manual call points to public areas,
consideration should be given for protective covers to MCP.
(o) Provide addressable smoke detectors to the common patient areas, with approved
protective covers (STI) in patient areas. Protective covers are not proposed in public
areas.
(p) All cables shall be concealed and supported on catenary wires in accordance with
good trade practice. Where cabling cannot be concealed, it shall be located within
steel conduits.
(q) Coordinate route of alarm loop cabling from main hospital to ensure ducting
provisions are provided.
(r) FENZ approval is required for the location of the fire alarm index
(s) Connect the FACP to the ATD within sprinkler valve room
(t) Obtain/provide FENZ’s written agreement for index layout.
(u) Provide a fireman’s push-to-talk hand-held microphone at the main fire alarm panel.
(v) Ceiling mounted devices shall not be fixed directly into the plasterboard ceilings or
ceiling tiles. An oversized backing plate of at least 9 mm thick plywood shall be
placed above each device to be screw fixed through the ceiling material. The backing
plate shall be provided by this trade. Where provided in tiled ceilings the backing
plate shall span between the ceiling tee rails. Backing plates shall be provided for all
detectors, sounders and strobes. Provide samples for approval prior to commencing
installation.
(w) Provide suitable interface to automatically OPEN final exit doors should they be fitted
with magnetic clamps, coordinate with mechanical trade to terminate fire signal at
door actuator/controller
(x) Provide uniquely addressed fire alarm interface for each of the following: coordinate
with respective trades to terminate at locations local to their equipment, and discuss
interface details - provide to suit
Sampling Zone
Protected Area Number of rooms
Device
A A-1 IPC Rooms (1 – 5) 5
A A-2 MHSOP Cluster 5
Rooms 6-9 & 20)
B B-1 Flexi-Bed Cluster 3
(Rooms 10 – 12)
B B-2 Flexi-Bed Cluster 3
(Rooms 13 – 15)
B B-3 Flexi-Bed Cluster 3
Shell (Rooms 16 – 18)
B B-4 Room 19 1
C C-1 Seclusion Room 1
(z) Aspirating sampling heads to be located in a secure location (ceiling space), near the
protected area to reduce transport times. Provide remote display units for each
sampling head to be located in the first floor plantroom adjacent to the FACP.
Alterative sampling devices configurations will be considered.
(aa) Allow for attendance at acceptance testing, to demonstrate system operation.
Acceptance testing will only take place once the complete system has been successful
commissioning and results have been submitted to the engineer for review.
2.8 Compliance
All fire protection installations covered by this specification shall comply with the relevant sections
of the NZ Building Code and all applicable NZ Standards.
2 Whilst the responsibilities for interface works and division of works resides with the
respective Trade Contractors the following information is provided for guidance only.
3 The Head Contractor has full control to alter and modify the trade allocation/demarcation of
interface works to suit the Head Contractor’s overall programme and delivery methodology
in order to achieve a fully integrated, interfaced and operational whole services installations,
systems and sub-systems.
(b) A cesspit drain inside the SVR to receive a flow of 1500 l/min (150 mm diameter
minimum) for final discharge to storm-water.
(c) Coordination around all other underground services
(d) Underground connection from SVR to Mauri Ora Building.
Depending on the Specific Scope of Works description (i.e. Section 2), some of the sub-sections
below may not be relevant, e.g. section-3.2.2, Not used is not applicable if no pre-action sprinkler
system is described in Section 2.
Systems or equipment not included within the original contract scope but subsequently
introduced as a variation to the contract shall be subject to the conditions contained within this
section, where relevant.
(c) Provide sampling nozzles and capillary tubes, where suspended ceilings are installed
(d) Provide separate zones for:
(i) Arrange sampling pipe network to provide optimum efficiency with a time for
the least favourable sampling point in the system not to exceed 60 seconds,
unless specified differently by the standard
(ii) Balance the volume of air drawn from the last sampling point to be less than
60% of the volume from the first sampling points
(iii) Submit details of the pipework design showing the proposed layout supported
by calculations showing response times and balance details of each sampling
point
(iv) Make all changes of direction with long radius ‘lazy’ bends
(v) Fit the far end of each trunk or branch pipe with an end cap drilled with a hole
or holes normally of 6 mm diameter, or otherwise appropriately sized to
achieve the performance as specified and as calculated by the system design;
to terminate within a flush box positioned no higher than 1.5 m AFFL
(vi) Seal all joints airtight using solvent cement, except at entry to enclosure
(vii) Support all pipework at no less than 2000 mm centres
3.1.18 Strobes
(a) To be provided/distributed so that
(b) UL or LPCB listed for life-safety
(c) Flashing at 1 Hz over the strobe’s entire operating voltage range
(d) Synchronised to flash simultaneously within the same evacuation zone
(e) Wall mounted unless otherwise specified
(f) When specified with integrated with built-in chime, with selectable tone/volume
(g) Tamper resistant
(i) Normal
(ii) Open
(iii) Short-circuit
(b) Select and configure suitable type to support the required operation/function
(c) Provide a dedicated alarm device address for each interface; do not group as a
common signal across multiple components, unless explicitly described, e.g. the
control of several common-mode motorised dampers via a single interface at the MCC
(d) Control circuits under fire condition shall generally be arranged to energise auxiliary
relays with voltage free normally open contacts to close
(e) House the module within enclosure incorporating bi-colour LED
(f) Include permanent label on enclosure to indicate function and device address
(g) Position interface/housing at easily accessible locations remotely, i.e. local to the
interfaced component (e.g. MCC)
(i) The concealed spaces shall NOT be subdivided by fire separations having an
FRR of -/30/30
(ii) The concealed spaces shall be partially constructed of, or contain, combustible
materials
(h) Each individual sprinkler zone shall be provided with an isolation valve and flow switch,
incorporating a serviceable zone check valve
(i) Each tail-end system shall be installed with an upstream stop valve and flow switch;
include NO downstream stop valve to facilitate testing
(j) Provide a tundish to receive the test drain discharge at each test drain location, and
include downstream pipework to connect into the plumber-installed drain at the
bottom of the riser
(k) Wet pipes shall be positioned to avoid passing through spaces protected by dry-pipe
systems
(l) In rack sprinklers shall be provided with isolation valves @ 1.5 m AFFL
(m) Review architectural and services drawings and provide external sprinklers as required
by the standard
(n) Use only non-ferrite material/component for installation with Faraday cages
(o) When omitting sprinklers from fume cupboards, include any additional requirements
prescribed by the SSC, e.g. ceiling voids containing plastic extract ductwork shall be
classified as OH3
(p) Where sprinkler positions are shown on the drawings, they should be supplemented
with additional sprinklers (at no additional cost to the contract) as required to comply
with the standard
(q) Do not use oversized escutcheons unless approved by the Architect
(r) Base-build shell-only construction (including tenancy spaces without suspended
ceiling) shall include the following:
(i) First fix sprinklers designed and spaced in accordance with OH3, unless space
has been clearly designated for general office use
(ii) Include 25 mm dia. plugged tees spaced in a grid measuring approximately 3
m x 3.6 m, for future connection of flexible droppers
3.2.3 Sprinklers
(a) Select to reflect the performance requirements for the installed/protected area,
including compatibility with system flow and pressure performance
(b) Corrosion resistant construction (i.e. tested to UL 199) for external, humid or corrosive
atmospheres, present or anticipated
(c) Fast response quartzoid bulb type unless specified otherwise
(d) Provide galvanised wire guards to sprinklers where subject to damage, i.e. as a
minimum to all plant spaces, risers, cupboards and where less than 2.2 m AFFL
(e) Install in upright position in areas without suspended ceiling, unless compliance to the
standard is not achieved
(f) Sprinkler location shall be central in square or rectangular ceiling tiles; seek Architect’s
design review before finalising layouts in unusual ceilings
(g) Ceiling sprinklers shall generally be semi recessed and finished in white with matching
escutcheons; alternatively, provide as described below.
(i) flush concealed with where specified, e.g. as indicated on the Architectural
drawings; include silicone seals for cleanroom/equivalent environment
(ii) stainless steel sprinkler construction (including matching escutcheon/cover) for
food production facilities, and laboratories where corrosive disinfectant are
expected
(iii) Raven/equivalent institutional sprinklers where anti-ligature fittings have been
specified
(iv) Sprinklers with single piece escutcheons shall be installed for fire rated ceilings,
or where ceiling penetration details dictates
(h) Kitchen hood and extract duct sprinkler shall be of stainless steel construction, with its
temperature rating appropriately selected to suit appliance selection
(i) Dry barrel sprinklers
3.6 Pump-set
(i) Switch position of ‘red’ (on), ‘green’ (off) and ‘amber’ (non- running fault)
(ii) Use pump set battery power for ‘red’ LED to record operation through pump
pressure switches
(iii) Use pump set battery power for ‘green’ LED operating through auxiliary relays
on the pump starter
(c) Supervise the pressure switch via the fire alarm panel to indicate FAULT condition
when pump fails to run
(d) Incorporate local ‘sonalert’ audible alarm to activate when in the ‘off’ position with:
(e) Provide hard-wired interface to the local controller to run the room ventilation fans,
etc, i.e. to force fan operation when pump runs
3.8.1 General
(a) Generally comply with the standard relevant to the system, in addition to the
requirements described herein
(b) Route all pipework so that they are concealed within ceiling/roof void; any exceptions
will have to be agreed/approved by the Architect only when no reasonable/practical
option is available
(c) Where pipe routes are shown on the drawings, they have been approximately
positioned in coordination with other trades to avoid clashes, and/or to suit the
Architect’s design intent where exposed; refer structural drawings and use beam
penetrations where provided
(d) Provide flexible stainless steel braided pipe connectors at pipe crossing across all
structural seismic separations
(e) Pipe hangars and supports shall be of hot dipped galvanized throughout
(f) Include protection against freezing for water-filled sections exposed to those
conditions
(g) Configure pipe route as shown on the drawings and the, mainly for the purpose of
coordination
(h) Provide suitable identification for all pipework at intervals not exceeding 10m,
including all concealed sections of pipework
(i) Clearances between the pipework and the structure shall generally be at least:
(j) Take particular care to clean out all piping before, during and after erection
(k) Take every precaution to prevent metal cuttings, turning and other debris from being
left in the pipes, and be responsible for any damage caused; cap open ends of
pipework while work is in progress
(l) Flush out piping systems prior to putting them into operation and clean out all
strainers
(m) Co-ordination with other services
(i) All piping arrangements shall be shown in detail on construction drawings and
reviewed in general detail prior to commencement of installation
(ii) Allow for co-ordination with light fittings, structure, plumbing and other services
(iii) The construction drawings shall indicate the sizes of pipes and the manner in
which the various systems are to be installed
(i) Light wall steel pipe and CPVC pipe and fittings shall not be used without
approval
(ii) AS 1074 for steel piping, medium weight grade as a minimum
(iii) AS 1432 for copper piping, Grade ‘B’ as a minimum
(i) UL listed
(ii) Stainless steel flexible hose, with stainless steel braided sheath
(iii) Welded collar
(iv) Flanged ends
Design
Pipework Pipework material Fitting type working
pressure (kPa)
Sprinkler See conditions/standards Roll grooved or welded, with 1200
(exposed) cited above. threaded joints also acceptable
Steel pipe with galvanised for pipe diameters below 50 mm.
coating having at least 300 Welding allowed only on black-
g/m2 zinc over internal and steel joints/fittings, and
external pipe surface. subsequently galvanized
Sprinkler PE100 SDR11 Electrofusion 1200
(buried) NZS 4130:2018
Design
Pipework Pipework material Fitting type working
pressure (kPa)
Hydrant See conditions/standards Roll grooved or welded; welding 1200
(exposed) cited above. allowed only on black steel
Steel pipe with galvanised joints/fittings, and subsequently
coating having at least 300 galvanized.
g/m2 zinc over internal and Mechanical coupling shall be
external pipe surface. ductile iron, hot dipped
galvanized to ASTM-A153; use
only stainless-steel nuts/bolts.
Hydrant PE100 SDR11 Electrofusion 1200
(buried) NZS 4130:2018
(i) Screwed fittings of malleable cast iron, as specified in BS 143 and BS 1256 may
be used; alternatively, JIS B2301 complies
(ii) Cut the ends of steel pipe, square to axis and remove all burrs before screwing
with taper threads to the tolerance specified in BS 21; remove all chips, dirt and
oil
(iii) No joints shall occur within the thickness of a floor, wall or ceiling
(i) Welded fittings shall be wrought carbon steel butt-welding type as specified in
either BS 1965 Part 1, BS 1640 Part 3 or JIS B2311
(ii) On site welding shall not be permitted without the written permission of the
Engineer
(i) Flanges shall be suitable for the pressure to which they will be subjected and as
specified in BS 4504
(ii) Use approved rubber gaskets dimensioned in accordance with BS 4865 Part 1
(vi) Standardise jointing methods for all pipework, unless otherwise specified
elsewhere
(vii) Provide support within 1000 mm either side of a rolled groove type fitting
(viii) Do not use explosive type fixings
(i) Gear operated, butterfly type (except where prohibited by the respective
standards), including position indicator
(ii) Includes weather/tamper proof supervisory switch; select suitable model for
NO/NC arrangement.
(iii) Provide individually addressable interface FAS module to each valve; provide
parallel termination if FBA supervision is also required
(iii) Ductile iron body/cover, fabric reinforced diaphragm; drip-tight seal using
resilient disc against the 316 stainless steel seat ring
(iv) Operates as rated under both flow and static conditions
(v) Under static conditions, limit pressure increase on outlet to 50 kPa above set
pressure
(vi) Include factory supplied strainer
(vii) Include visual indicator of valve position
(viii) Each valve assembly shall include a pressure gauge and isolation valve
immediately upstream and downstream of the main valve
(ix) Include a 15 mm dia. pressure relief valve immediately downstream of each
PRV
(x) Include a normally-closed valved bypass for the PRV
(xi) Limit pressure drop through 100mm dia PRV to 50 kPa for a flow of 1800
l/min
(xii) Include permanent tags to indicate pressure settings; settings shall be
adjustable
(i) When installed above ground (whether by the fire trade, or by others) for a
direct connection to the town’s main, its control valves shall be electrically
supervised by the FBA and the FACP; provide 2 pairs of 2.5 mm neutral screen
cable, oversized underground duct and supplementary draw wire/tape
(ii) Coordinate with local water authority for agreement of its location when
connecting directly to the town’s main
(iii) Comply with requirements of Acceptable Solution G12 and those of the local
water authority
(iv) Provide BPU when connecting to potable water supply for hydrant charging
line; include fixed permanent signage
(v) Provide RPZ BPU up stream of sprinkler pipe feed any wet chemical system
installed
(g) Strainer
(i) Full bore Y-type with easily removable stainless steel strainer basket
(ii) Include bleed valve with permanent drain line to waste
(iii) Limit pressure drop to 15 kPa at full flow
(e) Allow for 150 mm roll groove high flow test connection when highest design flow
exceeds 3500 l/min
3.9.1 Painting
(a) Preparation of surfaces
(i) All surfaces shall be prepared by thorough cleaning of all dirt, grease, scale,
welding flux and corrosion in accordance with AS/NZS 2312
(ii) For galvanised surfaces that have been subsequently cut or welded, prime the
affected area with organic zinc rich coating for protection of steel to AS/NZS
2312, two pack or accepted alternative
(iii) Prime/undercoat all surfaces
(iv) Galvanised and non-ferrous surfaces must be etch-primed
(b) Application
(i) Apply the first coat immediately after the substrate preparation and before
contamination of the substrate can occur
(ii) Apply all paint systems in strict accordance with manufacturer’s
recommendations
(iii) Each coat of paint or finish shall be uniform in colour, gloss, thickness and
texture and free of runs, sags or blisters
(c) Finishing
(i) Apply corrosion protection to meet the performance criteria scheduled in the
table below
(ii) Standards of surface preparation procedures and of corrosion treatments are
to meet the specified criteria and the referenced Standards/Codes for the
relevant application
(iii) Surface preparation procedures and coating systems for corrosion protection
are to meet all relevant requirements of the referenced Standards/Codes.
C5-M Very High Class Sa 2½ Blast Cleaning 1st Coat – Organic zinc primer, 75 micron
Marine thick
2nd Coat – polyurethane, 100 micron
thick
Or
Factory applied zinc primer and
thermoset powder coated finish
T Inland Tropical Class Sa 2½ Blast Cleaning One coat inorganic zinc coating, 75
micron thick
Or
zinc or aluminium thermal spray
metallic coating.
C1: Very Low Class Sa 2½ Blast Cleaning 1st Coat – zinc phosphate alkyd primer, 75
micron thick
‘Very thorough’ (commonly
2nd Coat – full gloss alkyd finish, 50
called ‘near white’) blast
micron thick
cleaning which removes
millscale, rust and foreign 3rd Coat – full gloss alkyd finish, 50
particles to the extent that micron thick
only traces remain. Or
Factory applied zinc primer and
thermoset powder coated finish
3.9.4 Application
(a) Apply the first coat immediately after the substrate preparation and before
contamination of the substrate can occur.
(b) Apply all paint systems in strict accordance with manufacturer’s recommendations.
(c) Each coat of paint or finish shall be uniform in colour, gloss, thickness and texture and
free of runs, sags or blisters.
3.9.5 Finishing
(a) Concrete Bases: 2 coats synthetic emulsion paint
(b) Equipment Panels/Switchboards: 2 final coats full gloss enamel
(c) Equipment: Factory spray application
(d) Other surfaces: 2 final coats full gloss enamel
(i) Provide identification to ceiling tile or access panel for servicing to test drain
valves, flow switches, concealed detectors or similar
(ii) Use colour markers of ‘black’ for general servicing and ‘red’ for Code required
identification e.g. concealed detectors
(iii) Use self-adhesive ‘dot’ type markers on ceiling suspension or plastic headed
pins for insertion in ceiling material
3.11 Wiring
(a) Installation shall at least comply with NZS 3000:2018
(b) Use low smoke halogen-free cables
(c) Where fire rating is required, it shall be rated for a minimum of 120 minutes having
classification of WS52W in accordance with AS/NZS 3013
(d) Provide screened cable for audio signals
(e) Provide fire rated cabling for all circuits associated with
(f) Cable containment must allow for the full replacement of a cable with the existing
cables still installed
(g) Cabling systems must be installed to allow for future replacement without requiring
demolition works. Cables buried or cast into concrete are not permitted
(h) A fault in one alarm zone shall not inhibit operation of any other zone
(i) Protect exposed wiring against mechanical damage by having wiring installed in
conduit or on trays; catenary wire support should be used only for concealed spaces
(j) Run parallel to walls and soffit
(k) Data loop outgoing and return paths shall be diverse
(l) Conduits shall be galvanised steel or high-impact uPVC, having a min. diameter of 20
mm
(m) Catenary wire shall be zinc-coated steel with PVC sheath
4 TENDER FORM
WSP NZ LTD
Consulting Engineers
TENDER FORM
for
FIRE SERVICES
at
HNZL – MAURI ORA MENTAL HEALTH UNIIT, ROTORUA
I/We, the undersigned, hereby tender to carry out the complete works in accordance with the
Specification, Drawings, General Conditions of the proposed contract and addenda, for the sum
set out hereunder:
Provisional Sums $
GST: $
Addendum
We, the undersigned, acknowledge having received the following addenda and have incorporated
them in our tender proposal.
SIGNATURE OF TENDERER
COMPANY
ADDRESS
13 $ ..............................
Sub-Total (excluding GST)
$
GST
$
Total INCLUDING GST
$
Experience
Chief Supervisor
Experience
Experience
Experience
ITEM COMPANY
a) …………………………………..
b) …………………………………..
c) …………………………………..
d) …………………………………..
All unit rates shall include all costs including but not limited to costs for supervision,
administration, mark-up, travel, profit and sales tax.
Labour rates and profit margins are used for works not covered by the unit schedule rates.
Item Supply/Install
1. Pipework and Fitting Schedule
20mm dia Black steel tube to AS1074 $............ Per metre
25mm dia Black steel tube to AS1074 $............ Per metre
32mm dia Black steel tube to AS1074 $............ Per metre
40mm dia Black steel tube to AS1074 $............ Per metre
50mm dia Black steel tube to AS1074 $............ Per metre
65mm dia Black steel tube to AS1074 $............ Per metre
80mm dia Black steel tube to AS1074 $............ Per metre
100mm dia Black steel tube to AS1074 $............ Per metre
150mm dia Black steel tube to AS1074 $............ Per metre
20 mm dia Black steel elbow $...................each
25 mm dia Black steel elbow $...................each
32 mm dia Black steel elbow $...................each
40 mm dia Black steel elbow $...................each
50 mm dia Black steel elbow $...................each
65 mm dia Black steel elbow $...................each
80 mm dia Black steel elbow $....................each
100 mm dia Black steel elbow $...................each
150 mm dia Black steel elbow $...................each
100mm dia uPVC $............ Per metre
150mm dia uPVC $............ Per metre
100mm dia uPVC $...................each
150mm dia uPVC $...................each
2. Sprinkler Heads
Below ceiling sprinkler head $...................each
Concealed sprinkler head $...................each
exposed sprinkler head $...................each
3. Valves
150mm dia wet sprinkler alarm valve c/w all $...................each
trim
150mm dia gate valve $...................each
150mm check valve $...................each
65 mm Hydrant landing valve $...................each
150mm sprinkler monitored isolation valve $...................each
Item Supply/Install
4. Fire Alarms/EWIS
Smoke detector $...................each
Heat detector $...................each
100mm recessed cone EWIS speaker $...................each
100mm surface mounted cone EWIS speaker $...................each
EWIS Horn speaker $...................each
Fire Alarms
Rate Per Hour
Normal Time Time x 1½ Time x 2
5 Appendices
5.1 Appendix A – Town’s Main Connection
This following Design Advice had been provided to the Civil Engineer to describe the cross-
responsibilities between the Civil and Fire trade for the Sprinkler town’s main water supply
connection.
The Fire Trade shall be responsible for coordinating with the Civil trade to provide this branch
connection while making sure that requirements prescribed by the sprinkler standard are met;
this includes submission of all related documentation required by the SSC.
The Civil trade will carry out all underground pipework and associated conduits, from the town
main connection to the SVR, and from the SVR to the building. coordinate with the Civil trade to
ensure all necessary provisions are achieved.
Flow tests from an earlier project have been included for reference, to indicate the expected drop
off when water is flowing. The results are from 2017 for a section of watermain in Hinemaru Street.
The fire sub-contractor needs to confirm the water supply prior to starting design. A copy of the
results shall be submitted to the engineer for information.