You are on page 1of 177

DAFTAR SEWA P E R A L A T AN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI 02 2019
HARGA
NO. PERALATAN SATUAN MINIMUM MAKSIMUM
(Rp) (Rp)

1 Dump Truck 3 ton Jam 85,000 100,000

2 Dump Truck 9 ton Jam 110,000 115,000

3 Truk Bak Terbuka Engkel Jam 125,000 130,000

4 Truk Tanki Air Jam 280,000 290,000

5 Bulldozer 100 - 150 hp Jam 675,000 700,000

6 Motor Grader Jam 625,000 640,000


7 Wheel Loader Jam 270,000 280,000

8 Excavator Jam 650,000 660,000

9 Crane 35 ton Jam 550,000 600,000

10 Flat Bed Truck jam 430,000 440,000

11 Baby Roller / Pedestrian Jam 110,000 120,000


12 P.Tire Roller 8 - 10 ton Jam 500,000 550,000

13 Baby Roller jam 40,000 42,000

14 Vibrator Roller self 7 ton Jam 500,000 510,000

15 Pile Driver / Hammer jam 150,000 160,000

16 Water Pump Jam 40,000 42,500

17 Asphalt Sprayer Jam 135,000 140,000

18 Pick Up single cabin Jam 40,000 55,000

19 A M P Jam 5,500,000 5,600,000

20 Asphalt Finisher Jam 340,000 350,000

21 Concrete Vibrator Jam 55,000 60,000

22 Compressor Jam 310,000 320,000

23 Concrete Mixer 0,125m3 Jam 75,000 80,000

24 Concrete Cutter jam 37,500 40,000

25 Stamper Jam 40,000 45,000

26 Genset 5-25kva+bbm Jam 180,000 183,000

27 Alat Pengecat Marka Jam 300,000 310,000


28 Mesin Las jam 180,000 200,000

29 Stone Crusher jam 850,000 900,000

30 Truck Trailler trip 7,250,000 7,400,000


DAFTAR SEWA P E R A L A T AN

EDISI 02 2019

KET.
DAFTAR UPAH PEKERJA

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI 02 2019

HARGA
NO. URAIAN PEKERJA SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
1 Pekerja Hr 80,000 90,000

2 Mandor Hr 125,000 135,000

3 Tukang listrik Hr 120,000 130,000

4 Tukang kayu Hr 120,000 130,000

5 Kep. tk. kayu Hr 130,000 140,000

6 Tukang batu Hr 120,000 130,000

7 Kep. tk. batu Hr 130,000 140,000

8 Tukang besi Hr 125,000 130,000

9 Kep. tk. besi Hr 130,000 140,000

10 T u k a n g c a t Hr 125,000 130,000

11 K e p . t k . c a t Hr 130,000 140,000

12 T u k a n g p l i t u r Hr 130,000 140,000

13 T u k a n g j a l a n Hr 80,000 90,000

14 T u k a n g g a l i Hr 80,000 90,000

15 Tukang masak aspal Hr 80,000 90,000

16 T k . l e i d e n g Hr 130,000 140,000

17 M a s i n i s Hr 175,000 200,000

18 P e m b . M a s i n i s Hr 125,000 150,000

19 P e n j a g a a p i Hr 80,000 90,000

20 P e n j a g a m a l a m Hr 80,000 90,000

21 Sopir Hr 175,000 200,000

22 Pembantu Sopir Hr 100,000 125,000

668638447.xls 177 utk


2,300,000 64,000

92,000

668638447.xls 177 utk


DAFTAR HARGA SATUAN BAHAN BANGUNAN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI 02 2019

HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)

I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 220,000 250,000
Bulat Belah m3 270,000 320,000
Pecah 10/15 m3 280,000 340,000
Pecah 5/7 m3 290,000 350,000
Pecah 3/5 m3 320,000 360,000
2 KERIKIL Timbun m3 180,000 200,000
Sawur / Koral m3 170,000 200,000
Beton 0,5/1 m3 300,000 380,000
Beton 1/2 m3 310,000 390,000
Beton 2/3 m3 310,000 380,000
Biasa m3 240,000 260,000
Tras Giling m3 290,000 320,000
3 BATU BATA ex lokal bh 600 650

4 PASIR Urug m3 160,000 220,000


Pasang m3 340,000 370,000
Beton m3 360,000 380,000
5 TANAH Padas m3 120,000 150,000
Liat m3 120,000 140,000
6 KAPUR Pasang m3 300,000 310,000
Semen Merah m3 200,000 200,000
7 PORTLAND CEMENT
Merk I 40 kg zak 45,000 48,000
Merk I 50 kg zak 58,000 60,000
Merk II 40 kg zak 43,000 46,000
Merk II 50 kg zak 55,000 58,000
Semen Putih 40 kg zak 85,000 90,000
Semen Putih 50 kg zak 95,000 102,000
Semen warna kg 11,000 15,000

II BAHAN PENUTUP ATAP

1 SIRAP (100 lbr) pak 185,000 200,000

2 GENTENG BETON Genteng Beton Warna standard bh 6,400 7,200


Genteng Beton Warna Special bh 9,800 10,500
Genteng Beton Warna Khusus bh 14,800 15,200
Kerpus Beton Warna Standard bh 9,900 11,000
Kerpus Beton Warna Special bh 11,250 13,000
Kerpus Beton Warna Khusus bh 13,200 15,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
3 GENTENG TANAH LIAT
Vlaam/Plentong bh 2,300 2,600
Kodok bh 2,500 3,100
Kodok Glasur bh 4,250 4,350
Nok kerpus Kodok bh 6,500 6,800
Nok kerpus Kodok Glasur bh 8,000 12,000
Plentong super besar 18 bh/m2 bh 5,100 5,350
Nok kerpus plentong super bh 9,000 9,200
4 GENTENG KACA
Vlaam tebal 2 mm bh 13,000 15,000
Vlaam tebal 3 mm bh 15,000 17,000
Kodok tebal 2 mm bh 14,000 15,000
Kodok tebal 3 mm bh 15,000 17,500

5 ASBES GELOMBANG BESAR


. 200 cm X 102 cm X 5 mm bh 85,000 115,000
. 225 cm X 102 cm X 5 mm bh 98,000 125,000
. 250 cm X 102 cm X 5 mm bh 108,000 135,000
. 200 cm X 102 cm X 6 mm bh 120,000 145,000
. 225 cm X 102 cm X 6 mm bh 130,000 155,000
. 250 cm X 102 cm X 6 mm bh 140,000 160,000
Asbes Gelombang Kecil
. 150 cm X 105 cm X 4 mm bh 42,000 55,000
. 180 cm X 105 cm X 4 mm bh 50,500 68,000
. 210 cm X 105 cm X 4 mm bh 59,500 81,000
. 240 cm X 105 cm X 4 mm bh 67,500 96,000
. 270 cm X 105 cm X 4 mm bh 75,000 104,000
. 300 cm X 105 cm X 4 mm bh 84,500 119,000
ONDULINE : 95 cm x 200cm x 0.3mm lbr 160,000 165,000
ONDUVILLA : 40cm x 106 cm x 0,3mm lbr 95,000 105,000
NOK Jabes nok
. Kerpus Genteng bh 31,000 40,000
. Stel Besar bh 44,000 50,000
. Paten Besar bh 43,000 47,000
Nokstel gelombang harflex
. Stel Besar bh 44,000 48,000
. Patent Besar bh 27,000 30,500
. Plat besar bh 50,000 55,000
NOK UNT ONDULINE & ONDUVILLA
Ukuran 50cm x 50 cm x 0,3mm lbr 115,000 125,000
6 ASBES PLAT
. 100cm X 100 cm X 3 mm bh 15,500 17,000
. 100cm X 100 cm X 4 mm bh 16,000 20,000
. 50 cm X 200 cm X 3 mm bh 14,200 15,000
. 40 cm X 200 cm X 3 mm bh 13,800 14,500
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
FIBER PLAT uk. 100cm x 100cm x 4mm lbr 25,000 30,000
unt Plafond uk. 120cm x 240cm x 4mm lbr 75,000 80,000
uk. 122cm x 244cm x 4mm lbr 77,000 85,200
GRC BOARD uk.122cm x 244cm x 5mm lbr 100,000 112,000
uk.122cm x 244cm x 6mm lbr 130,000 135,000
uk.122cm x 244cm x 8mm lbr 199,500 201,500
uk.122cm x 244cm x 10mm lbr 255,000 260,000
7 FIBRE GLASS (JABES)
180 X 92 cm bh 55,000 61,000
200 X 92 cm bh 60,000 66,000
250 X 92 cm bh 68,000 74,000
180 X 105 cm bh 68,000 90,000
210 X 105 cm bh 70,000 105,000
250 X 105 cm bh 80,000 120,000
8 SENG PLAT
BJLS 0,18 lebar 55 cm m' 20,000 24,500
BJLS 0,20 lebar 55 cm m' 22,000 30,000
BJLS 0,28 lebar 55 cm m' 26,000 30,000
BJLS 0,30 lebar 55 cm m' 30,000 36,000
9 SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 43,000 45,000
BJLS 0,20 panjang 180 cm lbr 47,000 55,000
BJLS 0,30 panjang 180 cm lbr 59,000 60,000
BJLS 0,40 panjang 180 cm lbr 69,000 72,000
III . B A H A N K A Y U
1 JATI Papan m3 22,000,000 23,000,000
Balok/pesagen m3 20,000,000 20,500,000
2 KAMPER Papan m3 7,200,000 7,800,000
Balok/pesagen m3 6,100,000 7,500,000
3 KRUING Papan m3 6,250,000 8,800,000
Balok/pesagen m3 5,200,000 6,000,000
4 MERANTI Papan m3 4,800,000 5,700,000
Balok/pesagen m3 4,500,000 5,400,000
5 LANAN Papan m3 3,290,000 3,300,000
Balok/pesagen m3 2,000,000 2,200,000
6 BENGKIRAI Papan m3 8,750,000 10,000,000
Balok/pesagen m3 9,000,000 9,850,000
7 DOLKEN Sedang 8 x 10 x 400 cm bt 21,000 24,000
Kecil 6 x 7 x 400 cm bt 18,000 21,000
Besar 10 x 12 x 400 cm bt 31,000 34,000
Kayu cetakan m3 2,200,000 2,700,000
Kayu bakar m3 150,000 170,000
Bambu bt 12,000 18,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
IV . BAHAN PENUTUP DINDING / LANTAI
1 UBIN (TEGEL BIASA)
PC polos 30 X 30 cm m2 35,000 38,000
20 X 20 cm m2 34,000 37,000
PC warna 30 X 30 cm m2 40,000 48,000
20 X 20 cm m2 39,500 45,000
Teraso 30 X 30 cm m2 52,000 56,000
2 TEGEL PLINT
PC warna 10 X 20 cm bh 5,200 5,500
PC abu-abu 15 x 20 bh 5,100 6,000
3 UBIN PORSELIN
Lokal 11 X 11 putih dos 42,000 43,000
11 X 11 warna dos 45,000 46,000
Lokal 15 X 15 putih dos 45,000 47,500
15 X 15 warna dos 46,000 49,000
4 MOZAIK PORSELIN
10 X 20 cm m2 50,000 72,000
15 X 15 cm m2 55,000 73,000
20 X 20 cm m2 55,000 74,000
20 X 25 cm m2 56,000 74,000

5 Keramik 30 X 30 cm m2 60,000 78,000


20 X 20 cm m2 60,000 76,000
33 x 33 cm m2 60,000 78,000
25 x 25 cm m2 55,000 75,000
15 x 20 cm m2 57,000 75,000
2,250 2,500
6 Parquet Jati m2 270,000 310,000
7 Batu Paros m2 110,000 115,000
8 Batu Tempel Hitam m2 105,000 120,000
9 GRANITO 40 x 40 cm m2 220,000 250,000
30 x 30 cm m2 300,000 320,000
10 Marmer m2 475,000 480,000
V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 36,000 40,000
Ø 20 cm - 100 cm bh 42,000 50,000
Ø 30 cm - 100 cm bh 64,000 80,000
Ø 50 cm - 100 cm bh 125,000 160,000
Ø 60 cm - 100 cm bh 175,000 215,000
Ø 70 cm - 100 cm bh 250,000 265,000
U 10 cm - 100 cm bh 30,000 32,500
U 15 cm - 100 cm bh 35,000 40,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
U 20 cm - 100 cm bh 39,000 45,000
U 30 cm - 100 cm bh 40,000 55,000
U 50 cm - 100 cm bh 65,000 80,000
2 LUBANG ANGIN (ROSTER) PC + PASIR
10 X 20 cm bh 9,000 12,000
20 X 20 cm bh 12,500 16,000
25 X 25 cm bh 16,500 20,000
30 X 30 cm bh 19,000 22,000
15 X 25 cm bh 18,000 20,000
15 X 30 cm bh 20,000 22,000
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 10,000 12,000
besi beton prestress kg 14,000 14,500
besi beton ulir kg 13,200 13,500

2 BESI PLAT Besi Strip kg 14,000 14,250

3 BESI PROFIL Besi Profil kg 14,500 14,750


a BAJA RINGAN
GALVALUME lebar : 7,5cm tebal : 1mm btg 135,000 140,000 panj : 6 m
type CT 75 lebar : 7,5cm tebal : 0.75mm btg 105,000 115,000 panj : 6 m
lebar : 7,5cm tebal : 0,65mm btg 95,000 105,000 panj : 6 m
b type RT 12 tinggi : 3,5 cm, tebal : 0,45mm btg 50,000 62,500 panj : 6 m
type RT 10 tinggi : 3,0 cm, tebal : 0,45mm btg 45,000 55,000 panj : 6 m
c HOLLOW GALVANIS LIPAT
tinggi 2 cm; tebal : 0,3 mm btg 20,000 25,000 panj : 4 m
tinggi 4 cm; tebal : 0,3 mm btg 27,000 30,000 panj : 4 m
4 JARING - JARING BAJA
Diameter 4 - 15 kg 14,000 15,000
Diameter 6 - 15 kg 14,000 16,000
Kawat Bronjong kg 12,500 14,000
5 BESI SIKU L 40 X 40 X 4 btg 133,500 139,200
L 50 X 50 X 5 btg 215,500 217,500
L 60 X 60 X 6 btg 312,000 355,000

6 KAWAT - Ikat beton/bendrat kg 18,000 21,000


- Harmonika 12 X 45 mm m2 20,000 35,000
- Harmonika 12 X 24 mm m2 20,000 21,000
- Harmonika 14 X 30 mm m2 20,000 21,000
- Harmonika 14 X 35 mm m2 25,000 27,500
- Kawat Nyamuk Nylon m2 20,000 25,000
- Kawat Kasa m2 15,000 18,000
- Saringan pasir m2 19,000 20,000
- Kawat loket m2 17,000 18,500
- Kawat duri rol 110,000 140,000
- Kawat bronjong kg 25,000 27,500
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)

VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 28,000 31,000 panjang 4 m
Pipa PVC DN 25 ( ¾" ) AW JIS btg 34,000 36,500 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 45,000 55,000 panjang 4 m
Pipa PVC DN 40 ( 1½" ) btg 56,000 70,000 panjang 4 m
Pipa PVC DN 63 ( 2" ) btg 70,000 105,000 panjang 4 m
Pipa PVC DN 90 ( 3" ) btg 125,000 185,000 panjang 4 m
Pipa PVC DN 110 ( 4" ) btg 270,000 280,000 panjang 4 m
Pipa PVC DN 160 ( 6" ) btg 530,000 550,000 panjang 4 m
Pipa PVC DN 200 ( 8" ) btg 900,000 1,050,000 panjang 4 m
Pipa PVC DN 250 ( 10" ) btg - - panjang 4 m
Pipa PVC DN 315 ( 12" ) btg - - panjang 4 m

2 Pipa Medium A Galvanis - SII


Pipa Medium Galvanis 0,50" btg 155,000 160,000 panjang 6 m
Pipa Medium Galvanis 0,75" btg 195,000 200,000 panjang 6 m
Pipa Medium Galvanis 1" btg 305,000 315,000 panjang 6 m
Pipa Medium Galvanis 1,25" btg 380,000 390,000 panjang 6 m
Pipa Medium Galvanis 1,50" btg 440,000 450,000 panjang 6 m
Pipa Medium Galvanis 2" btg 590,000 602,000 panjang 6 m
Pipa Medium Galvanis 2,50" btg 740,000 752,000 panjang 6 m
Pipa Medium Galvanis 3" btg 970,000 975,000 panjang 6 m
Pipa Medium Galvanis 4" btg 1,425,000 1,430,000 panjang 6 m
Pipa Medium Galvanis 5" btg 1,900,000 1,905,000 panjang 6 m
Pipa Medium Galvanis 6" btg - - panjang 6 m

VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 5,800 6,500
30 X 60 lbr 13,200 14,500
60 X 120 lbr 42,000 46,000
List Kayu Profil m' 4,800 5,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 60,000 68,000
3 HARD BOARD-uk: 4'X 8' lbr 51,000 55,000
GYPROC uk.120cmx240cmx9mm lbr 60,000 65,000
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 65,000 75,000
. 120 X 240 X 3 mm lbr 80,000 95,000
. 90 X 210 X 4 mm lbr 65,000 85,000
. 90 X 210 X 9 mm lbr 115,000 125,000
. 90 X 210 X 12 mm lbr 135,000 170,000
. 90 X 210 X 15 mm lbr 200,000 240,000
. 90 X 210 X 18 mm lbr 295,000 310,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
Tripleks
. 120 X 240 X 3 mm lbr 50,000 65,000
. 120 X 240 X 4 mm lbr 65,000 75,000
. 120 X 240 X 6 mm lbr 75,000 90,000
Multipleks
. 120 X 240 X 9 mm lbr 110,000 160,000
. 120 X 240 X 12 mm lbr 150,000 185,000
. 120 X 240 X 15 mm lbr 190,000 220,000
. 120 X 240 X 18 mm lbr 215,000 265,000
Formika ukuran pintu lbr 70,000 75,000

IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 25,000 30,000
Dempul plamur kg 25,000 30,000
Ambril/amplas lbr 3,500 4,100
Batu Apung kg 50,000 55,000
Cat dasar kg 40,000 42,500
. Emco kg 62,000 68,000
. Yunior 66 (nippon paint) kg 60,000 71,000
- Koas bh 14,000 17,500
. Deculux kg 63,000 75,000
. Siralax ons 15,000 21,000
. Spiritus ltr 13,000 18,000
. Plitur jadi ltr 65,000 65,000

2 TEMBOK
Kalkarium kg 4,500 5,000
Kapur sirih kg 4,250 4,750
Plamur kg 25,000 32,000
Cat Tembok kg 23,000 26,000
Sintex 5 kg 120,000 125,000
Danabride 5 kg 120,000 122,000
Catylac 5 kg 125,000 130,000
Mowilex 2,50 kg 310,000 420,000

3 BESI
Menie kg 25,000 36,000
Cat mengkilat kg 62,000 69,000
Cat kg 40,000 45,000
Thinner A ltr 15,000 20,000
Minyak cat ltr 15,000 20,000
Thinner Super ltr 17,500 35,000
Residu (teer/aspal) drum 55,000 60,000
Fibre glass (tanki air)
kapasitas 550 liter. bh 1,000,000 1,100,000
kapasitas 1100 liter. bh 1,600,000 1,700,000
Lem Aica Aibon kg 55,000 65,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
X.BAHAN KACA
1 POLOS 3 mm m2 75,000 85,000
5 mm m2 90,000 95,000
2 ES KABUR 3 mm m2 75,000 85,000
5 mm m2 88,000 95,000
3 RAY BAND 3 mm m2 75,000 85,000
5 mm m2 85,000 92,000

XI . BAHAN INSTALASI LISTRIK

1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m' 5,000 5,500

SPLN LMK 1 X 2 1/2 mm2 m' 5,500 6,200

. 1X4 mm2 m' 6,500 7,750

1X6 mm2 m' 10,100 11,000

NYY :. 2 X 1 1/2 mm2 m' 11,000 11,500

PRIMA 2 X 2 1/2 mm2 m' 15,500 16,500

. 2X4 mm2 m' 28,000 29,500

2X6 mm2 m' 37,000 39,000

3 X 1 1/2 mm2 m' 14,500 16,700

3 X 2 1/2 mm2 m' 21,000 22,100

3X4 mm2 m' 35,600 39,000

3X6 mm2 m' 50,000 56,000

NYM :. 2 X 1 1/2 mm2 m' 8,000 8,500

PRIMA 2 X 2 1/2 mm2 m' 11,500 12,000

. 2X4 mm2 m' 22,500 24,000

3 X 1 1/2 mm2 m' 13,200 14,500

3 X 2 1/2 mm2 m' 21,050 23,400

3X4 mm2 m' 32,000 36,000

3X6 mm2 m' 45,000 49,000

2 SKAKELAR
Out bauw . Seri bh 20,000 25,000

. Engkel bh 15,000 20,000

In bauw . Seri bh 16,500 25,000

. Engkel bh 14,000 17,500

3 FUSE BOX (SEKERING KASA)


1 group bh 135,000 165,000

2 group bh 245,000 280,000

3 group bh 350,000 395,000

4 STEKER - Biasa bh 10,000 15,000

Arde bh 15,000 17,500

T Biasa bh 12,500 15,500

T dengan Arde bh 17,000 20,000


HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
5 FITING Flaon bh 15,500 25,000

Gantung bh 12,500 20,000

Kap bh 12,500 20,000

Kombinasi bh 25,000 31,000

6 STOP KONTAK - Arde Outbow putih bh 22,000 30,000

Arde Outbow hitam bh 25,000 35,000

Arde IB bh 26,000 40,000

Arde Putar bh 35,000 50,000

XII . ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM Union : 1 X slag bh 100,000 125,000
2 X slag bh 165,000 200,000
Yale : 1 X slag bh 95,000 150,000
2 X slag bh 130,000 170,000
Kuda : 1 X slag bh 70,000 85,000
2 X slag bh 110,000 125,000

2 ENGSEL DAN GERENDEL


Engsel Angin bh 16,000 30,000
Kupu-kupu biasa bh 4,500 6,000
Nylon kupu-kupu bh 7,500 9,000
Espagnoled - dalam negeri bh 40,000 50,000
Grendel Tanam luar negeri bh 11,000 13,000
Grendel biasa bh 8,000 10,000
Kait Angin bh 17,500 20,000
Door Stop bh 275,000 350,000

XIII . BAHAN SANITAIR


1 KLOSET DUDUK bh 1,600,000 1,850,000
2 KLOSET JONGKOK bh 145,000 160,000
3 WASTAFEL PEDESTAL bh 950,000 1,050,000
4 WASTAFEL MEJA OVAL bh 750,000 950,000
5 WASTAFEL GANTUNG BULAT bh 300,000 325,000
6 WASTAFEL GANTUNG SUDUT bh 250,000 310,000
7 WASTAFEL GANTUNG SUDUT KECIL bh 240,000 275,000
8 WASTAFEL BAK CUCI bh 150,000 165,000
9 TEMPAT SABUN GANTUNG bh 45,000 55,000
10 TEMPAT SABUN TANAM bh 22,500 25,000
11 LAIN - LAIN
Kran Air bh 25,000 45,000
Seal tape bh 3,500 4,500
Floor drain bh 35,000 42,500
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
XIV . ALAT PENGIKAT KAYU
1 PAKU - ukuran 1" s/d 4" kg 15,000 17,500
2 PAKU - payung kg 20,000 26,000
3 PAKU - sekrup kg 7,000 8,000
4 PAKU - beton kg 25,000 30,000
5 MUR BAUT (kuda-kuda) kg 13,000 14,000
6 ANGKUR BAUT bh 13,000 13,500
7 LEM KAYU bh 12,500 20,000
8 Tali Ijuk kg 7,000 7,200

XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh 350,000 375,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 975,000 1,100,000
Fuji 250 watt bh 1,450,000 1,650,000
Shimizu . 100 watt bh 470,000 550,000
. 90 watt bh 350,000 425,000
Dab . 125 watt bh 400,000 420,000
. 175 watt bh 425,000 475,000

X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 85,000 90,000
Merah/hitam m2 90,000 95,000
2 HOLLAND Abu-abu m2 85,000 90,000
Merah/hitam m2 90,000 95,000
3 UNIDECOR Abu-abu m2 85,000 90,000
Merah/hitam m2 90,000 95,000
4 UNI Abu-abu m2 85,000 90,000
Merah/hitam m2 90,000 95,000
5 TRIHEX Abu-abu m2 85,000 90,000
Merah/hitam m2 90,000 95,000
6 OLYMPIA HEXA Abu-abu m2 85,000 90,000
7 HEXAGONAL Abu-abu m2 90,000 95,000
Merah/hitam m2 85,000 90,000
8 CASTLE Abu-abu m2 90,000 95,000
9 TRAPEZ Abu-abu m2 85,000 90,000
10 TRAPEZ GRASS BLOCK
Abu-abu m2 85,000 90,000
11 STANDARD GRASS BLOCK ABU-ABU BH 7,500 8,500
12 BATACO BH 4,800 5,500
13 KANSTEEN m' 25,000 30,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
XVII. L A I N - L A I N
1 KREI 25 MM m2 45,000 60,000
2 Sliding Pintu J4 bh 200,000 235,000
3 Naco per Daun bh 37,500 40,000
4 Rolling door Besi m2 325,000 335,000
Rolling door Almunium m2 275,000 290,000
5 Awning Almunium m2 225,000 250,000
6 Kusen Almunium 4" Putih m' 95,000 100,000
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg 1,380,000 1,480,000

8 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum 950,000 1,100,000

Hotmix Tebal = 4 Cm m2 67,500 70,000


Hotmix Tebal = 5 Cm m2 82,000 85,000
Hotmix Tebal = 6 Cm m2 97,000 100,000
Hotmix Tebal = 7 Cm m2 115,000 120,000
Binder Course ton 1,300,000 1,325,000
Wearing Course ton 1,300,000 1,400,000
Hot Roller Sheet ton 1,150,000 1,250,000
Sand Sheet ton 1,200,000 1,250,000
Sand Sheet Emulsi ton 1,450,000 1,500,000
Cold Mix ton 1,800,000 1,850,000
Prime / Tack Coard RC liter 7,200 8,000
Prime Coat MC liter 7,200 8,000
Prime / Tack Coat Emulsi liter 7,200 8,000
10 K A C A
Cermin tebal 5 mm m2 275,000 325,000

11 PAGAR BRC. Pagar BRC 90 A2 /lb 310,000 325,000


Pagar BRC 120 A2 /lb 375,000 390,000
12 LAIN-LAIN
Minyak Beton & bekisting ltr 9,000 10,000
Pintu Lipat Besi m2 400,000 425,000
Sunscreen Allumunim m2 350,000 400,000
Allumunium Foil m2 12,000 15,000
Soda api kg 13,000 15,000
Sabun kg 12,500 15,000
Air m3 20,000 25,000
Koas Alang-alang ikat 2,000 2,500
Solar (Industri) ltr 8,200 8,600
Premium (Industri) ltr 7,050 7,800
Pelumas ltr 39,500 47,000
Vynil 30x30 cm bh 6,200 6,500
DAFTAR HARGA SATUAN PEKERJAAN
BERDASAR PERMEN PUPERA NO.28/PRT/M/2016

SUMBER DATA : PASARAN BEBAS EDISI 02 2019


DAERAH : KOTA SEMARANG DAN SEKITAR

HARGA SATUAN PEKERJAAN


NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi 2,00
1 A.2.2.1.2 m' 600,272.75 691,977.00
m
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 141,212.50 173,827.50

3 A.2.2.1.5 Pembuatan Kantor Sementara dg Lantai Plesteran m2 1,972,217.50 2,228,435.00

4 A.2.2.1.6 Pembuatan Rumah Jaga (Konstruksi Kayu) m2 1,503,975.00 1,717,375.00

5 A.2.2.1.7 Pembuatan Gudang Semen dan Peralatan m2 1,370,393.75 1,581,442.50

6 A.2.2.1.8 Pembuatan Bedeng Pekerja m2 1,732,775.00 1,978,625.00

7 A.2.2.1.9 Membersihkan Lapangan dan Perataan m2 15,675.00 17,325.00

8 A.2.2.1.10 Pembuatan Steger/Perancah dari Bambu m2 405,407.20 449,448.12

9 A.2.2.1.11 Pembuatan Kotak Adukan ukuran 40cmx50cmx25cm bh 498,630.00 635,140.00

10 A.2.2.1.12 Pembuatan Jalan Sementara m2 165,687.50 191,262.50

11 A.2.2.1.13 Bongkaran Beton Bertulang m3 1,264,967.00 1,418,967.00

12 A.2.2.1.14 Bongkaran Dinding Tembok Bata Merah m3 591,233.50 664,933.50

13 A.2.2.1.15 Pagar Kawat Jaring Galvanis Panjang 240 cm m2 59,184.40 62,540.50


Pemasangan Pagar Panel Beton Pracetak 5 x 50 x
14 A.2.2.1.16 m2 313,538.50 346,453.25
240 cm

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m m3 69,437.50 77,962.50

2 A.2.3.1.2 Menggali Tanah Biasa Sedalam 2 m m3 85,387.50 95,782.50

3 A.2.3.1.3 Menggali Tanah Biasa Sedalam 3 m m3 101,612.50 113,899.50

4 A.2.3.1.4 Menggali Tanah Keras Sedalam 1 m m3 92,400.00 103,752.00

5 A.2.3.1.5 Menggali Tanah Cadas Sedalam 1 m m3 140,250.00 157,410.00

6 A.2.3.1.6 Menggali Tanah Lumpur Sedalam 1 m m3 111,787.50 125,482.50

7 A.2.3.1.7 Mengerjakan Striping Tebing Setinggi 1 m m2 5,087.50 5,692.50

8 A.2.3.1.8 MembuangTanah sejauh 30 m' m3 30,415.00 34,155.00


Pengurugan Kembali di hitung dari 1/3 kali koefisien
9 A.2.3.1.9 m3 16,958.33 18,975.00
Pekerjaan galian
10 A.2.3.1.10 Pemadatan Tanah (per 20 cm) m3 50,875.00 56,925.00

11 A.2.3.1.11 Urugan Pasir m3 238,975.00 321,585.00

12 A.2.3.1.12 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL m3 447,546.00 491,777.00

Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang


13 A.2.3.1.13 m2 61,462.50 64,597.50
Resapan

14 A.2.3.1.14 Mengurug Sirtu Padat m3 263,037.50 292,462.50

668638447.xls 177/16 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP m3 1,053,002.50 1,191,272.50

2 A.3.2.1.2 Pemasangan Pondasi Batu Belah 1SP : 4 PP m3 1,017,830.00 1,154,037.50

3 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP m3 993,393.50 1,128,165.50


4 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 976,239.00 1,110,004.50

5 A.3.2.1.5 Pemasangan Pondasi Batu Belah 1SP : 8 PP m3 952,666.00 1,085,045.50

6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 842,297.50 960,987.50
Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10
7 A.3.2.1.7 m3 929,643.00 1,058,128.50
PP
Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4
8 A.3.2.1.8 m3 911,207.00 1,038,889.50
PP
9 A.3.2.1.9 Pemasang Batu Kosong/Anstamping m3 576,691.50 698,131.50

Pasang Pondasi Siklop, 60% Beton Campuran 1PC :


10 A.3.2.1.10 m3 2,500,839.00 2,898,159.00
2PB : 3KR & 40% Batu Belah

11 A.3.2.1.11 Pasang Pondasi Sumuran diameter 100 cm m3 970,381.50 1,070,635.50

IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Membuat Beton mutu f'c=7,4 Mpa (K100), slum


1 A.4.1.1.1 m3 1,005,451.86 1,120,043.57
(12±2)cm, w/c = 0,87

Membuat Beton mutu f'c=9,8 Mpa (K125), slum


2 A.4.1.1.2 m3 1,033,025.92 1,150,107.33
(12±2)cm, w/c = 0,78

Membuat Beton mutu f'c=12,2 Mpa (K150), slum


3 A.4.1.1.3 m3 1,054,548.52 1,173,356.90
(12±2)cm, w/c = 0,72

Membuat Lantai Kerja Beton mutu f'c=7,4 MPa


4 A.4.1.1.4 m3 936,714.02 1,045,084.92
(K100), slum (3-6)cm, w/c = 0,87

Membuat Beton mutu f'c=14,5 MPa (K175), slum


5 A.4.1.1.5 m3 1,079,960.71 1,201,068.17
(12±2)cm, w/c = 0,66

Membuat Beton mutu f'c=16,9 MPa (K200), slum


6 A.4.1.1.6 m3 1,104,438.03 1,227,348.86
(12±2)cm, w/c = 0,61

Membuat Beton mutu f'c=19,3 MPa (K225), slum


7 A.4.1.1.7 m3 1,122,657.73 1,247,530.08
(12±2)cm, w/c = 0,58

Membuat Beton mutu f'c=21,7 MPa (K250), slum


8 A.4.1.1.8 m3 1,135,027.35 1,260,421.61
(12±2)cm, w/c = 0,56

Membuat Lantai Kerja Beton mutu f'c=24,0 MPa


9 A.4.1.1.9 m3 1,156,705.79 1,283,047.86
(K275), slum (12±2)cm, w/c = 0,53

Membuat Beton mutu f'c=26,4 MPa (K300), slum


10 A.4.1.1.10 m3 1,163,256.75 1,289,843.99
(12±2)cm, w/c = 0,52

Membuat Beton mutu f'c=28,8 MPa (K325), slum


11 A.4.1.1.11 m3 1,242,057.43 1,375,855.26
(12±2)cm, w/c = 0,49

Membuat Beton mutu f'c=31,2 MPa (K350), slum


12 A.4.1.1.12 m3 1,250,830.81 1,384,981.77
(12±2)cm, w/c = 0,48

668638447.xls 177/17 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
13 A.4.1.1.17 Pembesian dg Besi Polos atau Besi Ulir Kg 13,542.10 16,067.70

14 A.4.1.1.18 Kabel Presstresed Polos/strand Kg 17,580.75 18,310.05

15 A.4.1.1.19 Jaring Kawat baja/Wire Mesh Kg 28,741.35 31,621.15

16 A.4.1.1.20 Memasang Bekisting untuk Pondasi m2 181,313.00 200,200.00


17 A.4.1.1.21 Memasang Bekisting untuk Sloof m2 192,313.00 212,300.00

18 A.4.1.1.22 Memasang Bekisting untuk Kolom m2 381,826.50 442,612.50

19 A.4.1.1.23 Memasang Bekisting untuk Balok m2 398,986.50 462,412.50

20 A.4.1.1.24 Memasang Bekisting untuk Lantai m2 474,226.50 548,212.50

21 A.4.1.1.25 Memasang Bekisting untuk Dinding m2 433,526.50 502,012.50

22 A.4.1.1.26 Memasang Bekisting untuk Tangga m2 359,331.50 417,862.50

23 A.4.1.1.27 Memasang Jembatan Cor m2 101,145.00 112,596.00

24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 85,772.50 97,460.00

25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 110,305.25 124,239.50

IV A A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK

Pembuatan Lahan Produksi Tebal 8 cm Beton f'c


1 A.4.1.2.1 m2 86,412.04 96,101.95
14,5 Mpa, Slump (120 ± 20) mm K3

Pembuatan Lahan Produksi Tebal 10 cm Beton f'c =


2 A.4.1.2.2 m2 108,049.42 120,164.57
14,5 Mpa slum (120 ± 20 ) mm K3

Pembuatan Lahan Produksi Tebal 12 cm Beton


3 A.4.1.2.3 m2 126,645.30 140,811.68
f'c=14,5 Mpa, slum (120±20)mm, K3

Pembuatan Lahan Produksi Tebal 15 cm Beton


4 A.4.1.2.4 m2 162,052.13 180,224.85
f'c=14,5 Mpa, slum (120±20)mm, K3

Pembuatan Bekisting untuk Plat Beton Pra cetak (5


5 A.4.1.2.5 m2 119,707.91 131,896.01
kali Pakai)

Pembuatan Bekisting untuk Balok Beton Pra cetak


6 A.4.1.2.6 m2 40,776.00 45,914.60
(10 - 12 kali Pakai)

Pembuatan Bekisting untuk Kolom Beton Pra cetak


7 A.4.1.2.7 m2 36,201.00 40,564.60
(10 - 12 kali Pakai)

Pemasangan dan Membuka Bekisting untuk


8 A.4.1.2.8 bh 7,025.00 7,785.00
Komponen Plat Beton Pracetak

Pemasangan dan Membuka Bekisting untuk


9 A.4.1.2.9 bh 11,345.00 12,585.00
Komponen Balok Beton Pracetak

Pemasangan dan Membuka Bekisting untuk


10 A.4.1.2.10 bh 9,185.00 10,185.00
Komponen Kolom Beton Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


11 A.4.1.2.11 m3 69,635.50 68,735.00
Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


12 A.4.1.2.12 m3 71,560.50 70,645.00
Pracetak

Penuangan / Menebar Beton untuk Komponen


13 A.4.1.2.13 m3 64,344.50 63,515.00
Kolom Pracetak

668638447.xls 177/18 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
14 A.4.1.2.14 Ereksi Komponen Untuk Plat Pracetak bh 582,822.02 608,545.96

15 A.4.1.2.15 Ereksi Komponen Untuk Balok Pracetak bh 572,865.70 597,845.60

16 A.4.1.2.16 Ereksi Komponen Untuk Kolom Pracetak bh 823,379.04 864,459.42

17 A.4.1.2.17 Langsiran Komponen untuk Plat Pracetak (± 20 m) bh 157,399.44 164,718.62

18 A.4.1.2.18 Langsiran Komponen untuk Balok Pracetak (± 20 m) bh 125,059.44 128,715.62

19 A.4.1.2.19 Langsiran Komponen untuk Kolom Pracetak (± 20 m) bh 125,059.44 128,715.62

20 A.4.1.2.20 Bahan Grout Campuran m3 3,417,700.00 3,689,125.00

21 A.4.1.2.21 Bahan Grout Campuran (tidak Campuran) m3 3,061,300.00 3,368,750.00


22 A.4.1.2.22 Upah Pekerjaan Gruot pada Joint Beton Pra Cetak ttk 64,113.50 69,371.50

23 A.4.1.2.23 Pemasangan Bekisting Joint Pra Cetak ttk 117,848.50 134,788.50

24 A.4.1.2.24 Upah Pemasangan Joint dengan Sling ttk 52,816.50 58,019.50

HARGA SATUAN PEKERJAAN BESI &


V A.4.2.1
ALLUMUNIUM
1 A.4.2.1.1 Pemasangan Besi Profil Kg 32,813.00 34,548.25

2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF Kg 26,741.00 28,033.50

3 A.4.2.1.3 Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) kg 102,195.50 118,926.50

Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap,


4 A.4.2.1.4 m2 921,360.00 953,832.00
rangka baja Siku

5 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik cm 2,361.04 2,738.56

6 A.4.2.1.6 Pembuatan Rangka Jendela Besi Scuare Tube m2 249,740.48 281,136.02

7 A.4.2.1.7 Pemasangan Pintu Rolling Door Besi m2 639,485.00 678,271.00

8 A.4.2.1.8 Pemasangan Pintu Lipat (Folding Door) m2 546,117.00 584,023.00

9 A.4.2.1.9 Pemasangan Sunscreen Allumunium m2 509,630.00 575,234.00

10 A.4.2.1.10 Pemasangan Rolling Door Allumunium m2 543,675.00 583,825.00


11 A.4.2.1.11 Pemasangan Kusen Pintu Allumunium m' 130,263.65 138,100.05

12 A.4.2.1.12 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 552,563.00 586,802.70

13 A.4.2.1.13 Pemasangan Pintu Kaca Rangka Allumunium m2 520,074.50 554,218.50

14 A.4.2.1.14 Pemasangan Venetions Blinds & Vertical Blinds m2 188,980.00 202,763.00

15 A.4.2.1.15 Pemasangan Teralis Besi Strip (2x3) cm m2 568,149.96 620,584.20

16 A.4.2.1.16 Pemasangan Kawat Nyamuk m2 103,598.17 117,098.74

17 A.4.2.1.17 Pemasangan Jendela Nako & Tralis m2 136,372.50 148,978.50

Pemasangan Talang Datar / Jurai , Seng BJLS 28


18 A.4.2.1.18 m' 199,017.50 230,051.25
Lebar 90 cm

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


19 A.4.2.1.20 m2 121,962.50 131,730.50
Modul 60x120 cm dinding partisi

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


20 A.4.2.1.21 m2 154,880.00 167,563.00
Modul 60x60 cm dinding plafond

668638447.xls 177/19 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Atap Pelana Rangka Atap Baja Canal
21 A.4.2.1.22 m2 240,559.28 259,013.01
C dingin Profil C75

Pemasangan Atap Jurai Rangka Atap Baja Canal


22 A.4.2.1.23 m2 267,357.75 286,788.43
Dingin Profil C75

HARGA SATUAN PEKERJAAN PASANGAN


VI A.4.4.1
DINDING

Pemasangan Dinding Bata Merah ukuran (5x11x22)


1 A.4.4.1.1 m2 262,336.25 285,615.00
cm Tebal 1 bata Camp. 1SP: 2PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


2 A.4.4.1.2 m2 253,394.63 276,166.00
cm Tebal 1 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


3 A.4.4.1.3 m2 246,222.63 268,532.00
cm Tebal 1 Bata Camp. 1SP : 4PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


4 A.4.4.1.4 m2 244,205.50 266,453.00
cm Tebal 1 Bata Camp. 1SP : 5PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


5 A.4.4.1.5 m2 247,106.75 269,709.00
cm Tebal 1 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


6 A.4.4.1.6 m2 234,729.00 255,965.60
cm Tebal 1 Bata Camp. 1SP : 3 KP :10PP

Pemasangan Dinding Bata Merah Ukuran


7 A.4.4.1.7 m2 126,955.13 138,297.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP

Pemasangan Dinding Bata Merah Ukuran


8 A.4.4.1.8 m2 122,035.38 133,065.90
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran


9 A.4.4.1.9 m2 119,605.75 130,498.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP

Pemasangan Dinding Bata Merah Ukuran


10 A.4.4.1.10 m2 118,101.50 128,910.10
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP

Pemasangan Dinding Bata Merah Ukuran


11 A.4.4.1.11 m2 117,914.50 128,742.90
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran


12 A.4.4.1.12 m2 116,036.25 126,747.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
Pemasangan Dinding Bata Merah Ukuran
13 A.4.4.1.13 (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : m2 118,511.25 129,222.50
10PP
Pemasangan Dinding Bata Merah Ukuran
14 A.4.4.1.14 m2 105,924.50 115,241.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP

Pemasangan Dinding Bata Merah Ukuran


15 A.4.4.1.15 m2 107,464.50 117,067.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SM : 1KP : 2PP

Pemasangan Dinding HB/CB 20, speci camp. 1SP :


16 A.4.4.1.16 m2 423,093.00 459,534.90
3PP

Pemasangan Dinding HB/CB 20, speci camp. 1SP :


17 A.4.4.1.17 m2 432,049.75 469,443.70
4PP

Pemasangan Dinding HB/CB 15, speci camp. 1SP :


18 A.4.4.1.18 m2 332,961.75 361,501.80
3PP

668638447.xls 177/20 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Dinding HB/CB 15, speci camp. 1SP :
19 A.4.4.1.19 m2 339,311.50 368,533.00
4PP

Pemasangan Dinding HB/CB 10, speci camp. 1SP :


20 A.4.4.1.20 m2 267,069.00 295,247.70
3PP

Pemasangan Dinding HB/CB 10, speci camp. 1SP :


21 A.4.4.1.21 m2 272,295.38 301,016.10
4PP

Pemasangan Dinding Terawang (Rooster) Uk,


22 A.4.4.1.22 m2 366,795.00 472,532.50
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Terawang (Rooster) Uk,


23 A.4.4.1.23 m2 366,795.00 472,532.50
(12x11x24)cm Camp. 1SP : 4PP

Pemasangan Dinding Bata Berongga Ekspose Uk,


24 A.4.4.1.24 m2 149,385.50 160,121.50
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Bata Ringan Tebal 7,5 cm


25 A.4.4.1.25 m2 308,711.04 333,949.06
dengan Mortar Siap Pakai

Pemasangan Dinding Bata Ringan Tebal 10 cm


26 A.4.4.1.26 m2 309,274.24 332,520.71
dengan Mortar Siap Pakai

VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

1 A.4.4.2.1 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm m2 75,577.70 82,664.78

2 A.4.4.2.2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm m2 70,539.70 77,323.18

3 A.4.4.2.3 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm m2 68,632.30 75,312.82

4 A.4.4.2.4 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm m2 67,105.50 73,692.30

5 A.4.4.2.5 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm m2 66,546.70 73,112.38

6 A.4.4.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 65,970.30 72,505.62

7 A.4.4.2.7 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm m2 65,750.30 72,279.02

8 A.4.4.2.8 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm m2 65,530.30 72,052.42

Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15


9 A.4.4.2.9 m2 64,691.00 71,238.20
mm

Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15


10 A.4.4.2.10 m2 64,553.50 71,126.00
mm

Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15


11 A.4.4.2.11 m2 60,027.00 66,033.00
mm

Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15


12 A.4.4.2.12 m2 61,171.00 67,353.00
mm

13 A.4.4.2.13 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm m2 94,452.60 103,530.24

14 A.4.4.2.14 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm m2 71,229.00 77,866.60

15 A.4.4.2.15 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm m2 89,749.00 98,553.40

16 A.4.4.2.16 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm m2 89,128.60 97,915.84

17 A.4.4.2.17 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm m2 88,235.40 96,971.16

668638447.xls 177/21 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20
18 A.4.4.2.18 m2 85,613.00 94,050.00
mm

19 A.4.4.2.19 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm m2 41,483.20 45,419.88

Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10


20 A.4.4.2.20 m' 71,590.75 77,825.00
mm

Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal


21 A.4.4.2.21 m' 104,626.50 115,032.50
10 mm

Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10


22 A.4.4.2.22 m' 104,626.50 115,032.50
mm

23 A.4.4.2.23 Pemasangan Plesteran Ciprat 1Pc : 2 Pp m2 50,682.50 55,911.90

Pemasangan Finishing Siar Pasangan Dinding Bata


24 A.4.4.2.24 m2 29,190.15 32,097.56
Merah

Pemasangan Finishing Siar Pasangan Dinding


25 A.4.4.2.25 m2 13,882.00 15,257.00
Conblock ekspose

Pemasangan Finishing Siar Pas.Batu Kali Adukan


26 A.4.4.2.26 m2 62,741.25 68,940.30
1Pc : 2Pp

27 A.4.4.2.27 Pemasangan Acian m2 37,626.88 41,415.00

28 A.4.4.2.28 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) m2 46,158.20 50,026.90

29 A.4.4.2.29 Pemasangan Acian dg Mortar Siap Pakai (MSP) m2 40,040.00 43,738.75

HARGA SATUAN PEKERJAAN PENUTUP LANTAI


VIII A.4.4.3 dan DINDING

1 A.4.4.3.2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm m2 112,896.50 123,178.50

2 A.4.4.3.3 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm m2 114,851.00 125,455.00

3 A.4.4.3.5 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm m2 138,521.50 161,503.50

4 A.4.4.3.6 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm m2 140,866.00 161,513.00

5 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm m2 354,244.00 403,133.50

6 A.4.4.3.16 Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm m' 69,872.00 78,840.30

7 A.4.4.3.19 Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm m' 40,675.25 44,316.80

8 A.4.4.3.32 Pemasangan Lantai Keramik 10x 20 cm m2 236,157.63 288,390.30

Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20


9 A.4.4.3.33 m2 241,602.63 295,815.30
cm

10 A.4.4.3.34 Pemasangan Lantai Keramik 33 x 33 cm m2 237,517.96 281,126.63

11 A.4.4.3.35 Pemasangan Lantai Keramik 30 x 30 cm m2 236,192.50 278,788.50

12 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm m2 236,879.50 277,326.50

Pemasangan Lantai Keramik uk.10 x 33 cm, untuk


13 A.4.4.3.37 m2 437,426.00 484,500.50
variasi / border

14 A.4.4.3.39 Pemasangan Plint Keramik Ukuran 10x20 cm m' 39,184.75 44,536.80

15 A.4.4.3.40 Pemasangan Plint Keramik Ukuran 10x10 cm m' 85,544.25 91,589.30

668638447.xls 177/22 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
16 A.4.4.3.41 Pemasangan Plint Keramik Ukuran 5x20 cm m' 83,212.25 90,423.30

17 A.4.4.3.43 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm m2 706,297.63 729,468.30

18 A.4.4.3.44 Pemasangan Lantai Karpet m2 206,618.50 220,269.50

19 A.4.4.3.46 Pemasangan Lantai Parquet Jati m2 465,767.50 530,887.50


20 A.4.4.3.48 Pemasangan Dinding Porselen 11 x 11 cm m2 267,994.41 300,209.32

21 A.4.4.3.49 Pemasangan Dinding Porselen 10x20 cm m2 261,038.25 315,991.50

22 A.4.4.3.50 Pemasangan Dinding Porselen 20x20 cm m2 255,857.25 303,330.50

23 A.4.4.3.53 Pemasangan Dinding Keramik 10x20 cm m2 261,038.25 315,991.50

24 A.4.4.3.54 Pemasangan Dinding Keramik 20x20 cm m2 257,067.25 304,958.50


25 A.4.4.3.55 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm m2 805,007.62 838,428.92

Pemasangan Dinding Batu Paros / Batu Tempel


26 A.4.4.3.58 m2 278,348.13 298,842.50
Hitam

27 A.4.4.3.59 Pemasangan Lantai Vynil uk.30 x 30 cm m2 152,684.40 165,335.50

28 A.4.4.3.60 Pemasangan Wallpaper Lebar 50 Cm m2 122,551.00 132,055.00

29 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' 50,391.00 61,699.00

30 A.4.4.3.64 Pemasangan Paving Block Natural Tebal 6 Cm m2 184,324.25 200,459.05

31 A.4.4.3.65 Pemasangan Paving Block Natural Tebal 8 Cm m2 251,699.25 271,068.05


32 A.4.4.3.66 Pemasangan Paving Block Berwarna Tebal 6 Cm m2 196,545.25 212,680.05

33 A.4.4.3.67 Pemasangan Paving Block Berwarna Tebal 8 Cm m2 257,809.75 277,178.55

HARGA SATUAN PEKERJAAN LANGIT-


IX A.4.5.1
LANGIT

Pemasangan Langit-langit Asbes (1,00x1,00) m,


1 A.4.5.1.1 m2 32,351.00 35,414.50
tebal 4 mm, 5 mm & 6 mm

Pemasangan Langit-langit Akustik Ukuran (30x30)


2 A.4.5.1.2 m2 106,326.00 118,541.50
cm

Pemasangan Langit-langit Akustik Ukuran (30x60)


3 A.4.5.1.3 m2 109,158.50 119,955.00
cm

Pemasangan Langit-langit Akustik Ukuran (60x120)


4 A.4.5.1.4 m2 94,242.50 103,345.00
cm

Memasang Langit-langit Tripleks Uk (120x240) cm,


5 A.4.5.1.5 m2 51,425.00 57,997.50
Tebal 3 mm, 4 mm & 6 mm

Memasang Langit-langit Lambriziring Kayu Jati, tebal


6 A.4.5.1.6 m2 556,105.00 591,552.50
6 mm

Memasang Langit-langit Gypsu Board, Ukuran


7 A.4.5.1.7 m2 42,641.50 47,665.20
(120x240) tebal 9 mm

Memasang Langit-langit Akustik Uk (60x120) cm &


8 A.4.5.1.8 m2 229,652.50 250,717.50
Berikut Rangka Allumunium

9 A.4.5.1.9 List Langit-Langit Kayu Profil m1 17,836.50 19,283.00

668638447.xls 177/23 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
HARGA SATUAN PEKERJAAN PENUTUP
X A.4.5.2
ATAP
1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil m2 88,522.50 99,418.00

2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glasur m2 142,219.00 147,620.00

3 A.4.5.2.3 Pemasangan Atap Genteng Plentong Super / Besar m2 126,324.00 133,925.00


4 A.4.5.2.4 Pemasangan Genteng Bubung Plentong m' 109,978.00 119,086.00

5 A.4.5.2.5 Pemasangan Genteng Bubung Kodok / Glasur m' 122,353.00 132,561.00

6 A.4.5.2.6 Pemasangan Genteng Bubung Plentong Besar m' 126,203.00 135,641.00

7 A.4.5.2.7 Pemasangan Roof Light Fibreglass 90 x 180 m2 106,452.50 118,921.00


Pemasangan Atap Asbes Gelombang (2,50x0,92 m)
8 A.4.5.2.8 m2 65,835.00 73,843.00
x 5 mm

Pemasangan Atap Asbes Gelombang (2,25x0,92 m)


9 A.4.5.2.9 m2 67,479.50 75,817.50
x 5 mm

Pemasangan Atap Asbes Gelombang (2,00x0,92 m)


10 A.4.5.2.10 m2 67,809.50 76,477.50
x 5 mm

Pemasangan Atap Asbes Gelombang (1,80x0,92 m)


11 A.4.5.2.11 m2 75,069.50 79,315.50
x 5 mm

Pemasangan Atap Asbes Gelombang (3,00x1,05 m)


12 A.4.5.2.12 m2 58,102.00 73,980.50
x 4 mm

Pemasangan Atap Asbes Gelombang (2,70x1,05 m)


13 A.4.5.2.13 m2 60,219.50 76,213.50
x 4 mm

Pemasangan Atap Asbes Gelombang (2,40x1,05 m)


14 A.4.5.2.14 m2 58,239.50 74,629.50
x 4 mm

Pemasangan Atap Asbes Gelombang (2,10x1,05 m)


15 A.4.5.2.15 m2 58,949.00 73,606.50
x 4 mm

Pemasangan Atap Asbes Gelombang (1,50x1,05 m)


16 A.4.5.2.16 m2 62,529.50 76,565.50
x 4 mm

Pemasangan Atap Asbes Gelombang (3,00x1,08 m)


17 A.4.5.2.17 m2 67,490.50 70,900.50
x 6 mm

Pemasangan Atap Asbes Gelombang (2,70x1,08 m)


18 A.4.5.2.18 m2 70,845.50 74,365.50
x 6 mm

Pemasangan Atap Asbes Gelombang (2,40x1,08 m)


19 A.4.5.2.19 m2 67,677.50 71,725.50
x 6 mm

Pemasangan Atap Asbes Gelombang (2,10x1,08 m)


20 A.4.5.2.20 m2 68,689.50 72,902.50
x 6 mm

Pemasangan Atap Asbes Gelombang (1,80x1,08 m)


21 A.4.5.2.21 m2 72,594.50 76,444.50
x 6 mm

22 A.4.5.2.30 Pemasangan Atap Genteng Beton m2 111,540.00 124,822.50

23 A.4.5.2.31 Pemasangan Atap Genteng Aspal m2 228,294.00 255,524.50

24 A.4.5.2.32 Pemasangan Atap Genteng Metal m2 93,005.00 108,295.00

25 A.4.5.2.34 Pemasangan Atap Sirap m2 116,633.00 127,072.00

668638447.xls 177/24 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
26 A.4.5.2.35 Pemasangan Nok Genteng Beton m' 131,483.00 144,842.50

27 A.4.5.2.36 Pemasangan Nok Genteng Aspal m' 130,845.00 142,928.50

28 A.4.5.2.37 Pemasangan Nok Genteng Metal m' 70,757.50 78,628.00

29 A.4.5.2.38 Pemasangan Nok Sirap m' 61,655.00 68,183.50


30 A.4.5.2.39 Pemasangan Atap Seng Gelombang m2 40,513.00 45,760.00

31 A.4.5.2.40 Pemasangan Atap Nok Seng m' 33,506.00 37,499.00

32 A.4.5.2.43 Pasang Allumunium Foil / Sisalation m2 35,475.00 41,283.00

XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U

Pembuatan & Pemasangan Kosen Pintu & Jendela


1 A.4.6.1.1 m3 27,970,800.00 28,922,437.50
Kayu klas I

Pembuatan & Pemasangan Kosen Pintu & Jendela


2 A.4.6.1.2 m3 11,289,025.00 13,435,812.50
Kayu klas II atau III

Pembuatan & Pemasangan Pintu KlampStandard


3 A.4.6.1.3 m2 504,515.00 547,805.50
Kayu Klas II (Kayu Kamfer)

Pembuatan & Pemasangan Daun Pintu Klamp


4 A.4.6.1.4 m2 504,515.00 547,805.50
Sederhana Kayu Klas III

Pembuatan & Pemasangan Daun Pintu Panel, Kayu


5 A.4.6.1.5 m2 851,262.50 925,925.00
Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Kaca


6 A.4.6.1.6 m2 621,225.00 677,820.00
Kayu Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Jalusi


7 A.4.6.1.7 m2 2,089,450.00 2,211,825.00
Kayu Klas I atau II (jati)

Pembuatan&Pemasangan Pintu kayu lapis


8 A.4.6.1.8 (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 m2 650,512.50 726,715.00
cm)

Pembuatan&Pemasangan Pintu Plywood rangkap,


9 A.4.6.1.9 m2 708,642.00 790,025.50
rangka expose kayu klas I atau II

Pembuatan & Pemasangan Jalusi mati Kosen Kayu


10 A.4.6.1.10 m2 1,852,097.50 1,953,765.00
Klas I atau II

Pembuatan & Pemasangan Pintu Teakwood


11 A.4.6.1.11 m2 1,108,140.00 1,198,477.50
Rangkap, Rangka Expose Kayu Klas I

Pembuatan & Pemasangan Pintu Teakwood


12 A.4.6.1.12 Rangkap Lapis Formika, Rangka expose Kayu Klas m2 763,372.50 846,043.00
II

Pembuatan&Memasang Konstruksi Kuda-kuda


13 A.4.6.1.13 m3 9,839,500.00 11,744,425.00
Konvensional Kayu I; II & III Bentang 6 meter

Pembuatan&Pemasangan Konstruksi Kuda-kuda


14 A.4.6.1.14 m3 30,299,692.50 31,299,812.50
Expose, Kayu Klas I

15 A.4.6.1.15 Pemasangan konstruksi Gording, Kayu Klas II m3 8,942,560.00 10,763,775.00

Pemasangan Rangka Atap Genteng Keramik, Kayu


16 A.4.6.1.16 m2 146,338.50 176,495.00
Klas II

668638447.xls 177/25 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Rangka Atap Genteng Beton, Kayu
17 A.4.6.1.17 m2 170,494.50 206,195.00
Klas II

18 A.4.6.1.18 Pemasangan Rangka Atap Sirap, Kayu Klas II m2 126,181.00 151,129.00

Pemasangan Rangka Langit-langit (50x1,00) m,


19 A.4.6.1.19 m2 174,036.50 204,407.50
kayu Klas II atau III

Pemasangan Rangka Langit-langit (60x60) cm, kayu


20 A.4.6.1.20 m2 176,363.00 208,092.50
Klas II atau III

Pemasangan Listplank Uk. (3x20)cm Kayu klas I


21 A.4.6.1.21 m' 301,757.50 317,487.50
atau II

Pemasangan Listplank Uk. (3x30)cm Kayu klas I


22 A.4.6.1.22 m' 126,692.50 137,665.00
atau klas II

Pemasangan Rangka Dinding Pemisah (60x120) cm


23 A.4.6.1.23 m2 270,490.00 321,205.50
Kayu klas II atau III

Pemasangan Dinding Pemisah Teakwood Rangkap


24 A.4.6.1.24 m2 339,680.00 413,935.50
Rangka Kayu Klas II

Pemasangan Dinding Pemisah Plywood Rangkap


25 A.4.6.1.25 m2 350,460.00 425,122.50
Rangka Kayu Klas II

Pemasangan Dinding Lambriziring dari Papan Kelas


26 A.4.6.1.26 m2 492,470.00 529,320.00
I

Pemasangan Dinding Lambriziring dari Plywood


27 A.4.6.1.27 m2 42,806.50 48,543.00
ukuran (120x240) cm

Pemasangan Dinding Bilik, Rangka Kayu Klas III


28 A.4.6.1.28 m2 123,936.34 143,715.00
atau IV

HARGA SATUAN PEKERJAAN KUNCI dan


XII A.4.6.2
KACA

1 A.4.6.2.2 Pemasangan Kunci Tanam Biasa Buah 211,997.50 261,772.50

2 A.4.6.2.3 Pemasangan Kunci Kamar Mandi Buah 171,998.75 238,136.25

3 A.4.6.2.4 Pemasangan Kunci Selinder Buah 210,498.75 260,136.25

4 A.4.6.2.5 Pemasangan Engsel Pintu Buah 32,546.25 36,258.75

5 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu Buah 21,147.50 24,172.50


6 A.4.6.2.7 Pemasangan Engsel Angin Buah 55,728.75 74,654.25

7 A.4.6.2.9 Pemasangan Kait Angin Buah 43,615.00 48,433.00

8 A.4.6.2.10 Pasang Door Closer Buah 380,393.75 469,521.25

9 A.4.6.2.11 Pemasangan Kunci Selot Buah 39,957.50 44,808.50

10 A.4.6.2.13 Pemasangan Door Stop Buah 318,078.75 401,904.25

11 A.4.6.2.14 Pemasangan Rel Pintu Dorong Buah 313,472.50 359,925.50

12 A.4.6.2.15 Pemasangan Kunci Lemari Buah 52,703.75 58,768.05

13 A.4.6.2.16 Pemasangan Kaca tebal 3 mm m2 114,118.13 128,206.38

14 A.4.6.2.17 Pemasangan Kaca tebal 5 mm m2 132,268.13 140,306.38


15 A.4.6.2.18 Pemasangan Kaca Cermin tebal 5 mm m2 356,118.13 418,606.38

668638447.xls 177/26 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
HARGA SATUAN PEKERJAAN
XIII A.4.7.1
PENGECATAN

Pengikisan / pengerokan Permukaan Cat Tembok


1 A.4.7.1.1 m2 14,327.50 16,120.50
Lama

Pencucian Bidang Permukaan Tembok yang Pernah


2 A.4.7.1.2 m2 14,300.00 16,120.50
dicat

Pengerokan Karat Cat Lama permukaan Baja dg


3 A.4.7.1.3 m2 14,987.50 16,863.00
cara manual

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp


4 A.4.7.1.4 m2 44,302.50 51,144.50
Cat dasar, 2 Lp Cat Penutup)

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp


5 A.4.7.1.5 m2 62,628.50 71,593.50
Cat dasar, 3 Lp Cat Penutup)

6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil m2 37,493.50 39,748.50


7 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur m2 59,163.50 61,792.50

8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 10,683.75 11,946.00

9 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis m2 43,785.50 47,855.50

Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar


10 A.4.7.1.10 m2 22,037.40 25,010.70
2 Lap.Cat Penutup)

Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat


11 A.4.7.1.11 m2 15,159.10 16,998.30
Penutup)

12 A.4.7.1.12 Pengecatan Tembok dengan Kalkarium m2 9,516.10 10,420.30

13 A.4.7.1.13 Pelaburan Tembok dengan Kapur Sirih m2 15,862.55 17,838.15

Pelaburan Tembok lama dengan Kapur Sirih


14 A.4.7.1.14 m2 7,317.75 8,280.25
(pemeliharaan)

15 A.4.7.1.15 Pemasangan Wallpaper m2 89,663.75 101,131.25

16 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 32,144.75 35,934.25

Pengecatan Permukaan Baja dg Meni Besi &


17 A.4.7.1.17 m2 60,486.25 67,553.75
Perancah

HARGA SATUAN PEKERJAAN SANITASI


XIV A.5.1.1
DALAM GEDUNG

1 A.5.1.1.1 Pemasangan Closet Duduk / Mono Blok Unit 2,323,343.00 2,665,014.00

2 A.5.1.1.2 Pemasangan Closet Jongkok Porselen Unit 693,165.00 756,250.00

3 A.5.1.1.4 Pemasangan Urinoir Unit 759,715.00 820,490.00

4 A.5.1.1.5 Pemasangan Wastafel Unit 600,105.00 654,225.00

5 A.5.1.1.6 Pemasangan Bathcuip porselen Unit 1,106,737.50 1,182,670.50


6 A.5.1.1.7 Pemasangan Bak Fibreglass vol.1 m3 Unit 1,327,700.00 1,451,450.00

7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,606,154.27 1,768,063.54

8 A.5.1.1.11 Pemasangan Bak Beton Bertulang Vol. 1 m3 Unit 6,472,506.25 7,448,583.37

9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 351,092.50 393,717.50

10 A.5.1.1.14 Pemasangan Floor Drain buah 54,697.50 64,322.50

668638447.xls 177/27 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Bak Kontrol Pas.Batu Bata 30x30
11 A.5.1.1.15 bh 470,032.60 518,070.65
tinggi 35 cm

Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45


12 A.5.1.1.16 bh 692,034.60 761,539.15
tinggi 50 cm

Pemasangan Bak Kontrol Pas.Batu Bata 60x60


13 A.5.1.1.17 bh 832,171.10 918,674.18
tinggi 60 cm

14 A.5.1.1.18 Pemasangan Pipa Galvanis Ø ½" m' 65,677.33 69,078.17

15 A.5.1.1.19 Pemasangan Kran Ø ½" atau Ø ¾" bh 87,597.13 114,604.88


16 A.5.1.1.20 Pemasangan Pipa Galvanis Ø ¾" m' 77,044.00 80,444.83

17 A.5.1.1.21 Pemasangan Pipa Galvanis Ø 1" m' 108,302.33 113,124.00

18 A.5.1.1.22 Pemasangan Pipa Galvanis Ø 1½ " m' 144,508.83 150,771.50

19 A.5.1.1.23 Pemasangan Pipa Galvanis Ø 3" m' 256,114.83 263,814.83

20 A.5.1.1.24 Pemasangan Pipa Galvanis Ø 4" m' 459,294.00 465,715.25

21 A.5.1.1.25 Pemasangan Pipa PVC tipe AW Ø ½" m' 24,156.00 26,578.75

22 A.5.1.1.26 Pemasangan Pipa PVC tipe AW Ø ¾" m' 26,713.50 28,923.13

23 A.5.1.1.27 Pemasangan Pipa PVC tipe AW Ø 1" m' 31,402.25 36,808.75

24 A.5.1.1.28 Pemasangan Pipa PVC tipe AW Ø 1½" m' 34,244.83 39,939.17


25 A.5.1.1.29 Pemasangan Pipa PVC tipe AW Ø 2" m' 38,223.17 49,885.00

26 A.5.1.1.31 Pemasangan Pipa PVC tipe AW Ø 3" m' 62,949.33 82,567.83

27 A.5.1.1.32 Pemasangan Pipa PVC tipe AW Ø 4" m' 88,946.00 92,931.67

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø


28 A.5.1.1.33 m' 82,054.50 91,256.00
20 cm

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø


29 A.5.1.1.34 m' 39,374.50 44,786.50
15 cm

30 A.5.1.1.35 Pemasangan Pipa Beton Ø 15 - 20 cm m' 117,727.50 134,740.65

31 A.5.1.1.36 Pemasangan Pipa Beton Ø 30 - 100 cm m' 589,459.75 633,798.00

XV A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 A.8.4.6.1 Pemasangan Lampu Titik 385,880.00 431,508.00

2 A.8.4.6.2 Pemasangan MCB buah 488,840.00 536,448.00

HARGA SATUAN PEKERJAAN


XVI A.8.4.1
PEMASANGAN PIPA

1 A.8.4.1.1 Pemasangan Pipa PVC Ø 63 mm m' 15,755.30 18,167.60

2 A.8.4.1.2 Pemasangan Pipa PVC Ø 90 mm m' 24,568.50 27,611.10

3 A.8.4.1.3 Pemasangan Pipa PVC Ø 110 mm m' 28,616.50 34,622.50

4 A.8.4.1.4 Pemasangan Pipa PVC Ø 150 mm m' 33,253.00 41,408.40

5 A.8.4.1.5 Pemasangan Pipa PVC Ø 200 mm m' 49,593.50 65,354.30

6 A.8.4.1.6 Pemasangan Pipa PVC Ø 250 mm m' 66,781.00 100,240.80

7 A.8.4.1.7 Pemasangan Pipa PVC Ø 300 mm m' 100,820.50 133,578.50

668638447.xls 177/28 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
8 A.8.4.1.8 Pemasangan Pipa PVC Ø 400 mm m' 191,323.00 256,069.00

9 A.8.4.1.9 Pemasangan Pipa PVC Ø 450 mm m' 364,589.50 417,840.50

10 A.8.4.1.10 Pemasangan Pipa PVC Ø 500 mm m' 449,586.50 469,599.90

11 A.8.4.1.11 Pemasangan Pipa PVC Ø 600 mm m' 524,579.00 563,717.00

12 A.8.4.1.12 Pemasangan Pipa PVC Ø 800 mm m' 750,596.00 807,125.00

13 A.8.4.1.13 Pemasangan Pipa PVC Ø 900 mm m' 983,405.50 1,041,247.90

14 A.8.4.1.14 Pemasangan Pipa PVC Ø 1.000 mm m' 1,134,683.00 1,190,692.80

15 A.8.4.1.15 Pemasangan Pipa PVC Ø 1.100 mm m' 1,247,334.00 1,340,002.40

16 A.8.4.1.16 Pemasangan Pipa PVC Ø 1.200 mm m' 1,337,974.00 1,434,298.80

17 A.8.4.1.17 Pemasangan Pipa HDPE Ø 63 mm m' 33,632.50 39,779.30

18 A.8.4.1.18 Pemasangan Pipa HDPE Ø 100 mm m' 45,639.00 51,884.80

19 A.8.4.1.19 Pemasangan Pipa HDPE Ø 125 mm m' 57,645.50 63,990.30

20 A.8.4.1.20 Pemasangan Pipa HDPE Ø 150 mm m' 82,423.00 89,053.80

21 A.8.4.1.21 Pemasangan Pipa HDPE Ø 200 mm m' 138,853.00 151,687.80

22 A.8.4.1.22 Pemasangan Pipa HDPE Ø 250 mm m' 172,034.50 179,969.90

23 A.8.4.1.23 Pemasangan Pipa HDPE Ø 300 mm m' 206,167.50 220,302.50

24 A.8.4.1.24 Pemasangan Pipa HDPE Ø 400 mm m' 271,914.50 288,352.90

25 A.8.4.1.25 Pemasangan Pipa HDPE Ø 450 mm m' 328,482.00 346,247.00

26 A.8.4.1.26 Pemasangan Pipa HDPE Ø 500 mm m' 407,665.50 437,829.70

27 A.8.4.1.27 Pemasangan Pipa HDPE Ø 600 mm m' 565,053.50 596,737.90

28 A.8.4.1.28 Pemasangan Pipa HDPE Ø 800 mm m' 875,902.50 920,371.10

29 A.8.4.1.29 Pemasangan Pipa HDPE Ø 900 mm m' 1,069,150.50 1,149,908.10

30 A.8.4.1.30 Pemasangan Pipa HDPE Ø 1.000 mm m' 1,289,530.00 1,348,639.60

31 A.8.4.1.31 Pemasangan Pipa HDPE Ø 1.100 mm m' 1,428,251.00 1,517,901.00

32 A.8.4.1.32 Pemasangan Pipa HDPE Ø 1.200 mm m' 1,638,026.50 1,738,223.30

33 A.8.4.1.33 Pemasangan Pipa GIP Ø 63 mm m' 76,131.00 84,942.00

34 A.8.4.1.34 Pemasangan Pipa GIP Ø 100 mm m' 90,383.33 103,840.00

35 A.8.4.1.35 Pemasangan Pipa GIP Ø 125 mm m' 102,393.50 118,530.50

36 A.8.4.1.36 Pemasangan Pipa GIP Ø 150 mm m' 118,886.17 136,962.83

37 A.8.4.1.37 Pemasangan Pipa GIP Ø 200 mm m' 179,212.00 205,142.67

38 A.8.4.1.38 Pemasangan Pipa GIP Ø 250 mm m' 213,999.50 245,375.17

39 A.8.4.1.39 Pemasangan Pipa GIP Ø 300 mm m' 243,001.00 272,697.33

40 A.8.4.1.40 Pemasangan Pipa GIP Ø 400 mm m' 312,618.17 337,613.83

41 A.8.4.1.41 Pemasangan Pipa GIP Ø 450 mm m' 355,294.50 390,098.50

42 A.8.4.1.42 Pemasangan Pipa GIP Ø 500 mm m' 408,589.50 445,450.50

43 A.8.4.1.43 Pemasangan Pipa GIP Ø 600 mm m' 406,015.50 440,379.50

668638447.xls 177/29 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
44 A.8.4.1.44 Pemasangan Pipa GIP Ø 800 mm m' 623,122.50 675,075.50

45 A.8.4.1.45 Pemasangan Pipa GIP Ø 900 mm m' 707,465.00 775,632.00

46 A.8.4.1.46 Pemasangan Pipa GIP Ø 1.000 mm m' 790,388.50 852,626.50

47 A.8.4.1.47 Pemasangan Pipa GIP Ø 1.100 mm m' 862,400.00 929,720.00

48 A.8.4.1.48 Pemasangan Pipa GIP Ø 1.200 mm m' 945,323.50 1,017,714.50

49 A.8.4.1.49 Pemasangan Pipa DCI Ø 100 mm m' 91,701.50 104,281.10

50 A.8.4.1.50 Pemasangan Pipa DCI Ø 125 mm m' 115,703.50 129,108.10

51 A.8.4.1.51 Pemasangan Pipa DCI Ø 150 mm m' 146,338.50 166,189.10

52 A.8.4.1.52 Pemasangan Pipa DCI Ø 200 mm m' 199,798.50 223,103.10

53 A.8.4.1.53 Pemasangan Pipa DCI Ø 250 mm m' 234,470.50 259,176.50

54 A.8.4.1.54 Pemasangan Pipa DCI Ø 300 mm m' 259,627.50 284,698.70

55 A.8.4.1.55 Pemasangan Pipa DCI Ø 400 mm m' 391,253.50 426,070.70

56 A.8.4.1.56 Pemasangan Pipa DCI Ø 450 mm m' 459,305.00 493,336.80

57 A.8.4.1.57 Pemasangan Pipa DCI Ø 500 mm m' 522,428.50 566,170.00

58 A.8.4.1.58 Pemasangan Pipa DCI Ø 600 mm m' 582,741.50 644,318.40

59 A.8.4.1.59 Pemasangan Pipa DCI Ø 800 mm m' 897,336.00 978,114.50

60 A.8.4.1.60 Pemasangan Pipa DCI Ø 900 mm m' 1,066,373.00 1,165,137.60

61 A.8.4.1.61 Pemasangan Pipa DCI Ø 1.000 mm m' 1,277,699.50 1,388,965.60

62 A.8.4.1.62 Pemasangan Pipa DCI Ø 1.100 mm m' 1,433,096.50 1,569,059.80

63 A.8.4.1.63 Pemasangan Pipa DCI Ø 1.200 mm m' 1,627,604.00 1,781,323.50

64 A.8.4.1.64 Pemasangan Baja PVC Ø 63 mm m' 78,331.00 86,578.80

65 A.8.4.1.65 Pemasangan Pipa Baja Ø 100 mm m' 89,309.00 100,350.80

66 A.8.4.1.66 Pemasangan Pipa Baja Ø 125 mm m' 101,095.50 112,577.30

67 A.8.4.1.67 Pemasangan Pipa Baja Ø 150 mm m' 114,416.50 130,056.30

68 A.8.4.1.68 Pemasangan Pipa Baja Ø 200 mm m' 178,139.50 199,565.30

69 A.8.4.1.69 Pemasangan Pipa Baja Ø 250 mm m' 227,826.50 257,788.30

70 A.8.4.1.70 Pemasangan Pipa Baja Ø 300 mm m' 261,420.50 287,158.30

71 A.8.4.1.71 Pemasangan Pipa Baja Ø 400 mm m' 394,350.00 431,984.30

72 A.8.4.1.72 Pemasangan Pipa Baja Ø 450 mm m' 410,470.50 453,594.90

73 A.8.4.1.73 Pemasangan Pipa Baja Ø 500 mm m' 465,289.00 527,818.50

74 A.8.4.1.74 Pemasangan Pipa Baja Ø 600 mm m' 495,979.00 549,794.30

75 A.8.4.1.75 Pemasangan Pipa Baja Ø 800 mm m' 800,481.00 884,175.60

76 A.8.4.1.76 Pemasangan Pipa Baja Ø 900 mm m' 913,649.00 998,371.00

77 A.8.4.1.77 Pemasangan Pipa Baja Ø 1.000 mm m' 1,045,192.50 1,143,297.10

78 A.8.4.1.78 Pemasangan Pipa Baja Ø 1.100 mm m' 1,166,709.50 1,271,924.50

79 A.8.4.1.79 Pemasangan Pipa Baja Ø 1.200 mm m' 1,289,816.00 1,402,339.40

668638447.xls 177/30 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp

HARGA SATUAN PEKERJAAN


XVII A.8.4.2
PEMOTONGAN PIPA

1 A.8.4.2.1 Pemotongan Pipa PVC Ø 63 mm bh 821.15 910.25

2 A.8.4.2.2 Pemotongan Pipa PVC Ø 90 mm bh 2,396.90 2,645.50

3 A.8.4.2.3 Pemotongan Pipa PVC Ø 110 mm bh 3,810.40 4,202.00

4 A.8.4.2.4 Pemotongan Pipa PVC Ø 150 mm bh 5,311.90 5,857.50

5 A.8.4.2.5 Pemotongan Pipa PVC Ø 200 mm bh 14,097.60 15,554.00

6 A.8.4.2.6 Pemotongan Pipa PVC Ø 250 mm bh 22,467.50 24,788.50

7 A.8.4.2.7 Pemotongan Pipa PVC Ø 300 mm bh 27,039.10 29,837.50

8 A.8.4.2.8 Pemotongan Pipa PVC Ø 400 mm bh 58,160.30 64,179.50

9 A.8.4.2.9 Pemotongan Pipa PVC Ø 450 mm bh 74,250.00 81,939.00

10 A.8.4.2.10 Pemotongan Pipa PVC Ø 500 mm bh 91,668.50 101,167.00

11 A.8.4.2.11 Pemotongan Pipa PVC Ø 600 mm bh 110,187.00 121,616.00

12 A.8.4.2.12 Pemasangan Pipa PVC Ø 800 mm bh 193,154.50 213,207.50

13 A.8.4.2.13 Pemotongan Pipa PVC Ø 900 mm bh 202,356.00 223,366.00

14 A.8.4.2.14 Pemotongan Pipa PVC Ø 1.000 mm bh 228,019.00 251,696.50

15 A.8.4.2.15 Pemotongan Pipa PVC Ø 1.100 mm bh 253,517.00 279,845.50

16 A.8.4.2.16 Pemotongan Pipa PVC Ø 1.200 mm bh 279,042.50 308,027.50

17 A.8.4.2.17 Pemotongan Pipa HDPE Ø 63 mm bh 4,196.50 4,627.70

18 A.8.4.2.18 Pemotongan Pipa HDPE Ø 100 mm bh 9,042.00 9,960.50

19 A.8.4.2.19 Pemotongan Pipa HDPE Ø 125 mm bh 12,369.50 13,623.50

20 A.8.4.2.20 Pemotongan Pipa HDPE Ø 150 mm bh 16,384.50 18,051.00

21 A.8.4.2.21 Pemotongan Pipa HDPE Ø 200 mm bh 26,845.50 29,590.00

22 A.8.4.2.22 Pemotongan Pipa HDPE Ø 250 mm bh 36,520.00 40,254.50

23 A.8.4.2.23 Pemotongan Pipa HDPE Ø 300 mm bh 46,227.50 50,957.50

24 A.8.4.2.24 Pemotongan Pipa HDPE Ø 400 mm bh 72,957.50 80,454.00

25 A.8.4.2.25 Pemotongan Pipa HDPE Ø 450 mm bh 87,356.50 96,343.50

26 A.8.4.2.26 Pemotongan Pipa HDPE Ø 500 mm bh 97,850.50 107,833.00

27 A.8.4.2.27 Pemotongan Pipa HDPE Ø 600 mm bh 123,310.00 136,009.50

28 A.8.4.2.28 Pemotongan Pipa HDPE Ø 800 mm bh 193,913.50 213,961.00

29 A.8.4.2.29 Pemotongan Pipa HDPE Ø 900 mm bh 261,299.50 288,425.50

30 A.8.4.2.30 Pemotongan Pipa HDPE Ø 1.000 mm bh 310,706.00 343,002.00

31 A.8.4.2.31 Pemotongan Pipa HDPE Ø 1.100 mm bh 342,358.50 377,938.00

32 A.8.4.2.32 Pemotongan Pipa HDPE Ø 1.200 mm bh 422,361.50 466,356.00

33 A.8.4.2.33 Pemotongan Pipa GIP Ø 63 mm bh 3,377.00 3,718.00

34 A.8.4.2.34 Pemotongan Pipa GIP Ø 100 mm bh 10,076.00 11,099.00

668638447.xls 177/31 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
35 A.8.4.2.35 Pemotongan Pipa GIP Ø 125 mm bh 15,911.50 17,528.50

36 A.8.4.2.36 Pemotongan Pipa GIP Ø 150 mm bh 22,753.50 25,063.50

37 A.8.4.2.37 Pemotongan Pipa GIP Ø 200 mm bh 58,905.00 64,889.00

38 A.8.4.2.38 Pemotongan Pipa GIP Ø 250 mm bh 82,153.50 90,502.50

39 A.8.4.2.39 Pemotongan Pipa GIP Ø 300 mm bh 87,263.00 96,129.00

40 A.8.4.2.40 Pemotongan Pipa GIP Ø 400 mm bh 127,886.00 140,877.00

41 A.8.4.2.41 Pemotongan Pipa GIP Ø 450 mm bh 146,943.50 161,870.50

42 A.8.4.2.42 Pemotongan Pipa GIP Ø 500 mm bh 149,633.00 164,835.00

43 A.8.4.2.43 Pemotongan Pipa GIP Ø 600 mm bh 163,086.00 179,652.00

44 A.8.4.2.44 Pemotongan Pipa GIP Ø 800 mm bh 271,452.50 299,029.50

45 A.8.4.2.45 Pemotongan Pipa GIP Ø 900 mm bh 306,652.50 337,804.50

46 A.8.4.2.46 Pemotongan Pipa GIP Ø 1.000 mm bh 341,940.50 376,678.50

47 A.8.4.2.47 Pemotongan Pipa GIP Ø 1.100 mm bh 377,091.00 415,404.00

48 A.8.4.2.48 Pemotongan Pipa GIP Ø 1.200 mm bh 412,654.00 454,575.00

49 A.8.4.2.49 Pemotongan Pipa DCI Ø 100 mm bh 9,245.50 10,264.10

50 A.8.4.2.50 Pemotongan Pipa DCI Ø 125 mm bh 14,624.50 16,241.50

51 A.8.4.2.51 Pemotongan Pipa DCI Ø 150 mm bh 20,966.00 23,282.60

52 A.8.4.2.52 Pemotongan Pipa DCI Ø 200 mm bh 48,328.50 53,683.30

53 A.8.4.2.53 Pemotongan Pipa DCI Ø 250 mm bh 62,876.00 69,845.60

54 A.8.4.2.54 Pemotongan Pipa DCI Ø 300 mm bh 67,523.50 75,012.30

55 A.8.4.2.55 Pemotongan Pipa DCI Ø 400 mm bh 124,355.00 138,155.60

56 A.8.4.2.56 Pemotongan Pipa DCI Ø 450 mm bh 150,128.00 166,773.20

57 A.8.4.2.57 Pemotongan Pipa DCI Ø 500 mm bh 173,046.50 192,223.90

58 A.8.4.2.58 Pemotongan Pipa DCI Ø 600 mm bh 173,046.50 192,223.90

59 A.8.4.2.59 Pemotongan Pipa DCI Ø 800 mm bh 342,144.00 379,984.00

60 A.8.4.2.60 Pemotongan Pipa DCI Ø 900 mm bh 443,470.50 492,499.70

61 A.8.4.2.61 Pemotongan Pipa DCI Ø 1.000 mm bh 528,946.00 587,413.20

62 A.8.4.2.62 Pemotongan Pipa DCI Ø 1.100 mm bh 622,209.50 690,972.70

63 A.8.4.2.63 Pemotongan Pipa DCI Ø 1.200 mm bh 723,437.00 803,376.20

64 A.8.4.2.64 Pemotongan pipa Baja Ø 63 mm bh 4,955.50 5,566.00

65 A.8.4.2.65 Pemotongan Pipa Baja Ø 100 mm bh 12,331.00 13,761.00

66 A.8.4.2.66 Pemotongan Pipa Baja Ø 125 mm bh 18,738.50 20,872.50

67 A.8.4.2.67 Pemotongan Pipa Baja Ø 150 mm bh 25,443.00 28,319.50

68 A.8.4.2.68 Pemotongan Pipa Baja Ø 200 mm bh 64,053.00 71,192.00

69 A.8.4.2.69 Pemotongan Pipa Baja Ø 250 mm bh 88,682.00 98,538.00

70 A.8.4.2.70 Pemotongan Pipa Baja Ø 300 mm bh 99,418.00 110,462.00

668638447.xls 177/32 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
71 A.8.4.2.71 Pemotongan Pipa Baja Ø 400 mm bh 191,169.00 212,338.50

72 A.8.4.2.72 Pemotongan Pipa Baja Ø 450 mm bh 180,653.00 200,590.50

73 A.8.4.2.73 Pemotongan Pipa Baja Ø 500 mm bh 193,996.00 215,528.50

74 A.8.4.2.74 Pemotongan Pipa Baja Ø 600 mm bh 206,899.00 229,806.50

75 A.8.4.2.75 Pemotongan Pipa Baja Ø 800 mm bh 347,490.00 385,924.00

76 A.8.4.2.76 Pemotongan Pipa Baja Ø 900 mm bh 393,266.50 436,755.00

77 A.8.4.2.77 Pemotongan Pipa Baja Ø 1.000 mm bh 439,307.00 487,877.50

78 A.8.4.2.78 Pemotongan Pipa Baja Ø 1.100 mm bh 485,171.50 538,807.50

79 A.8.4.2.79 Pemotongan Pipa Baja Ø 1.200 mm bh 531,212.00 589,930.00

HARGA SATUAN PEKERJAAN


XVIII A.8.4.3
PEMASANGAN AKSESORIS PIPA

1 A.8.4.3.1 Pemasangan Valve Ø 150 mm bh 303,759.50 345,636.50

2 A.8.4.3.2 Pemasangan Valve Ø 200 mm bh 382,695.50 430,017.50

3 A.8.4.3.3 Pemasangan Valve Ø 250 mm bh 438,795.50 480,837.50

4 A.8.4.3.4 Pemasangan Valve Ø 300 mm bh 517,000.00 575,300.00

5 A.8.4.3.5 Pemasangan Valve Ø 400 mm bh 907,659.50 997,716.50

6 A.8.4.3.6 Pemasangan Valve Ø 450 mm bh 962,659.50 1,052,716.50

7 A.8.4.3.7 Pemasangan Valve Ø 500 mm bh 1,116,500.00 1,216,600.00

8 A.8.4.3.8 Pemasangan Valve Ø 600 mm bh 769,846.00 830,280.00

9 A.8.4.3.9 Pemasangan Valve Ø 700 mm bh 885,659.50 944,916.50

10 A.8.4.3.10 Pemasangan Valve Ø 800 mm bh 1,002,479.50 1,073,517.50

11 A.8.4.3.11 Pemasangan Valve Ø 900 mm bh 1,088,895.50 1,164,707.50

12 A.8.4.3.12 Pemasangan Valve Ø 1.000 mm bh 1,336,483.50 1,416,937.50

13 A.8.4.3.13 Pemasangan Valve Ø 1.100 mm bh 1,465,750.00 1,553,750.00

14 A.8.4.3.14 Pemasangan Valve Ø 1.200 mm bh 1,498,750.00 1,597,750.00

15 A.8.4.3.15 Pemasangan Tee Ø 150 mm bh 31,927.50 37,159.10

16 A.8.4.3.16 Pemasangan Tee Ø 200 mm bh 54,296.00 63,665.80

17 A.8.4.3.17 Pemasangan Tee Ø 250 mm bh 84,463.50 95,791.30

18 A.8.4.3.18 Pemasangan Tee Ø 300 mm bh 119,592.00 133,870.00

19 A.8.4.3.19 Pemasangan Tee Ø 400 mm bh 168,707.00 186,857.00

20 A.8.4.3.20 Pemasangan Tee Ø 450 mm bh 209,764.50 229,850.50

21 A.8.4.3.21 Pemasangan Tee Ø 500 mm bh 240,922.00 263,164.00

22 A.8.4.3.22 Pemasangan Tee Ø 600 mm bh 306,900.00 339,730.60

23 A.8.4.3.23 Pemasangan Tee Ø 700 mm bh 370,172.00 401,819.00

24 A.8.4.3.24 Pemasangan Tee Ø 800 mm bh 422,279.00 463,720.40

25 A.8.4.3.25 Pemasangan Tee Ø 900 mm bh 488,378.00 534,536.20

668638447.xls 177/33 hspk ok


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
26 A.8.4.3.26 Pemasangan Tee Ø 1.000 mm bh 552,618.00 603,231.20

27 A.8.4.3.27 Pemasangan Tee Ø 1.100 mm bh 614,603.00 669,352.20

28 A.8.4.3.28 Pemasangan Tee Ø 1.200 mm bh 680,702.00 740,168.00

HARGA SATUAN PEKERJAAN


XIX A.8.4.4
PENYAMBUNGAN PIPA BARU KE PIPA LAMA

Penyambungan Pipa Baru ke Pipa yang ada Ø 80


1 A.8.4.4.1 bh 480,694.50 556,506.50
mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


2 A.8.4.4.2 bh 555,527.50 643,276.70
100 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


3 A.8.4.4.3 bh 795,767.50 906,952.20
150 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


4 A.8.4.4.4 bh 1,003,007.50 1,148,627.70
200 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


5 A.8.4.4.5 bh 1,182,747.50 1,346,303.20
250 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


6 A.8.4.4.6 bh 1,351,487.50 1,532,978.70
300 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


7 A.8.4.4.7 bh 1,688,967.50 1,917,329.70
400 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


8 A.8.4.4.8 bh 1,863,207.50 2,115,005.20
450 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


9 A.8.4.4.9 bh 2,048,447.50 2,323,680.70
500 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


10 A.8.4.4.10 bh 2,385,927.50 2,708,031.70
600 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


11 A.8.4.4.11 bh 2,756,407.50 3,125,382.70
700 mm

Penyambungan Pipa Baru ke Pipa yang ada Ø


12 A.8.4.4.11 bh 3,082,887.50 3,509,733.70
800 mm

HARGA SATUAN PEKERJAAN


XX A.8.4.5
PENGETESAN
1 A.8.4.5.1 Pengetesan Pipa Ø 50 mm m' 1,358.83 1,485.44

2 A.8.4.5.2 Pengetesan Pipa Ø 75 mm m' 1,359.16 1,485.88

3 A.8.4.5.3 Pengetesan Pipa Ø 100 mm m' 1,359.82 1,486.76

4 A.8.4.5.4 Pengetesan Pipa Ø 150 mm m' 1,361.47 1,488.96

5 A.8.4.5.5 Pengetesan Pipa Ø 200 mm m' 1,363.62 1,491.82

6 A.8.4.5.6 Pengetesan Pipa Ø 250 mm m' 1,366.59 1,495.78

7 A.8.4.5.7 Pengetesan Pipa Ø 300 mm m' 1,370.22 1,500.62

8 A.8.4.5.8 Pengetesan Pipa Ø 400 mm m' 1,379.29 1,512.72

9 A.8.4.5.9 Pengetesan Pipa Ø 500 mm m' 1,384.57 1,519.76

10 A.8.4.5.10 Pengetesan Pipa Ø 600 mm m' 1,405.20 1,547.26

668638447.xls 177/34 hspk ok


DAFTAR HARGA SATUAN PEKERJAAN
BERDASAR PERMEN PUPERA NO.28/PRT/M/2016

SUMBER DATA : PASARAN BEBAS EDISI 02 2019


DAERAH : KOTA SEMARANG DAN SEKITAR

HARGA SATUAN PEKERJAAN


NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi 2,00
1 A.2.2.1.2 m' 600,272.75 691,977.00
m
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 141,212.50 173,827.50

3 A.2.2.1.5 Pembuatan Kantor Sementara dg Lantai Plesteran m2 1,972,217.50 2,228,435.00

4 A.2.2.1.6 Pembuatan Rumah Jaga (Konstruksi Kayu) m2 1,503,975.00 1,717,375.00

5 A.2.2.1.7 Pembuatan Gudang Semen dan Peralatan m2 1,370,393.75 1,581,442.50

6 A.2.2.1.8 Pembuatan Bedeng Pekerja m2 1,732,775.00 1,978,625.00

7 A.2.2.1.9 Membersihkan Lapangan dan Perataan m2 15,675.00 17,325.00

8 A.2.2.1.10 Pembuatan Steger/Perancah dari Bambu m2 405,407.20 449,448.12


Pembuatan Kotak Adukan ukuran
9 A.2.2.1.11 bh 498,630.00 635,140.00
40cmx50cmx25cm
10 A.2.2.1.12 Pembuatan Jalan Sementara m2 165,687.50 191,262.50

11 A.2.2.1.13 Bongkaran Beton Bertulang m3 1,264,967.00 1,418,967.00

12 A.2.2.1.14 Bongkaran Dinding Tembok Bata Merah m3 591,233.50 664,933.50

13 A.2.2.1.15 Pagar Kawat Jaring Galvanis Panjang 240 cm m2 59,184.40 62,540.50


Pemasangan Pagar Panel Beton Pracetak 5 x 50 x
14 A.2.2.1.16 m2 313,538.50 346,453.25
240 cm

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m m3 69,437.50 77,962.50

2 A.2.3.1.2 Menggali Tanah Biasa Sedalam 2 m m3 85,387.50 95,782.50

3 A.2.3.1.3 Menggali Tanah Biasa Sedalam 3 m m3 101,612.50 113,899.50

4 A.2.3.1.4 Menggali Tanah Keras Sedalam 1 m m3 92,400.00 103,752.00

5 A.2.3.1.5 Menggali Tanah Cadas Sedalam 1 m m3 140,250.00 157,410.00

6 A.2.3.1.6 Menggali Tanah Lumpur Sedalam 1 m m3 111,787.50 125,482.50

7 A.2.3.1.7 Mengerjakan Striping Tebing Setinggi 1 m m2 5,087.50 5,692.50

8 A.2.3.1.8 MembuangTanah sejauh 30 m' m3 30,415.00 34,155.00


Pengurugan Kembali di hitung dari 1/3 kali koefisien
9 A.2.3.1.9 m3 16,958.33 18,975.00
Pekerjaan galian
10 A.2.3.1.10 Pemadatan Tanah (per 20 cm) m3 50,875.00 56,925.00

11 A.2.3.1.11 Urugan Pasir m3 238,975.00 321,585.00

12 A.2.3.1.12 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL m3 447,546.00 491,777.00

Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang


13 A.2.3.1.13 m2 61,462.50 64,597.50
Resapan

14 A.2.3.1.14 Mengurug Sirtu Padat m3 263,037.50 292,462.50

668638447.xls 177/35 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP m3 1,053,002.50 1,191,272.50

2 A.3.2.1.2 Pemasangan Pondasi Batu Belah 1SP : 4 PP m3 1,017,830.00 1,154,037.50

3 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP m3 993,393.50 1,128,165.50

4 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 976,239.00 1,110,004.50


5 A.3.2.1.5 Pemasangan Pondasi Batu Belah 1SP : 8 PP m3 952,666.00 1,085,045.50

6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 842,297.50 960,987.50
Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10
7 A.3.2.1.7 m3 929,643.00 1,058,128.50
PP
Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4
8 A.3.2.1.8 m3 911,207.00 1,038,889.50
PP
9 A.3.2.1.9 Pemasang Batu Kosong/Anstamping m3 576,691.50 698,131.50

Pasang Pondasi Siklop, 60% Beton Campuran


10 A.3.2.1.10 m3 2,500,839.00 2,898,159.00
1PC : 2PB : 3KR & 40% Batu Belah

11 A.3.2.1.11 Pasang Pondasi Sumuran diameter 100 cm m3 970,381.50 1,070,635.50

IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Membuat Beton mutu f'c=7,4 Mpa (K100), slum


1 A.4.1.1.1 m3 1,005,451.86 1,120,043.57
(12±2)cm, w/c = 0,87

Membuat Beton mutu f'c=9,8 Mpa (K125), slum


2 A.4.1.1.2 m3 1,033,025.92 1,150,107.33
(12±2)cm, w/c = 0,78

Membuat Beton mutu f'c=12,2 Mpa (K150), slum


3 A.4.1.1.3 m3 1,054,548.52 1,173,356.90
(12±2)cm, w/c = 0,72

Membuat Lantai Kerja Beton mutu f'c=7,4 MPa


4 A.4.1.1.4 m3 936,714.02 1,045,084.92
(K100), slum (3-6)cm, w/c = 0,87

Membuat Beton mutu f'c=14,5 MPa (K175), slum


5 A.4.1.1.5 m3 1,079,960.71 1,201,068.17
(12±2)cm, w/c = 0,66

Membuat Beton mutu f'c=16,9 MPa (K200), slum


6 A.4.1.1.6 m3 1,104,438.03 1,227,348.86
(12±2)cm, w/c = 0,61

Membuat Beton mutu f'c=19,3 MPa (K225), slum


7 A.4.1.1.7 m3 1,122,657.73 1,247,530.08
(12±2)cm, w/c = 0,58

Membuat Beton mutu f'c=21,7 MPa (K250), slum


8 A.4.1.1.8 m3 1,135,027.35 1,260,421.61
(12±2)cm, w/c = 0,56

Membuat Lantai Kerja Beton mutu f'c=24,0 MPa


9 A.4.1.1.9 m3 1,156,705.79 1,283,047.86
(K275), slum (12±2)cm, w/c = 0,53

Membuat Beton mutu f'c=26,4 MPa (K300), slum


10 A.4.1.1.10 m3 1,163,256.75 1,289,843.99
(12±2)cm, w/c = 0,52

Membuat Beton mutu f'c=28,8 MPa (K325), slum


11 A.4.1.1.11 m3 1,242,057.43 1,375,855.26
(12±2)cm, w/c = 0,49

Membuat Beton mutu f'c=31,2 MPa (K350), slum


12 A.4.1.1.12 m3 1,250,830.81 1,384,981.77
(12±2)cm, w/c = 0,48

668638447.xls 177/36 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
13 A.4.1.1.17 Pembesian dg Besi Polos atau Besi Ulir Kg 13,542.10 16,067.70

14 A.4.1.1.18 Kabel Presstresed Polos/strand Kg 17,580.75 18,310.05

15 A.4.1.1.19 Jaring Kawat baja/Wire Mesh Kg 28,741.35 31,621.15

16 A.4.1.1.20 Memasang Bekisting untuk Pondasi m2 181,313.00 200,200.00

17 A.4.1.1.21 Memasang Bekisting untuk Sloof m2 192,313.00 212,300.00


18 A.4.1.1.22 Memasang Bekisting untuk Kolom m2 381,826.50 442,612.50

19 A.4.1.1.23 Memasang Bekisting untuk Balok m2 398,986.50 462,412.50

20 A.4.1.1.24 Memasang Bekisting untuk Lantai m2 474,226.50 548,212.50

21 A.4.1.1.25 Memasang Bekisting untuk Dinding m2 433,526.50 502,012.50

22 A.4.1.1.26 Memasang Bekisting untuk Tangga m2 359,331.50 417,862.50

23 A.4.1.1.27 Memasang Jembatan Cor m2 101,145.00 112,596.00

24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 85,772.50 97,460.00

25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 110,305.25 124,239.50

IV A A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK

Pembuatan Lahan Produksi Tebal 8 cm Beton f'c


1 A.4.1.2.1 m2 86,412.04 96,101.95
14,5 Mpa, Slump (120 ± 20) mm K3

Pembuatan Lahan Produksi Tebal 10 cm Beton f'c =


2 A.4.1.2.2 m2 108,049.42 120,164.57
14,5 Mpa slum (120 ± 20 ) mm K3

Pembuatan Lahan Produksi Tebal 12 cm Beton


3 A.4.1.2.3 m2 126,645.30 140,811.68
f'c=14,5 Mpa, slum (120±20)mm, K3

Pembuatan Lahan Produksi Tebal 15 cm Beton


4 A.4.1.2.4 m2 162,052.13 180,224.85
f'c=14,5 Mpa, slum (120±20)mm, K3

Pembuatan Bekisting untuk Plat Beton Pra cetak (5


5 A.4.1.2.5 m2 119,707.91 131,896.01
kali Pakai)

Pembuatan Bekisting untuk Balok Beton Pra cetak


6 A.4.1.2.6 m2 40,776.00 45,914.60
(10 - 12 kali Pakai)

Pembuatan Bekisting untuk Kolom Beton Pra cetak


7 A.4.1.2.7 m2 36,201.00 40,564.60
(10 - 12 kali Pakai)

Pemasangan dan Membuka Bekisting untuk


8 A.4.1.2.8 bh 7,025.00 7,785.00
Komponen Plat Beton Pracetak

Pemasangan dan Membuka Bekisting untuk


9 A.4.1.2.9 bh 11,345.00 12,585.00
Komponen Balok Beton Pracetak

Pemasangan dan Membuka Bekisting untuk


10 A.4.1.2.10 bh 9,185.00 10,185.00
Komponen Kolom Beton Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


11 A.4.1.2.11 m3 69,635.50 68,735.00
Pracetak

Penuangan / Menebar Beton untuk Komponen Plat


12 A.4.1.2.12 m3 71,560.50 70,645.00
Pracetak

Penuangan / Menebar Beton untuk Komponen


13 A.4.1.2.13 m3 64,344.50 63,515.00
Kolom Pracetak

668638447.xls 177/37 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
14 A.4.1.2.14 Ereksi Komponen Untuk Plat Pracetak bh 582,822.02 608,545.96

15 A.4.1.2.15 Ereksi Komponen Untuk Balok Pracetak bh 572,865.70 597,845.60

16 A.4.1.2.16 Ereksi Komponen Untuk Kolom Pracetak bh 823,379.04 864,459.42

17 A.4.1.2.17 Langsiran Komponen untuk Plat Pracetak (± 20 m) bh 157,399.44 164,718.62

18 A.4.1.2.18 Langsiran Komponen untuk Balok Pracetak (± 20 m) bh 125,059.44 128,715.62

Langsiran Komponen untuk Kolom Pracetak (± 20


19 A.4.1.2.19 bh 125,059.44 128,715.62
m)

20 A.4.1.2.20 Bahan Grout Campuran m3 3,417,700.00 3,689,125.00


21 A.4.1.2.21 Bahan Grout Campuran (tidak Campuran) m3 3,061,300.00 3,368,750.00

22 A.4.1.2.22 Upah Pekerjaan Gruot pada Joint Beton Pra Cetak ttk 64,113.50 69,371.50

23 A.4.1.2.23 Pemasangan Bekisting Joint Pra Cetak ttk 117,848.50 134,788.50

24 A.4.1.2.24 Upah Pemasangan Joint dengan Sling ttk 52,816.50 58,019.50

HARGA SATUAN PEKERJAAN BESI &


V A.4.2.1
ALLUMUNIUM
1 A.4.2.1.1 Pemasangan Besi Profil Kg 32,813.00 34,548.25
2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF Kg 26,741.00 28,033.50

3 A.4.2.1.3 Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) kg 102,195.50 118,926.50

Pembuatan Pintu Besi Plat Baja tebal 2 mm


4 A.4.2.1.4 m2 921,360.00 953,832.00
rangkap, rangka baja Siku

5 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik cm 2,361.04 2,738.56

6 A.4.2.1.6 Pembuatan Rangka Jendela Besi Scuare Tube m2 249,740.48 281,136.02

7 A.4.2.1.7 Pemasangan Pintu Rolling Door Besi m2 639,485.00 678,271.00

8 A.4.2.1.8 Pemasangan Pintu Lipat (Folding Door) m2 546,117.00 584,023.00

9 A.4.2.1.9 Pemasangan Sunscreen Allumunium m2 509,630.00 575,234.00

10 A.4.2.1.10 Pemasangan Rolling Door Allumunium m2 543,675.00 583,825.00

11 A.4.2.1.11 Pemasangan Kusen Pintu Allumunium m' 130,263.65 138,100.05


12 A.4.2.1.12 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 552,563.00 586,802.70

13 A.4.2.1.13 Pemasangan Pintu Kaca Rangka Allumunium m2 520,074.50 554,218.50

14 A.4.2.1.14 Pemasangan Venetions Blinds & Vertical Blinds m2 188,980.00 202,763.00

15 A.4.2.1.15 Pemasangan Teralis Besi Strip (2x3) cm m2 568,149.96 620,584.20

16 A.4.2.1.16 Pemasangan Kawat Nyamuk m2 103,598.17 117,098.74

17 A.4.2.1.17 Pemasangan Jendela Nako & Tralis m2 136,372.50 148,978.50

Pemasangan Talang Datar / Jurai , Seng BJLS 28


18 A.4.2.1.18 m' 199,017.50 230,051.25
Lebar 90 cm

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


19 A.4.2.1.20 m2 121,962.50 131,730.50
Modul 60x120 cm dinding partisi

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;


20 A.4.2.1.21 m2 154,880.00 167,563.00
Modul 60x60 cm dinding plafond

668638447.xls 177/38 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Atap Pelana Rangka Atap Baja Canal
21 A.4.2.1.22 m2 240,559.28 259,013.01
C dingin Profil C75

Pemasangan Atap Jurai Rangka Atap Baja Canal


22 A.4.2.1.23 m2 267,357.75 286,788.43
Dingin Profil C75

HARGA SATUAN PEKERJAAN PASANGAN


VI A.4.4.1
DINDING

Pemasangan Dinding Bata Merah ukuran (5x11x22)


1 A.4.4.1.1 m2 262,336.25 285,615.00
cm Tebal 1 bata Camp. 1SP: 2PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


2 A.4.4.1.2 m2 253,394.63 276,166.00
cm Tebal 1 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


3 A.4.4.1.3 m2 246,222.63 268,532.00
cm Tebal 1 Bata Camp. 1SP : 4PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


4 A.4.4.1.4 m2 244,205.50 266,453.00
cm Tebal 1 Bata Camp. 1SP : 5PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


5 A.4.4.1.5 m2 247,106.75 269,709.00
cm Tebal 1 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran (5x11x22)


6 A.4.4.1.6 m2 234,729.00 255,965.60
cm Tebal 1 Bata Camp. 1SP : 3 KP :10PP

Pemasangan Dinding Bata Merah Ukuran


7 A.4.4.1.7 m2 126,955.13 138,297.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP

Pemasangan Dinding Bata Merah Ukuran


8 A.4.4.1.8 m2 122,035.38 133,065.90
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP

Pemasangan Dinding Bata Merah Ukuran


9 A.4.4.1.9 m2 119,605.75 130,498.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP

Pemasangan Dinding Bata Merah Ukuran


10 A.4.4.1.10 m2 118,101.50 128,910.10
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP

Pemasangan Dinding Bata Merah Ukuran


11 A.4.4.1.11 m2 117,914.50 128,742.90
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP

Pemasangan Dinding Bata Merah Ukuran


12 A.4.4.1.12 m2 116,036.25 126,747.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
Pemasangan Dinding Bata Merah Ukuran
13 A.4.4.1.13 (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : m2 118,511.25 129,222.50
10PP
Pemasangan Dinding Bata Merah Ukuran
14 A.4.4.1.14 m2 105,924.50 115,241.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP
Pemasangan Dinding Bata Merah Ukuran
15 A.4.4.1.15 (5x11x22)cm Tebal 1/2 Bata Camp. 1SM : 1KP : m2 107,464.50 117,067.50
2PP
Pemasangan Dinding HB/CB 20, speci camp. 1SP :
16 A.4.4.1.16 m2 423,093.00 459,534.90
3PP

Pemasangan Dinding HB/CB 20, speci camp. 1SP :


17 A.4.4.1.17 m2 432,049.75 469,443.70
4PP

Pemasangan Dinding HB/CB 15, speci camp. 1SP :


18 A.4.4.1.18 m2 332,961.75 361,501.80
3PP

668638447.xls 177/39 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Dinding HB/CB 15, speci camp. 1SP :
19 A.4.4.1.19 m2 339,311.50 368,533.00
4PP

Pemasangan Dinding HB/CB 10, speci camp. 1SP :


20 A.4.4.1.20 m2 267,069.00 295,247.70
3PP

Pemasangan Dinding HB/CB 10, speci camp. 1SP :


21 A.4.4.1.21 m2 272,295.38 301,016.10
4PP

Pemasangan Dinding Terawang (Rooster) Uk,


22 A.4.4.1.22 m2 366,795.00 472,532.50
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Terawang (Rooster) Uk,


23 A.4.4.1.23 m2 366,795.00 472,532.50
(12x11x24)cm Camp. 1SP : 4PP

Pemasangan Dinding Bata Berongga Ekspose Uk,


24 A.4.4.1.24 m2 149,385.50 160,121.50
(12x11x24)cm Camp. 1SP : 3PP

Pemasangan Dinding Bata Ringan Tebal 7,5 cm


25 A.4.4.1.25 m2 308,711.04 333,949.06
dengan Mortar Siap Pakai

Pemasangan Dinding Bata Ringan Tebal 10 cm


26 A.4.4.1.26 m2 309,274.24 332,520.71
dengan Mortar Siap Pakai

VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

1 A.4.4.2.1 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm m2 75,577.70 82,664.78

2 A.4.4.2.2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm m2 70,539.70 77,323.18


3 A.4.4.2.3 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm m2 68,632.30 75,312.82

4 A.4.4.2.4 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm m2 67,105.50 73,692.30

5 A.4.4.2.5 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm m2 66,546.70 73,112.38

6 A.4.4.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 65,970.30 72,505.62

7 A.4.4.2.7 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm m2 65,750.30 72,279.02

8 A.4.4.2.8 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm m2 65,530.30 72,052.42

Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15


9 A.4.4.2.9 m2 64,691.00 71,238.20
mm

Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15


10 A.4.4.2.10 m2 64,553.50 71,126.00
mm

Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15


11 A.4.4.2.11 m2 60,027.00 66,033.00
mm

Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15


12 A.4.4.2.12 m2 61,171.00 67,353.00
mm

13 A.4.4.2.13 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm m2 94,452.60 103,530.24

14 A.4.4.2.14 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm m2 71,229.00 77,866.60


15 A.4.4.2.15 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm m2 89,749.00 98,553.40

16 A.4.4.2.16 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm m2 89,128.60 97,915.84

17 A.4.4.2.17 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm m2 88,235.40 96,971.16

668638447.xls 177/40 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20
18 A.4.4.2.18 m2 85,613.00 94,050.00
mm

19 A.4.4.2.19 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm m2 41,483.20 45,419.88

Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10


20 A.4.4.2.20 m' 71,590.75 77,825.00
mm

Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal


21 A.4.4.2.21 m' 104,626.50 115,032.50
10 mm

Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10


22 A.4.4.2.22 m' 104,626.50 115,032.50
mm

23 A.4.4.2.23 Pemasangan Plesteran Ciprat 1Pc : 2 Pp m2 50,682.50 55,911.90

Pemasangan Finishing Siar Pasangan Dinding Bata


24 A.4.4.2.24 m2 29,190.15 32,097.56
Merah

Pemasangan Finishing Siar Pasangan Dinding


25 A.4.4.2.25 m2 13,882.00 15,257.00
Conblock ekspose

Pemasangan Finishing Siar Pas.Batu Kali Adukan


26 A.4.4.2.26 m2 62,741.25 68,940.30
1Pc : 2Pp

27 A.4.4.2.27 Pemasangan Acian m2 37,626.88 41,415.00

28 A.4.4.2.28 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) m2 46,158.20 50,026.90

29 A.4.4.2.29 Pemasangan Acian dg Mortar Siap Pakai (MSP) m2 40,040.00 43,738.75

HARGA SATUAN PEKERJAAN PENUTUP LANTAI


VIII A.4.4.3 dan DINDING

Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30


1 A.4.4.3.2 m2 112,896.50 123,178.50
cm

Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20


2 A.4.4.3.3 m2 114,851.00 125,455.00
cm

3 A.4.4.3.5 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm m2 138,521.50 161,503.50

4 A.4.4.3.6 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm m2 140,866.00 161,513.00

5 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm m2 354,244.00 403,133.50


6 A.4.4.3.16 Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm m' 69,872.00 78,840.30

7 A.4.4.3.19 Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm m' 40,675.25 44,316.80

8 A.4.4.3.32 Pemasangan Lantai Keramik 10x 20 cm m2 236,157.63 288,390.30

Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20


9 A.4.4.3.33 m2 241,602.63 295,815.30
cm

10 A.4.4.3.34 Pemasangan Lantai Keramik 33 x 33 cm m2 237,517.96 281,126.63

11 A.4.4.3.35 Pemasangan Lantai Keramik 30 x 30 cm m2 236,192.50 278,788.50

12 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm m2 236,879.50 277,326.50

Pemasangan Lantai Keramik uk.10 x 33 cm, untuk


13 A.4.4.3.37 m2 437,426.00 484,500.50
variasi / border

14 A.4.4.3.39 Pemasangan Plint Keramik Ukuran 10x20 cm m' 39,184.75 44,536.80

15 A.4.4.3.40 Pemasangan Plint Keramik Ukuran 10x10 cm m' 85,544.25 91,589.30

668638447.xls 177/41 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
16 A.4.4.3.41 Pemasangan Plint Keramik Ukuran 5x20 cm m' 83,212.25 90,423.30

17 A.4.4.3.43 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm m2 706,297.63 729,468.30

18 A.4.4.3.44 Pemasangan Lantai Karpet m2 206,618.50 220,269.50

19 A.4.4.3.46 Pemasangan Lantai Parquet Jati m2 465,767.50 530,887.50

20 A.4.4.3.48 Pemasangan Dinding Porselen 11 x 11 cm m2 267,994.41 300,209.32


21 A.4.4.3.49 Pemasangan Dinding Porselen 10x20 cm m2 261,038.25 315,991.50

22 A.4.4.3.50 Pemasangan Dinding Porselen 20x20 cm m2 255,857.25 303,330.50

23 A.4.4.3.53 Pemasangan Dinding Keramik 10x20 cm m2 261,038.25 315,991.50

24 A.4.4.3.54 Pemasangan Dinding Keramik 20x20 cm m2 257,067.25 304,958.50

25 A.4.4.3.55 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm m2 805,007.62 838,428.92

Pemasangan Dinding Batu Paros / Batu Tempel


26 A.4.4.3.58 m2 278,348.13 298,842.50
Hitam

27 A.4.4.3.59 Pemasangan Lantai Vynil uk.30 x 30 cm m2 152,684.40 165,335.50

28 A.4.4.3.60 Pemasangan Wallpaper Lebar 50 Cm m2 122,551.00 132,055.00


29 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' 50,391.00 61,699.00

30 A.4.4.3.64 Pemasangan Paving Block Natural Tebal 6 Cm m2 184,324.25 200,459.05

31 A.4.4.3.65 Pemasangan Paving Block Natural Tebal 8 Cm m2 251,699.25 271,068.05

32 A.4.4.3.66 Pemasangan Paving Block Berwarna Tebal 6 Cm m2 196,545.25 212,680.05

33 A.4.4.3.67 Pemasangan Paving Block Berwarna Tebal 8 Cm m2 257,809.75 277,178.55

HARGA SATUAN PEKERJAAN LANGIT-


IX A.4.5.1
LANGIT

Pemasangan Langit-langit Asbes (1,00x1,00) m,


1 A.4.5.1.1 m2 32,351.00 35,414.50
tebal 4 mm, 5 mm & 6 mm

Pemasangan Langit-langit Akustik Ukuran (30x30)


2 A.4.5.1.2 m2 106,326.00 118,541.50
cm

Pemasangan Langit-langit Akustik Ukuran (30x60)


3 A.4.5.1.3 m2 109,158.50 119,955.00
cm

Pemasangan Langit-langit Akustik Ukuran (60x120)


4 A.4.5.1.4 m2 94,242.50 103,345.00
cm

Memasang Langit-langit Tripleks Uk (120x240) cm,


5 A.4.5.1.5 m2 51,425.00 57,997.50
Tebal 3 mm, 4 mm & 6 mm

Memasang Langit-langit Lambriziring Kayu Jati,


6 A.4.5.1.6 m2 556,105.00 591,552.50
tebal 6 mm

Memasang Langit-langit Gypsu Board, Ukuran


7 A.4.5.1.7 m2 42,641.50 47,665.20
(120x240) tebal 9 mm

Memasang Langit-langit Akustik Uk (60x120) cm &


8 A.4.5.1.8 m2 229,652.50 250,717.50
Berikut Rangka Allumunium

9 A.4.5.1.9 List Langit-Langit Kayu Profil m1 17,836.50 19,283.00

668638447.xls 177/42 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
HARGA SATUAN PEKERJAAN PENUTUP
X A.4.5.2
ATAP
1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil m2 88,522.50 99,418.00

2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glasur m2 142,219.00 147,620.00

3 A.4.5.2.3 Pemasangan Atap Genteng Plentong Super / Besar m2 126,324.00 133,925.00

4 A.4.5.2.4 Pemasangan Genteng Bubung Plentong m' 109,978.00 119,086.00


5 A.4.5.2.5 Pemasangan Genteng Bubung Kodok / Glasur m' 122,353.00 132,561.00

6 A.4.5.2.6 Pemasangan Genteng Bubung Plentong Besar m' 126,203.00 135,641.00

7 A.4.5.2.7 Pemasangan Roof Light Fibreglass 90 x 180 m2 106,452.50 118,921.00


Pemasangan Atap Asbes Gelombang (2,50x0,92 m)
8 A.4.5.2.8 m2 65,835.00 73,843.00
x 5 mm

Pemasangan Atap Asbes Gelombang (2,25x0,92 m)


9 A.4.5.2.9 m2 67,479.50 75,817.50
x 5 mm

Pemasangan Atap Asbes Gelombang (2,00x0,92 m)


10 A.4.5.2.10 m2 67,809.50 76,477.50
x 5 mm

Pemasangan Atap Asbes Gelombang (1,80x0,92 m)


11 A.4.5.2.11 m2 75,069.50 79,315.50
x 5 mm

Pemasangan Atap Asbes Gelombang (3,00x1,05 m)


12 A.4.5.2.12 m2 58,102.00 73,980.50
x 4 mm

Pemasangan Atap Asbes Gelombang (2,70x1,05 m)


13 A.4.5.2.13 m2 60,219.50 76,213.50
x 4 mm

Pemasangan Atap Asbes Gelombang (2,40x1,05 m)


14 A.4.5.2.14 m2 58,239.50 74,629.50
x 4 mm

Pemasangan Atap Asbes Gelombang (2,10x1,05 m)


15 A.4.5.2.15 m2 58,949.00 73,606.50
x 4 mm

Pemasangan Atap Asbes Gelombang (1,50x1,05 m)


16 A.4.5.2.16 m2 62,529.50 76,565.50
x 4 mm

Pemasangan Atap Asbes Gelombang (3,00x1,08 m)


17 A.4.5.2.17 m2 67,490.50 70,900.50
x 6 mm

Pemasangan Atap Asbes Gelombang (2,70x1,08 m)


18 A.4.5.2.18 m2 70,845.50 74,365.50
x 6 mm

Pemasangan Atap Asbes Gelombang (2,40x1,08 m)


19 A.4.5.2.19 m2 67,677.50 71,725.50
x 6 mm

Pemasangan Atap Asbes Gelombang (2,10x1,08 m)


20 A.4.5.2.20 m2 68,689.50 72,902.50
x 6 mm

Pemasangan Atap Asbes Gelombang (1,80x1,08 m)


21 A.4.5.2.21 m2 72,594.50 76,444.50
x 6 mm

22 A.4.5.2.30 Pemasangan Atap Genteng Beton m2 111,540.00 124,822.50

23 A.4.5.2.31 Pemasangan Atap Genteng Aspal m2 228,294.00 255,524.50

24 A.4.5.2.32 Pemasangan Atap Genteng Metal m2 93,005.00 108,295.00

25 A.4.5.2.34 Pemasangan Atap Sirap m2 116,633.00 127,072.00

668638447.xls 177/43 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
26 A.4.5.2.35 Pemasangan Nok Genteng Beton m' 131,483.00 144,842.50

27 A.4.5.2.36 Pemasangan Nok Genteng Aspal m' 130,845.00 142,928.50

28 A.4.5.2.37 Pemasangan Nok Genteng Metal m' 70,757.50 78,628.00

29 A.4.5.2.38 Pemasangan Nok Sirap m' 61,655.00 68,183.50

30 A.4.5.2.39 Pemasangan Atap Seng Gelombang m2 40,513.00 45,760.00


31 A.4.5.2.40 Pemasangan Atap Nok Seng m' 33,506.00 37,499.00

32 A.4.5.2.43 Pasang Allumunium Foil / Sisalation m2 35,475.00 41,283.00

XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U

Pembuatan & Pemasangan Kosen Pintu & Jendela


1 A.4.6.1.1 m3 27,970,800.00 28,922,437.50
Kayu klas I

Pembuatan & Pemasangan Kosen Pintu & Jendela


2 A.4.6.1.2 m3 11,289,025.00 13,435,812.50
Kayu klas II atau III

Pembuatan & Pemasangan Pintu KlampStandard


3 A.4.6.1.3 m2 504,515.00 547,805.50
Kayu Klas II (Kayu Kamfer)

Pembuatan & Pemasangan Daun Pintu Klamp


4 A.4.6.1.4 m2 504,515.00 547,805.50
Sederhana Kayu Klas III

Pembuatan & Pemasangan Daun Pintu Panel, Kayu


5 A.4.6.1.5 m2 851,262.50 925,925.00
Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Kaca


6 A.4.6.1.6 m2 621,225.00 677,820.00
Kayu Klas I atau II

Pembuatan & Pemasangan Pintu & Jendela Jalusi


7 A.4.6.1.7 m2 2,089,450.00 2,211,825.00
Kayu Klas I atau II (jati)

Pembuatan&Pemasangan Pintu kayu lapis


8 A.4.6.1.8 (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 m2 650,512.50 726,715.00
cm)

Pembuatan&Pemasangan Pintu Plywood rangkap,


9 A.4.6.1.9 m2 708,642.00 790,025.50
rangka expose kayu klas I atau II

Pembuatan & Pemasangan Jalusi mati Kosen Kayu


10 A.4.6.1.10 m2 1,852,097.50 1,953,765.00
Klas I atau II

Pembuatan & Pemasangan Pintu Teakwood


11 A.4.6.1.11 m2 1,108,140.00 1,198,477.50
Rangkap, Rangka Expose Kayu Klas I

Pembuatan & Pemasangan Pintu Teakwood


12 A.4.6.1.12 Rangkap Lapis Formika, Rangka expose Kayu Klas m2 763,372.50 846,043.00
II

Pembuatan&Memasang Konstruksi Kuda-kuda


13 A.4.6.1.13 m3 9,839,500.00 11,744,425.00
Konvensional Kayu I; II & III Bentang 6 meter

Pembuatan&Pemasangan Konstruksi Kuda-kuda


14 A.4.6.1.14 m3 30,299,692.50 31,299,812.50
Expose, Kayu Klas I

15 A.4.6.1.15 Pemasangan konstruksi Gording, Kayu Klas II m3 8,942,560.00 10,763,775.00

Pemasangan Rangka Atap Genteng Keramik, Kayu


16 A.4.6.1.16 m2 146,338.50 176,495.00
Klas II

668638447.xls 177/44 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Rangka Atap Genteng Beton, Kayu
17 A.4.6.1.17 m2 170,494.50 206,195.00
Klas II

18 A.4.6.1.18 Pemasangan Rangka Atap Sirap, Kayu Klas II m2 126,181.00 151,129.00

Pemasangan Rangka Langit-langit (50x1,00) m,


19 A.4.6.1.19 m2 174,036.50 204,407.50
kayu Klas II atau III

Pemasangan Rangka Langit-langit (60x60) cm, kayu


20 A.4.6.1.20 m2 176,363.00 208,092.50
Klas II atau III

Pemasangan Listplank Uk. (3x20)cm Kayu klas I


21 A.4.6.1.21 m' 301,757.50 317,487.50
atau II

Pemasangan Listplank Uk. (3x30)cm Kayu klas I


22 A.4.6.1.22 m' 126,692.50 137,665.00
atau klas II

Pemasangan Rangka Dinding Pemisah (60x120) cm


23 A.4.6.1.23 m2 270,490.00 321,205.50
Kayu klas II atau III

Pemasangan Dinding Pemisah Teakwood Rangkap


24 A.4.6.1.24 m2 339,680.00 413,935.50
Rangka Kayu Klas II

Pemasangan Dinding Pemisah Plywood Rangkap


25 A.4.6.1.25 m2 350,460.00 425,122.50
Rangka Kayu Klas II

Pemasangan Dinding Lambriziring dari Papan Kelas


26 A.4.6.1.26 m2 492,470.00 529,320.00
I

Pemasangan Dinding Lambriziring dari Plywood


27 A.4.6.1.27 m2 42,806.50 48,543.00
ukuran (120x240) cm

Pemasangan Dinding Bilik, Rangka Kayu Klas III


28 A.4.6.1.28 m2 123,936.34 143,715.00
atau IV

HARGA SATUAN PEKERJAAN KUNCI dan


XII A.4.6.2
KACA

1 A.4.6.2.2 Pemasangan Kunci Tanam Biasa Buah 211,997.50 261,772.50


2 A.4.6.2.3 Pemasangan Kunci Kamar Mandi Buah 171,998.75 238,136.25

3 A.4.6.2.4 Pemasangan Kunci Selinder Buah 210,498.75 260,136.25

4 A.4.6.2.5 Pemasangan Engsel Pintu Buah 32,546.25 36,258.75

5 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu Buah 21,147.50 24,172.50

6 A.4.6.2.7 Pemasangan Engsel Angin Buah 55,728.75 74,654.25

7 A.4.6.2.9 Pemasangan Kait Angin Buah 43,615.00 48,433.00

8 A.4.6.2.10 Pasang Door Closer Buah 380,393.75 469,521.25

9 A.4.6.2.11 Pemasangan Kunci Selot Buah 39,957.50 44,808.50


10 A.4.6.2.13 Pemasangan Door Stop Buah 318,078.75 401,904.25

11 A.4.6.2.14 Pemasangan Rel Pintu Dorong Buah 313,472.50 359,925.50

12 A.4.6.2.15 Pemasangan Kunci Lemari Buah 52,703.75 58,768.05

13 A.4.6.2.16 Pemasangan Kaca tebal 3 mm m2 114,118.13 128,206.38

14 A.4.6.2.17 Pemasangan Kaca tebal 5 mm m2 132,268.13 140,306.38

15 A.4.6.2.18 Pemasangan Kaca Cermin tebal 5 mm m2 356,118.13 418,606.38

668638447.xls 177/45 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
HARGA SATUAN PEKERJAAN
XIII A.4.7.1
PENGECATAN

Pengikisan / pengerokan Permukaan Cat Tembok


1 A.4.7.1.1 m2 14,327.50 16,120.50
Lama

Pencucian Bidang Permukaan Tembok yang Pernah


2 A.4.7.1.2 m2 14,300.00 16,120.50
dicat

Pengerokan Karat Cat Lama permukaan Baja dg


3 A.4.7.1.3 m2 14,987.50 16,863.00
cara manual

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp


4 A.4.7.1.4 m2 44,302.50 51,144.50
Cat dasar, 2 Lp Cat Penutup)

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp


5 A.4.7.1.5 m2 62,628.50 71,593.50
Cat dasar, 3 Lp Cat Penutup)

6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil m2 37,493.50 39,748.50

7 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur m2 59,163.50 61,792.50

8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 10,683.75 11,946.00

9 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis m2 43,785.50 47,855.50

Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar


10 A.4.7.1.10 m2 22,037.40 25,010.70
2 Lap.Cat Penutup)

Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat


11 A.4.7.1.11 m2 15,159.10 16,998.30
Penutup)

12 A.4.7.1.12 Pengecatan Tembok dengan Kalkarium m2 9,516.10 10,420.30

13 A.4.7.1.13 Pelaburan Tembok dengan Kapur Sirih m2 15,862.55 17,838.15

Pelaburan Tembok lama dengan Kapur Sirih


14 A.4.7.1.14 m2 7,317.75 8,280.25
(pemeliharaan)

15 A.4.7.1.15 Pemasangan Wallpaper m2 89,663.75 101,131.25

16 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 32,144.75 35,934.25

Pengecatan Permukaan Baja dg Meni Besi &


17 A.4.7.1.17 m2 60,486.25 67,553.75
Perancah

HARGA SATUAN PEKERJAAN SANITASI


XIV A.5.1.1
DALAM GEDUNG

1 A.5.1.1.1 Pemasangan Closet Duduk / Mono Blok Unit 2,323,343.00 2,665,014.00

2 A.5.1.1.2 Pemasangan Closet Jongkok Porselen Unit 693,165.00 756,250.00

3 A.5.1.1.4 Pemasangan Urinoir Unit 759,715.00 820,490.00

4 A.5.1.1.5 Pemasangan Wastafel Unit 600,105.00 654,225.00

5 A.5.1.1.6 Pemasangan Bathcuip porselen Unit 1,106,737.50 1,182,670.50

6 A.5.1.1.7 Pemasangan Bak Fibreglass vol.1 m3 Unit 1,327,700.00 1,451,450.00

7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,606,154.27 1,768,063.54

8 A.5.1.1.11 Pemasangan Bak Beton Bertulang Vol. 1 m3 Unit 6,472,506.25 7,448,583.37

9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 351,092.50 393,717.50
10 A.5.1.1.14 Pemasangan Floor Drain buah 54,697.50 64,322.50

668638447.xls 177/46 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
Rp Rp
Pemasangan Bak Kontrol Pas.Batu Bata 30x30
11 A.5.1.1.15 bh 470,032.60 518,070.65
tinggi 35 cm

Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45


12 A.5.1.1.16 bh 692,034.60 761,539.15
tinggi 50 cm

Pemasangan Bak Kontrol Pas.Batu Bata 60x60


13 A.5.1.1.17 bh 832,171.10 918,674.18
tinggi 60 cm

14 A.5.1.1.18 Pemasangan Pipa Galvanis Ø ½" m' 65,677.33 69,078.17

15 A.5.1.1.19 Pemasangan Kran Ø ½" atau Ø ¾" bh 87,597.13 114,604.88

16 A.5.1.1.20 Pemasangan Pipa Galvanis Ø ¾" m' 77,044.00 80,444.83

17 A.5.1.1.21 Pemasangan Pipa Galvanis Ø 1" m' 108,302.33 113,124.00

18 A.5.1.1.22 Pemasangan Pipa Galvanis Ø 1½ " m' 144,508.83 150,771.50


19 A.5.1.1.23 Pemasangan Pipa Galvanis Ø 3" m' 256,114.83 263,814.83

20 A.5.1.1.24 Pemasangan Pipa Galvanis Ø 4" m' 459,294.00 465,715.25

21 A.5.1.1.25 Pemasangan Pipa PVC tipe AW Ø ½" m' 24,156.00 26,578.75

22 A.5.1.1.26 Pemasangan Pipa PVC tipe AW Ø ¾" m' 26,713.50 28,923.13

23 A.5.1.1.27 Pemasangan Pipa PVC tipe AW Ø 1" m' 31,402.25 36,808.75

24 A.5.1.1.28 Pemasangan Pipa PVC tipe AW Ø 1½" m' 34,244.83 39,939.17

25 A.5.1.1.29 Pemasangan Pipa PVC tipe AW Ø 2" m' 38,223.17 49,885.00

26 A.5.1.1.31 Pemasangan Pipa PVC tipe AW Ø 3" m' 62,949.33 82,567.83


27 A.5.1.1.32 Pemasangan Pipa PVC tipe AW Ø 4" m' 88,946.00 92,931.67

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø


28 A.5.1.1.33 m' 82,054.50 91,256.00
20 cm

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø


29 A.5.1.1.34 m' 39,374.50 44,786.50
15 cm

30 A.5.1.1.35 Pemasangan Pipa Beton Ø 15 - 20 cm m' 117,727.50 134,740.65

31 A.5.1.1.36 Pemasangan Pipa Beton Ø 30 - 100 cm m' 589,459.75 633,798.00

XV A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 A.8.4.6.1 Pemasangan Lampu Titik 385,880.00 431,508.00

2 A.8.4.6.2 Pemasangan MCB buah 488,840.00 536,448.00

668638447.xls 177/47 hspk


DAFTAR HARGA SATUAN PEKERJAAN (AHSP) NO.28/PRT/M/2016
BIDANG CIPTA KARYA
SUMBER DATA : PASARAN BEBAS
D A E R A H : KOTA SEMARANG & SEKITAR
EDISI 02 2019

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
I A. 2.2.1 K.3 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi
1 A.2.2.1.2 1 m' 600,272.75 691,977.00
2,00 m
A TENAGA 69,100.00 75,500.00
L.01 0.2 OH Pekerja 80,000.00 90,000.00 16,000.00 18,000.00
L.02 0.4 OH Tukang Kayu 120,000.00 130,000.00 48,000.00 52,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.02 OH Mandor 125,000.00 135,000.00 2,500.00 2,700.00
B BAHAN 476,602.50 553,570.00
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 21,000.00 24,000.00 26,250.00 30,000.00
2.5 Kg Portalnd Semen 1,125.00 1,200.00 2,812.50 3,000.00
1.2 Lbr Seng Gelombang 3" - 5" 47,000.00 55,000.00 56,400.00 66,000.00
0.005 m3 Pasir Beton 360,000.00 380,000.00 1,800.00 1,900.00
0.009 m3 Koral Beton 310,000.00 380,000.00 2,790.00 3,420.00
0.072 m3 Kayu 5/7X4m Kayu Kruing 5,200,000.00 6,000,000.00 374,400.00 432,000.00
0.06 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 900.00 1,050.00
0.45 Kg Meni Besi 25,000.00 36,000.00 11,250.00 16,200.00
C PERALATAN
D Jumlah A + B + C 545,702.50 629,070.00
E Overhead & Profit (contah 10%) 10% 54,570.25 62,907.00
F Harga Satuan Pekerjaan (D+E) 600,272.75 691,977.00
Overhead & Profit (contah 10%)
2 A.2.2.1.4 1 m' Pengukuran dan Pemasangan Bouwplank 141,212.50 173,827.50
A Tenaga 21,925.00 24,075.00
L.01 0.1 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 106,450.00 133,950.00
0.012 m3 Kayu 5/7x 4m Kayu Kruing 5,200,000.00 6,000,000.00 62,400.00 72,000.00
0.02 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 300.00 350.00
0.007 m3 Kayu Papan 3/20 Kruing 6,250,000.00 8,800,000.00 43,750.00 61,600.00
C PERALATAN
D Jumlah A + B + C 128,375.00 158,025.00
E Overhead & Profit (contah 10%) 10% 12,837.50 15,802.50
F Harga Satuan Pekerjaan (D+E) 141,212.50 173,827.50

3 A.2.2.1.5 K.3 1 m2 Pembuatan Kantor Sementara dg Lantai Plesteran 1,972,217.50 2,228,435.00

A Tenaga 565,250.00 618,750.00


L.01 2 OH Pekerja 80,000.00 90,000.00 160,000.00 180,000.00
L.02 2 OH Tukang Kayu 120,000.00 130,000.00 240,000.00 260,000.00
L.02 1 OH Tukang Batu 120,000.00 130,000.00 120,000.00 130,000.00
L.03 0.3 OH Kepala Tukang 130,000.00 140,000.00 39,000.00 42,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 1,227,675.00 1,407,100.00
1.25 Btg Kayu Dolken Ø 8 - 10 / 4 m 21,000.00 24,000.00 26,250.00 30,000.00
0.18 m3 Kayu 5,200,000.00 6,000,000.00 936,000.00 1,080,000.00
0.80 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 12,000.00 14,000.00
1.1 Kg Besi Strip 14,000.00 14,250.00 15,400.00 15,675.00
35 Kg Portland Sement 1,125.00 1,200.00 39,375.00 42,000.00
0.15 m3 Pasir pasang 340,000.00 370,000.00 51,000.00 55,500.00
0.1 m3 Pasir Beton 360,000.00 380,000.00 36,000.00 38,000.00
0.15 m3 Koral Beton 310,000.00 380,000.00 46,500.00 57,000.00
30 buah Batu bata Merah 600.00 650.00 18,000.00 19,500.00
0.25 Lbr Seng Plat 20,000.00 24,500.00 5,000.00 6,125.00
0.20 buah Jendela Naco 37,500.00 40,000.00 7,500.00 8,000.00
0.08 m2 Kaca Polos 75,000.00 85,000.00 6,000.00 6,800.00
0.15 buah Kunci Tanam 165,000.00 200,000.00 24,750.00 30,000.00
0.06 Lbr Plywood 4 mm 65,000.00 75,000.00 3,900.00 4,500.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 1,792,925.00 2,025,850.00
E Overhead & Profit (contah 10%) 10% 179,292.50 202,585.00
F Harga Satuan Pekerjaan (D+E) 1,972,217.50 2,228,435.00

4 A.2.2.1.6 K.3 1 m2 Pembuatan Rumah Jaga (Konstruksi Kayu) 1,503,975.00 1,717,375.00


A Tenaga 285,750.00 312,750.00
L.01 1 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00
L.02 1.50 OH Tukang Kayu 120,000.00 130,000.00 180,000.00 195,000.00
L.03 0.15 OH Kepala Tukang 130,000.00 140,000.00 19,500.00 21,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 1,081,500.00 1,248,500.00
3.00 Btg Kayu Dolken Ø 8 - 10 / 4 m 21,000.00 24,000.00 63,000.00 72,000.00
0.18 m3 Kayu 5,200,000.00 6,000,000.00 936,000.00 1,080,000.00
0.80 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 12,000.00 14,000.00
1.50 Lbr Seng Gelombang 47,000.00 55,000.00 70,500.00 82,500.00
C PERALATAN
D Jumlah A + B + C 1,367,250.00 1,561,250.00
E Overhead & Profit (contah 10%) 10% 136,725.00 156,125.00
F Harga Satuan Pekerjaan (D+E) 1,503,975.00 1,717,375.00

5. A.2.2.1.7 K.3 1 m2 Pembuatan Gudang Semen dan Peralatan 1,370,393.75 1,581,442.50


A Tenaga 352,250.00 384,750.00
L.01 1 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00
L.02 2 OH Tukang Kayu 120,000.00 130,000.00 240,000.00 260,000.00
L.03 0.2 OH Kepala Tukang 130,000.00 140,000.00 26,000.00 28,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 1,240,812.50 1,431,550.00
1.7 Btg Kayu Dolken diameter 8 - 10 / 400 cm 21,000.00 24,000.00 35,700.00 40,800.00
0.21 m3 Kayu 5,200,000.00 6,000,000.00 1,092,000.00 1,260,000.00
0.3 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 4,500.00 5,250.00
10.5 Kg Portland Semen 1,125.00 1,200.00 11,812.50 12,600.00
0.03 m3 Pasir Beton 360,000.00 380,000.00 10,800.00 11,400.00
0.05 m3 Koral Beton 310,000.00 380,000.00 15,500.00 19,000.00
1.5 Lbr Seng Gelombang 47,000.00 55,000.00 70,500.00 82,500.00
0.25 Lbr Seng Plat 20,000.00 24,500.00 5,000.00 6,125.00
C PERALATAN
D Jumlah A + B + C 1,245,812.50 1,437,675.00
E Overhead & Profit (contah 10%) 10% 124,581.25 143,767.50
F Harga Satuan Pekerjaan (D+E) 1,370,393.75 1,581,442.50

6. A.2.2.1.8 K.3 1 m2 Pembuatan Bedeng Pekerja 1,732,775.00 1,978,625.00


A Tenaga 352,250.00 384,750.00
L.01 1 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00
L.02 2 OH Tukang Kayu 120,000.00 130,000.00 240,000.00 260,000.00
L.03 0.2 OH Kepala Tukang 130,000.00 140,000.00 26,000.00 28,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 1,223,000.00 1,414,000.00
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 21,000.00 24,000.00 26,250.00 30,000.00
0.186 m3 Kayu 5,200,000.00 6,000,000.00 967,200.00 1,116,000.00
0.30 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 4,500.00 5,250.00
18.00 Kg Portland Semen 1,125.00 1,200.00 20,250.00 21,600.00
0.03 m3 Pasir Beton 360,000.00 380,000.00 10,800.00 11,400.00
0.05 m3 Koral Beton 310,000.00 380,000.00 15,500.00 19,000.00
1.50 Lbr Seng Gelombang 47,000.00 55,000.00 70,500.00 82,500.00
1.35 Lbr Playwood 80,000.00 95,000.00 108,000.00 128,250.00
C PERALATAN
D Jumlah A + B + C 1,575,250.00 1,798,750.00
E Overhead & Profit (contah 10%) 10% 157,525.00 179,875.00
F Harga Satuan Pekerjaan (D+E) 1,732,775.00 1,978,625.00

7. A.2.2.1.9 K.3 1 m2 Membersihkan Lapangan dan Perataan 15,675.00 17,325.00


A Tenaga 14,250.00 15,750.00
L.01 0.1 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 14,250.00 15,750.00
E Overhead & Profit (contah 10%) 10% 1,425.00 1,575.00
F Harga Satuan Pekerjaan (D+E) 15,675.00 17,325.00

8 A.2.2.1.10 K.3 1 m2 Pembuatan Steger/Perancah dari Bambu 405,407.20 449,448.12


A Tenaga 352,250.00 384,750.00
L.01 1.00 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00
L.02 2.00 OH Tukang Kayu 120,000.00 130,000.00 240,000.00 260,000.00
L.03 0.20 OH Kepala Tukang 130,000.00 140,000.00 26,000.00 28,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 16,302.00 23,839.20
1.250 Btg Bambu diameter 6 - 8 / 600 cm 12,000.00 18,000.00 15,000.00 22,500.00
0.186 Kg Tali Ijuk 7,000.00 7,200.00 1,302.00 1,339.20
C PERALATAN
D Jumlah A + B + C 368,552.00 408,589.20
E Overhead & Profit (contah 10%) 10% 36,855.20 40,858.92
F Harga Satuan Pekerjaan (D+E) 405,407.20 449,448.12

Pembuatan Kotak Adukan ukuran


9 A.2.2.1.11 1 bh 498,630.00 635,140.00
40cmx50cmx25cm
A Tenaga 39,900.00 43,200.00
L.02 0.30 OH Tukang Kayu 120,000.00 130,000.00 36,000.00 39,000.00
L.03 0.03 OH Kepala Tukang 130,000.00 140,000.00 3,900.00 4,200.00
B Bahan 413,400.00 534,200.00
0.036 m3 Kayu Papan Kelas III 6,250,000.00 8,800,000.00 225,000.00 316,800.00
0.036 m3 Kayu Balok Kelas III 5,200,000.00 6,000,000.00 187,200.00 216,000.00
0.080 kg Paku Biasa 15,000.00 17,500.00 1,200.00 1,400.00
C PERALATAN
D Jumlah A + B + C 453,300.00 577,400.00
E Overhead & Profit (contah 10%) 10% 45,330.00 57,740.00
F Harga Satuan Pekerjaan (D+E) 498,630.00 635,140.00

10 A.2.2.1.12 1 m2 Pembuatan Jalan Sementara 165,687.50 191,262.50


A Tenaga 80,625.00 90,675.00

L.01 1 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00

L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00


B. Bahan 70,000.00 83,200.00

0.150 m3 Batu Belah 270,000.00 320,000.00 40,500.00 48,000.00


0.090 m3 Batu Pecah 290,000.00 350,000.00 26,100.00 31,500.00

0.010 m3 Pasir Pasang 340,000.00 370,000.00 3,400.00 3,700.00

C PERALATAN
D Jumlah A + B + C 150,625.00 173,875.00
E Overhead & Profit (contah 10%) 10% 15,062.50 17,387.50
F Harga Satuan Pekerjaan (D+E) 165,687.50 191,262.50

11 A.2.2.1.13 1 m3 Bongkaran Beton Bertulang 1,264,967.00 1,418,967.00


A Tenaga 1,149,970.00 1,289,970.00
L.01 13.334 OH Pekerja 80,000.00 90,000.00 1,066,720.00 1,200,060.00
L.04 0.666 OH Mandor 125,000.00 135,000.00 83,250.00 89,910.00
B Bahan
C PERALATAN
D Jumlah A + B + C 1,149,970.00 1,289,970.00
E Overhead & Profit (contah 10%) 10% 114,997.00 128,997.00
F Harga Satuan Pekerjaan (D+E) 1,264,967.00 1,418,967.00

12 A.2.2.1.14 1 m3 Bongkaran Dinding Tembok Bata Merah 591,233.50 664,933.50


A Tenaga 537,485.00 604,485.00
L.01 6.667 OH Pekerja 80,000.00 90,000.00 533,360.00 600,030.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00
B Bahan
C PERALATAN
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
D Jumlah A + B + C 537,485.00 604,485.00
E Overhead & Profit (contah 10%) 10% 53,748.50 60,448.50
F Harga Satuan Pekerjaan (D+E) 591,233.50 664,933.50

13 A.2.2.1.15 1 m2 Pagar Kawat Jaring Galvanis Panjang 240 cm 59,184.40 62,540.50


A Tenaga 9,350.00 10,250.00

L.01 0.042 OH Pekerja 80,000.00 90,000.00 3,360.00 3,780.00


L.02 0.004 OH Tukang 120,000.00 130,000.00 480.00 520.00
L.03 0.002 OH Kepala Tukang 130,000.00 140,000.00 260.00 280.00
L.04 0.042 OH Mandor 125,000.00 135,000.00 5,250.00 5,670.00
B Bahan 44,454.00 46,605.00

0.1434 Lbr Kawat Jaring 310,000 325,000 44,454.00 46,605.00


C PERALATAN
D Jumlah A + B + C 53,804.00 56,855.00
E Overhead & Profit (contah 10%) 10% 5,380.40 5,685.50
F Harga Satuan Pekerjaan (D+E) 59,184.40 62,540.50

Pemasangan Pagar Panel Beton Pracetak 5 x 50 x


14 A.2.2.1.16 1 m2 313,538.50 346,453.25
240 cm
A Tenaga 48,935.00 54,245.00
L.01 0.375 OH Pekerja 80,000.00 90,000.00 30,000.00 33,750.00
L.02 0.125 OH Tukang Batu 120,000.00 130,000.00 15,000.00 16,250.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.019 OH Mandor 125,000.00 135,000.00 2,375.00 2,565.00
B Bahan 236,100.00 260,712.50
0.986 Lbr Panel Beton Pracetak 65,000.00 75,000.00 64,090.00 73,950.00
0.525 Btg Kolom Beton Pracetak 145,000.00 162,500.00 76,125.00 85,312.50
45.000 Kg Semen (SM) 1,125.00 1,200.00 50,625.00 54,000.00
0.146 m3 Koral 310,000.00 325,000.00 45,260.00 47,450.00
C PERALATAN
D Jumlah A + B + C 285,035.00 314,957.50
E Overhead & Profit (contah 10%) 10% 28,503.50 31,495.75
F Harga Satuan Pekerjaan (D+E) 313,538.50 346,453.25
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

1 A.2.3.1.1 1 m3 Menggali Tanah Biasa Sedalam 1 m 69,437.50 77,962.50


A TENAGA 63,125.00 70,875.00
L.01 0.75 OH Pekerja 80,000.00 90,000.00 60,000.00 67,500.00
L.04 0.025 OH Mandor 125,000.00 135,000.00 3,125.00 3,375.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 63,125.00 70,875.00
E Overhead & Profit (contah 10%) 10% 6,312.50 7,087.50
F Harga Satuan Pekerjaan (D+E) 69,437.50 77,962.50
Overhead & Profit (contah 10%)
2 A.2.3.1.2 1 m3 Menggali Tanah Biasa Sedalam 2 m 85,387.50 95,782.50
A TENAGA 77,625.00 87,075.00
L.01 0.90 OH Pekerja 80,000.00 90,000.00 72,000.00 81,000.00
L.04 0.045 OH Mandor 125,000.00 135,000.00 5,625.00 6,075.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 77,625.00 87,075.00
E Overhead & Profit (contah 10%) 10% 7,762.50 8,707.50
F Harga Satuan Pekerjaan (D+E) 85,387.50 95,782.50

3 A.2.3.1.3 1 m3 Menggali Tanah Biasa Sedalam 3 m 101,612.50 113,899.50


A TENAGA 92,375.00 103,545.00
L.01 1.05 OH Pekerja 80,000.00 90,000.00 84,000.00 94,500.00
L.04 0.067 OH Mandor 125,000.00 135,000.00 8,375.00 9,045.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 92,375.00 103,545.00
E Overhead & Profit (contah 10%) 10% 9,237.50 10,354.50
F Harga Satuan Pekerjaan (D+E) 101,612.50 113,899.50

4 A.2.3.1.4 1 m3 Menggali Tanah Keras Sedalam 1 m 92,400.00 103,752.00


TENAGA 84,000.00 94,320.00
L.01 1.000 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00
L.04 0.032 OH Mandor 125,000.00 135,000.00 4,000.00 4,320.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 84,000.00 94,320.00
E Overhead & Profit (contah 10%) 10% 8,400.00 9,432.00
F Harga Satuan Pekerjaan (D+E) 92,400.00 103,752.00

5 A.2.3.1.5 1 m3 Menggali Tanah Cadas Sedalam 1 m 140,250.00 157,410.00


A TENAGA 127,500.00 143,100.00
L.01 1.50 OH Pekerja 80,000.00 90,000.00 120,000.00 135,000.00
L.04 0.060 OH Mandor 125,000.00 135,000.00 7,500.00 8,100.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 127,500.00 143,100.00
E Overhead & Profit (contah 10%) 10% 12,750.00 14,310.00
F Harga Satuan Pekerjaan (D+E) 140,250.00 157,410.00

6 A.2.3.1.6 1 m3 Menggali Tanah Lumpur Sedalam 1 m 111,787.50 125,482.50


A TENAGA 101,625.00 114,075.00
L.01 1.200 OH Pekerja 80,000.00 90,000.00 96,000.00 108,000.00
L.04 0.045 OH Mandor 125,000.00 135,000.00 5,625.00 6,075.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 101,625.00 114,075.00
E Overhead & Profit (contah 10%) 10% 10,162.50 11,407.50
F Harga Satuan Pekerjaan (D+E) 111,787.50 125,482.50

7 A.2.3.1.7 1 m2 Mengerjakan Striping Tebing Setinggi 1 m 5,087.50 5,692.50


A TENAGA 4,625.00 5,175.00
L.01 0.05 OH Pekerja 80,000.00 90,000.00 4,000.00 4,500.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 4,625.00 5,175.00
E Overhead & Profit (contah 10%) 10% 462.50 517.50
F Harga Satuan Pekerjaan (D+E) 5,087.50 5,692.50

8 A.2.3.1.8 1 m3 MembuangTanah sejauh 30 m' 30,415.00 34,155.00


A TENAGA 27,650.00 31,050.00
L.01 0.330 OH Pekerja 80,000.00 90,000.00 26,400.00 29,700.00
L.04 0.010 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/52 2-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B BAHAN
C PERALATAN
D Jumlah A + B + C 27,650.00 31,050.00
E Overhead & Profit (contah 10%) 10% 2,765.00 3,105.00
F Harga Satuan Pekerjaan (D+E) 30,415.00 34,155.00

Pengurugan Kembali di hitung dari 1/3 kali koefisien


9 A.2.3.1.9 1 m3 16,958.33 18,975.00
Pekerjaan galian
A TENAGA 46,250.00 51,750.00
L.01 0.50 OH Pekerja 80,000.00 90,000.00 40,000.00 45,000.00
L.04 0.050 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 46,250.00 51,750.00
E Overhead & Profit (contah 10%) 10% 4,625.00 5,175.00
F Harga Satuan Pekerjaan (D+E) 50,875.00 56,925.00

10 A.2.3.1.10 1 m3 Pemadatan Tanah (per 20 cm) 50,875.00 56,925.00


A TENAGA 46,250.00 51,750.00
L.01 0.5 OH Pekerja 80,000.00 90,000.00 40,000.00 45,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 46,250.00 51,750.00
E Overhead & Profit (contah 10%) 10% 4,625.00 5,175.00
F Harga Satuan Pekerjaan (D+E) 50,875.00 56,925.00

11 A.2.3.1.11 1 m3 Urugan Pasir 238,975.00 321,585.00


A TENAGA 25,250.00 28,350.00
L.01 0.30 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B BAHAN 192,000.00 264,000.00
1.2 m3 Pasir Urug 160,000.00 220,000.00 192,000.00 264,000.00
C PERALATAN
D Jumlah A + B + C 217,250.00 292,350.00
E Overhead & Profit (contah 10%) 10% 21,725.00 29,235.00
F Harga Satuan Pekerjaan (D+E) 238,975.00 321,585.00

12 A.2.3.1.12 1 m3 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL 447,546.00 491,777.00


A TENAGA 127,200.00 140,400.00
L.01 0.800 OH Pekerja 80,000.00 90,000.00 64,000.00 72,000.00
L.02 0.400 OH Tukang Batu 120,000.00 130,000.00 48,000.00 52,000.00
L.03 0.04 OH Kepala Tukang 130,000.00 140,000.00 5,200.00 5,600.00
L.04 0.080 OH Mandor 125,000.00 135,000.00 10,000.00 10,800.00
B BAHAN 279,660.00 306,670.00
0.135 m3 Pasir Pasang 340,000.00 370,000.00 45,900.00 49,950.00
0.400 m3 Kapur Padam 300,000.00 310,000.00 120,000.00 124,000.00
0.948 m3 Tanah Liat 120,000.00 140,000.00 113,760.00 132,720.00
C PERALATAN
D Jumlah A + B + C 406,860.00 447,070.00
E Overhead & Profit (contah 10%) 10% 40,686.00 44,707.00
F Harga Satuan Pekerjaan (D+E) 447,546.00 491,777.00

Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang


13 A.2.3.1.13 1 m2 61,462.50 64,597.50
Resapan
A TENAGA 13,875.00 15,525.00
0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B BAHAN 42,000.00 43,200.00
6.00 kg Ijuk 7,000.00 7,200.00 42,000.00 43,200.00
C PERALATAN
D Jumlah A + B + C 55,875.00 58,725.00
E Overhead & Profit (contah 10%) 10% 5,587.50 5,872.50
F Harga Satuan Pekerjaan (D+E) 61,462.50 64,597.50

14 A.2.3.1.14 1 m3 Mengurug Sirtu Padat 263,037.50 292,462.50


A TENAGA 23,125.00 25,875.00
0.25 OH Pekerja 80,000.00 90,000.00 20,000.00 22,500.00
0.025 OH Mandor 125,000.00 135,000.00 3,125.00 3,375.00
B BAHAN 216,000.00 240,000.00
1.2 m3 Sirtu 180,000.00 200,000.00 216,000.00 240,000.00
C PERALATAN
D Jumlah A + B + C 239,125.00 265,875.00
E Overhead & Profit (contah 10%) 10% 23,912.50 26,587.50
F Harga Satuan Pekerjaan (D+E) 263,037.50 292,462.50

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/53 2-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 1 m3 Pemasangan Pondasi Batu Belah 1SP : 3 PP 1,053,002.50 1,191,272.50
A TENAGA 229,125.00 253,125.00
L.01 1.5 OH Pekerja 80,000.00 90,000.00 120,000.00 135,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B BAHAN 728,150.00 829,850.00
1.2 m3 Batu Belah 15/20 280,000.00 340,000.00 336,000.00 408,000.00
202 Kg Portland Sement 1,125.00 1,200.00 227,250.00 242,400.00
0.485 m3 Pasir Pasang 340,000.00 370,000.00 164,900.00 179,450.00
C PERALATAN
D Jumlah A + B + C 957,275.00 1,082,975.00
E Overhead & Profit (contoh 10%) 10% 95,727.50 108,297.50
F Harga Satuan Pekerjaan (D+E) 1,053,002.50 1,191,272.50
Overhead & Profit (contoh 10%)
2 A.3.2.1.2 1 m3 Pemasangan Pondasi Batu Belah 1SP : 4 PP 1,017,830.00 1,154,037.50
A TENAGA 229,125.00 253,125.00
L.01 1.5 OH Pekerja 80,000.00 90,000.00 120,000.00 135,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B BAHAN 696,175.00 796,000.00
1.2 m3 Batu Belah 15/20 280,000.00 340,000.00 336,000.00 408,000.00
163 Kg Portland Sement 1,125.00 1,200.00 183,375.00 195,600.00
0.52 m3 Pasir Pasang 340,000.00 370,000.00 176,800.00 192,400.00
C PERALATAN
D Jumlah A + B + C 925,300.00 1,049,125.00
E Overhead & Profit (contoh 10%) 10% 92,530.00 104,912.50
F Harga Satuan Pekerjaan (D+E) 1,017,830.00 1,154,037.50

3 A.3.2.1.3 1 m3 Pemasangan Pondasi Batu Belah 1SP : 5 PP 993,393.50 1,128,165.50


A TENAGA 229,125.00 253,125.00
L.01 1.5 OH Pekerja 80,000.00 90,000.00 120,000.00 135,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B BAHAN 673,960.00 772,480.00
1.2 m3 Batu Belah 15/20 280,000.00 340,000.00 336,000.00 408,000.00
136 Kg Portland Sement 1,125.00 1,200.00 153,000.00 163,200.00
0.544 m3 Pasir Pasang 340,000.00 370,000.00 184,960.00 201,280.00
C PERALATAN
D Jumlah A + B + C 903,085.00 1,025,605.00
E Overhead & Profit (contoh 10%) 10% 90,308.50 102,560.50
F Harga Satuan Pekerjaan (D+E) 993,393.50 1,128,165.50

4 A.3.2.1.4 1 m3 Pemasangan Pondasi Batu Belah 1SP : 6 PP 976,239.00 1,110,004.50


A TENAGA 229,125.00 253,125.00
L.01 1.5 OH Pekerja 80,000.00 90,000.00 120,000.00 135,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B BAHAN 658,365.00 755,970.00
1.2 m3 Batu Belah 15/20 280,000.00 340,000.00 336,000.00 408,000.00
117 Kg Portland Sement 1,125.00 1,200.00 131,625.00 140,400.00
0.561 m3 Pasir Pasang 340,000.00 370,000.00 190,740.00 207,570.00
C PERALATAN
D Jumlah A + B + C 887,490.00 1,009,095.00
E Overhead & Profit (contoh 10%) 10% 88,749.00 100,909.50
F Harga Satuan Pekerjaan (D+E) 976,239.00 1,110,004.50

5 A.3.2.1.5 1 m3 Pemasangan Pondasi Batu Belah 1SP : 8 PP 952,666.00 1,085,045.50


A Tenaga 229,125.00 253,125.00
L.01 1.5 OH Pekerja 80,000.00 90,000.00 120,000.00 135,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B Bahan 636,935.00 733,280.00
1.2 m3 Batu Belah 15/20 280,000.00 340,000.00 336,000.00 408,000.00
91 Kg Portland Sement 1,125.00 1,200.00 102,375.00 109,200.00
0.584 m3 Pasir Pasang 340,000.00 370,000.00 198,560.00 216,080.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/54 3-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 866,060.00 986,405.00
E Overhead & Profit (contoh 10%) 10% 86,606.00 98,640.50
F Harga Satuan Pekerjaan (D+E) 952,666.00 1,085,045.50

6 A.3.2.1.6 1 m3 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP 842,297.50 960,987.50
A Tenaga 229,125.00 253,125.00
L.01 1.5 OH Pekerja 80,000.00 90,000.00 120,000.00 135,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B Bahan 536,600.00 620,500.00
1.2 m3 Batu Belah 15/20 280,000.00 340,000.00 336,000.00 408,000.00
0.17 m3 Kapur Pasang (KP) 300,000.00 310,000.00 51,000.00 52,700.00
0.17 Kg Semen Merah (SM) 200,000.00 200,000.00 34,000.00 34,000.00
0.340 m3 Pasir Pasang 340,000.00 370,000.00 115,600.00 125,800.00
C PERALATAN
D Jumlah A + B + C 765,725.00 873,625.00
E Overhead & Profit (contoh 10%) 10% 76,572.50 87,362.50
F Harga Satuan Pekerjaan (D+E) 842,297.50 960,987.50

7 A.3.2.1.7 1 m3 Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10 PP 929,643.00 1,058,128.50


A Tenaga 229,125.00 253,125.00
L.01 1.5 OH Pekerja 80,000.00 90,000.00 120,000.00 135,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B Bahan 616,005.00 708,810.00
1.2 m3 Batu Belah 15/20 280,000.00 340,000.00 336,000.00 408,000.00
61 kg Portland Sement 1,125.00 1,200.00 68,625.00 73,200.00
0.147 m3 Kapur Pasang 300,000.00 310,000.00 44,100.00 45,570.00
0.492 m3 Pasir Pasang 340,000.00 370,000.00 167,280.00 182,040.00
C PERALATAN
D Jumlah A + B + C 845,130.00 961,935.00
E Overhead & Profit (contoh 10%) 10% 84,513.00 96,193.50
F Harga Satuan Pekerjaan (D+E) 929,643.00 1,058,128.50

8 A.3.2.1.8 1 m3 Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4 PP 911,207.00 1,038,889.50


A Tenaga 229,125.00 253,125.00
L.01 1.5 OH Pekerja 80,000.00 90,000.00 120,000.00 135,000.00
L.02 0.750 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B Bahan 599,245.00 691,320.00
1.2 m3 Batu Belah 15/20 280,000.00 340,000.00 336,000.00 408,000.00
41 kg Portland Sement 1,125.00 1,200.00 46,125.00 49,200.00
0.131 m3 Kapur Pasang 300,000.00 310,000.00 39,300.00 40,610.00
0.523 m3 Pasir 340,000.00 370,000.00 177,820.00 193,510.00
C PERALATAN
D Jumlah A + B + C 828,370.00 944,445.00
E Overhead & Profit (contoh 10%) 10% 82,837.00 94,444.50
F Harga Satuan Pekerjaan (D+E) 911,207.00 1,038,889.50

9 A.3.2.1.9 1 m3 Pemasang Batu Kosong/Anstamping 576,691.50 698,131.50


A Tenaga 119,145.00 131,625.00
L.01 0.78 OH Pekerja 80,000.00 90,000.00 62,400.00 70,200.00
L.02 0.39 OH Tukang Batu 120,000.00 130,000.00 46,800.00 50,700.00
L.03 0.039 OH Kepala Tukang 130,000.00 140,000.00 5,070.00 5,460.00
L.04 0.039 OH Mandor 125,000.00 135,000.00 4,875.00 5,265.00
B Bahan 405,120.00 503,040.00
1.2 m3 Batu Belah 15/20 280,000.00 340,000.00 336,000.00 408,000.00
0.432 m3 Pasir Urug 160,000.00 220,000.00 69,120.00 95,040.00
C PERALATAN
D Jumlah A + B + C 524,265.00 634,665.00
E Overhead & Profit (contoh 10%) 10% 52,426.50 63,466.50
F Harga Satuan Pekerjaan (D+E) 576,691.50 698,131.50

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/55 3-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pasang Pondasi Siklop, 60% Beton Campuran 1PC : 2PB :
10 A.3.2.1.10 1 m3 2,500,839.00 2,898,159.00
3KR & 40% Batu Belah
A Tenaga 403,800.00 448,650.00
L.01 3.4 OH Pekerja 80,000.00 90,000.00 272,000.00 306,000.00
L.02 0.85 OH Tukang Batu 120,000.00 130,000.00 102,000.00 110,500.00
L.03 0.085 OH Kepala Tukang 130,000.00 140,000.00 11,050.00 11,900.00
L.04 0.15 OH Mandor 125,000.00 135,000.00 18,750.00 20,250.00
B Bahan 1,869,690.00 2,186,040.00
0.480 m3 Batu Belah 15/20 cm 280,000.00 340,000.00 134,400.00 163,200.00
126 Kg Besi Beton 10,000.00 12,000.00 1,260,000.00 1,512,000.00
194 Kg Portland Semen 1,125.00 1,200.00 218,250.00 232,800.00
0.312 m3 Pasir Beton 360,000.00 380,000.00 112,320.00 118,560.00
0.468 m3 Koral Beton 240,000.00 260,000.00 112,320.00 121,680.00
1.8 Kg Kawat Beton 18,000.00 21,000.00 32,400.00 37,800.00
C PERALATAN
D Jumlah A + B + C 2,273,490.00 2,634,690.00
E Overhead & Profit (contoh 10%) 10% 227,349.00 263,469.00
F Harga Satuan Pekerjaan (D+E) 2,500,839.00 2,898,159.00

11 A.3.2.1.11 1 m3 Pasang Pondasi Sumuran diameter 100 cm 970,381.50 1,070,635.50


A Tenaga 313,275.00 347,265.00
L.01 2.40 OH Pekerja 80,000.00 90,000.00 192,000.00 216,000.00
L.02 0.8 OH Tukang Batu 120,000.00 130,000.00 96,000.00 104,000.00
L.03 0.08 OH Kepala Tukang 130,000.00 140,000.00 10,400.00 11,200.00
L.04 0.119 OH Mandor 125,000.00 135,000.00 14,875.00 16,065.00
B Bahan 568,890.00 626,040.00
0.45 m3 Batu Belah 15/20 cm 280,000.00 340,000.00 126,000.00 153,000.00
194 Kg Portland Semen 1,125.00 1,200.00 218,250.00 232,800.00
0.312 m3 Pasir Beton 360,000.00 380,000.00 112,320.00 118,560.00
0.468 m3 Koral Beton 240,000.00 260,000.00 112,320.00 121,680.00
C PERALATAN
D Jumlah A + B + C 882,165.00 973,305.00
E Overhead & Profit (contoh 10%) 10% 88,216.50 97,330.50
F Harga Satuan Pekerjaan (D+E) 970,381.50 1,070,635.50

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/56 3-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c


1 A.4.1.1.1 1 m3 1,005,451.86 1,120,043.57
= 0,87
A Tenaga 179,015.00 199,375.00
L.01 1.65 OH Pekerja 80,000.00 90,000.00 132,000.00 148,500.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 735,032.14 818,846.43
247 Kg Portland Semen 1,125.00 1,200.00 277,875.00 296,400.00
869 Kg Pasir Beton 257.14 271.43 223,457.14 235,871.43
999 Kg Kerikil (maksimum 30 mm) 229.63 281.48 229,400.00 281,200.00
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 914,047.14 1,018,221.43
E Overhead & Profit (contoh 10%) 10% 91,404.71 101,822.14
F Harga Satuan Pekerjaan (D+E) 1,005,451.86 1,120,043.57
10%
Overhead & Profit (contoh 10%)
Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c
2 A.4.1.1.2 1 m3 1,033,025.92 1,150,107.33
= 0,78
A Tenaga 179,015.00 199,375.00
L.01 1.650 OH Pekerja 80,000.00 90,000.00 132,000.00 148,500.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 760,099.47 846,177.12
276 Kg Portland Semen 1,125.00 1,200.00 310,500.00 331,200.00
828 kg Pasir Beton 257.14 271.43 212,914.29 224,742.86
1,012 kg Kerikil (maksimum 30 mm) 229.63 281.48 232,385.19 284,859.26
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 939,114.47 1,045,552.12
E Overhead & Profit (contoh 10%) 10% 93,911.45 104,555.21
F Harga Satuan Pekerjaan (D+E) 1,033,025.92 1,150,107.33

Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm,


3 A.4.1.1.3 1 m3 1,054,548.52 1,173,356.90
w/c = 0,72
A Tenaga 179,015.00 199,375.00
L.01 1.650 OH Pekerja 80,000.00 90,000.00 132,000.00 148,500.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 779,665.48 867,313.10
299 Kg Portland Semen 1,125.00 1,200.00 336,375.00 358,800.00
799 kg Pasir Beton 257.14 271.43 205,457.14 216,871.43
1,017 kg Kerikil (maksimum 30 mm) 229.63 281.48 233,533.33 286,266.67
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 958,680.48 1,066,688.10
E Overhead & Profit (contoh 10%) 10% 95,868.05 106,668.81
F Harga Satuan Pekerjaan (D+E) 1,054,548.52 1,173,356.90

Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum


4 A.4.1.1.4 1.00 m3 936,714.02 1,045,084.92
(3-6)cm, w/c = 0,87
A Tenaga 123,350.00 137,610.00
L.01 1.200 OH Pekerja 80,000.00 90,000.00 96,000.00 108,000.00
L.02 0.200 OH Tukang Batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.020 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 728,208.20 812,467.20
230 Kg Portland Semen 1,125.00 1,200.00 258,750.00 276,000.00
893 kg Pasir Beton 257.14 271.43 229,628.57 242,385.71
1,027 kg Kerikil (maksimum 30 mm) 229.63 281.48 235,829.63 289,081.48
200 ltr Air 20.00 25.00 4,000.00 5,000.00
C PERALATAN
D Jumlah A + B + C 851,558.20 950,077.20
E Overhead & Profit (contoh 10%) 10% 85,155.82 95,007.72
F Harga Satuan Pekerjaan (D+E) 936,714.02 1,045,084.92

Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm,


5 A.4.1.1.5 1 m3 1,079,960.71 1,201,068.17
w/c = 0,66
A Tenaga 179,015.00 199,375.00
L.01 1.65 OH Pekerja 80,000.00 90,000.00 132,000.00 148,500.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/57 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 802,767.46 892,505.16
326 Kg Portland Semen 1,125.00 1,200.00 366,750.00 391,200.00
760 Kg Pasir Beton 257.14 271.43 195,428.57 206,285.71
1,029 Kg Kerikil (maksimum 30 mm) 229.63 281.48 236,288.89 289,644.44
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 981,782.46 1,091,880.16
E Overhead & Profit (contoh 10%) 10% 98,178.25 109,188.02
F Harga Satuan Pekerjaan (D+E) 1,079,960.71 1,201,068.17

Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm,


6 A.4.1.1.6 1 m3 1,104,438.03 1,227,348.86
w/c = 0,61
A Tenaga 179,015.00 199,375.00
L.01 1.650 OH Pekerja 80,000.00 90,000.00 132,000.00 148,500.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 825,019.58 916,396.69
352 Kg Portland Semen 1,125.00 1,200.00 396,000.00 422,400.00
731 Kg Pasir Beton 257.14 271.43 187,971.43 198,414.29
1,031 Kg Kerikil (maksimum 30 mm) 229.63 281.48 236,748.15 290,207.41
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,004,034.58 1,115,771.69
E Overhead & Profit (contoh 10%) 10% 100,403.46 111,577.17
F Harga Satuan Pekerjaan (D+E) 1,104,438.03 1,227,348.86

Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm,


7 A.4.1.1.7 1 m3 1,122,657.73 1,247,530.08
w/c = 0,58
A Tenaga 179,015.00 199,375.00
L.01 1.650 OH Pekerja 80,000.00 90,000.00 132,000.00 148,500.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 841,582.94 934,743.25
371 Kg Portland Semen 1,125.00 1,200.00 417,375.00 445,200.00
698 Kg Pasir Beton 257.14 271.43 179,485.71 189,457.14
1,047 Kg Kerikil (maksimum 30 mm) 229.63 281.48 240,422.22 294,711.11
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,020,597.94 1,134,118.25
E Overhead & Profit (contoh 10%) 10% 102,059.79 113,411.83
F Harga Satuan Pekerjaan (D+E) 1,122,657.73 1,247,530.08

Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm,


8 A.4.1.1.8 1 m3 1,135,027.35 1,260,421.61
w/c = 0,56
A Tenaga 179,015.00 199,375.00
L.01 1.650 OH Pekerja 80,000.00 90,000.00 132,000.00 148,500.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 852,828.04 946,462.83
384 Kg Portland Semen 1,125.00 1,200.00 432,000.00 460,800.00
692 Kg Pasir Beton 257.14 271.43 177,942.86 187,828.57
1,039 Kg Kerikil (maksimum 30 mm) 229.63 281.48 238,585.19 292,459.26
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,031,843.04 1,145,837.83
E Overhead & Profit (contoh 10%) 10% 103,184.30 114,583.78
F Harga Satuan Pekerjaan (D+E) 1,135,027.35 1,260,421.61

Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum


9 A.4.1.1.9 1 m3 1,156,705.79 1,283,047.86
(12±2)cm, w/c = 0,53
A Tenaga 179,015.00 199,375.00
L.01 1.650 OH Pekerja 80,000.00 90,000.00 132,000.00 148,500.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 872,535.71 967,032.14
406 Kg Portland Semen 1,125.00 1,200.00 456,750.00 487,200.00
684 kg Pasir Beton 257.14 271.43 175,885.71 185,657.14
1,026 kg Kerikil (maksimum 30 mm) 229.63 281.48 235,600.00 288,800.00
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,051,550.71 1,166,407.14
E Overhead & Profit (contoh 10%) 10% 105,155.07 116,640.71
F Harga Satuan Pekerjaan (D+E) 1,156,705.79 1,283,047.86

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/58 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm,
10 A.4.1.1.10 1 m3 1,163,256.75 1,289,843.99
w/c = 0,52
A Tenaga 179,015.00 199,375.00
L.01 1.650 OH Pekerja 80,000.00 90,000.00 132,000.00 148,500.00
L.02 0.275 OH Tukang Batu 120,000.00 130,000.00 33,000.00 35,750.00
L.03 0.028 OH Kepala Tukang 130,000.00 140,000.00 3,640.00 3,920.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 878,491.14 973,210.45
413 Kg Portland Semen 1,125.00 1,200.00 464,625.00 495,600.00
681 Kg Pasir Beton 257.14 271.43 175,114.29 184,842.86
1,021 Kg Kerikil (maksimum 30 mm) 229.63 281.48 234,451.85 287,392.59
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,057,506.14 1,172,585.45
E Overhead & Profit (contoh 10%) 10% 105,750.61 117,258.54
F Harga Satuan Pekerjaan (D+E) 1,163,256.75 1,289,843.99

Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm,


11 A.4.1.1.11 1 m3 1,242,057.43 1,375,855.26
w/c = 0,49
A Tenaga 227,675.00 253,575.00
L.01 2.1 OH Pekerja 80,000.00 90,000.00 168,000.00 189,000.00
L.02 0.35 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.105 OH Mandor 125,000.00 135,000.00 13,125.00 14,175.00
B Bahan 901,468.12 997,202.51
439 Kg Portland Semen 1,125.00 1,200.00 493,875.00 526,800.00
670 Kg Pasir Beton 257.14 271.43 172,285.71 181,857.14
1,006 Kg Kerikil (maksimum 30 mm) 229.63 281.48 231,007.41 283,170.37
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,129,143.12 1,250,777.51
E Overhead & Profit (contoh 10%) 10% 112,914.31 125,077.75
F Harga Satuan Pekerjaan (D+E) 1,242,057.43 1,375,855.26

Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm,


12 A.4.1.1.12 1 m3 1,250,830.81 1,384,981.77
w/c = 0,48
A Tenaga 227,675.00 253,575.00
L.01 2.10 OH Pekerja 80,000.00 90,000.00 168,000.00 189,000.00
L.02 0.350 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.105 OH Mandor 125,000.00 135,000.00 13,125.00 14,175.00
B Bahan 909,443.92 1,005,499.34
448 Kg Portland Semen 1,125.00 1,200.00 504,000.00 537,600.00
667 Kg Pasir Beton 257.14 271.43 171,514.29 181,042.86
1,000 Kg Kerikil (maksimum 30 mm) 229.63 281.48 229,629.63 281,481.48
215 ltr Air 20.00 25.00 4,300.00 5,375.00
C PERALATAN
D Jumlah A + B + C 1,137,118.92 1,259,074.34
E Overhead & Profit (contoh 10%) 10% 113,711.89 125,907.43
F Harga Satuan Pekerjaan (D+E) 1,250,830.81 1,384,981.77

13 A.4.1.1.17 10 Kg Pembesian dg Besi Polos atau Besi Ulir 135,421.00 160,677.00


A Tenaga 15,410.00 16,920.00
L.01 0.07 OH Pekerja 80,000.00 90,000.00 5,600.00 6,300.00
L.02 0.07 OH Tukang Besi 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00
B Bahan 107,700.00 129,150.00
10.50 Kg Besi Beton (polos/ulir) 10,000.00 12,000.00 105,000.00 126,000.00
0.150 Kg Kawat Beton 18,000.00 21,000.00 2,700.00 3,150.00
C PERALATAN
D Jumlah A + B + C 123,110.00 146,070.00
E Overhead & Profit (contoh 10%) 10% 12,311.00 14,607.00
F Harga Satuan Pekerjaan (D+E) 135,421.00 160,677.00

14 A.4.1.1.18 10 Kg Kabel Presstresed Polos/strand 175,807.50 183,100.50


A Tenaga 11,025.00 12,105.00
L.01 0.05 OH Pekerja 80,000.00 90,000.00 4,000.00 4,500.00
L.02 0.05 OH Tukang Besi 120,000.00 130,000.00 6,000.00 6,500.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 148,800.00 154,350.00
10.5 Kg Besi presstred polos 14,000.00 14,500.00 147,000.00 152,250.00
0.1 Kg Kawat Beton 18,000.00 21,000.00 1,800.00 2,100.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/59 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 159,825.00 166,455.00
E Overhead & Profit (contoh 10%) 10% 15,982.50 16,645.50
F Harga Satuan Pekerjaan (D+E) 175,807.50 183,100.50

15 A.4.1.1.19 10 Kg Jaring Kawat baja/Wire Mesh 287,413.50 316,211.50


A Tenaga 5,385.00 5,915.00
L.01 0.025 OH Pekerja 80,000.00 90,000.00 2,000.00 2,250.00
L.02 0.025 OH Tukang Besi 120,000.00 130,000.00 3,000.00 3,250.00
L.03 0.002 OH Kepala Tukang 130,000.00 140,000.00 260.00 280.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00
B Bahan 255,900.00 281,550.00
10.20 Kg Jaring Kawat Baja dilas 25,000.00 27,500.00 255,000.00 280,500.00
0.05 Kg Kawat Beton 18,000.00 21,000.00 900.00 1,050.00
C PERALATAN
D Jumlah A + B + C 261,285.00 287,465.00
E Overhead & Profit (contoh 10%) 10% 26,128.50 28,746.50
F Harga Satuan Pekerjaan (D+E) 287,413.50 316,211.50

16 A.4.1.1.20 1 m2 Memasang Bekisting untuk Pondasi 181,313.00 200,200.00


A Tenaga 79,430.00 87,750.00
L.01 0.52 OH Pekerja 80,000.00 90,000.00 41,600.00 46,800.00
L.02 0.26 OH Tukang Kayu 120,000.00 130,000.00 31,200.00 33,800.00
L.03 0.026 OH Kepala Tukang 130,000.00 140,000.00 3,380.00 3,640.00
L.04 0.026 OH Mandor 125,000.00 135,000.00 3,250.00 3,510.00
B Bahan 85,400.00 94,250.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.3 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 4,500.00 5,250.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 164,830.00 182,000.00
E Overhead & Profit (contoh 10%) 10% 16,483.00 18,200.00
F Harga Satuan Pekerjaan (D+E) 181,313.00 200,200.00

17 A.4.1.1.21 1 m2 Memasang Bekisting untuk Sloof 192,313.00 212,300.00


A Tenaga 79,430.00 87,750.00
L.01 0.52 OH Pekerja 80,000.00 90,000.00 41,600.00 46,800.00
L.02 0.26 OH Tukang Kayu 120,000.00 130,000.00 31,200.00 33,800.00
L.03 0.026 OH Kepala Tukang 130,000.00 140,000.00 3,380.00 3,640.00
L.04 0.026 OH Mandor 125,000.00 135,000.00 3,250.00 3,510.00
B Bahan 95,400.00 105,250.00
0.045 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 90,000.00 99,000.00
0.3 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 4,500.00 5,250.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 174,830.00 193,000.00
E Overhead & Profit (contoh 10%) 10% 17,483.00 19,300.00
F Harga Satuan Pekerjaan (D+E) 192,313.00 212,300.00

18 A.4.1.1.22 1 m2 Memasang Bekisting untuk Kolom 381,826.50 442,612.50


A Tenaga 100,815.00 111,375.00
L.01 0.66 OH Pekerja 80,000.00 90,000.00 52,800.00 59,400.00
L.02 0.33 OH Tukang Kayu 120,000.00 130,000.00 39,600.00 42,900.00
L.03 0.033 OH Kepala Tukang 130,000.00 140,000.00 4,290.00 4,620.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00
B Bahan 246,300.00 291,000.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 6,000.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II 5,200,000.00 6,000,000.00 78,000.00 90,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 160,000.00 38,500.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 347,115.00 402,375.00
E Overhead & Profit (contoh 10%) 10% 34,711.50 40,237.50
F Harga Satuan Pekerjaan (D+E) 381,826.50 442,612.50

19 A.4.1.1.23 1 m2 Memasang Bekisting untuk Balok 398,986.50 462,412.50


A Tenaga 100,815.00 111,375.00
L.01 0.66 OH Pekerja 80,000.00 90,000.00 52,800.00 59,400.00
L.02 0.33 OH Tukang Kayu 120,000.00 130,000.00 39,600.00 42,900.00
L.03 0.033 OH Kepala Tukang 130,000.00 140,000.00 4,290.00 4,620.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/60 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 261,900.00 309,000.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 6,000.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.018 m3 Balok Kayu Klas II 5,200,000.00 6,000,000.00 93,600.00 108,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 160,000.00 38,500.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 362,715.00 420,375.00
E Overhead & Profit (contoh 10%) 10% 36,271.50 42,037.50
F Harga Satuan Pekerjaan (D+E) 398,986.50 462,412.50

20 A.4.1.1.24 1 m2 Memasang Bekisting untuk Lantai 474,226.50 548,212.50


A Tenaga 100,815.00 111,375.00
L.01 0.66 OH Pekerja 80,000.00 90,000.00 52,800.00 59,400.00
L.02 0.33 OH Tukang Kayu 120,000.00 130,000.00 39,600.00 42,900.00
L.03 0.033 OH Kepala Tukang 130,000.00 140,000.00 4,290.00 4,620.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00
B Bahan 330,300.00 387,000.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 6,000.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II (Borneo) 5,200,000.00 6,000,000.00 78,000.00 90,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 160,000.00 38,500.00 56,000.00
6 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 126,000.00 144,000.00
C PERALATAN
D Jumlah A + B + C 431,115.00 498,375.00
E Overhead & Profit (contoh 10%) 10% 43,111.50 49,837.50
F Harga Satuan Pekerjaan (D+E) 474,226.50 548,212.50

21 A.4.1.1.25 1 m2 Memasang Bekisting untuk Dinding 433,526.50 502,012.50


A Tenaga 100,815.00 111,375.00
L.01 0.66 OH Pekerja 80,000.00 90,000.00 52,800.00 59,400.00
L.02 0.33 OH Tukang Kayu 120,000.00 130,000.00 39,600.00 42,900.00
L.03 0.033 OH Kepala Tukang 130,000.00 140,000.00 4,290.00 4,620.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00
B Bahan 293,300.00 345,000.00
0.03 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 60,000.00 66,000.00
0.4 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 6,000.00 7,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.02 m3 Balok Kayu Klas II 5,200,000.00 6,000,000.00 104,000.00 120,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 160,000.00 38,500.00 56,000.00
3 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 63,000.00 72,000.00
4 Buah Formite/Penjaga jarak / Spacer (alat bantu) 5,000.00 5,500.00 20,000.00 22,000.00
C PERALATAN
D Jumlah A + B + C 394,115.00 456,375.00
E Overhead & Profit (contoh 10%) 10% 39,411.50 45,637.50
F Harga Satuan Pekerjaan (D+E) 433,526.50 502,012.50

22 A.4.1.1.26 1 m2 Memasang Bekisting untuk Tangga 359,331.50 417,862.50


A Tenaga 100,815.00 111,375.00
L.01 0.66 OH Pekerja 80,000.00 90,000.00 52,800.00 59,400.00
L.02 0.33 OH Tukang Kayu 120,000.00 130,000.00 39,600.00 42,900.00
L.03 0.033 OH Kepala Tukang 130,000.00 140,000.00 4,290.00 4,620.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00
B Bahan 225,850.00 268,500.00
0.03 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 60,000.00 66,000.00
0.4 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 6,000.00 7,000.00
0.15 Ltr Minyak Bekisting 9,000.00 10,000.00 1,350.00 1,500.00
0.015 m3 Balok Kayu Klas II 5,200,000.00 6,000,000.00 78,000.00 90,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 160,000.00 38,500.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 326,665.00 379,875.00
E Overhead & Profit (contoh 10%) 10% 32,666.50 37,987.50
F Harga Satuan Pekerjaan (D+E) 359,331.50 417,862.50

23 A.4.1.1.27 1 m2 Memasang Jembatan Cor 101,145.00 112,596.00


A Tenaga 19,650.00 21,780.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.02 0.05 OH Tukang Kayu 120,000.00 130,000.00 6,000.00 6,500.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 72,300.00 80,580.00
0.0264 m3 Kayu Terentang 2,000,000.00 2,200,000.00 52,800.00 58,080.00
0.6 kg Paku Biasa 2" - 5" 15,000.00 17,500.00 9,000.00 10,500.00
0.5 m3 Dolken Kayu Galam diameter 8 - 10 / 4 m 21,000.00 24,000.00 10,500.00 12,000.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/61 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 91,950.00 102,360.00
E Overhead & Profit (contoh 10%) 10% 9,195.00 10,236.00
F Harga Satuan Pekerjaan (D+E) 101,145.00 112,596.00

24 A.4.1.1.28 1 m' Membuat Ring Balok Beton Bertulang (11 x 11) cm 85,772.50 97,460.00
A Tenaga 23,605.00 26,055.00
L.01 0.180 OH Pekerja 80,000.00 90,000.00 14,400.00 16,200.00
L.02 0.020 OH Tukang batu 120,000.00 130,000.00 2,400.00 2,600.00
L.02 0.020 OH Tukang Kayu 120,000.00 130,000.00 2,400.00 2,600.00
L.02 0.020 OH Tukang Besi 125,000.00 130,000.00 2,500.00 2,600.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.009 OH Mandor 125,000.00 135,000.00 1,125.00 1,215.00
B Bahan 54,370.00 62,545.00
0.002 m3 Kayu Klas III 3,290,000.00 3,300,000.00 6,580.00 6,600.00
0.01 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 150.00 175.00
3.0 Kg Besi Beton Polos 10,000.00 12,000.00 30,000.00 36,000.00
0.45 Kg Kawat Beton 18,000.00 21,000.00 8,100.00 9,450.00
4.0 Kg Portland Semen 1,125.00 1,200.00 4,500.00 4,800.00
0.006 m3 Pasir Beton 360,000.00 380,000.00 2,160.00 2,280.00
0.009 m3 Kerikil 320,000.00 360,000.00 2,880.00 3,240.00
C PERALATAN
D Jumlah A + B + C 77,975.00 88,600.00
E Overhead & Profit (contoh 10%) 10% 7,797.50 8,860.00
F Harga Satuan Pekerjaan (D+E) 85,772.50 97,460.00

25 A.4.1.1.29 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 110,305.25 124,239.50
A Tenaga 38,980.00 43,025.00
L.01 0.297 OH Pekerja 80,000.00 90,000.00 23,760.00 26,730.00
L.02 0.033 OH Tukang batu 120,000.00 130,000.00 3,960.00 4,290.00
L.02 0.033 OH Tukang Kayu 120,000.00 130,000.00 3,960.00 4,290.00
L.02 0.033 OH Tukang Besi 125,000.00 130,000.00 4,125.00 4,290.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 61,297.50 69,920.00
0.003 m3 Kayu Klas III 3,290,000.00 3,300,000.00 9,870.00 9,900.00
0.02 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 300.00 350.00
3.6 Kg Besi Beton Polos 10,000.00 12,000.00 36,000.00 43,200.00
0.05 Kg Kawat Beton 18,000.00 21,000.00 900.00 1,050.00
5.5 Kg Portland Semen 1,125.00 1,200.00 6,187.50 6,600.00
0.009 m3 Pasir Beton 360,000.00 380,000.00 3,240.00 3,420.00
0.015 m3 Kerikil 320,000.00 360,000.00 4,800.00 5,400.00
C PERALATAN
D Jumlah A + B + C 100,277.50 112,945.00
E Overhead & Profit (contoh 10%) 10% 10,027.75 11,294.50
F Harga Satuan Pekerjaan (D+E) 110,305.25 124,239.50

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/62 4-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
IV A A.4.1.2 HARGA SATUAN PEKERJAAN BETON PRACETAK
UNTUK PRODUKSI PRACETAK BISA DILAKUKAN DI PABRIK (COR DI PLANT) ATAU DI LAPANGAN (CAST IN PLACE). INDEKS YANG ADA DALAM PEDOMAN INI
HANYA UNTUK PEKERJAAN PRODUKSI YANG DILAKUKAN DI LAPANGAN, TERUTAMA UNTUK ANALISA CETAKAN (BEKISTING) PRACETAK BAIK UNTUK
KOMPONEN KOLOM, BALOK DAN PELAT.

Pembuatan Lahan Produksi Tebal 8 cm Beton f'c 14,5 Mpa,


1 A.4.1.2.1 1 m2 86,412.04 96,101.95
Slump (120 ± 20) mm K3
A Tenaga 14,335.00 15,965.00
L.01 0.132 OH Pekerja 80,000.00 90,000.00 10,560.00 11,880.00
L.02 0.022 OH Tukang Batu 120,000.00 130,000.00 2,640.00 2,860.00
L.03 0.002 OH Kepala Tukang 130,000.00 140,000.00 260.00 280.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 64,221.40 71,400.41
26.080 Kg Portland Semen 1,125.00 1,200.00 29,340.00 31,296.00
60.800 Kg Pasir Beton 257.14 271.43 15,634.29 16,502.86
82.320 Kg Kerikil (maksimum 30 mm) 229.63 281.48 18,903.11 23,171.56
17.200 ltr Air 20.00 25.00 344.00 430.00
C PERALATAN
D Jumlah A + B + C 78,556.40 87,365.41
E Overhead & Profit (contoh 10%) 10% 7,855.64 8,736.54
F Harga Satuan Pekerjaan (D+E) 86,412.04 96,101.95
10%
Overhead & Profit (contoh 10%)
Pembuatan Lahan Produksi Tebal 10 cm Beton f'c = 14,5 Mpa
2 A.4.1.2.2 1 m2 108,049.42 120,164.57
slum (120 ± 20 ) mm K3
A Tenaga 17,950.00 19,990.00
L.01 0.165 OH Pekerja 80,000.00 90,000.00 13,200.00 14,850.00
L.02 0.028 OH Tukang Batu 120,000.00 130,000.00 3,360.00 3,640.00
L.03 0.003 OH Kepala Tukang 130,000.00 140,000.00 390.00 420.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 80,276.75 89,250.52
32.60 Kg Portland Semen 1,125.00 1,200.00 36,675.00 39,120.00
76.00 kg Pasir Beton 257.14 271.43 19,542.86 20,628.57
102.90 kg Kerikil (maksimum 30 mm) 229.63 281.48 23,628.89 28,964.44
21.50 ltr Air 20.00 25.00 430.00 537.50
C PERALATAN
D Jumlah A + B + C 98,226.75 109,240.52
E Overhead & Profit (contoh 10%) 10% 9,822.67 10,924.05
F Harga Satuan Pekerjaan (D+E) 108,049.42 120,164.57

Pembuatan Lahan Produksi Tebal 12 cm Beton f'c=14,5 Mpa,


3 A.4.1.2.3 1 m2 126,645.30 140,811.68
slum (120±20)mm, K3
A Tenaga 18,800.00 20,910.00
L.01 0.165 OH Pekerja 80,000.00 90,000.00 13,200.00 14,850.00
L.02 0.033 OH Tukang Batu 120,000.00 130,000.00 3,960.00 4,290.00
L.03 0.003 OH Kepala Tukang 130,000.00 140,000.00 390.00 420.00
L.04 0.010 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B Bahan 96,332.10 107,100.62
39.120 Kg Portland Semen 1,125.00 1,200.00 44,010.00 46,944.00
91.200 kg Pasir Beton 257.14 271.43 23,451.43 24,754.29
123.480 kg Kerikil (maksimum 30 mm) 229.63 281.48 28,354.67 34,757.33
25.800 ltr Air 20.00 25.00 516.00 645.00
C PERALATAN
D Jumlah A + B + C 115,132.10 128,010.62
E Overhead & Profit (contoh 10%) 10% 11,513.21 12,801.06
F Harga Satuan Pekerjaan (D+E) 126,645.30 140,811.68

Pembuatan Lahan Produksi Tebal 15 cm Beton f'c=14,5 Mpa,


4 A.4.1.2.4 1.00 m2 162,052.13 180,224.85
slum (120±20)mm, K3
A Tenaga 26,905.00 29,965.00
L.01 0.248 OH Pekerja 80,000.00 90,000.00 19,840.00 22,320.00
L.02 0.041 OH Tukang Batu 120,000.00 130,000.00 4,920.00 5,330.00
L.03 0.004 OH Kepala Tukang 130,000.00 140,000.00 520.00 560.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00
B Bahan 120,415.12 133,875.77
48.900 Kg Portland Semen 1,125.00 1,200.00 55,012.50 58,680.00
114.000 kg Pasir Beton 257.14 271.43 29,314.29 30,942.86
154.350 kg Kerikil (maksimum 30 mm) 229.63 281.48 35,443.33 43,446.67
32.250 ltr Air 20.00 25.00 645.00 806.25
C PERALATAN
D Jumlah A + B + C 147,320.12 163,840.77
E Overhead & Profit (contoh 10%) 10% 14,732.01 16,384.08
F Harga Satuan Pekerjaan (D+E) 162,052.13 180,224.85

Pembuatan Bekisting untuk Plat Beton Pra cetak (5 kali


5 A.4.1.2.5 1 m2 119,707.91 131,896.01
Pakai)
A Tenaga 10,845.00 11,765.00
L.01 0.007 OH Pekerja 80,000.00 90,000.00 560.00 630.00
L.02 0.076 OH Tukang Batu 120,000.00 130,000.00 9,120.00 9,880.00
L.03 0.008 OH Kepala Tukang 130,000.00 140,000.00 1,040.00 1,120.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/63 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 97,980.37 108,140.47
0.008 m3 Lantai Kerja Tebal 10 cm 93,671.40 104,508.49 749.37 836.07
9.394 Kg Besi Hollow (50x50x3) mm 5,500.00 6,000.00 51,667.00 56,364.00
0.005 m3 Kayu Kaso 5/7 5,200,000.00 6,000,000.00 26,000.00 30,000.00
0.080 lbr Phenol film 12 mm 125,000.00 130,000.00 10,000.00 10,400.00
0.200 ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
3.882 bh Dinabolt Ø 12 mm (10 s/d 15 cm) 2,000.00 2,200.00 7,764.00 8,540.40
C PERALATAN
D Jumlah A + B + C 108,825.37 119,905.47
E Overhead & Profit (contoh 10%) 10% 10,882.54 11,990.55
F Harga Satuan Pekerjaan (D+E) 119,707.91 131,896.01

Pembuatan Bekisting untuk Balok Beton Pra cetak (10 - 12


6 A.4.1.2.6 1 m2 40,776.00 45,914.60
kali Pakai)
A Tenaga 5,525.00 5,995.00
L.01 0.004 OH Pekerja 80,000.00 90,000.00 320.00 360.00
L.02 0.038 OH Tukang Batu 120,000.00 130,000.00 4,560.00 4,940.00
L.03 0.004 OH Kepala Tukang 130,000.00 140,000.00 520.00 560.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00
B Bahan 35,251.00 39,919.60
0.046 Kg Paku (5 s/d 7) cm 15,000.00 17,500.00 690.00 805.00
0.005 m3 Kayu Kaso 5/7 5,200,000.00 6,000,000.00 26,000.00 30,000.00
0.043 lbr Phenol film 12 mm 125,000.00 130,000.00 5,375.00 5,590.00
0.200 ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.693 bh Dinabolt Ø 12 mm (10 s/d 15 cm) 2,000.00 2,200.00 1,386.00 1,524.60
C PERALATAN
D Jumlah A + B + C 40,776.00 45,914.60
E Overhead & Profit (contoh 10%) 10% 4,077.60 4,591.46
F Harga Satuan Pekerjaan (D+E) 44,853.60 50,506.06

Pembuatan Bekisting untuk Kolom Beton Pra cetak (10 - 12


7 A.4.1.2.7 1 m2 36,201.00 40,564.60
kali Pakai)
A Tenaga 5,525.00 5,995.00
L.01 0.004 OH Pekerja 80,000.00 90,000.00 320.00 360.00
L.02 0.038 OH Tukang Batu 120,000.00 130,000.00 4,560.00 4,940.00
L.03 0.004 OH Kepala Tukang 130,000.00 140,000.00 520.00 560.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00
B Bahan 30,676.00 34,569.60
0.046 Kg Paku (5 s/d 7) cm 15,000.00 17,500.00 690.00 805.00
0.004 m3 Kayu Kaso 5/7 5,200,000.00 6,000,000.00 20,800.00 24,000.00
0.048 lbr Phenol film 12 mm 125,000.00 130,000.00 6,000.00 6,240.00
0.200 ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.693 bh Dinabolt Ø 12 mm (10 s/d 15 cm) 2,000.00 2,200.00 1,386.00 1,524.60
C PERALATAN
D Jumlah A + B + C 36,201.00 40,564.60
E Overhead & Profit (contoh 10%) 10% 3,620.10 4,056.46
F Harga Satuan Pekerjaan (D+E) 39,821.10 44,621.06

Pemasangan dan Membuka Bekisting untuk Komponen Plat


8 A.4.1.2.8 1 bh 7,025.00 7,785.00
Beton Pracetak
A Tenaga 7,025.00 7,785.00
L.01 0.053 OH Pekerja 80,000.00 90,000.00 4,240.00 4,770.00
L.02 0.018 OH Tukang Batu 120,000.00 130,000.00 2,160.00 2,340.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan
C PERALATAN
D Jumlah A + B + C 7,025.00 7,785.00
E Overhead & Profit (contoh 10%) 10% 702.50 778.50
F Harga Satuan Pekerjaan (D+E) 7,727.50 8,563.50

Pemasangan dan Membuka Bekisting untuk Komponen


9 A.4.1.2.9 1 bh 11,345.00 12,585.00
Balok Beton Pracetak
A Tenaga 11,345.00 12,585.00
L.01 0.089 OH Pekerja 80,000.00 90,000.00 7,120.00 8,010.00
L.02 0.030 OH Tukang Batu 120,000.00 130,000.00 3,600.00 3,900.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan
C PERALATAN
D Jumlah A + B + C 11,345.00 12,585.00
E Overhead & Profit (contoh 10%) 10% 1,134.50 1,258.50
F Harga Satuan Pekerjaan (D+E) 12,479.50 13,843.50

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/64 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan dan Membuka Bekisting untuk Komponen
10 A.4.1.2.10 1 bh 9,185.00 10,185.00
Kolom Beton Pracetak
A Tenaga 9,185.00 10,185.00
L.01 0.071 OH Pekerja 80,000.00 90,000.00 5,680.00 6,390.00
L.02 0.024 OH Tukang Batu 120,000.00 130,000.00 2,880.00 3,120.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan
C PERALATAN
D Jumlah A + B + C 9,185.00 10,185.00
E Overhead & Profit (contoh 10%) 10% 918.50 1,018.50
F Harga Satuan Pekerjaan (D+E) 10,103.50 11,203.50

11 A.4.1.2.11 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 69,635.50 68,735.00

A Tenaga 63,305.00 68,735.00


L.01 0.064 OH Pekerja 80,000.00 90,000.00 5,120.00 5,760.00
L.02 0.244 OH Tukang Batu 120,000.00 130,000.00 29,280.00 31,720.00
L.02 0.128 OH Tukang Vibrator 120,000.00 130,000.00 15,360.00 16,640.00
L.03 0.034 OH Kapala Tukang 130,000.00 140,000.00 4,420.00 4,760.00
L.04 0.073 OH Mandor 125,000.00 135,000.00 9,125.00 9,855.00
B Bahan - -
C PERALATAN
D Jumlah A + B + C 63,305.00 68,735.00
E Overhead & Profit (contoh 10%) 10% 6,330.50 6,873.50
F Harga Satuan Pekerjaan (D+E) 69,635.50 75,608.50

12 A.4.1.2.12 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 71,560.50 70,645.00

A Tenaga 65,055.00 70,645.00


L.01 0.069 OH Pekerja 80,000.00 90,000.00 5,520.00 6,210.00
L.02 0.242 OH Tukang Batu 120,000.00 130,000.00 29,040.00 31,460.00
L.02 0.138 OH Tukang Vibrator 120,000.00 130,000.00 16,560.00 17,940.00
L.03 0.037 OH Kapala Tukang 130,000.00 140,000.00 4,810.00 5,180.00
L.04 0.073 OH Mandor 125,000.00 135,000.00 9,125.00 9,855.00
B Bahan - -
C PERALATAN
D Jumlah A + B + C 65,055.00 70,645.00
E Overhead & Profit (contoh 10%) 10% 6,505.50 7,064.50
F Harga Satuan Pekerjaan (D+E) 71,560.50 77,709.50

Penuangan / Menebar Beton untuk Komponen Kolom


13 A.4.1.2.13 1 m3 64,344.50 63,515.00
Pracetak
A Tenaga 58,495.00 63,515.00
L.01 0.061 OH Pekerja 80,000.00 90,000.00 4,880.00 5,490.00
L.02 0.213 OH Tukang Batu 120,000.00 130,000.00 25,560.00 27,690.00
L.02 0.122 OH Tukang Vibrator 120,000.00 130,000.00 14,640.00 15,860.00
L.03 0.033 OH Kapala Tukang 130,000.00 140,000.00 4,290.00 4,620.00
L.04 0.073 OH Mandor 125,000.00 135,000.00 9,125.00 9,855.00
B Bahan - -
C PERALATAN
D Jumlah A + B + C 58,495.00 63,515.00
E Overhead & Profit (contoh 10%) 10% 5,849.50 6,351.50
F Harga Satuan Pekerjaan (D+E) 64,344.50 69,866.50

14 A.4.1.2.14 1 bh Ereksi Komponen Untuk Plat Pracetak 582,822.02 608,545.96


A Tenaga 49,245.00 54,270.00
L.08 0.067 OH Operator Crane 175,000.00 200,000.00 11,725.00 13,400.00
L.09 0.067 OH Pembantu Operator Crane 120,000.00 130,000.00 8,040.00 8,710.00
L.01 0.067 OH Pekerja 80,000.00 90,000.00 5,360.00 6,030.00
L.02 0.067 OH Tukang Batu 120,000.00 130,000.00 8,040.00 8,710.00
L.02 0.134 OH Tukang Ereksi 120,000.00 130,000.00 16,080.00 17,420.00
L.03 0.067 OH Kepala Tukang 130,000.00 140,000.00 8,710.00 9,380.00
L.04 0.067 OH Mandor 125,000.00 135,000.00 8,375.00 9,045.00
B Bahan 54,743.20 57,413.60
6.676 Ltr Solar 8,200.00 8,600.00 54,743.20 57,413.60
C PERALATAN 425,850.00 441,540.00
0.067 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 304,850.00 309,540.00
1.100 bh/hr Sewa Pipe Suport 110,000.00 120,000.00 121,000.00 132,000.00
D Jumlah A + B + C 529,838.20 553,223.60
E Overhead & Profit (contoh 10%) 10% 52,983.82 55,322.36
F Harga Satuan Pekerjaan (D+E) 582,822.02 608,545.96

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/65 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Indek Kenaikan Lantai Ereksi Komponen untuk Plat Pracetak
Indeks Kenaikan Lantai Indeks Kenaikan Lantai
Lantai Lantai
Ereksi Plat Ereksi Plat

1 1.0000 13 1.114
2 1.0000 14 1.134

3 1.0000 15 1.155

4 1.0000 16 1.176
5 1.0000 17 1.197

6 1.0000 18 1.219
7 1.0000 19 1.241

8 1.0180 20 1.264
9 1.0370 21 1.287

10 1.0550 22 1.310
11 1.0750 23 1.334

12 1.0940 24 1.358

15 A.4.1.2.15 1 bh Ereksi Komponen Untuk Balok Pracetak 572,865.70 597,845.60


A Tenaga 44,835.00 49,410.00
L.08 0.061 OH Operator Crane 175,000.00 200,000.00 10,675.00 12,200.00
L.09 0.061 OH Pembantu Operator Crane 120,000.00 130,000.00 7,320.00 7,930.00
L.01 0.061 OH Pekerja 80,000.00 90,000.00 4,880.00 5,490.00
L.02 0.061 OH Tukang Batu 120,000.00 130,000.00 7,320.00 7,930.00
L.02 0.122 OH Tukang Ereksi 120,000.00 130,000.00 14,640.00 15,860.00
L.03 0.061 OH Kepala Tukang 130,000.00 140,000.00 7,930.00 8,540.00
L.04 0.061 OH Mandor 125,000.00 135,000.00 7,625.00 8,235.00
B Bahan 50,102.00 52,546.00
6.110 Ltr Solar 8,200.00 8,600.00 50,102.00 52,546.00
C PERALATAN 425,850.00 441,540.00
0.067 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 304,850.00 309,540.00
1.100 bh/hr Sewa Pipe Suport 110,000.00 120,000.00 121,000.00 132,000.00
D Jumlah A + B + C 520,787.00 543,496.00
E Overhead & Profit (contoh 10%) 10% 52,078.70 54,349.60
F Harga Satuan Pekerjaan (D+E) 572,865.70 597,845.60

Indek Kenaikan Lantai Ereksi Komponen untuk Balok Pracetak


Indeks Kenaikan Lantai Indeks Kenaikan Lantai
Lantai Lantai
Ereksi Balok Ereksi Balok
1 1.0000 13 1.068

2 1.0000 14 1.080
3 1.0000 15 1.092

4 1.0000 16 1.104
5 1.0000 17 1.116

6 1.0000 18 1.129
7 1.0000 19 1.141

8 1.0110 20 1.154
9 1.0220 21 1.166

10 1.0340 22 1.179

11 1.0450 23 1.192
12 1.0570 24 1.206

16 A.4.1.2.16 1 bh Ereksi Komponen Untuk Kolom Pracetak 823,379.04 864,459.42


A Tenaga 61,005.00 67,230.00
L.08 0.083 OH Operator Crane 175,000.00 200,000.00 14,525.00 16,600.00
L.09 0.083 OH Pembantu Operator Crane 120,000.00 130,000.00 9,960.00 10,790.00
L.01 0.083 OH Pekerja 80,000.00 90,000.00 6,640.00 7,470.00
L.02 0.083 OH Tukang Batu 120,000.00 130,000.00 9,960.00 10,790.00
L.02 0.166 OH Tukang Ereksi 120,000.00 130,000.00 19,920.00 21,580.00
L.03 0.083 OH Kepala Tukang 130,000.00 140,000.00 10,790.00 11,620.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00
B Bahan 67,871.40 71,182.20
8.277 Ltr Solar 8,200.00 8,600.00 67,871.40 71,182.20
C PERALATAN 619,650.00 647,460.00
0.083 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 377,650.00 383,460.00
2.200 bh/hr Sewa Pipe Suport 110,000.00 120,000.00 242,000.00 264,000.00
D Jumlah A + B + C 748,526.40 785,872.20
E Overhead & Profit (contoh 10%) 10% 74,852.64 78,587.22
F Harga Satuan Pekerjaan (D+E) 823,379.04 864,459.42

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/66 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Indek Kenaikan Lantai Ereksi Komponen untuk Balok Pracetak
Indeks Kenaikan Lantai Indeks Kenaikan Lantai
Lantai Lantai
Ereksi Balok Ereksi Balok

1 1.0000 13 1.162
2 1.0000 14 1.191

3 1.0000 15 1.221

4 1.0000 16 1.252
5 1.0000 17 1.284

6 1.0000 18 1.318
7 1.0000 19 1.350

8 1.0250 20 1.384
9 1.0510 21 1.419

10 1.0780 22 1.455
11 1.1050 23 1.492

12 1.1330 24 1.530

17 A.4.1.2.17 1 bh Langsiran Komponen untuk Plat Pracetak (± 20 m) 157,399.44 164,718.62


A Tenaga 41,085.00 45,650.00
L.08 0.083 OH Operator Crane 175,000.00 200,000.00 14,525.00 16,600.00
L.09 0.083 OH Pembantu Operator Crane 120,000.00 130,000.00 9,960.00 10,790.00
L.01 0.083 OH Pekerja 80,000.00 90,000.00 6,640.00 7,470.00
L.02 0.083 OH Tukang Batu 120,000.00 130,000.00 9,960.00 10,790.00
B Bahan 15,555.40 16,314.20
1.897 Ltr Solar 8,200.00 8,600.00 15,555.40 16,314.20
C PERALATAN 86,450.00 87,780.00
0.019 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 86,450.00 87,780.00
D Jumlah A + B + C 143,090.40 149,744.20
E Overhead & Profit (contoh 10%) 10% 14,309.04 14,974.42
F Harga Satuan Pekerjaan (D+E) 157,399.44 164,718.62

18 A.4.1.2.18 1 bh Langsiran Komponen untuk Balok Pracetak (± 20 m) 125,059.44 128,715.62


A Tenaga 11,685.00 12,920.00
L.08 0.019 OH Operator Crane 175,000.00 200,000.00 3,325.00 3,800.00
L.09 0.019 OH Pembantu Operator Crane 120,000.00 130,000.00 2,280.00 2,470.00
L.01 0.019 OH Pekerja 80,000.00 90,000.00 1,520.00 1,710.00
L.02 0.038 OH Tukang Batu 120,000.00 130,000.00 4,560.00 4,940.00
B Bahan 15,555.40 16,314.20
1.897 Ltr Solar 8,200.00 8,600.00 15,555.40 16,314.20
C PERALATAN 86,450.00 87,780.00
0.019 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 86,450.00 87,780.00
D Jumlah A + B + C 113,690.40 117,014.20
E Overhead & Profit (contoh 10%) 10% 11,369.04 11,701.42
F Harga Satuan Pekerjaan (D+E) 125,059.44 128,715.62

19 A.4.1.2.19 1 bh Langsiran Komponen untuk Kolom Pracetak (± 20 m) 125,059.44 128,715.62


A Tenaga 11,685.00 12,920.00
L.08 0.019 OH Operator Crane 175,000.00 200,000.00 3,325.00 3,800.00
L.09 0.019 OH Pembantu Operator Crane 120,000.00 130,000.00 2,280.00 2,470.00
L.01 0.019 OH Pekerja 80,000.00 90,000.00 1,520.00 1,710.00
L.02 0.038 OH Tukang Batu 120,000.00 130,000.00 4,560.00 4,940.00
B Bahan 15,555.40 16,314.20
1.897 Ltr Solar 8,200.00 8,600.00 15,555.40 16,314.20
C PERALATAN 86,450.00 87,780.00
0.019 Unit/hr Sewa Crane 4,550,000.00 4,620,000.00 86,450.00 87,780.00
D Jumlah A + B + C 113,690.40 117,014.20
E Overhead & Profit (contoh 10%) 10% 11,369.04 11,701.42
F Harga Satuan Pekerjaan (D+E) 125,059.44 128,715.62

20 A.4.1.2.20 1 m3 Bahan Grout Campuran 3,417,700.00 3,689,125.00


A Tenaga - -

B Bahan 3,107,000.00 3,353,750.00


1,200 Kg Semen Grout 1,500.00 1,650.00 1,800,000.00 1,980,000.00
650 kg Screening 2,000.00 2,100.00 1,300,000.00 1,365,000.00
350 Ltr Air 20.00 25.00 7,000.00 8,750.00
C PERALATAN - -
D Jumlah A + B + C 3,107,000.00 3,353,750.00
E Overhead & Profit (contoh 10%) 10% 310,700.00 335,375.00
F Harga Satuan Pekerjaan (D+E) 3,417,700.00 3,689,125.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/67 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
21 A.4.1.2.21 1 m3 Bahan Grout Campuran (tidak Campuran) 3,061,300.00 3,368,750.00
A Tenaga - -

B Bahan 2,783,000.00 3,062,500.00


1,850 Kg Semen Grout 1,500.00 1,650.00 2,775,000.00 3,052,500.00
400 Ltr Air 20.00 25.00 8,000.00 10,000.00
C PERALATAN - -
D Jumlah A + B + C 2,783,000.00 3,062,500.00
E Overhead & Profit (contoh 10%) 10% 278,300.00 306,250.00
F Harga Satuan Pekerjaan (D+E) 3,061,300.00 3,368,750.00

22 A.4.1.2.22 1 ttk Upah Pekerjaan Gruot pada Joint Beton Pra Cetak 64,113.50 69,371.50
A Tenaga 58,285.00 63,065.00
L.02 0.367 OH Tukang Batu 120,000.000 130,000.000 44,040.000 47,710.000
L.03 0.074 OH Kepala Tukang 130,000.000 140,000.000 9,620.000 10,360.000
L.04 0.037 OH Mandor 125,000.000 135,000.000 4,625.000 4,995.000

B Bahan - -

C PERALATAN - -
D Jumlah A + B + C 58,285.00 63,065.00
E Overhead & Profit (contoh 10%) 10% 5,828.50 6,306.50
F Harga Satuan Pekerjaan (D+E) 64,113.50 69,371.50

23 A.4.1.2.23 1 ttk Pemasangan Bekisting Joint Pra Cetak 117,848.50 134,788.50


A Tenaga 31,975.00 35,115.00
L.01 0.147 OH Pekerja 80,000.00 90,000.00 11,760.000 13,230.000
L.02 0.147 OH Tukang Batu 120,000.000 130,000.000 17,640.000 19,110.000
L.03 0.015 OH Kepala Tukang 130,000.000 140,000.000 1,950.000 2,100.000
L.04 0.005 OH Mandor 125,000.000 135,000.000 625.000 675.000
B Bahan 75,160.00 87,420.00
0.012 m3 Kayu Kaso 5/7 5,200,000.00 6,000,000.00 62,400.00 72,000.00
0.004 m3 Papan Cor 2,200,000.00 2,700,000.00 8,800.00 10,800.00
0.264 Kg Paku (5 s/d 7) cm 15,000.00 17,500.00 3,960.00 4,620.00
C PERALATAN - -
D Jumlah A + B + C 107,135.00 122,535.00
E Overhead & Profit (contoh 10%) 10% 10,713.50 12,253.50
F Harga Satuan Pekerjaan (D+E) 117,848.50 134,788.50

24 A.4.1.2.24 1 ttk Upah Pemasangan Joint dengan Sling 52,816.50 58,019.50


A Tenaga 48,015.00 52,745.00
L.01 0.220 OH Pekerja 80,000.00 90,000.00 17,600.000 19,800.000
L.02 0.022 OH Tukang Batu 120,000.000 130,000.000 2,640.000 2,860.000
L.02 0.220 OH Tukang Besi 120,000.000 130,000.000 26,400.000 28,600.000
L.04 0.011 OH Mandor 125,000.000 135,000.000 1,375.000 1,485.000
B Bahan

C PERALATAN - -
D Jumlah A + B + C 48,015.00 52,745.00
E Overhead & Profit (contoh 10%) 10% 4,801.50 5,274.50
F Harga Satuan Pekerjaan (D+E) 52,816.50 58,019.50

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/68 4a-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

V A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


1 A.4.2.1.1 1 Kg Pemasangan Besi Profil 32,813.00 34,548.25
A Tenaga 13,155.00 14,445.00
L.01 0.06 OH Pekerja 80,000.00 90,000.00 4,800.00 5,400.00
L.02 0.06 OH Tukang Besi 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 16,675.00 16,962.50
1.15 Kg Besi Profil 14,500.00 14,750.00 16,675.00 16,962.50
C PERALATAN
D Jumlah A + B + C 29,830.00 31,407.50
E Overhead & Profit (contoh 10%) 10% 2,983.00 3,140.75
F Harga Satuan Pekerjaan (D+E) 32,813.00 34,548.25

2 A.4.2.1.2 1 Kg Pemasangan Rangka Kuda-kuda Baja IWF 26,741.00 28,033.50


A Tenaga 13,155.00 14,445.00
L.01 0.06 OH Pekerja 80,000.00 90,000.00 4,800.00 5,400.00
L.02 0.06 OH Tukang Besi 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 11,155.00 11,040.00
1.15 kg Besi Baja IWF 9,700.00 9,600.00 11,155.00 11,040.00
C PERALATAN
D Jumlah A + B + C 24,310.00 25,485.00
E Overhead & Profit (contoh 10%) 10% 2,431.00 2,548.50
F Harga Satuan Pekerjaan (D+E) 26,741.00 28,033.50

3 A.4.2.1.3 100 kg Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) 102,195.50 118,926.50


A Tenaga 20,755.00 22,815.00
L.01 0.100 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.02 0.100 OH Tukang Besi 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.001 OH Kepala Tukang 130,000.00 140,000.00 130.00 140.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 12,150.00 13,300.00
1 ltr Solar 8,200.00 8,600.00 8,200.00 8,600.00
0.1 ltr Minyak Pelumas 39,500.00 47,000.00 3,950.00 4,700.00
C PERALATAN 60,000 72,000
0.800 jam Sewa Alat 75,000 90,000 60,000 72,000
D Jumlah A + B + C 92,905.00 108,115.00
E Overhead & Profit (contoh 10%) 10% 9,290.50 10,811.50
F Harga Satuan Pekerjaan (D+E) 102,195.50 118,926.50

Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap,


4 A.4.2.1.4 1 m2 921,360.00 953,832.00
rangka baja Siku
A Tenaga 230,150.00 252,720.00
L.01 1.05 OH Pekerja 80,000.00 90,000.00 84,000.00 94,500.00
L.02 1.05 OH Tukang Besi 120,000.00 130,000.00 126,000.00 136,500.00
L.03 0.105 OH Kepala Tukang 130,000.00 140,000.00 13,650.00 14,700.00
L.04 0.052 OH Mandor 125,000.00 135,000.00 6,500.00 7,020.00
B Bahan 607,450.00 614,400.00
15 Kg Besi Siku L.30.30.3 9,700.00 9,600.00 145,500.00 144,000.00
32.8 Kg Besi Plat Baja 14,000.00 14,250.00 459,200.00 467,400.00
0.05 Kg Kawat Las 55,000.00 60,000.00 2,750.00 3,000.00
C PERALATAN
D Jumlah A + B + C 837,600.00 867,120.00
E Overhead & Profit (contoh 10%) 10% 83,760.00 86,712.00
F Harga Satuan Pekerjaan (D+E) 921,360.00 953,832.00

5 A.4.2.1.5 10 cm Pengerjaan Pengelasan dengan Las Listrik 23,610.40 27,385.60


A Tenaga 6,110.00 6,750.00
L.01 0.04 OH Pekerja 80,000.00 90,000.00 3,200.00 3,600.00
L.02 0.02 OH Tukang Besi 120,000.00 130,000.00 2,400.00 2,600.00
L.03 0.002 OH Kepala Tukang 130,000.00 140,000.00 260.00 280.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 2,604.00 2,846.00
0.04 kg Kawat Las 55,000.00 60,000.00 2,200.00 2,400.00
0.03 ltr Solar 8,200.00 8,600.00 246.00 258.00
0.004 ltr Minyak Pelumas 39,500.00 47,000.00 158.00 188.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/69 5-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

C PERALATAN 12,750 15,300


0.170 jam Sewa Alat 75,000 90,000 12,750 15,300
D Jumlah A + B + C 21,464.00 24,896.00
E Overhead & Profit (contoh 10%) 10% 2,146.40 2,489.60
F Harga Satuan Pekerjaan (D+E) 23,610.40 27,385.60

6 A.4.2.1.6 1 m2 Pembuatan Rangka Jendela Besi Scuare Tube 249,740.48 281,136.02


A Tenaga 142,450.00 156,420.00
L.01 0.65 OH Pekerja 80,000.00 90,000.00 52,000.00 58,500.00
L.02 0.65 OH Tukang Las Biasa 120,000.00 130,000.00 78,000.00 84,500.00
L.03 0.065 OH Kepala Tukang 130,000.00 140,000.00 8,450.00 9,100.00
L.04 0.032 OH Mandor 125,000.00 135,000.00 4,000.00 4,320.00
B Bahan 84,586.80 99,158.20
4.760 m' Besi Scuare tube 5,000.00 6,000.00 23,800.00 28,560.00
4.522 m' Besi List Kaca 1 x 1 cm 3,000.00 3,500.00 13,566.00 15,827.00
20.000 cm Pengelasan 2,361.04 2,738.56 47,220.80 54,771.20
C PERALATAN
D Jumlah A + B + C 227,036.80 255,578.20
E Overhead & Profit (contoh 10%) 10% 22,703.68 25,557.82
F Harga Satuan Pekerjaan (D+E) 249,740.48 281,136.02

7 A.4.2.1.7 1 m2 Pemasangan Pintu Rolling Door Besi 639,485.00 678,271.00


A Tenaga 256,350.00 281,610.00
L.01 1.2 OH Pekerja 80,000.00 90,000.00 96,000.00 108,000.00
L.02 1.2 OH Tukang Besi 120,000.00 130,000.00 144,000.00 156,000.00
L.03 0.12 OH Kepala Tukang 130,000.00 140,000.00 15,600.00 16,800.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 325,000.00 335,000.00
1 m2 Pintu Gulung Besi 325,000.00 335,000.00 325,000.00 335,000.00
C PERALATAN
D Jumlah A + B + C 581,350.00 616,610.00
E Overhead & Profit (contoh 10%) 10% 58,135.00 61,661.00
F Harga Satuan Pekerjaan (D+E) 639,485.00 678,271.00

8 A.4.2.1.8 1 m2 Pemasangan Pintu Lipat (Folding Door) 546,117.00 584,023.00


A Tenaga 96,470.00 105,930.00
L.01 0.44 OH Pekerja 80,000.00 90,000.00 35,200.00 39,600.00
L.02 0.44 OH Tukang Besi 120,000.00 130,000.00 52,800.00 57,200.00
L.03 0.044 OH Kepala Tukang 130,000.00 140,000.00 5,720.00 6,160.00
L.04 0.022 OH Mandor 125,000.00 135,000.00 2,750.00 2,970.00
B Bahan 400,000.00 425,000.00
1 m2 Pintu Lipat 400,000.00 425,000.00 400,000.00 425,000.00
C PERALATAN
D Jumlah A + B + C 496,470.00 530,930.00
E Overhead & Profit (contoh 10%) 10% 49,647.00 53,093.00
F Harga Satuan Pekerjaan (D+E) 546,117.00 584,023.00

9 A.4.2.1.9 1 m2 Pemasangan Sunscreen Allumunium 509,630.00 575,234.00


A Tenaga 113,300.00 122,940.00
L.01 0.08 OH Pekerja 80,000.00 90,000.00 6,400.00 7,200.00
L.02 0.8 OH Tukang Besi 120,000.00 130,000.00 96,000.00 104,000.00
L.03 0.08 OH Kepala Tukang 130,000.00 140,000.00 10,400.00 11,200.00
L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00
B Bahan 350,000.00 400,000.00
1 m2 Sunscreen Allumunium 350,000.00 400,000.00 350,000.00 400,000.00
C PERALATAN
D Jumlah A + B + C 463,300.00 522,940.00
E Overhead & Profit (contoh 10%) 10% 46,330.00 52,294.00
F Harga Satuan Pekerjaan (D+E) 509,630.00 575,234.00

10 A.4.2.1.10 1 m2 Pemasangan Rolling Door Allumunium 543,675.00 583,825.00


A Tenaga 219,250.00 240,750.00
L.01 1 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00
L.02 1 OH Tukang Besi 120,000.00 130,000.00 120,000.00 130,000.00
L.03 0.1 OH Kepala Tukang 130,000.00 140,000.00 13,000.00 14,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/70 5-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

B Bahan 275,000.00 290,000.00


1 m2 Rolling Allumunium 275,000.00 290,000.00 275,000.00 290,000.00
C PERALATAN
D Jumlah A + B + C 494,250.00 530,750.00
E Overhead & Profit (contoh 10%) 10% 49,425.00 53,075.00
F Harga Satuan Pekerjaan (D+E) 543,675.00 583,825.00

11 A.4.2.1.11 1 m' Pemasangan Kusen Pintu Allumunium 130,263.65 138,100.05


A Tenaga 9,421.50 10,345.50
L.01 0.043 OH Pekerja 80,000.00 90,000.00 3,440.00 3,870.00
L.02 0.043 OH Tukang Besi 120,000.00 130,000.00 5,160.00 5,590.00
L.03 0.0043 OH Kepala Tukang 130,000.00 140,000.00 559.00 602.00
L.04 0.0021 OH Mandor 125,000.00 135,000.00 262.50 283.50
B Bahan 109,000.00 115,200.00
1.1 m' Profil Allumunium 95,000.00 100,000.00 104,500.00 110,000.00
2 buah Skrup Fixer 750.00 800.00 1,500.00 1,600.00
0.06 Tube Sealant 50,000.00 60,000.00 3,000.00 3,600.00
C PERALATAN
D Jumlah A + B + C 118,421.50 125,545.50
E Overhead & Profit (contoh 10%) 10% 11,842.15 12,554.55
F Harga Satuan Pekerjaan (D+E) 130,263.65 138,100.05

12 A.4.2.1.12 1 m2 Pemasangan Pintu Allumunium Strip Lebar 8 cm 552,563.00 586,802.70


A Tenaga 18,630.00 20,457.00
L.01 0.085 OH Pekerja 80,000.00 90,000.00 6,800.00 7,650.00
L.02 0.085 OH Tukang Besi 120,000.00 130,000.00 10,200.00 11,050.00
L.03 0.0085 OH Kepala Tukang 130,000.00 140,000.00 1,105.00 1,190.00
L.04 0.0042 OH Mandor 125,000.00 135,000.00 525.00 567.00
B Bahan 483,700.00 513,000.00
4.4 m' Profil Allumunium 95,000.00 100,000.00 418,000.00 440,000.00
14.6 m' Allumunium Strip 4,500.00 5,000.00 65,700.00 73,000.00
C PERALATAN
D Jumlah A + B + C 502,330.00 533,457.00
E Overhead & Profit (contoh 10%) 10% 50,233.00 53,345.70
F Harga Satuan Pekerjaan (D+E) 552,563.00 586,802.70

13 A.4.2.1.13 1 m2 Pemasangan Pintu Kaca Rangka Allumunium 520,074.50 554,218.50


A Tenaga 18,795.00 20,635.00
L.01 0.085 OH Pekerja 80,000.00 90,000.00 6,800.00 7,650.00
L.02 0.085 OH Tukang Besi 120,000.00 130,000.00 10,200.00 11,050.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 454,000.00 483,200.00
4.4 m' Pintu Allumunium 95,000.00 100,000.00 418,000.00 440,000.00
4.5 m' Profil Kaca 5,000.00 6,000.00 22,500.00 27,000.00
0.27 tube Sealant 50,000.00 60,000.00 13,500.00 16,200.00
C PERALATAN
D Jumlah A + B + C 472,795.00 503,835.00
E Overhead & Profit (contoh 10%) 10% 47,279.50 50,383.50
F Harga Satuan Pekerjaan (D+E) 520,074.50 554,218.50

14 A.4.2.1.14 1 m2 Pemasangan Venetions Blinds & Vertical Blinds 188,980.00 202,763.00


A Tenaga 76,800.00 84,330.00
L.01 0.35 OH Pekerja 80,000.00 90,000.00 28,000.00 31,500.00
L.02 0.35 OH Tukang Besi 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
B Bahan 95,000.00 100,000.00
1 m2 Venetions Blinds atau Vertical Blinds (tirai) 95,000.00 100,000.00 95,000.00 100,000.00
C PERALATAN
D Jumlah A + B + C 171,800.00 184,330.00
E Overhead & Profit (contoh 10%) 10% 17,180.00 18,433.00
F Harga Satuan Pekerjaan (D+E) 188,980.00 202,763.00

15 A.4.2.1.15 1 m2 Pemasangan Teralis Besi Strip (2x3) cm 568,149.96 620,584.20


A Tenaga 366,085.00 401,985.00
L.01 1.67 OH Pekerja 80,000.00 90,000.00 133,600.00 150,300.00
L.02 1.67 OH Tukang Las 120,000.00 130,000.00 200,400.00 217,100.00
L.03 0.167 OH Kepala Tukang 130,000.00 140,000.00 21,710.00 23,380.00
L.04 0.083 OH Mandor 125,000.00 135,000.00 10,375.00 11,205.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/71 5-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

B Bahan 150,414.96 162,182.45


6.177 kg Besi Strip 14,000.00 14,250.00 86,478.00 88,022.25
27.08 cm Pengelasan 2,361.04 2,738.56 63,936.96 74,160.20
C PERALATAN
D Jumlah A + B + C 516,499.96 564,167.45
E Overhead & Profit (contoh 10%) 10% 51,650.00 56,416.75
F Harga Satuan Pekerjaan (D+E) 568,149.96 620,584.20

16 A.4.2.1.16 1 m2 Pemasangan Kawat Nyamuk 103,598.17 117,098.74


A Tenaga 21,925.00 24,075.00
L.01 0.1 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.02 0.1 OH Tukang 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 72,255.15 82,378.40
1.1 m2 Kawat Nyamuk nylon 20,000.00 25,000.00 22,000.00 27,500.00
11.11 cm Pengelasan 2,361.04 2,738.56 26,231.15 30,425.40
1.716 kg Baja Strip (0,2x2) cm 14,000.00 14,250.00 24,024.00 24,453.00
C PERALATAN
D Jumlah A + B + C 94,180.15 106,453.40
E Overhead & Profit (contoh 10%) 10% 9,418.02 10,645.34
F Harga Satuan Pekerjaan (D+E) 103,598.17 117,098.74

17 A.4.2.1.17 1 m2 Pemasangan Jendela Nako & Tralis 136,372.50 148,978.50


A Tenaga 42,725.00 46,935.00
L.01 0.2 OH Pekerja 80,000.00 90,000.00 16,000.00 18,000.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00
B Bahan 81,250.00 88,500.00
1.1 m2 Jendela Nako 37,500.00 40,000.00 41,250.00 44,000.00
10 buah Paku Skrup 1 - 2,5 cm 500.00 600.00 5,000.00 6,000.00
7 m' Besi Strip 5,000.00 5,500.00 35,000.00 38,500.00
C PERALATAN
D Jumlah A + B + C 123,975.00 135,435.00
E Overhead & Profit (contoh 10%) 10% 12,397.50 13,543.50
F Harga Satuan Pekerjaan (D+E) 136,372.50 148,978.50

Pemasangan Talang Datar / Jurai , Seng BJLS 28 Lebar 90


18 A.4.2.1.18 1 m' 199,017.50 230,051.25
cm
A Tenaga 68,500.00 74,850.00
L.01 0.20 OH Pekerja 80,000.00 90,000.00 16,000.00 18,000.00
L.02 0.4 OH Tukang Kayu 120,000.00 130,000.00 48,000.00 52,000.00
L.03 0.025 OH Kepala Tukang 130,000.00 140,000.00 3,250.00 3,500.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B Bahan 112,425.00 134,287.50
1.05 Lbr Seng Plaat 20,000.00 24,500.00 21,000.00 25,725.00
0.015 Kg Paku Biasa 1 - 2,5 cm 15,000.00 17,500.00 225.00 262.50
0.019 m3 Kayu Papan Klas II atau III 4,800,000.00 5,700,000.00 91,200.00 108,300.00
C PERALATAN
D Jumlah A + B + C 180,925.00 209,137.50
E Overhead & Profit (contoh 10%) 10% 18,092.50 20,913.75
F Harga Satuan Pekerjaan (D+E) 199,017.50 230,051.25

Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat


19 A.4.2.1.19 1 m' 77,962.50 87,956.00
BJLS 30 Lebar 45 cm
A Tenaga 42,725.00 46,935.00
L.01 0.20 OH Pekerja 80,000.00 90,000.00 16,000.00 18,000.00
L.02 0.20 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00
B Bahan 28,150.00 33,025.00
1.05 Lbr Seng Plaat 20,000.00 24,500.00 21,000.00 25,725.00
0.01 Kg Paku Biasa 1 - 2,5 cm 15,000.00 17,500.00 150.00 175.00
0.5 Kg Besi strip 14,000.00 14,250.00 7,000.00 7,125.00
C PERALATAN
D Jumlah A + B + C 70,875.00 79,960.00
E Overhead & Profit (contoh 10%) 10% 7,087.50 7,996.00
F Harga Satuan Pekerjaan (D+E) 77,962.50 87,956.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/72 5-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul


20 A.4.2.1.20 1 m2 121,962.50 131,730.50
60x120 cm dinding partisi
A Tenaga 54,875.00 60,255.00
L.01 0.250 OH Pekerja 80,000.00 90,000.00 20,000.00 22,500.00
L.02 0.250 OH Tukang Besi 120,000.00 130,000.00 30,000.00 32,500.00
L.03 0.025 OH Kepala Tukang 130,000.00 140,000.00 3,250.00 3,500.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00
B Bahan 56,000.00 59,500.00
3.50 m' Rangka metal hollow 40.40.2 mm 8,000.00 8,500.00 28,000.00 29,750.00
1.00 **) Assesoris (perkuatan; las dll) 28,000.00 29,750.00 28,000.00 29,750.00
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C 110,875.00 119,755.00
E Overhead & Profit (contoh 10%) 10% 11,087.50 11,975.50
F Harga Satuan Pekerjaan (D+E) 121,962.50 131,730.50

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul


21 A.4.2.1.21 1 m2 154,880.00 167,563.00
60x60 cm dinding plafond
A Tenaga 76,800.00 84,330.00
L.01 0.350 OH Pekerja 80,000.00 90,000.00 28,000.00 31,500.00
L.02 0.350 OH Tukang Besi 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
B Bahan 64,000.00 68,000.00
4.00 m' Rangka metal hollow 40.40.2 mm 8,000.00 8,500.00 32,000.00 34,000.00
1.00 **) Assesoris (perkuatan; las dll) 32,000.00 34,000.00 32,000.00 34,000.00
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C 140,800.00 152,330.00
E Overhead & Profit (contoh 10%) 10% 14,080.00 15,233.00
F Harga Satuan Pekerjaan (D+E) 154,880.00 167,563.00

Pemasangan Atap Pelana Rangka Atap Baja Canal C


22 A.4.2.1.22 1 m2 240,559.28 259,013.01
dingin Profil C75
A Tenaga 160,915.00 176,695.00
L.01 0.734 OH Pekerja 80,000.00 90,000.00 58,720.00 66,060.00
L.02 0.734 OH Tukang Besi 120,000.00 130,000.00 88,080.00 95,420.00
L.03 0.073 OH Kepala Tukang 130,000.00 140,000.00 9,490.00 10,220.00
L.04 0.037 OH Mandor 125,000.00 135,000.00 4,625.00 4,995.00
B Bahan 53,331.00 54,250.50
3.065 kg Baja Ringan Canal Dingin C75 14,500.00 14,750.00 44,442.50 45,208.75
C PERALATAN 4,444.25 4,520.88
10 % Peralatan *) harga bahan 44,442.50 45,208.75 4,444.25 4,520.88
D Jumlah A + B + C 218,690.25 235,466.38
E Overhead & Profit (contoh 10%) 10% 21,869.03 23,546.64
F Harga Satuan Pekerjaan (D+E) 240,559.28 259,013.01

Pemasangan Atap Jurai Rangka Atap Baja Canal Dingin


23 A.4.2.1.23 1 m2 267,357.75 286,788.43
Profil C75
A Tenaga 166,710.00 183,058.00
L.01 0.7604 OH Pekerja 80,000.00 90,000.00 60,832.00 68,436.00
L.02 0.7604 OH Tukang Besi 120,000.00 130,000.00 91,248.00 98,852.00
L.03 0.0760 OH Kepala Tukang 130,000.00 140,000.00 9,880.00 10,640.00
L.04 0.0380 OH Mandor 125,000.00 135,000.00 4,750.00 5,130.00
B Bahan 70,470.00 71,685.00
4.05 kg Baja Ringan Canal Dingin C75 14,500.00 14,750.00 58,725.00 59,737.50
C PERALATAN 5,872.50 5,973.75
10 % Peralatan *) harga bahan 58,725.00 59,737.50 5,872.50 5,973.75
D Jumlah A + B + C 243,052.50 260,716.75
E Overhead & Profit (contoh 10%) 10% 24,305.25 26,071.68
F Harga Satuan Pekerjaan (D+E) 267,357.75 286,788.43

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/73 5-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

VI A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


Pemasangan Dinding Bata Merah ukuran (5x11x22) cm
1 A.4.4.1.1 1 m2 262,336.25 285,615.00
Tebal 1 bata Camp. 1SP: 2PP
A Tenaga 78,350.00 86,850.00
L.01 0.6 OH Pekerja 80,000.00 90,000.00 48,000.00 54,000.00
L.02 0.2 OH Tukang Batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang Batu 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 160,137.50 172,800.00
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
43.5 Kg Portland Semen (PC) 1,125.00 1,200.00 48,937.50 52,200.00
0.08 m3 Pasir Pasang (PP) 340,000.00 370,000.00 27,200.00 29,600.00
C PERALATAN
D Jumlah A + B + C 238,487.50 259,650.00
E Overhead & Profit (contoh 10%) 10% 23,848.75 25,965.00
F Harga Satuan Pekerjaan (D+E) 262,336.25 285,615.00
Overhead & Profit (contoh 10%)
Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm
2 A.4.4.1.2 1 m2 253,394.63 276,166.00
Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga 78,350.00 86,850.00
L.01 0.6 OH Pekerja 80,000.00 90,000.00 48,000.00 54,000.00
L.02 0.2 OH Tukang Batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang Batu 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 152,008.75 164,210.00
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
32.95 Kg Portland Semen (PC) 1,125.00 1,200.00 37,068.75 39,540.00
0.091 m3 Pasir Pasang (PP) 340,000.00 370,000.00 30,940.00 33,670.00
C PERALATAN
D Jumlah A + B + C 230,358.75 251,060.00
E Overhead & Profit (contoh 10%) 10% 23,035.88 25,106.00
F Harga Satuan Pekerjaan (D+E) 253,394.63 276,166.00

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


3 A.4.4.1.3 1 m2 246,222.63 268,532.00
Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga 78,350.00 86,850.00
L.01 0.6 OH Pekerja 80,000.00 90,000.00 48,000.00 54,000.00
L.02 0.2 OH Tukang Batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang Batu 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 145,488.75 157,270.00
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
26.55 Kg Portland Semen (PC) 1,125.00 1,200.00 29,868.75 31,860.00
0.093 m3 Pasir Pasang (PP) 340,000.00 370,000.00 31,620.00 34,410.00
C PERALATAN
D Jumlah A + B + C 223,838.75 244,120.00
E Overhead & Profit (contoh 10%) 10% 22,383.88 24,412.00
F Harga Satuan Pekerjaan (D+E) 246,222.63 268,532.00

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


4 A.4.4.1.4 1 m2 244,205.50 266,453.00
Tebal 1 Bata Camp. 1SP : 5PP
A Tenaga 78,350.00 86,850.00
L.01 0.6 OH Pekerja 80,000.00 90,000.00 48,000.00 54,000.00
L.02 0.2 OH Tukang Batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang Batu 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 143,655.00 155,380.00
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
22.2 Kg Portland Semen (PC) 1,125.00 1,200.00 24,975.00 26,640.00
0.102 m3 Pasir Pasang (PP) 340,000.00 370,000.00 34,680.00 37,740.00
C PERALATAN
D Jumlah A + B + C 222,005.00 242,230.00
E Overhead & Profit (contoh 10%) 10% 22,200.50 24,223.00
F Harga Satuan Pekerjaan (D+E) 244,205.50 266,453.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/74 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm
5 A.4.4.1.5 1 m2 247,106.75 269,709.00
Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga 78,350.00 86,850.00
L.01 0.6 OH Pekerja 80,000.00 90,000.00 48,000.00 54,000.00
L.02 0.2 OH Tukang Batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang Batu 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 146,292.50 158,340.00
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
18.5 Kg Portland Semen (PC) 1,125.00 1,200.00 20,812.50 22,200.00
0.122 m3 Pasir Pasang (PP) 340,000.00 370,000.00 41,480.00 45,140.00
C PERALATAN
D Jumlah A + B + C 224,642.50 245,190.00
E Overhead & Profit (contoh 10%) 10% 22,464.25 24,519.00
F Harga Satuan Pekerjaan (D+E) 247,106.75 269,709.00

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


6 A.4.4.1.6 1 m2 234,729.00 255,965.60
Tebal 1 Bata Camp. 1SP : 3 KP :10PP
A Tenaga 78,350.00 86,850.00
L.01 0.6 OH Pekerja 80,000.00 90,000.00 48,000.00 54,000.00
L.02 0.2 OH Tukang Batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang Batu 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 135,040.00 145,846.00
140 Buah Bata Merah 600.00 650.00 84,000.00 91,000.00
10.08 Kg Portland Semen (PC) 1,125.00 1,200.00 11,340.00 12,096.00
0.0925 m3 Pasir Pasang (PP) 340,000.00 370,000.00 31,450.00 34,225.00
0.0275 m3 Kapur Pasang (KP) 300,000.00 310,000.00 8,250.00 8,525.00
C PERALATAN
D Jumlah A + B + C 213,390.00 232,696.00
E Overhead & Profit (contoh 10%) 10% 21,339.00 23,269.60
F Harga Satuan Pekerjaan (D+E) 234,729.00 255,965.60

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


7 A.4.4.1.7 1 m2 126,955.13 138,297.50
Tebal 1/2 Bata Camp. 1SP : 2PP
A Tenaga 39,175.00 43,425.00
L.01 0.30 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 76,238.75 82,300.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
18.95 Kg Portland Semen 1,125.00 1,200.00 21,318.75 22,740.00
0.038 m3 Pasir Pasang 340,000.00 370,000.00 12,920.00 14,060.00
C PERALATAN
D Jumlah A + B + C 115,413.75 125,725.00
E Overhead & Profit (contoh 10%) 10% 11,541.38 12,572.50
F Harga Satuan Pekerjaan (D+E) 126,955.13 138,297.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


8 A.4.4.1.8 1 m2 122,035.38 133,065.90
Tebal 1/2 Bata Camp. 1SP : 3PP
A Tenaga 39,175.00 43,425.00
L.01 0.30 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 71,766.25 77,544.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
14.37 Kg Portland Semen 1,125.00 1,200.00 16,166.25 17,244.00
0.04 m3 Pasir Pasang 340,000.00 370,000.00 13,600.00 14,800.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/75 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 110,941.25 120,969.00
E Overhead & Profit (contoh 10%) 10% 11,094.13 12,096.90
F Harga Satuan Pekerjaan (D+E) 122,035.38 133,065.90

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


9 A.4.4.1.9 1 m2 119,605.75 130,498.50
Tebal 1/2 Bata Camp. 1SP : 4PP
A Tenaga 39,175.00 43,425.00
L.01 0.30 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 69,557.50 75,210.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
11.50 Kg Portland Semen 1,125.00 1,200.00 12,937.50 13,800.00
0.043 m3 Pasir Pasang 340,000.00 370,000.00 14,620.00 15,910.00
C PERALATAN
D Jumlah A + B + C 108,732.50 118,635.00
E Overhead & Profit (contoh 10%) 10% 10,873.25 11,863.50
F Harga Satuan Pekerjaan (D+E) 119,605.75 130,498.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


10 A.4.4.1.10 1 m2 118,101.50 128,910.10
Tebal 1/2 Bata Camp. 1SP : 5PP
A Tenaga 39,175.00 43,425.00
L.01 0.30 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 68,190.00 73,766.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
9.68 Kg Portland Semen 1,125.00 1,200.00 10,890.00 11,616.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 107,365.00 117,191.00
E Overhead & Profit (contoh 10%) 10% 10,736.50 11,719.10
F Harga Satuan Pekerjaan (D+E) 118,101.50 128,910.10

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


11 A.4.4.1.11 1 m2 117,914.50 128,742.90
Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga 39,175.00 43,425.00
L.01 0.30 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 68,020.00 73,614.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
8.32 Kg Portland Semen 1,125.00 1,200.00 9,360.00 9,984.00
0.049 m3 Pasir Pasang 340,000.00 370,000.00 16,660.00 18,130.00
C PERALATAN
D Jumlah A + B + C 107,195.00 117,039.00
E Overhead & Profit (contoh 10%) 10% 10,719.50 11,703.90
F Harga Satuan Pekerjaan (D+E) 117,914.50 128,742.90

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


12 A.4.4.1.12 1 m2 116,036.25 126,747.50
Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga 39,175.00 43,425.00
L.01 0.30 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 66,312.50 71,800.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
6.50 Kg Portland Semen 1,125.00 1,200.00 7,312.50 7,800.00
0.05 m3 Pasir Pasang 340,000.00 370,000.00 17,000.00 18,500.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/76 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 105,487.50 115,225.00
E Overhead & Profit (contoh 10%) 10% 10,548.75 11,522.50
F Harga Satuan Pekerjaan (D+E) 116,036.25 126,747.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


13 A.4.4.1.13 1 m2 118,511.25 129,222.50
Tebal 1/2 Bata Camp. 1SP : 3KP : 10PP
A Tenaga 39,175.00 43,425.00
L.01 0.30 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 68,562.50 74,050.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
4.5 Kg Portland Semen 1,125.00 1,200.00 5,062.50 5,400.00
0.05 m3 Pasir Pasang 340,000.00 370,000.00 17,000.00 18,500.00
0.015 m3 Kapur Padam 300,000.00 310,000.00 4,500.00 4,650.00
C PERALATAN
D Jumlah A + B + C 107,737.50 117,475.00
E Overhead & Profit (contoh 10%) 10% 10,773.75 11,747.50
F Harga Satuan Pekerjaan (D+E) 118,511.25 129,222.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


14 A.4.4.1.14 1 m2 105,924.50 115,241.50
Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP
A Tenaga 39,175.00 43,425.00
L.01 0.30 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 57,120.00 61,340.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
0.018 m3 Semen Merah 200,000.00 200,000.00 3,600.00 3,600.00
0.018 m3 Pasir Pasang 340,000.00 370,000.00 6,120.00 6,660.00
0.018 m3 Kapur Padam 300,000.00 310,000.00 5,400.00 5,580.00
C PERALATAN
D Jumlah A + B + C 96,295.00 104,765.00
E Overhead & Profit (contoh 10%) 10% 9,629.50 10,476.50
F Harga Satuan Pekerjaan (D+E) 105,924.50 115,241.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


15 A.4.4.1.15 1 m2 107,464.50 117,067.50
Tebal 1/2 Bata Camp. 1SM : 1KP : 2PP
A Tenaga 39,175.00 43,425.00
L.01 0.30 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 58,520.00 63,000.00
70 Buah Bata Merah 5 x 11 x 22 600.00 650.00 42,000.00 45,500.00
0.014 m3 Semen Merah 200,000.00 200,000.00 2,800.00 2,800.00
0.028 m3 Pasir Pasang 340,000.00 370,000.00 9,520.00 10,360.00
0.014 m3 Kapur Padam 300,000.00 310,000.00 4,200.00 4,340.00
C PERALATAN
D Jumlah A + B + C 97,695.00 106,425.00
E Overhead & Profit (contoh 10%) 10% 9,769.50 10,642.50
F Harga Satuan Pekerjaan (D+E) 107,464.50 117,067.50

16 A.4.4.1.16 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 3PP 423,093.00 459,534.90
A Tenaga 50,200.00 55,530.00
L.01 0.350 OH Pekerja 80,000.00 90,000.00 28,000.00 31,500.00
L.02 0.150 OH Tukang Batu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/77 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 334,430.00 362,229.00
12.500 buah Batako 4,000.00 4,250.00 50,000.00 53,125.00
30.320 kg PC 1,125.00 1,200.00 34,110.00 36,384.00
0.728 m3 Pasir Pasang 340,000.00 370,000.00 247,520.00 269,360.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 384,630.00 417,759.00
E Overhead & Profit (contoh 10%) 10% 38,463.00 41,775.90
F Harga Satuan Pekerjaan (D+E) 423,093.00 459,534.90

17 A.4.4.1.17 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 4PP 432,049.75 469,443.70
A Tenaga 50,200.00 55,530.00
L.01 0.350 OH Pekerja 80,000.00 90,000.00 28,000.00 31,500.00
L.02 0.150 OH Tukang Batu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00

B Bahan 342,572.50 371,237.00


12.500 buah Batako 4,000.00 4,250.00 50,000.00 53,125.00
24.260 kg PC 1,125.00 1,200.00 27,292.50 29,112.00
0.772 m3 Pasir Pasang 340,000.00 370,000.00 262,480.00 285,640.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 392,772.50 426,767.00
E Overhead & Profit (contoh 10%) 10% 39,277.25 42,676.70
F Harga Satuan Pekerjaan (D+E) 432,049.75 469,443.70

18 A.4.4.1.18 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 3PP 332,961.75 361,501.80
A Tenaga 43,560.00 48,240.00
L.01 0.320 OH Pekerja 80,000.00 90,000.00 25,600.00 28,800.00
L.02 0.120 OH Tukang Batu 120,000.00 130,000.00 14,400.00 15,600.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.016 OH Mandor 125,000.00 135,000.00 2,000.00 2,160.00
B Bahan 259,132.50 280,398.00
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
22.740 kg PC 1,125.00 1,200.00 25,582.50 27,288.00
0.550 m3 Pasir Pasang 340,000.00 370,000.00 187,000.00 203,500.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 302,692.50 328,638.00
E Overhead & Profit (contoh 10%) 10% 30,269.25 32,863.80
F Harga Satuan Pekerjaan (D+E) 332,961.75 361,501.80

19 A.4.4.1.19 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 4PP 339,311.50 368,533.00
A Tenaga 43,560.00 48,240.00
L.01 0.320 OH Pekerja 80,000.00 90,000.00 25,600.00 28,800.00
L.02 0.120 OH Tukang Batu 120,000.00 130,000.00 14,400.00 15,600.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.016 OH Mandor 125,000.00 135,000.00 2,000.00 2,160.00
B Bahan 264,905.00 286,790.00
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
18.200 kg PC 1,125.00 1,200.00 20,475.00 21,840.00
0.582 m3 Pasir Pasang 340,000.00 370,000.00 197,880.00 215,340.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 308,465.00 335,030.00
E Overhead & Profit (contoh 10%) 10% 30,846.50 33,503.00
F Harga Satuan Pekerjaan (D+E) 339,311.50 368,533.00

20 A.4.4.1.20 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP 267,069.00 295,247.70
A Tenaga 39,175.00 43,425.00
L.01 0.300 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.100 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.010 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/78 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 203,615.00 224,982.00
12.500 buah Batako 4,800.00 5,500.00 60,000.00 68,750.00
15.160 kg PC 1,125.00 1,200.00 17,055.00 18,192.00
0.364 m3 Pasir Pasang 340,000.00 370,000.00 123,760.00 134,680.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 242,790.00 268,407.00
E Overhead & Profit (contoh 10%) 10% 24,279.00 26,840.70
F Harga Satuan Pekerjaan (D+E) 267,069.00 295,247.70

21 A.4.4.1.21 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP 272,295.38 301,016.10
A Tenaga 39,175.00 43,425.00
L.01 0.300 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.100 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.010 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00

B Bahan 208,366.25 230,226.00


12.500 buah Batako 4,800.00 5,500.00 60,000.00 68,750.00
12.130 kg PC 1,125.00 1,200.00 13,646.25 14,556.00
0.388 m3 Pasir Pasang 340,000.00 370,000.00 131,920.00 143,560.00
0.280 kg Besi Angkur Ø 8 mm 10,000.00 12,000.00 2,800.00 3,360.00
C PERALATAN
D Jumlah A + B + C 247,541.25 273,651.00
E Overhead & Profit (contoh 10%) 10% 24,754.13 27,365.10
F Harga Satuan Pekerjaan (D+E) 272,295.38 301,016.10

Pemasangan Dinding Terawang (Rooster) Uk,


22 A.4.4.1.22 1 m2 366,795.00 472,532.50
(12x11x24)cm Camp. 1SP : 3PP
A Tenaga 39,175.00 43,425.00
L.01 0.30 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 294,275.00 386,150.00
30 Buah Terawang / Roster 9,000.00 12,000.00 270,000.00 360,000.00
11 kg Portland Semen 1,125.00 1,200.00 12,375.00 13,200.00
0.035 m3 Pasir Pasang 340,000.00 370,000.00 11,900.00 12,950.00
C PERALATAN
D Jumlah A + B + C 333,450.00 429,575.00
E Overhead & Profit (contoh 10%) 10% 33,345.00 42,957.50
F Harga Satuan Pekerjaan (D+E) 366,795.00 472,532.50

Pemasangan Dinding Terawang (Rooster) Uk,


23 A.4.4.1.23 1 m2 366,795.00 472,532.50
(12x11x24)cm Camp. 1SP : 4PP
A Tenaga 39,175.00 43,425.00
L.01 0.30 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 294,275.00 386,150.00
30 Buah Terawang / Roster 9,000.00 12,000.00 270,000.00 360,000.00
11 kg Portland Semen 1,125.00 1,200.00 12,375.00 13,200.00
0.035 m3 Pasir Pasang 340,000.00 370,000.00 11,900.00 12,950.00
C PERALATAN
D Jumlah A + B + C 333,450.00 429,575.00
E Overhead & Profit (contoh 10%) 10% 33,345.00 42,957.50
F Harga Satuan Pekerjaan (D+E) 366,795.00 472,532.50

Pemasangan Dinding Bata Berongga Ekspose Uk,


24 A.4.4.1.24 1 m2 149,385.50 160,121.50
(12x11x24)cm Camp. 1SP : 3PP
m2 Tenaga 39,175.00 43,425.00
L.01 0.30 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.1 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/79 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
OH Bahan 96,630.00 102,140.00
70 Buah Bata Roster 1,000.00 1,050.00 70,000.00 73,500.00
14 kg Portland Semen 1,125.00 1,200.00 15,750.00 16,800.00
0.032 m3 Pasir Pasang 340,000.00 370,000.00 10,880.00 11,840.00
C PERALATAN
D Jumlah A + B + C 135,805.00 145,565.00
E Overhead & Profit (contoh 10%) 10% 13,580.50 14,556.50
F Harga Satuan Pekerjaan (D+E) 149,385.50 160,121.50

Pemasangan Dinding Bata Ringan Tebal 7,5 cm dengan


25 A.4.4.1.25 1 m2 308,711.04 333,949.06
Mortar Siap Pakai
m2 Tenaga 0.075 226,875.00 247,905.00
L.01 0.67 OH Pekerja 0.12 725000 80,000.00 90,000.00 53,600.00 60,300.00
L.02 1.3 OH Tukang Batu 1 6525 120,000.00 130,000.00 156,000.00 169,000.00
L.03 0.13 OH Kepala Tukang 13.3333333333333 130,000.00 140,000.00 16,900.00 18,200.00
L.04 0.003 OH Mandor 111.111111111111 125,000.00 135,000.00 375.00 405.00
OH Bahan 53,771.40 55,685.05
8.40 Buah Bata Ringan Tebal 7,5 cm 90000 6,300.00 6,525.00 52,920.00 54,810.00
0.473 kg Mortar Siap Pakai 1,800.00 1,850.00 851.40 875.05

C PERALATAN
D Jumlah A + B + C 280,646.40 303,590.05
E Overhead & Profit (contoh 10%) 10% 28,064.64 30,359.01
F Harga Satuan Pekerjaan (D+E) 308,711.04 333,949.06

Pemasangan Dinding Bata Ringan Tebal 10 cm dengan


26 A.4.4.1.26 1 m2 309,274.24 332,520.71
Mortar Siap Pakai
m2 Tenaga 0.075 211,745.00 231,615.00
L.01 0.671 OH Pekerja 0.12 700000 80,000.00 90,000.00 53,680.00 60,390.00
L.02 1.300 OH Tukang Batu 0.1 8400 120,000.00 130,000.00 156,000.00 169,000.00
L.03 0.013 OH Kepala Tukang 10 130,000.00 140,000.00 1,690.00 1,820.00
L.04 0.003 OH Mandor 83.3333333333333 125,000.00 135,000.00 375.00 405.00
OH Bahan 69,413.40 70,676.55
8.40 Buah Bata Ringan Tebal 10 cm 90000 8,250.00 8,400.00 69,300.00 70,560.00
0.063 kg Mortar Siap Pakai 1,800.00 1,850.00 113.40 116.55

C PERALATAN
D Jumlah A + B + C 281,158.40 302,291.55
E Overhead & Profit (contoh 10%) 10% 28,115.84 30,229.16
F Harga Satuan Pekerjaan (D+E) 309,274.24 332,520.71

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/80 6-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.1 1 m2 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm 75,577.70 82,664.78
A Tenaga 45,825.00 50,625.00
L.01 0.3 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00

L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00


B Bahan 22,882.00 24,524.80
15.504 Kg Portland Semen 1,125.00 1,200.00 17,442.00 18,604.80
0.016 m3 Pasir Pasang 340,000.00 370,000.00 5,440.00 5,920.00
C PERALATAN
D Jumlah A + B + C 68,707.00 75,149.80
E Overhead & Profit (contoh 10%) 10% 6,870.70 7,514.98
F Harga Satuan Pekerjaan (D+E) 75,577.70 82,664.78
Overhead & Profit (contoh 10%)
2 A.4.4.2.2 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm 70,539.70 77,323.18
A Tenaga 45,825.00 50,625.00
L.01 0.3 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00


L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 18,302.00 19,668.80
10.224 Kg Portland Semen 1,125.00 1,200.00 11,502.00 12,268.80
0.020 m3 Pasir Pasang 340,000.00 370,000.00 6,800.00 7,400.00
C PERALATAN
D Jumlah A + B + C 64,127.00 70,293.80
E Overhead & Profit (contoh 10%) 10% 6,412.70 7,029.38
F Harga Satuan Pekerjaan (D+E) 70,539.70 77,323.18

3 A.4.4.2.3 1 m2 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm 68,632.30 75,312.82


A Tenaga 45,825.00 50,625.00

L.01 0.3 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00


L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 16,568.00 17,841.20
7.776 Kg Portland Semen 1,125.00 1,200.00 8,748.00 9,331.20
0.023 m3 Pasir Pasang 340,000.00 370,000.00 7,820.00 8,510.00
C PERALATAN
D Jumlah A + B + C 62,393.00 68,466.20
E Overhead & Profit (contoh 10%) 10% 6,239.30 6,846.62
F Harga Satuan Pekerjaan (D+E) 68,632.30 75,312.82

4 A.4.4.2.4 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm 67,105.50 73,692.30


A Tenaga 45,825.00 50,625.00

L.01 0.3 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00


L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00

L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00


B Bahan 15,180.00 16,368.00
6.240 Kg Portland Semen 1,125.00 1,200.00 7,020.00 7,488.00
0.024 m3 Pasir Pasang 340,000.00 370,000.00 8,160.00 8,880.00
C PERALATAN
D Jumlah A + B + C 61,005.00 66,993.00
E Overhead & Profit (contoh 10%) 10% 6,100.50 6,699.30
F Harga Satuan Pekerjaan (D+E) 67,105.50 73,692.30

5 A.4.4.2.5 1 m2 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm 66,546.70 73,112.38


A Tenaga 45,825.00 50,625.00
L.01 0.3 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00
L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 14,672.00 15,840.80
5.184 Kg Portland Semen 1,125.00 1,200.00 5,832.00 6,220.80
0.026 m3 Pasir Pasang 340,000.00 370,000.00 8,840.00 9,620.00
C PERALATAN
D Jumlah A + B + C 60,497.00 66,465.80
E Overhead & Profit (contoh 10%) 10% 6,049.70 6,646.58
F Harga Satuan Pekerjaan (D+E) 66,546.70 73,112.38

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/81 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
6 A.4.4.2.6 1 m2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm 65,970.30 72,505.62
Tenaga 45,825.00 50,625.00

L.01 0.3 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00

L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00


Bahan 14,148.00 15,289.20
4.416 Kg Portland Semen 1,125.00 1,200.00 4,968.00 5,299.20
0.027 m3 Pasir Pasang 340,000.00 370,000.00 9,180.00 9,990.00
C PERALATAN
D Jumlah A + B + C 59,973.00 65,914.20
E Overhead & Profit (contoh 10%) 10% 5,997.30 6,591.42
F Harga Satuan Pekerjaan (D+E) 65,970.30 72,505.62

7 A.4.4.2.7 1 m2 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm 65,750.30 72,279.02


A Tenaga 45,825.00 50,625.00

L.01 0.3 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00

L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00


B Bahan 13,948.00 15,083.20
3.936 Kg Portland Semen 1,125.00 1,200.00 4,428.00 4,723.20
0.028 m3 Pasir Pasang 340,000.00 370,000.00 9,520.00 10,360.00
C PERALATAN
D Jumlah A + B + C 59,773.00 65,708.20
E Overhead & Profit (contoh 10%) 10% 5,977.30 6,570.82
F Harga Satuan Pekerjaan (D+E) 65,750.30 72,279.02

8 A.4.4.2.8 1 m2 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm 65,530.30 72,052.42


A Tenaga 45,825.00 50,625.00

L.01 0.30 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00


L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 13,748.00 14,877.20
3.456 Kg Portland Semen 1,125.00 1,200.00 3,888.00 4,147.20
0.029 m3 Pasir Pasang 340,000.00 370,000.00 9,860.00 10,730.00
C PERALATAN
D Jumlah A + B + C 59,573.00 65,502.20
E Overhead & Profit (contoh 10%) 10% 5,957.30 6,550.22
F Harga Satuan Pekerjaan (D+E) 65,530.30 72,052.42

9 A.4.4.2.9 1 m2 Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15 mm 64,691.00 71,238.20


A Tenaga 47,010.00 52,110.00

L.01 0.36 OH Pekerja 80,000.00 90,000.00 28,800.00 32,400.00


L.02 0.12 OH Tukang batu 120,000.00 130,000.00 14,400.00 15,600.00

L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00

L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00


B Bahan 11,800.00 12,652.00
5.760 Kg Portland Semen 1,125.00 1,200.00 6,480.00 6,912.00
0.003 m3 Kapur Pasang 300,000.00 310,000.00 900.00 930.00
0.013 m3 Pasir Pasang 340,000.00 370,000.00 4,420.00 4,810.00
C PERALATAN
D Jumlah A + B + C 58,810.00 64,762.00
E Overhead & Profit (contoh 10%) 10% 5,881.00 6,476.20
F Harga Satuan Pekerjaan (D+E) 64,691.00 71,238.20

10 A.4.4.2.10 1 m2 Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm 64,553.50 71,126.00


A Tenaga 47,010.00 52,110.00
L.01 0.36 OH Pekerja 80,000.00 90,000.00 28,800.00 32,400.00
L.02 0.12 OH Tukang batu 120,000.00 130,000.00 14,400.00 15,600.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
B Bahan 11,675.00 12,550.00
3 kg Portland Semen 1,125.00 1,200.00 3,375.00 3,600.00
0.005 m3 Kapur Padam 300,000.00 310,000.00 1,500.00 1,550.00
0.020 m3 Pasir Pasang 340,000.00 370,000.00 6,800.00 7,400.00
C PERALATAN
D Jumlah A + B + C 58,685.00 64,660.00
E Overhead & Profit (contoh 10%) 10% 5,868.50 6,466.00
F Harga Satuan Pekerjaan (D+E) 64,553.50 71,126.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/82 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
11 A.4.4.2.11 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15 mm 60,027.00 66,033.00
A Tenaga 47,010.00 52,110.00

L.01 0.36 OH Pekerja 80,000.00 90,000.00 28,800.00 32,400.00

L.02 0.12 OH Tukang batu 120,000.00 130,000.00 14,400.00 15,600.00

L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00

L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00


B Bahan 7,560.00 7,920.00
0.009 m3 Semen Merah 200,000.00 200,000.00 1,800.00 1,800.00
0.009 m3 Kapur Padam 300,000.00 310,000.00 2,700.00 2,790.00
0.009 m3 Pasir Pasang 340,000.00 370,000.00 3,060.00 3,330.00
C PERALATAN
D Jumlah A + B + C 54,570.00 60,030.00
E Overhead & Profit (contoh 10%) 10% 5,457.00 6,003.00
F Harga Satuan Pekerjaan (D+E) 60,027.00 66,033.00

12 A.4.4.2.12 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15 mm 61,171.00 67,353.00


A Tenaga 47,010.00 52,110.00

L.01 0.36 OH Pekerja 80,000.00 90,000.00 28,800.00 32,400.00

L.02 0.12 OH Tukang batu 120,000.00 130,000.00 14,400.00 15,600.00

L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00

L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00


B Bahan 8,600.00 9,120.00
0.007 m3 Semen Merah 200,000.00 200,000.00 1,400.00 1,400.00
0.007 m3 Kapur Padam 300,000.00 310,000.00 2,100.00 2,170.00
0.015 m3 Pasir Pasang 340,000.00 370,000.00 5,100.00 5,550.00
C PERALATAN
D Jumlah A + B + C 55,610.00 61,230.00
E Overhead & Profit (contoh 10%) 10% 5,561.00 6,123.00
F Harga Satuan Pekerjaan (D+E) 61,171.00 67,353.00

13 A.4.4.2.13 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm 94,452.60 103,530.24


A Tenaga 61,350.00 67,770.00

L.01 0.40 OH Pekerja 80,000.00 90,000.00 32,000.00 36,000.00

L.02 0.20 OH Tukang batu 120,000.00 130,000.00 24,000.00 26,000.00

L.03 0.020 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00

L.04 0.022 OH Mandor 125,000.00 135,000.00 2,750.00 2,970.00


B Bahan 24,516.00 26,348.40
13.632 kg Portland Semen 1,125.00 1,200.00 15,336.00 16,358.40
0.027 m3 Pasir Pasang 340,000.00 370,000.00 9,180.00 9,990.00
C PERALATAN
D Jumlah A + B + C 85,866.00 94,118.40
E Overhead & Profit (contoh 10%) 10% 8,586.60 9,411.84
F Harga Satuan Pekerjaan (D+E) 94,452.60 103,530.24

14 A.4.4.2.14 1 m2 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm 71,229.00 77,866.60


A Tenaga 49,025.00 53,955.00
L.01 0.26 OH Pekerja 80,000.00 90,000.00 20,800.00 23,400.00
L.02 0.2 OH Tukang batu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00
B Bahan 22,204.00 23,911.60
10.368 Kg Portland Semen 1,125.00 1,200.00 11,664.00 12,441.60
0.031 m3 Pasir Pasang 340,000.00 370,000.00 10,540.00 11,470.00
C PERALATAN
D Jumlah A + B + C 72,854.00 79,621.60
E Overhead & Profit (contoh 10%) 10% 7,285.40 7,962.16
F Harga Satuan Pekerjaan (D+E) 80,139.40 87,583.76

15 A.4.4.2.15 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm 89,749.00 98,553.40


A Tenaga 61,350.00 67,770.00

L.01 0.40 OH Pekerja 80,000.00 90,000.00 32,000.00 36,000.00

L.02 0.20 OH Tukang batu 120,000.00 130,000.00 24,000.00 26,000.00


L.03 0.020 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00

L.04 0.022 OH Mandor 125,000.00 135,000.00 2,750.00 2,970.00


B Bahan 20,240.00 21,824.00
8.320 kg Portland Semen 1,125.00 1,200.00 9,360.00 9,984.00
0.032 m3 Pasir Pasang 340,000.00 370,000.00 10,880.00 11,840.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/83 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 81,590.00 89,594.00
E Overhead & Profit (contoh 10%) 10% 8,159.00 8,959.40
F Harga Satuan Pekerjaan (D+E) 89,749.00 98,553.40

16 A.4.4.2.16 1 m2 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm 89,128.60 97,915.84


A Tenaga 61,350.00 67,770.00

L.01 0.400 OH Pekerja 80,000.00 90,000.00 32,000.00 36,000.00

L.02 0.200 OH Tukang batu 120,000.00 130,000.00 24,000.00 26,000.00

L.03 0.020 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00

L.04 0.022 OH Mandor 125,000.00 135,000.00 2,750.00 2,970.00


B Bahan 19,676.00 21,244.40
6.912 Kg Portland Semen 1,125.00 1,200.00 7,776.00 8,294.40
0.035 m3 Pasir Pasang 340,000.00 370,000.00 11,900.00 12,950.00
C PERALATAN
D Jumlah A + B + C 81,026.00 89,014.40
E Overhead & Profit (contoh 10%) 10% 8,102.60 8,901.44
F Harga Satuan Pekerjaan (D+E) 89,128.60 97,915.84

17 A.4.4.2.17 1 m2 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm 88,235.40 96,971.16


A Tenaga 61,350.00 67,770.00

L.01 0.40 OH Pekerja 80,000.00 90,000.00 32,000.00 36,000.00

L.02 0.2 OH Tukang batu 120,000.00 130,000.00 24,000.00 26,000.00

L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00


L.04 0.022 OH Mandor 125,000.00 135,000.00 2,750.00 2,970.00
B Bahan 18,864.00 20,385.60
5.888 Kg Portland Semen 1,125.00 1,200.00 6,624.00 7,065.60
0.036 m3 Pasir Pasang 340,000.00 370,000.00 12,240.00 13,320.00
C PERALATAN
D Jumlah A + B + C 80,214.00 88,155.60
E Overhead & Profit (contoh 10%) 10% 8,021.40 8,815.56
F Harga Satuan Pekerjaan (D+E) 88,235.40 96,971.16

18 A.4.4.2.18 1 m2 Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20 mm 85,613.00 94,050.00


A Tenaga 67,210.00 74,250.00

L.01 0.440 OH Pekerja 80,000.00 90,000.00 35,200.00 39,600.00

L.02 0.22 OH Tukang batu 120,000.00 130,000.00 26,400.00 28,600.00

L.03 0.022 OH Kepala Tukang 130,000.00 140,000.00 2,860.00 3,080.00

L.04 0.022 OH Mandor 125,000.00 135,000.00 2,750.00 2,970.00


B Bahan 10,620.00 11,250.00
0.009 m3 Semen Merah 200,000.00 200,000.00 1,800.00 1,800.00
0.009 m3 Kapur Padam 300,000.00 310,000.00 2,700.00 2,790.00
0.018 m3 Pasir Pasang 340,000.00 370,000.00 6,120.00 6,660.00
C PERALATAN
D Jumlah A + B + C 77,830.00 85,500.00
E Overhead & Profit (contoh 10%) 10% 7,783.00 8,550.00
F Harga Satuan Pekerjaan (D+E) 85,613.00 94,050.00

19 A.4.4.2.19 1 m2 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm 41,483.20 45,419.88


A Tenaga 23,040.00 25,450.00

L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00


L.02 0.075 OH Tukang batu 120,000.00 130,000.00 9,000.00 9,750.00

L.03 0.008 OH Kepala Tukang 130,000.00 140,000.00 1,040.00 1,120.00


L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 14,672.00 15,840.80
5.184 Kg Portland Semen 1,125.00 1,200.00 5,832.00 6,220.80
0.026 m3 Pasir Pasang 340,000.00 370,000.00 8,840.00 9,620.00
C PERALATAN
D Jumlah A + B + C 37,712.00 41,290.80
E Overhead & Profit (contoh 10%) 10% 3,771.20 4,129.08
F Harga Satuan Pekerjaan (D+E) 41,483.20 45,419.88

20 A.4.4.2.20 1 m' Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm 71,590.75 77,825.00

A Tenaga 60,100.00 65,340.00

L.01 0.080 OH Pekerja 80,000.00 90,000.00 6,400.00 7,200.00

L.02 0.40 OH Tukang batu 120,000.00 130,000.00 48,000.00 52,000.00

L.03 0.040 OH Kepala Tukang 130,000.00 140,000.00 5,200.00 5,600.00

L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/84 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 4,982.50 5,410.00
0.5 Kg Portland Semen 1,125.00 1,200.00 562.50 600.00
0.013 m3 Pasir Pasang 340,000.00 370,000.00 4,420.00 4,810.00
C PERALATAN
D Jumlah A + B + C 65,082.50 70,750.00
E Overhead & Profit (contoh 10%) 10% 6,508.25 7,075.00
F Harga Satuan Pekerjaan (D+E) 71,590.75 77,825.00

Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal 10


21 A.4.4.2.21 1 m' 104,626.50 115,032.50
mm
A Tenaga 68,865.00 76,075.00
L.01 0.450 OH Pekerja 80,000.00 90,000.00 36,000.00 40,500.00
L.02 0.225 OH Tukang batu 120,000.00 130,000.00 27,000.00 29,250.00
L.03 0.023 OH Kepala Tukang 130,000.00 140,000.00 2,990.00 3,220.00
L.04 0.023 OH Mandor 125,000.00 135,000.00 2,875.00 3,105.00
B Bahan 26,250.00 28,500.00
10 Kg Portland Semen 1,125.00 1,200.00 11,250.00 12,000.00
15 Kg Batu Granit 1,000.00 1,100.00 15,000.00 16,500.00
C PERALATAN
D Jumlah A + B + C 95,115.00 104,575.00
E Overhead & Profit (contoh 10%) 10% 9,511.50 10,457.50
F Harga Satuan Pekerjaan (D+E) 104,626.50 115,032.50

22 A.4.4.2.22 1 m' Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10 mm 104,626.50 115,032.50

A Tenaga 68,865.00 76,075.00


L.01 0.450 OH Pekerja 80,000.00 90,000.00 36,000.00 40,500.00
L.02 0.225 OH Tukang batu 120,000.00 130,000.00 27,000.00 29,250.00
L.03 0.023 OH Kepala Tukang 130,000.00 140,000.00 2,990.00 3,220.00
L.04 0.023 OH Mandor 125,000.00 135,000.00 2,875.00 3,105.00
B Bahan 26,250.00 28,500.00
10 Kg Portland Semen 1,125.00 1,200.00 11,250.00 12,000.00
15 m3 Batu Traso 1,000.00 1,100.00 15,000.00 16,500.00
C PERALATAN
D Jumlah A + B + C 95,115.00 104,575.00
E Overhead & Profit (contoh 10%) 10% 9,511.50 10,457.50
F Harga Satuan Pekerjaan (D+E) 104,626.50 115,032.50

23 A.4.4.2.23 1 m2 Pemasangan Plesteran Ciprat 1Pc : 2 Pp 50,682.50 55,911.90


Tenaga 39,175.00 43,425.00

L.01 0.30 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00

L.02 0.1 OH Tukang batu 120,000.00 130,000.00 12,000.00 13,000.00

L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00

L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00


Bahan 6,900.00 7,404.00
4.32 Kg Portland Semen 1,125.00 1,200.00 4,860.00 5,184.00
0.006 m3 Pasir Pasang 340,000.00 370,000.00 2,040.00 2,220.00
C PERALATAN
D Jumlah A + B + C 46,075.00 50,829.00
E Overhead & Profit (contoh 10%) 10% 4,607.50 5,082.90
F Harga Satuan Pekerjaan (D+E) 50,682.50 55,911.90

Pemasangan Finishing Siar Pasangan Dinding Bata


24 A.4.4.2.24 1 m2 29,190.15 32,097.56
Merah
A Tenaga 23,040.00 25,450.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00

L.02 0.075 OH Tukang batu 120,000.00 130,000.00 9,000.00 9,750.00

L.03 0.008 OH Kepala Tukang 130,000.00 140,000.00 1,040.00 1,120.00


L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 3,496.50 3,729.60
3.108 Kg Portland Semen 1,125.00 1,200.00 3,496.50 3,729.60
C PERALATAN
D Jumlah A + B + C 26,536.50 29,179.60
E Overhead & Profit (contoh 10%) 10% 2,653.65 2,917.96
F Harga Satuan Pekerjaan (D+E) 29,190.15 32,097.56

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/85 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Finishing Siar Pasangan Dinding Conblock
25 A.4.4.2.25 1 m2 13,882.00 15,257.00
ekspose
A Tenaga 10,820.00 11,950.00
L.01 0.070 OH Pekerja 80,000.00 90,000.00 5,600.00 6,300.00

L.02 0.035 OH Tukang batu 120,000.00 130,000.00 4,200.00 4,550.00

L.03 0.004 OH Kepala Tukang 130,000.00 140,000.00 520.00 560.00

L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00


B Bahan 1,800.00 1,920.00
1.600 Kg Portland Semen 1,125.00 1,200.00 1,800.00 1,920.00
C PERALATAN
D Jumlah A + B + C 12,620.00 13,870.00
E Overhead & Profit (contoh 10%) 10% 1,262.00 1,387.00
F Harga Satuan Pekerjaan (D+E) 13,882.00 15,257.00

Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc :


26 A.4.4.2.26 1 m2 62,741.25 68,940.30
2Pp
Tenaga 45,825.00 50,625.00

L.01 0.3 OH Pekerja 80,000.00 90,000.00 24,000.00 27,000.00

L.02 0.15 OH Tukang batu 120,000.00 130,000.00 18,000.00 19,500.00

L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00

L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00


Bahan 11,212.50 12,048.00
6.34 Kg Portland Semen 1,125.00 1,200.00 7,132.50 7,608.00
0.012 m3 Pasir Pasang 340,000.00 370,000.00 4,080.00 4,440.00
C PERALATAN
D Jumlah A + B + C 57,037.50 62,673.00
E Overhead & Profit (contoh 10%) 10% 5,703.75 6,267.30
F Harga Satuan Pekerjaan (D+E) 62,741.25 68,940.30

27 A.4.4.2.27 1 m2 Pemasangan Acian 37,626.88 41,415.00

Tenaga 30,550.00 33,750.00


L.01 0.20 OH Pekerja 80,000.00 90,000.00 16,000.00 18,000.00
L.02 0.10 OH Tukang batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.010 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.010 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
Bahan 3,656.25 3,900.00
3.25 Kg Portland Semen 1,125.00 1,200.00 3,656.25 3,900.00
C PERALATAN
D Jumlah A + B + C 34,206.25 37,650.00
E Overhead & Profit (contoh 10%) 10% 3,420.63 3,765.00
F Harga Satuan Pekerjaan (D+E) 37,626.88 41,415.00

28 A.4.4.2.28 1 m2 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) 46,158.20 50,026.90

Tenaga 30,550.00 33,750.00


L.01 0.20 OH Pekerja 80,000.00 90,000.00 16,000.00 18,000.00
L.02 0.10 OH Tukang batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.010 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.010 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
Bahan 11,412.00 11,729.00
6.34 Kg Portland Semen 1,800.00 1,850.00 11,412.00 11,729.00
C PERALATAN
D Jumlah A + B + C 41,962.00 45,479.00
E Overhead & Profit (contoh 10%) 10% 4,196.20 4,547.90
F Harga Satuan Pekerjaan (D+E) 46,158.20 50,026.90

29 A.4.4.2.29 1 m2 Pemasangan Acian dg Mortar Siap Pakai (MSP) 40,040.00 43,738.75


Tenaga 30,550.00 33,750.00
L.01 0.20 OH Pekerja 80,000.00 90,000.00 16,000.00 18,000.00
L.02 0.10 OH Tukang batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.010 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.010 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
Bahan 5,850.00 6,012.50
3.25 Kg Mortar Siap Pakai 1,800.00 1,850.00 5,850.00 6,012.50
C PERALATAN
D Jumlah A + B + C 36,400.00 39,762.50
E Overhead & Profit (contoh 10%) 10% 3,640.00 3,976.25
F Harga Satuan Pekerjaan (D+E) 40,040.00 43,738.75

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/86 7-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN PENUTUP LANTAI


VIII A.4.4.3
dan DINDING

1 A.4.4.3.2 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm 112,896.50 123,178.50


A Tenaga 38,315.00 42,325.00
L.01 0.25 OH Pekerja 80,000.00 90,000.00 20,000.00 22,500.00
L.02 0.125 OH Tukang Batu 120,000.00 130,000.00 15,000.00 16,250.00
L.03 0.013 OH Kepala Tukang 130,000.00 140,000.00 1,690.00 1,820.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00
B Bahan 64,318.18 69,655.45
11.87 Buah Ubin Abu-abu 30x30 cm 11.1111 3,181.82 3,454.55 37,768.18 41,005.45
10.0 Kg Portland Semen 0.3 1,125.00 1,200.00 11,250.00 12,000.00
0.0450 m3 Pasir Pasang 0.09 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN

D Jumlah A + B + C 102,633.18 111,980.45


E Overhead & Profit (contoh 10%) 10% 10,263.32 11,198.05
F Harga Satuan Pekerjaan (D+E) 112,896.50 123,178.50

2 A.4.4.3.3 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm 114,851.00 125,455.00


A Tenaga 41,370.00 45,700.00
L.01 0.27 OH Pekerja 80,000.00 90,000.00 21,600.00 24,300.00
L.02 0.135 OH Tukang Batu 120,000.00 130,000.00 16,200.00 17,550.00
L.03 0.014 OH Kepala Tukang 130,000.00 140,000.00 1,820.00 1,960.00
L.04 0.014 OH Mandor 125,000.00 135,000.00 1,750.00 1,890.00
B Bahan 63,040.00 68,350.00
26.5 Buah Ubin Abu-abu 20x20 cm 1,360.00 1,480.00 36,040.00 39,220.00
10.4 Kg Portland Semen 1,125.00 1,200.00 11,700.00 12,480.00
0.0450 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 104,410.00 114,050.00
E Overhead & Profit (contoh 10%) 10% 10,441.00 11,405.00
F Harga Satuan Pekerjaan (D+E) 114,851.00 125,455.00

3 A.4.4.3.5 1 m2 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm 138,521.50 161,503.50


A Tenaga 39,715.00 43,875.00
L.01 0.26 OH Pekerja 80,000.00 90,000.00 20,800.00 23,400.00
L.02 0.130 OH Tukang Batu 120,000.00 130,000.00 15,600.00 16,900.00
L.03 0.013 OH Kepala Tukang 130,000.00 140,000.00 1,690.00 1,820.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00
B Bahan 86,213.64 102,946.36
11.87 Buah Ubin Warna 30x30 cm 3,636.36 4,363.64 43,163.64 51,796.36
10.0 Kg Portland Semen 1,125.00 1,200.00 11,250.00 12,000.00
1.50 Kg Semen warna 11,000.00 15,000.00 16,500.00 22,500.00
0.0450 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 125,928.64 146,821.36
E Overhead & Profit (contoh 10%) 10% 12,592.86 14,682.14
F Harga Satuan Pekerjaan (D+E) 138,521.50 161,503.50

4 A.4.4.3.6 1 m2 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm 140,866.00 161,513.00


A Tenaga 41,370.00 45,700.00
L.01 0.27 OH Pekerja 80,000.00 90,000.00 21,600.00 24,300.00
L.02 0.135 OH Tukang Batu 120,000.00 130,000.00 16,200.00 17,550.00
L.03 0.014 OH Kepala Tukang 130,000.00 140,000.00 1,820.00 1,960.00
L.04 0.014 OH Mandor 125,000.00 135,000.00 1,750.00 1,890.00
B Bahan 86,690.00 101,130.00
26.5 Buah Ubin Warna 20x20 cm 1,580.00 1,800.00 41,870.00 47,700.00
10.4 Kg Portland Semen 1,125.00 1,200.00 11,700.00 12,480.00
1.62 Kg Semen warna 11,000.00 15,000.00 17,820.00 24,300.00
0.0450 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 128,060.00 146,830.00
E Overhead & Profit (contoh 10%) 10% 12,806.00 14,683.00
F Harga Satuan Pekerjaan (D+E) 140,866.00 161,513.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.4.3.9 1 m2 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm 354,244.00 403,133.50
A Tenaga 38,315.00 42,325.00
L.01 0.250 OH Pekerja 80,000.00 90,000.00 20,000.00 22,500.00
L.02 0.125 OH Tukang Batu 120,000.00 130,000.00 15,000.00 16,250.00
L.03 0.013 OH Kepala Tukang 130,000.00 140,000.00 1,690.00 1,820.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00
B Bahan 283,725.00 324,160.00
6.63 Buah Ubin Granito 40x40 cm 0.4 36,666.67 41,666.67 243,100.00 276,250.00

9.8 Kg Portland Semen 0.16 1,125.00 1,200.00 11,025.00 11,760.00


1.300 Kg Semen warna 6.25 11,000.00 15,000.00 14,300.00 19,500.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 322,040.00 366,485.00
E Overhead & Profit (contoh 10%) 10% 32,204.00 36,648.50
F Harga Satuan Pekerjaan (D+E) 354,244.00 403,133.50

6 A.4.4.3.16 1 m' Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm 69,872.00 78,840.30

A Tenaga 19,795.00 21,735.00


L.01 0.090 OH Pekerja 80,000.00 90,000.00 7,200.00 8,100.00
L.02 0.090 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 43,725.00 49,938.00
5.30 Buah Ubin Plin Pc Abu-abu 15x20 cm 5,100.00 6,000.00 27,030.00 31,800.00
1.2 Kg Portland Semen 1,125.00 1,200.00 1,395.00 1,488.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 63,520.00 71,673.00
E Overhead & Profit (contoh 10%) 10% 6,352.00 7,167.30
F Harga Satuan Pekerjaan (D+E) 69,872.00 78,840.30

7 A.4.4.3.19 1 m' Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm 40,675.25 44,316.80


A Tenaga 19,795.00 21,735.00
L.01 0.090 OH Pekerja 80,000.00 90,000.00 7,200.00 8,100.00
L.02 0.090 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 17,182.50 18,553.00
2.65 Buah Ubin Plin Pc SWarna 15x20 cm 5,200.00 5,500.00 13,780.00 14,575.00
1.14 Kg Portland Semen 1,125.00 1,200.00 1,282.50 1,368.00
0.100 Kg Semen Warna 11,000.00 15,000.00 1,100.00 1,500.00
0.003 m3 Pasir Pasang 340,000.00 370,000.00 1,020.00 1,110.00
C PERALATAN
D Jumlah A + B + C 36,977.50 40,288.00
E Overhead & Profit (contoh 10%) 10% 3,697.75 4,028.80
F Harga Satuan Pekerjaan (D+E) 40,675.25 44,316.80

8 A.4.4.3.32 1 m2 Pemasangan Lantai Keramik 10x 20 cm 236,157.63 288,390.30


A Tenaga 106,925.00 118,125.00
L.01 0.70 OH Pekerja 80,000.00 90,000.00 56,000.00 63,000.00
L.02 0.350 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 107,763.75 144,048.00
53.00 Buah Keramik 10 x 20 cm 1,000.00 1,440.00 53,000.00 76,320.00

8.19 Kg Portland Semen 1,125.00 1,200.00 9,213.75 9,828.00


2.75 Kg Semen Warna 11,000.00 15,000.00 30,250.00 41,250.00
0.0450 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 214,688.75 262,173.00
E Overhead & Profit (contoh 10%) 10% 21,468.88 26,217.30
F Harga Satuan Pekerjaan (D+E) 236,157.63 288,390.30
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

9 A.4.4.3.33 1 m2 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm 241,602.63 295,815.30

A Tenaga 106,925.00 118,125.00


L.01 0.70 OH Pekerja 80,000.00 90,000.00 56,000.00 63,000.00
L.02 0.350 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 112,713.75 150,798.00
106.00 Buah Keramik 10 x 10 cm / 5 x 20 cm 500.00 720.00 53,000.00 76,320.00
8.19 Kg Portland Semen 1,125.00 1,200.00 9,213.75 9,828.00
3.20 Kg Semen Warna 11,000.00 15,000.00 35,200.00 48,000.00
0.0450 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 219,638.75 268,923.00
E Overhead & Profit (contoh 10%) 10% 21,963.88 26,892.30

F Harga Satuan Pekerjaan (D+E) 241,602.63 295,815.30

10 A.4.4.3.34 1 m2 Pemasangan Lantai Keramik 33 x 33 cm 237,517.96 281,126.63


A Tenaga 106,925.00 118,125.00
L.01 0.70 OH Pekerja 80,000.00 90,000.00 56,000.00 63,000.00
L.02 0.35 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 109,000.42 137,444.67

10 Buah Ubin Keramik 33 x 33 cm 6,666.67 8,666.67 66,666.67 86,666.67


8.19 Kg Portland Semen 1,125.00 1,200.00 9,213.75 9,828.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
1.62 Kg Semen Warna 11,000.00 15,000.00 17,820.00 24,300.00
C PERALATAN
D Jumlah A + B + C 215,925.42 255,569.67
E Overhead & Profit (contoh 10%) 10% 21,592.54 25,556.97
F Harga Satuan Pekerjaan (D+E) 237,517.96 281,126.63

11 A.4.4.3.35 1 m2 Pemasangan Lantai Keramik 30 x 30 cm 236,192.50 278,788.50


A Tenaga 106,925.00 118,125.00
L.01 0.70 OH Pekerja 80,000.00 90,000.00 56,000.00 63,000.00
L.02 0.35 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 107,795.45 135,319.09
11.87 Buah Ubin Keramik 30 x 30 cm 5,454.55 7,090.91 64,745.45 84,169.09
10.00 Kg Portland Semen 1,125.00 1,200.00 11,250.00 12,000.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
1.50 Kg Semen Warna 11,000.00 15,000.00 16,500.00 22,500.00
C PERALATAN
D Jumlah A + B + C 214,720.45 253,444.09
E Overhead & Profit (contoh 10%) 10% 21,472.05 25,344.41
F Harga Satuan Pekerjaan (D+E) 236,192.50 278,788.50

12 A.4.4.3.36 1 m2 Pemasangan Lantai Keramik 20 x 20 cm 236,879.50 277,326.50


A Tenaga 106,925.00 118,125.00
L.01 0.70 OH Pekerja 80,000.00 90,000.00 56,000.00 63,000.00
L.02 0.35 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 108,420.00 133,990.00
26.5 Buah Ubin Keramik 20 x 20 cm 2,400.00 3,040.00 63,600.00 80,560.00
10.40 Kg Portland Semen 1,125.00 1,200.00 11,700.00 12,480.00
1.62 Kg Semen Warna 11,000.00 15,000.00 17,820.00 24,300.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 215,345.00 252,115.00
E Overhead & Profit (contoh 10%) 10% 21,534.50 25,211.50
F Harga Satuan Pekerjaan (D+E) 236,879.50 277,326.50
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Lantai Keramik uk.10 x 33 cm, untuk
13 A.4.4.3.37 1 m2 437,426.00 484,500.50
variasi / border
A Tenaga 158,265.00 174,895.00
L.01 1.05 OH Pekerja 80,000.00 90,000.00 84,000.00 94,500.00
L.02 0.525 OH Tukang Batu 120,000.00 130,000.00 63,000.00 68,250.00
L.03 0.053 OH Kepala Tukang 130,000.00 140,000.00 6,890.00 7,420.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 239,395.00 265,560.00
33.0 Buah Ubin Keramik 5,000.00 5,200.00 165,000.00 171,600.00
9.80 Kg Portland Semen 1,125.00 1,200.00 11,025.00 11,760.00
4.37 Kg Semen Warna 11,000.00 15,000.00 48,070.00 65,550.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
C PERALATAN
D Jumlah A + B + C 397,660.00 440,455.00
E Overhead & Profit (contoh 10%) 10% 39,766.00 44,045.50
F Harga Satuan Pekerjaan (D+E) 437,426.00 484,500.50

14 A.4.4.3.39 1 m' Pemasangan Plint Keramik Ukuran 10x20 cm 39,184.75 44,536.80


A Tenaga 19,795.00 21,735.00
L.01 0.09 OH Pekerja 80,000.00 90,000.00 7,200.00 8,100.00
L.02 0.09 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 15,827.50 18,753.00
5.3 Buah Ubin Keramik 2,500.00 3,000.00 13,250.00 15,900.00
1.14 Kg Portland Semen 1,125.00 1,200.00 1,282.50 1,368.00
0.003 m3 Pasir Pasang 340,000.00 370,000.00 1,020.00 1,110.00
0.025 Kg Semen Warna 11,000.00 15,000.00 275.00 375.00
C PERALATAN
D Jumlah A + B + C 35,622.50 40,488.00
E Overhead & Profit (contoh 10%) 10% 3,562.25 4,048.80
F Harga Satuan Pekerjaan (D+E) 39,184.75 44,536.80

15 A.4.4.3.40 1 m' Pemasangan Plint Keramik Ukuran 10x10 cm 85,544.25 91,589.30


A Tenaga 19,795.00 21,735.00
L.01 0.09 OH Pekerja 80,000.00 90,000.00 7,200.00 8,100.00
L.02 0.09 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 57,972.50 61,528.00
10.6 Buah Ubin Keramik 5,200.00 5,500.00 55,120.00 58,300.00
1.14 Kg Portland Semen 1,125.00 1,200.00 1,282.50 1,368.00
0.003 m3 Pasir Pasang 340,000.00 370,000.00 1,020.00 1,110.00
0.05 Kg Semen Warna 11,000.00 15,000.00 550.00 750.00
C PERALATAN
D Jumlah A + B + C 77,767.50 83,263.00
E Overhead & Profit (contoh 10%) 10% 7,776.75 8,326.30
F Harga Satuan Pekerjaan (D+E) 85,544.25 91,589.30

16 A.4.4.3.41 1 m' Pemasangan Plint Keramik Ukuran 5x20 cm 83,212.25 90,423.30


A Tenaga 19,795.00 21,735.00
L.01 0.09 OH Pekerja 80,000.00 90,000.00 7,200.00 8,100.00
L.02 0.09 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 55,852.50 60,468.00
10.6 Buah Ubin Keramik 5,000.00 5,400.00 53,000.00 57,240.00
1.14 Kg Portland Semen 1,125.00 1,200.00 1,282.50 1,368.00
0.003 m3 Pasir Pasang 340,000.00 370,000.00 1,020.00 1,110.00
0.05 Kg Semen Warna 11,000.00 15,000.00 550.00 750.00
C PERALATAN
D Jumlah A + B + C 75,647.50 82,203.00
E Overhead & Profit (contoh 10%) 10% 7,564.75 8,220.30
F Harga Satuan Pekerjaan (D+E) 83,212.25 90,423.30
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
17 A.4.4.3.43 1 m2 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm 706,297.63 729,468.30
A Tenaga 106,925.00 118,125.00
L.01 0.7 OH Pekerja 80,000.00 90,000.00 56,000.00 63,000.00
L.02 0.35 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 535,163.75 545,028.00
1.06 buah Marmer 475,000.00 480,000.00 503,500.00 508,800.00
8.19 kg Portland Semen 1,125.00 1,200.00 9,213.75 9,828.00
0.045 m3 Pasir Pasang 340,000.00 370,000.00 15,300.00 16,650.00
0.65 kg Semen Warna 11,000.00 15,000.00 7,150.00 9,750.00
C PERALATAN
D Jumlah A + B + C 642,088.75 663,153.00
E Overhead & Profit (contoh 10%) 10% 64,208.88 66,315.30
F Harga Satuan Pekerjaan (D+E) 706,297.63 729,468.30

18 A.4.4.3.44 1 m2 Pemasangan Lantai Karpet 206,618.50 220,269.50


A Tenaga 37,335.00 40,995.00
L.01 0.17 OH Pekerja 80,000.00 90,000.00 13,600.00 15,300.00
L.02 0.17 OH Tukang Batu 120,000.00 130,000.00 20,400.00 22,100.00
L.03 0.017 OH Kepala Tukang 130,000.00 140,000.00 2,210.00 2,380.00
L.04 0.009 OH Mandor 125,000.00 135,000.00 1,125.00 1,215.00
B Bahan 150,500.00 159,250.00
1.05 m2 Karpet 125,000.00 130,000.00 131,250.00 136,500.00
0.35 kg Lem 55,000.00 65,000.00 19,250.00 22,750.00
C PERALATAN
D Jumlah A + B + C 187,835.00 200,245.00
E Overhead & Profit (contoh 10%) 10% 18,783.50 20,024.50
F Harga Satuan Pekerjaan (D+E) 206,618.50 220,269.50

19 A.4.4.3.46 1 m2 Pemasangan Lantai Parquet Jati 465,767.50 530,887.50


A Tenaga 106,925.00 118,125.00
L.01 0.70 OH Pekerja 80,000.00 90,000.00 56,000.00 63,000.00
L.02 0.35 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 316,500.00 364,500.00
1.05 m2 Parquet Jati 270,000.00 310,000.00 283,500.00 325,500.00
0.6 Kg Lem Vynil 55,000.00 65,000.00 33,000.00 39,000.00
C PERALATAN
D Jumlah A + B + C 423,425.00 482,625.00
E Overhead & Profit (contoh 10%) 10% 42,342.50 48,262.50
F Harga Satuan Pekerjaan (D+E) 465,767.50 530,887.50

20 A.4.4.3.48 1 m2 Pemasangan Dinding Porselen 11 x 11 cm 267,994.41 300,209.32


A Tenaga 152,750.00 168,750.00
L.01 1.00 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00
L.02 0.50 OH Tukang Batu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.050 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.050 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 90,881.28 104,167.56
86 bh Porselen 512.20 524.39 44,048.78 45,097.56
9.30 Kg Portland Semen 82.6446 1,125.00 1,200.00 10,462.50 11,160.00

2.750 Kg Semen Warna 0.0121 11,000.00 15,000.00 30,250.00 41,250.00

0.018 m3 Pasir Pasang 0.11 340,000.00 370,000.00 6,120.00 6,660.00


C PERALATAN
D Jumlah A + B + C 243,631.28 272,917.56
E Overhead & Profit (contoh 10%) 10% 24,363.13 27,291.76
F Harga Satuan Pekerjaan (D+E) 267,994.41 300,209.32

21 A.4.4.3.49 1 m2 Pemasangan Dinding Porselen 10x20 cm 261,038.25 315,991.50


A Tenaga 137,475.00 151,875.00
L.01 0.9 OH Pekerja 80,000.00 90,000.00 72,000.00 81,000.00
L.02 0.45 OH Tukang Batu 120,000.00 130,000.00 54,000.00 58,500.00
L.03 0.045 OH Kepala Tukang 130,000.00 140,000.00 5,850.00 6,300.00
L.04 0.045 OH Mandor 125,000.00 135,000.00 5,625.00 6,075.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 99,832.50 135,390.00
53 Buah Keramik 1,000.00 1,440.00 53,000.00 76,320.00
9.3 Kg Portland Semen 1,125.00 1,200.00 10,462.50 11,160.00
0.018 m3 Pasir Pasang 340,000.00 370,000.00 6,120.00 6,660.00
2.75 Kg Semen Warna 11,000.00 15,000.00 30,250.00 41,250.00
C PERALATAN
D Jumlah A + B + C 237,307.50 287,265.00
E Overhead & Profit (contoh 10%) 10% 23,730.75 28,726.50
F Harga Satuan Pekerjaan (D+E) 261,038.25 315,991.50

22 A.4.4.3.50 1 m2 Pemasangan Dinding Porselen 20x20 cm 255,857.25 303,330.50


A Tenaga 137,475.00 151,875.00
L.01 0.9 OH Pekerja 80,000.00 90,000.00 72,000.00 81,000.00
L.02 0.45 OH Tukang Batu 120,000.00 130,000.00 54,000.00 58,500.00
L.03 0.045 OH Kepala Tukang 130,000.00 140,000.00 5,850.00 6,300.00
L.04 0.045 OH Mandor 125,000.00 135,000.00 5,625.00 6,075.00
B Bahan 95,122.50 123,880.00
26.0 Buah Keramik 2,200.00 2,960.00 57,200.00 76,960.00
9.3 Kg Portland Semen 1,125.00 1,200.00 10,462.50 11,160.00
0.018 m3 Pasir Pasang 340,000.00 370,000.00 6,120.00 6,660.00
1.94 Kg Semen Warna 11,000.00 15,000.00 21,340.00 29,100.00
C PERALATAN
D Jumlah A + B + C 232,597.50 275,755.00
E Overhead & Profit (contoh 10%) 10% 23,259.75 27,575.50
F Harga Satuan Pekerjaan (D+E) 255,857.25 303,330.50

23 A.4.4.3.53 1 m2 Pemasangan Dinding Keramik 10x20 cm 261,038.25 315,991.50


A Tenaga 137,475.00 151,875.00
L.01 0.9 OH Pekerja 80,000.00 90,000.00 72,000.00 81,000.00
L.02 0.45 OH Tukang Batu 120,000.00 130,000.00 54,000.00 58,500.00
L.03 0.045 OH Kepala Tukang 130,000.00 140,000.00 5,850.00 6,300.00
L.04 0.045 OH Mandor 125,000.00 135,000.00 5,625.00 6,075.00
B Bahan 99,832.50 135,390.00
53.0 Buah Keramik 1,000.00 1,440.00 53,000.00 76,320.00
9.3 Kg Portland Semen 1,125.00 1,200.00 10,462.50 11,160.00
0.018 m3 Pasir Pasang 340,000.00 370,000.00 6,120.00 6,660.00
2.75 Kg Semen Warna 11,000.00 15,000.00 30,250.00 41,250.00
C PERALATAN
D Jumlah A + B + C 237,307.50 287,265.00
E Overhead & Profit (contoh 10%) 10% 23,730.75 28,726.50
F Harga Satuan Pekerjaan (D+E) 261,038.25 315,991.50

24 A.4.4.3.54 1 m2 Pemasangan Dinding Keramik 20x20 cm 257,067.25 304,958.50


A Tenaga 137,475.00 151,875.00
L.01 0.9 OH Pekerja 80,000.00 90,000.00 72,000.00 81,000.00
L.02 0.45 OH Tukang Batu 120,000.00 130,000.00 54,000.00 58,500.00
L.03 0.045 OH Kepala Tukang 130,000.00 140,000.00 5,850.00 6,300.00
L.04 0.045 OH Mandor 125,000.00 135,000.00 5,625.00 6,075.00
B Bahan 96,222.50 125,360.00
26.5 Buah Keramik 2,200.00 2,960.00 58,300.00 78,440.00
9.3 Kg Portland Semen 1,125.00 1,200.00 10,462.50 11,160.00
0.018 m3 Pasir Pasang 340,000.00 370,000.00 6,120.00 6,660.00
1.94 Kg Semen Warna 11,000.00 15,000.00 21,340.00 29,100.00
C PERALATAN
D Jumlah A + B + C 233,697.50 277,235.00
E Overhead & Profit (contoh 10%) 10% 23,369.75 27,723.50
F Harga Satuan Pekerjaan (D+E) 257,067.25 304,958.50

25 A.4.4.3.55 1 m2 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm 805,007.62 838,428.92


A Tenaga 198,575.00 219,375.00
L.01 1.3 OH Pekerja 80,000.00 90,000.00 104,000.00 117,000.00
L.02 0.65 OH Tukang Batu 120,000.00 130,000.00 78,000.00 84,500.00
L.03 0.065 OH Kepala Tukang 130,000.00 140,000.00 8,450.00 9,100.00
L.04 0.065 OH Mandor 125,000.00 135,000.00 8,125.00 8,775.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 533,250.11 542,833.11
1.06 buah Marmer 475,000.00 480,000.00 503,500.00 508,800.00
3.003 buah Paku 12 cm 35.00 35.00 105.11 105.11
12.44 kg Portlan Semen 1,125.00 1,200.00 13,995.00 14,928.00
0.025 m3 Pasir Pasang 340,000.00 370,000.00 8,500.00 9,250.00
0.65 kg Semen Warna 11,000.00 15,000.00 7,150.00 9,750.00
C PERALATAN
D Jumlah A + B + C 731,825.11 762,208.11
E Overhead & Profit (contoh 10%) 10% 73,182.51 76,220.81
F Harga Satuan Pekerjaan (D+E) 805,007.62 838,428.92

26 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam 278,348.13 298,842.50

A Tenaga 106,925.00 118,125.00


L.01 0.70 OH Pekerja 80,000.00 90,000.00 56,000.00 63,000.00
L.02 0.35 OH Tukang Batu 120,000.00 130,000.00 42,000.00 45,500.00
L.03 0.035 OH Kepala Tukang 130,000.00 140,000.00 4,550.00 4,900.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 146,118.75 153,550.00
1.10 m2 Batu Paros 110,000.00 115,000.00 121,000.00 126,500.00
11.75 Kg Portland Semen 1,125.00 1,200.00 13,218.75 14,100.00
0.035 m3 Pasir Pasang 340,000.00 370,000.00 11,900.00 12,950.00
C PERALATAN
D Jumlah A + B + C 253,043.75 271,675.00
E Overhead & Profit (contoh 10%) 10% 25,304.38 27,167.50
F Harga Satuan Pekerjaan (D+E) 278,348.13 298,842.50

27 A.4.4.3.59 1 m2 Pemasangan Lantai Vynil uk.30 x 30 cm 152,684.40 165,335.50


A Tenaga 51,460.00 56,900.00
L.01 0.35 OH Pekerja 80,000.00 90,000.00 28,000.00 31,500.00
L.02 0.175 OH Tukang Batu 120,000.00 130,000.00 21,000.00 22,750.00
L.03 0.017 OH Kepala Tukang 130,000.00 140,000.00 2,210.00 2,380.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 87,344.00 93,405.00
11.87 bh Vynil 30x30cm 6,200.00 6,500.00 73,594.00 77,155.00
0.25 kg Lem 55,000.00 65,000.00 13,750.00 16,250.00

C PERALATAN
D Jumlah A + B + C 138,804.00 150,305.00
E Overhead & Profit (contoh 10%) 10% 13,880.40 15,030.50
F Harga Satuan Pekerjaan (D+E) 152,684.40 165,335.50

28 A.4.4.3.60 1 m2 Pemasangan Wallpaper Lebar 50 Cm 122,551.00 132,055.00


A Tenaga 51,460.00 56,900.00
L.01 0.35 OH Pekerja 80,000.00 90,000.00 28,000.00 31,500.00
L.02 0.175 OH Tukang Batu 120,000.00 130,000.00 21,000.00 22,750.00
L.03 0.017 OH Kepala Tukang 130,000.00 140,000.00 2,210.00 2,380.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 59,950.00 63,150.00
2.2 m' Wallpaper 26,000.00 27,000.00 57,200.00 59,400.00
0.25 kg Lem 11,000.00 15,000.00 2,750.00 3,750.00
C PERALATAN
D Jumlah A + B + C 111,410.00 120,050.00
E Overhead & Profit (contoh 10%) 10% 11,141.00 12,005.00
F Harga Satuan Pekerjaan (D+E) 122,551.00 132,055.00

29 A.4.4.3.63 1 m' Pemasangan Plint Kayu Klas II Ukuran 2x10 cm 50,391.00 61,699.00
Tenaga 26,310.00 28,890.00
L.01 0.12 OH Pekerja 80,000.00 90,000.00 9,600.00 10,800.00
L.02 0.12 OH Tukang Batu 120,000.00 130,000.00 14,400.00 15,600.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
Bahan 19,500.00 27,200.00
0.003 m3 Papan Kayu Klas II 6,250,000.00 8,800,000.00 18,750.00 26,400.00
0.05 kg Paku Sekrup 5 cm 15,000.00 16,000.00 750.00 800.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 45,810.00 56,090.00
E Overhead & Profit (contoh 10%) 10% 4,581.00 5,609.00
F Harga Satuan Pekerjaan (D+E) 50,391.00 61,699.00

30 A.4.4.3.64 1 m2 Pemasangan Paving Block Natural Tebal 6 Cm 184,324.25 200,459.05


Tenaga 86,662.50 94,675.50
L.01 0.25 OH Pekerja 80,000.00 90,000.00 20,000.00 22,500.00
L.02 0.5 OH Tukang Batu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.0013 OH Mandor 125,000.00 135,000.00 162.50 175.50
Bahan 73,550.00 79,600.00
1.01 m2 Paving Block Tebal 6 Cm 55,000.00 60,000.00 55,550.00 60,600.00
0.05 m3 Pasir Beton 360,000.00 380,000.00 18,000.00 19,000.00
C PERALATAN 7,355.00 7,960.00
10 % Peralatan 73,550.00 79,600.00 7,355.00 7,960.00
D Jumlah A + B + C 167,567.50 182,235.50
E Overhead & Profit (contoh 10%) 10% 16,756.75 18,223.55
F Harga Satuan Pekerjaan (D+E) 184,324.25 200,459.05

31 A.4.4.3.65 1 m2 Pemasangan Paving Block Natural Tebal 8 Cm 251,699.25 271,068.05


Tenaga 106,662.50 117,175.50
L.01 0.5 OH Pekerja 80,000.00 90,000.00 40,000.00 45,000.00
L.02 0.5 OH Tukang Batu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.0013 OH Mandor 125,000.00 135,000.00 162.50 175.50
Bahan 111,050.00 117,500.00
1.01 m2 Paving Block Tebal 8 Cm 85,000.00 90,000.00 85,850.00 90,900.00
0.07 m3 Pasir Beton 360,000.00 380,000.00 25,200.00 26,600.00
C PERALATAN 11,105.00 11,750.00
10 % Peralatan 111,050.00 117,500.00 11,105.00 11,750.00
D Jumlah A + B + C 228,817.50 246,425.50
E Overhead & Profit (contoh 10%) 10% 22,881.75 24,642.55
F Harga Satuan Pekerjaan (D+E) 251,699.25 271,068.05

32 A.4.4.3.66 1 m2 Pemasangan Paving Block Berwarna Tebal 6 Cm 196,545.25 212,680.05


Tenaga 86,662.50 94,675.50
L.01 0.25 OH Pekerja 80,000.00 90,000.00 20,000.00 22,500.00
L.02 0.5 OH Tukang Batu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.0013 OH Mandor 125,000.00 135,000.00 162.50 175.50
Bahan 83,650.00 89,700.00
1.01 m2 Paving Block Berwarna Tebal 6 Cm 65,000.00 70,000.00 65,650.00 70,700.00
0.05 m3 Pasir Beton 360,000.00 380,000.00 18,000.00 19,000.00
C PERALATAN 8,365.00 8,970.00
10 % Peralatan 83,650.00 89,700.00 8,365.00 8,970.00
D Jumlah A + B + C 178,677.50 193,345.50
E Overhead & Profit (contoh 10%) 10% 17,867.75 19,334.55
F Harga Satuan Pekerjaan (D+E) 196,545.25 212,680.05

33 A.4.4.3.67 1 m2 Pemasangan Paving Block Berwarna Tebal 8 Cm 257,809.75 277,178.55


Tenaga 106,662.50 117,175.50
L.01 0.5 OH Pekerja 80,000.00 90,000.00 40,000.00 45,000.00
L.02 0.5 OH Tukang Batu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.0013 OH Mandor 125,000.00 135,000.00 162.50 175.50
Bahan 116,100.00 122,550.00
1.01 m2 Paving Block Tebal Berwarna 8 Cm 90,000.00 95,000.00 90,900.00 95,950.00
0.07 m3 Pasir Beton 360,000.00 380,000.00 25,200.00 26,600.00
C PERALATAN 11,610.00 12,255.00
10 % Peralatan 116,100.00 122,550.00 11,610.00 12,255.00
D Jumlah A + B + C 234,372.50 251,980.50
E Overhead & Profit (contoh 10%) 10% 23,437.25 25,198.05
F Harga Satuan Pekerjaan (D+E) 257,809.75 277,178.55
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT

Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4


1 A.4.5.1.1 1 m2 32,351.00 35,414.50
mm, 5 mm & 6 mm

A Tenaga 12,210.00 13,320.00


L.01 0.03 OH Pekerja 80,000.00 90,000.00 2,400.00 2,700.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00
B Bahan 17,200.00 18,875.00
1.1 Lbr Plat Asbes 15,500.00 17,000.00 17,050.00 18,700.00
0.01 Kg Paku 15,000.00 17,500.00 150.00 175.00
C PERALATAN
D Jumlah A + B + C 29,410.00 32,195.00
E Overhead & Profit (contoh 10%) 10% 2,941.00 3,219.50
F Harga Satuan Pekerjaan (D+E) 32,351.00 35,414.50
Overhead & Profit (contoh 10%)
2 A.4.5.1.2 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x30) cm 106,326.00 118,541.50
A Tenaga 26,310.00 28,890.00
L.01 0.12 OH Pekerja 80,000.00 90,000.00 9,600.00 10,800.00
L.02 0.12 OH Tukang Kayu 120,000.00 130,000.00 14,400.00 15,600.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 70,350.00 78,875.00
12.0 Lbr Akustik Uk.30 x 30 cm 5,800.00 6,500.00 69,600.00 78,000.00
0.05 Kg Paku 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 96,660.00 107,765.00
E Overhead & Profit (contoh 10%) 10% 9,666.00 10,776.50
F Harga Satuan Pekerjaan (D+E) 106,326.00 118,541.50

3 A.4.5.1.3 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x60) cm 109,158.50 119,955.00


A Tenaga 21,925.00 24,075.00
L.01 0.10 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.02 0.10 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 77,310.00 84,975.00
5.80 Lbr Akustik 13,200.00 14,500.00 76,560.00 84,100.00
0.05 Kg Paku 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 99,235.00 109,050.00
E Overhead & Profit (contoh 10%) 10% 9,923.50 10,905.00
F Harga Satuan Pekerjaan (D+E) 109,158.50 119,955.00

4 A.4.5.1.4 1 m2 Pemasangan Langit-langit Akustik Ukuran (60x120) cm 94,242.50 103,345.00


A Tenaga 21,925.00 24,075.00
L.01 0.10 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.02 0.10 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 63,750.00 69,875.00
1.50 Lbr Akustik 42,000.00 46,000.00 63,000.00 69,000.00
0.05 Kg Paku 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 85,675.00 93,950.00
E Overhead & Profit (contoh 10%) 10% 8,567.50 9,395.00
F Harga Satuan Pekerjaan (D+E) 94,242.50 103,345.00

Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3


5 A.4.5.1.5 1 m2 51,425.00 57,997.50
mm, 4 mm & 6 mm

A Tenaga 21,925.00 24,075.00


L.01 0.10 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.02 0.10 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/95 9-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 24,825.00 28,650.00
0.375 Lbr Tripleks (4 mm) 65,000.00 75,000.00 24,375.00 28,125.00
0.03 Kg Paku Tripleks 15,000.00 17,500.00 450.00 525.00
C PERALATAN
D Jumlah A + B + C 46,750.00 52,725.00
E Overhead & Profit (contoh 10%) 10% 4,675.00 5,272.50
F Harga Satuan Pekerjaan (D+E) 51,425.00 57,997.50

6 A.4.5.1.6 1 m2 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm 556,105.00 591,552.50


A Tenaga 175,400.00 192,600.00
L.01 0.8 OH Pekerja 80,000.00 90,000.00 64,000.00 72,000.00
L.02 0.8 OH Tukang Kayu 120,000.00 130,000.00 96,000.00 104,000.00
L.03 0.08 OH Kepala Tukang 130,000.00 140,000.00 10,400.00 11,200.00
L.04 0.04 OH Mandor 125,000.00 135,000.00 5,000.00 5,400.00
B Bahan 330,150.00 345,175.00
0.015 m3 Kayu Jati,Papan 22,000,000.00 23,000,000.00 330,000.00 345,000.00
0.01 Kg Paku 15,000.00 17,500.00 150.00 175.00
C PERALATAN
D Jumlah A + B + C 505,550.00 537,775.00
E Overhead & Profit (contoh 10%) 10% 50,555.00 53,777.50
F Harga Satuan Pekerjaan (D+E) 556,105.00 591,552.50

Memasang Langit-langit Gypsu Board, Ukuran (120x240)


7 A.4.5.1.7 1 m2 42,641.50 47,665.20
tebal 9 mm

A Tenaga 15,275.00 16,875.00


L.01 0.1 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.02 0.05 OH Tukang Kayu 120,000.00 130,000.00 6,000.00 6,500.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 23,490.00 26,457.00
0.364 Lbr Gypsum Board 60,000.00 68,000.00 21,840.00 24,752.00
0.11 Kg Paku Sekrup 15,000.00 15,500.00 1,650.00 1,705.00
C PERALATAN
D Jumlah A + B + C 38,765.00 43,332.00
E Overhead & Profit (contoh 10%) 10% 3,876.50 4,333.20
F Harga Satuan Pekerjaan (D+E) 42,641.50 47,665.20

Memasang Langit-langit Akustik Uk (60x120) cm & Berikut


8 A.4.5.1.8 1 m2 229,652.50 250,717.50
Rangka Allumunium

A Tenaga 109,625.00 120,375.00


L.01 0.5 OH Pekerja 80,000.00 90,000.00 40,000.00 45,000.00
L.02 0.5 OH Tukang Kayu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.025 OH Mandor 125,000.00 135,000.00 3,125.00 3,375.00
B Bahan 99,150.00 107,550.00
3.6 m' Profil Allumunium "T" 3,500.00 4,000.00 12,600.00 14,400.00
0.15 kg Kawat Ø 4 mm 6,500.00 7,000.00 975.00 1,050.00
1.05 bh Ramset 21,500.00 22,000.00 22,575.00 23,100.00
1.5 lmb Akustik 60 x 120 cm 42,000.00 46,000.00 63,000.00 69,000.00
C PERALATAN
D Jumlah A + B + C 208,775.00 227,925.00
E Overhead & Profit (contoh 10%) 10% 20,877.50 22,792.50
F Harga Satuan Pekerjaan (D+E) 229,652.50 250,717.50

9 A.4.5.1.9 1 m1 List Langit-Langit Kayu Profil 17,836.50 19,283.00


A Tenaga 11,025.00 12,105.00
L.01 0.05 OH Pekerja 80,000.00 90,000.00 4,000.00 4,500.00
L.02 0.05 OH Tukang Kayu 120,000.00 130,000.00 6,000.00 6,500.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 5,190.00 5,425.00
1.05 m1 List Kayu Profil 4,800.00 5,000.00 5,040.00 5,250.00
0.01 Kg Paku 15,000.00 17,500.00 150.00 175.00
C PERALATAN
D Jumlah A + B + C 16,215.00 17,530.00
E Overhead & Profit (contoh 10%) 10% 1,621.50 1,753.00
F Harga Satuan Pekerjaan (D+E) 17,836.50 19,283.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/96 9-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
X A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP
1 A.4.5.2.1 1 m2 Pemasangan Atap Genteng Plentong Kecil 88,522.50 99,418.00
A Tenaga 22,975.00 25,380.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.02 0.075 OH Tukang Kayu 120,000.00 130,000.00 9,000.00 9,750.00
L.03 0.0075 OH Kepala Tukang 130,000.00 140,000.00 975.00 1,050.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 57,500.00 65,000.00
25 Buah Genteng Plentong 2,300.00 2,600.00 57,500.00 65,000.00
C PERALATAN
D Jumlah A + B + C 80,475.00 90,380.00
E Overhead & Profit (contoh 10%) 10% 8,047.50 9,038.00
F Harga Satuan Pekerjaan (D+E) 88,522.50 99,418.00
Overhead & Profit (contoh 10%)
2 A.4.5.2.2 1 m2 Pemasangan Atap Genteng Kodok / Glasur 142,219.00 147,620.00
A Tenaga 23,040.00 25,450.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.02 0.075 OH Tukang Kayu 120,000.00 130,000.00 9,000.00 9,750.00
L.03 0.008 OH Kepala Tukang 130,000.00 140,000.00 1,040.00 1,120.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 106,250.00 108,750.00
25 Buah Genteng Kodok / Glasur 4,250.00 4,350.00 106,250.00 108,750.00
C PERALATAN
D Jumlah A + B + C 129,290.00 134,200.00
E Overhead & Profit (contoh 10%) 10% 12,929.00 13,420.00
F Harga Satuan Pekerjaan (D+E) 142,219.00 147,620.00

3 A.4.5.2.3 1 m2 Pemasangan Atap Genteng Plentong Super / Besar 126,324.00 133,925.00


A Tenaga 23,040.00 25,450.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.02 0.075 OH Tukang Kayu 120,000.00 130,000.00 9,000.00 9,750.00
L.03 0.008 OH Kepala Tukang 130,000.00 140,000.00 1,040.00 1,120.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 91,800.00 96,300.00
12 Buah Genteng Plentong Super / Besar 7,650.00 8,025.00 91,800.00 96,300.00
C PERALATAN
D Jumlah A + B + C 114,840.00 121,750.00
E Overhead & Profit (contoh 10%) 10% 11,484.00 12,175.00
F Harga Satuan Pekerjaan (D+E) 126,324.00 133,925.00

4 A.4.5.2.4 1 m' Pemasangan Genteng Bubung Plentong 109,978.00 119,086.00


A Tenaga 58,850.00 65,070.00
L.01 0.4 OH Pekerja 80,000.00 90,000.00 32,000.00 36,000.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 41,130.00 43,190.00
5 Buah Genteng Bubung Plentong 4,250.00 4,350.00 21,250.00 21,750.00
8 Kg Portland Semen 1,125.00 1,200.00 9,000.00 9,600.00
0.032 m3 Pasir Pasang 340,000.00 370,000.00 10,880.00 11,840.00
C PERALATAN
D Jumlah A + B + C 99,980.00 108,260.00
E Overhead & Profit (contoh 10%) 10% 9,998.00 10,826.00
F Harga Satuan Pekerjaan (D+E) 109,978.00 119,086.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/97 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.5.2.5 1 m' Pemasangan Genteng Bubung Kodok / Glasur 122,353.00 132,561.00
A Tenaga 58,850.00 65,070.00
L.01 0.4 OH Pekerja 80,000.00 90,000.00 32,000.00 36,000.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 52,380.00 55,440.00
5 Buah Genteng Bubung Kodok / Glasur 6,500.00 6,800.00 32,500.00 34,000.00
8 Kg Portland Semen 1,125.00 1,200.00 9,000.00 9,600.00
0.032 m3 Pasir Pasang 340,000.00 370,000.00 10,880.00 11,840.00
C PERALATAN
D Jumlah A + B + C 111,230.00 120,510.00
E Overhead & Profit (contoh 10%) 10% 11,123.00 12,051.00
F Harga Satuan Pekerjaan (D+E) 122,353.00 132,561.00

6 A.4.5.2.6 1 m' Pemasangan Genteng Bubung Plentong Besar 126,203.00 135,641.00


A Tenaga 58,850.00 65,070.00
L.01 0.4 OH Pekerja 80,000.00 90,000.00 32,000.00 36,000.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 55,880.00 58,240.00
4 Buah Genteng Bubung Plentong Besar 9,000.00 9,200.00 36,000.00 36,800.00
8 Kg Portland Semen 1,125.00 1,200.00 9,000.00 9,600.00
0.032 m3 Pasir Pasang 340,000.00 370,000.00 10,880.00 11,840.00
C PERALATAN
D Jumlah A + B + C 114,730.00 123,310.00
E Overhead & Profit (contoh 10%) 10% 11,473.00 12,331.00
F Harga Satuan Pekerjaan (D+E) 126,203.00 135,641.00

7 A.4.5.2.7 1 m2 Pemasangan Roof Light Fibreglass 90 x 180 106,452.50 118,921.00


A Tenaga 21,025.00 23,235.00
L.01 0.14 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.067 OH Tukang Kayu 120,000.00 130,000.00 8,040.00 8,710.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 75,750.00 84,875.00
0.6 Lbr Rooflight 90 x 180 125,000.00 140,000.00 75,000.00 84,000.00
0.05 Kg Paku Biasa 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 96,775.00 108,110.00
E Overhead & Profit (contoh 10%) 10% 9,677.50 10,811.00
F Harga Satuan Pekerjaan (D+E) 106,452.50 118,921.00

Pemasangan Atap Asbes Gelombang (2,50x0,92 m) x 5


8 A.4.5.2.8 1 m2 65,835.00 73,843.00
mm

A Tenaga 22,240.00 24,550.00


L.01 0.14 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.075 OH Tukang Kayu 120,000.00 130,000.00 9,000.00 9,750.00
L.03 0.008 OH Kepala Tukang 130,000.00 140,000.00 1,040.00 1,120.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 37,610.00 42,580.00
0.5 Lbr Asbes Gelombang 71,500.00 81,200.00 35,750.00 40,600.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 59,850.00 67,130.00
E Overhead & Profit (contoh 10%) 10% 5,985.00 6,713.00
F Harga Satuan Pekerjaan (D+E) 65,835.00 73,843.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/98 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Atap Asbes Gelombang (2,25x0,92 m) x 5
9 A.4.5.2.9 1 m2 67,479.50 75,817.50
mm

A Tenaga 21,385.00 23,625.00


L.01 0.14 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 39,960.00 45,300.00
0.6 Lbr Asbes Gelombang 63,500.00 72,200.00 38,100.00 43,320.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 61,345.00 68,925.00
E Overhead & Profit (contoh 10%) 10% 6,134.50 6,892.50
F Harga Satuan Pekerjaan (D+E) 67,479.50 75,817.50

Pemasangan Atap Asbes Gelombang (2,00x0,92 m) x 5


10 A.4.5.2.10 1 m2 67,809.50 76,477.50
mm

A Tenaga 21,385.00 23,625.00


L.01 0.14 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 40,260.00 45,900.00
0.6 Lbr Asbes Gelombang 64,000.00 73,200.00 38,400.00 43,920.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 61,645.00 69,525.00
E Overhead & Profit (contoh 10%) 10% 6,164.50 6,952.50
F Harga Satuan Pekerjaan (D+E) 67,809.50 76,477.50

Pemasangan Atap Asbes Gelombang (1,80x0,92 m) x 5


11 A.4.5.2.11 1 m2 75,069.50 79,315.50
mm

A Tenaga 21,385.00 23,625.00


L.01 0.14 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 46,860.00 48,480.00
0.75 Lbr Asbes Gelombang 60,000.00 62,000.00 45,000.00 46,500.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 68,245.00 72,105.00
E Overhead & Profit (contoh 10%) 10% 6,824.50 7,210.50
F Harga Satuan Pekerjaan (D+E) 75,069.50 79,315.50

Pemasangan Atap Asbes Gelombang (3,00x1,05 m) x 4


12 A.4.5.2.12 1 m2 58,102.00 73,980.50
mm
A Tenaga 21,385.00 23,625.00
L.01 0.14 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 31,435.00 43,630.00
0.35 Lbr Asbes Gelombang 84,500.00 119,000.00 29,575.00 41,650.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 52,820.00 67,255.00
E Overhead & Profit (contoh 10%) 10% 5,282.00 6,725.50
F Harga Satuan Pekerjaan (D+E) 58,102.00 73,980.50

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/99 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Atap Asbes Gelombang (2,70x1,05 m) x 4
13 A.4.5.2.13 1 m2 60,219.50 76,213.50
mm
A Tenaga 21,385.00 23,625.00
L.01 0.14 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 33,360.00 45,660.00
0.42 Lbr Asbes Gelombang 75,000.00 104,000.00 31,500.00 43,680.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 54,745.00 69,285.00
E Overhead & Profit (contoh 10%) 10% 5,474.50 6,928.50
F Harga Satuan Pekerjaan (D+E) 60,219.50 76,213.50

Pemasangan Atap Asbes Gelombang (2,40x1,05 m) x 4


14 A.4.5.2.14 1 m2 58,239.50 74,629.50
mm
A Tenaga 21,385.00 23,625.00
L.01 0.14 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.070 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 31,560.00 44,220.00
0.44 Lbr Asbes Gelombang 67,500.00 96,000.00 29,700.00 42,240.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 52,945.00 67,845.00
E Overhead & Profit (contoh 10%) 10% 5,294.50 6,784.50
F Harga Satuan Pekerjaan (D+E) 58,239.50 74,629.50

Pemasangan Atap Asbes Gelombang (2,10x1,05 m) x 4


15 A.4.5.2.15 1 m2 58,949.00 73,606.50
mm
A Tenaga 21,385.00 23,625.00
L.01 0.14 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.070 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 32,205.00 43,290.00
0.51 Lbr Asbes Gelombang 59,500.00 81,000.00 30,345.00 41,310.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 53,590.00 66,915.00
E Overhead & Profit (contoh 10%) 10% 5,359.00 6,691.50
F Harga Satuan Pekerjaan (D+E) 58,949.00 73,606.50

Pemasangan Atap Asbes Gelombang (1,50x1,05 m) x 4


16 A.4.5.2.16 1 m2 62,529.50 76,565.50
mm
A Tenaga 21,385.00 23,625.00
L.01 0.14 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.070 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 35,460.00 45,980.00
0.80 Lbr Asbes Gelombang 42,000.00 55,000.00 33,600.00 44,000.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 56,845.00 69,605.00
E Overhead & Profit (contoh 10%) 10% 5,684.50 6,960.50
F Harga Satuan Pekerjaan (D+E) 62,529.50 76,565.50

Pemasangan Atap Asbes Gelombang (3,00x1,08 m) x 6


17 A.4.5.2.17 1 m2 67,490.50 70,900.50
mm
A Tenaga 21,385.00 23,625.00
L.01 0.14 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 39,970.00 40,830.00
0.37 Lbr Asbes Gelombang 103,000.00 105,000.00 38,110.00 38,850.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/100 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 61,355.00 64,455.00
E Overhead & Profit (contoh 10%) 10% 6,135.50 6,445.50
F Harga Satuan Pekerjaan (D+E) 67,490.50 70,900.50

Pemasangan Atap Asbes Gelombang (2,70x1,08 m) x 6


18 A.4.5.2.18 1 m2 70,845.50 74,365.50
mm
A Tenaga 21,385.00 23,625.00
L.01 0.14 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 43,020.00 43,980.00
0.42 Lbr Asbes Gelombang 98,000.00 100,000.00 41,160.00 42,000.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 64,405.00 67,605.00
E Overhead & Profit (contoh 10%) 10% 6,440.50 6,760.50
F Harga Satuan Pekerjaan (D+E) 70,845.50 74,365.50

Pemasangan Atap Asbes Gelombang (2,40x1,08 m) x 6


19 A.4.5.2.19 1 m2 67,677.50 71,725.50
mm
A Tenaga 21,385.00 23,625.00
L.01 0.14 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.070 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 40,140.00 41,580.00
0.44 Lbr Asbes Gelombang 87,000.00 90,000.00 38,280.00 39,600.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 61,525.00 65,205.00
E Overhead & Profit (contoh 10%) 10% 6,152.50 6,520.50
F Harga Satuan Pekerjaan (D+E) 67,677.50 71,725.50

Pemasangan Atap Asbes Gelombang (2,10x1,08 m) x 6


20 A.4.5.2.20 1 m2 68,689.50 72,902.50
mm
A Tenaga 21,385.00 23,625.00
L.01 0.14 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.070 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 41,060.00 42,650.00
0.49 Lbr Asbes Gelombang 80,000.00 83,000.00 39,200.00 40,670.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 62,445.00 66,275.00
E Overhead & Profit (contoh 10%) 10% 6,244.50 6,627.50
F Harga Satuan Pekerjaan (D+E) 68,689.50 72,902.50

Pemasangan Atap Asbes Gelombang (1,80x1,08 m) x 6


21 A.4.5.2.21 1 m2 72,594.50 76,444.50
mm
A Tenaga 21,385.00 23,625.00
L.01 0.14 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.070 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 44,610.00 45,870.00
0.57 Lbr Asbes Gelombang 75,000.00 77,000.00 42,750.00 43,890.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 65,995.00 69,495.00
E Overhead & Profit (contoh 10%) 10% 6,599.50 6,949.50
F Harga Satuan Pekerjaan (D+E) 72,594.50 76,444.50

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/101 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
22 A.4.5.2.30 1 m2 Pemasangan Atap Genteng Beton 111,540.00 124,822.50
A Tenaga 30,550.00 33,750.00
L.01 0.2 OH Pekerja 80,000.00 90,000.00 16,000.00 18,000.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B Bahan 70,850.00 79,725.00
11 Lbr Genteng Beton Standrad 6,400.00 7,200.00 70,400.00 79,200.00
0.03 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 450.00 525.00
C PERALATAN
D Jumlah A + B + C 101,400.00 113,475.00
E Overhead & Profit (contoh 10%) 10% 10,140.00 11,347.50
F Harga Satuan Pekerjaan (D+E) 111,540.00 124,822.50

23 A.4.5.2.31 1 m2 Pemasangan Atap Genteng Aspal 228,294.00 255,524.50


A Tenaga 53,640.00 58,770.00
L.01 0.2 OH Pekerja 80,000.00 90,000.00 16,000.00 18,000.00
L.02 0.3 OH Tukang Kayu 120,000.00 130,000.00 36,000.00 39,000.00
L.03 0.003 OH Kepala Tukang 130,000.00 140,000.00 390.00 420.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B Bahan 153,900.00 173,525.00
6.9 Buah Genteng Aspal 18,000.00 20,000.00 124,200.00 138,000.00
0.35 lbr Plywood 6 mm 75,000.00 90,000.00 26,250.00 31,500.00
0.03 kg Paku Biasa 2" - 5" 15,000.00 17,500.00 450.00 525.00
0.50 buah Plastic Aerotor 6,000.00 7,000.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 207,540.00 232,295.00
E Overhead & Profit (contoh 10%) 10% 20,754.00 23,229.50
F Harga Satuan Pekerjaan (D+E) 228,294.00 255,524.50

24 A.4.5.2.32 1 m2 Pemasangan Atap Genteng Metal 93,005.00 108,295.00


A Tenaga 30,550.00 33,750.00
L.01 0.2 OH Pekerja 80,000.00 90,000.00 16,000.00 18,000.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B Bahan 54,000.00 64,700.00
1.02 m2 Genteng Metal 50,000.00 60,000.00 51,000.00 61,200.00
0.20 Kg Paku Biasa Ø ½" - 1" 15,000.00 17,500.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 84,550.00 98,450.00
E Overhead & Profit (contoh 10%) 10% 8,455.00 9,845.00
F Harga Satuan Pekerjaan (D+E) 93,005.00 108,295.00

25 A.4.5.2.34 1 m2 Pemasangan Atap Sirap 116,633.00 127,072.00


A Tenaga 47,530.00 52,020.00
L.01 0.166 OH Pekerja 80,000.00 90,000.00 13,280.00 14,940.00
L.02 0.25 OH Tukang Kayu 120,000.00 130,000.00 30,000.00 32,500.00
L.03 0.025 OH Kepala Tukang 130,000.00 140,000.00 3,250.00 3,500.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 58,500.00 63,500.00
30 Lbr Genteng Sirap 1,850.00 2,000.00 55,500.00 60,000.00
0.2 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 106,030.00 115,520.00
E Overhead & Profit (contoh 10%) 10% 10,603.00 11,552.00
F Harga Satuan Pekerjaan (D+E) 116,633.00 127,072.00

26 A.4.5.2.35 1 m' Pemasangan Nok Genteng Beton 131,483.00 144,842.50


A Tenaga 61,100.00 67,500.00
L.01 0.4 OH Pekerja 80,000.00 90,000.00 32,000.00 36,000.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.02 OH Mandor 125,000.00 135,000.00 2,500.00 2,700.00
B Bahan 58,430.00 64,175.00
3.5 Buah Nok Genteng Beton 9,900.00 11,000.00 34,650.00 38,500.00
0.05 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 750.00 875.00
10.8 Kg Portland Semen 1,125.00 1,200.00 12,150.00 12,960.00
0.032 m3 Pasir Pasang 340,000.00 370,000.00 10,880.00 11,840.00
1 Kg Semen Warna 11,000.00 15,000.00 11,000.00 15,000.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/102 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 119,530.00 131,675.00
E Overhead & Profit (contoh 10%) 10% 11,953.00 13,167.50
F Harga Satuan Pekerjaan (D+E) 131,483.00 144,842.50

27 A.4.5.2.36 1 m' Pemasangan Nok Genteng Aspal 130,845.00 142,928.50


A Tenaga 44,000.00 48,060.00
L.01 0.125 OH Pekerja 80,000.00 90,000.00 10,000.00 11,250.00
L.02 0.250 OH Tukang Kayu 120,000.00 130,000.00 30,000.00 32,500.00
L.03 0.025 OH Kepala Tukang 130,000.00 140,000.00 3,250.00 3,500.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 74,950.00 81,875.00
2.0 Buah Nok Genteng Beton 28,000.00 30,000.00 56,000.00 60,000.00
0.05 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 750.00 875.00
0.0035 m3 Balok Kayu 5,200,000.00 6,000,000.00 18,200.00 21,000.00
C PERALATAN
D Jumlah A + B + C 118,950.00 129,935.00
E Overhead & Profit (contoh 10%) 10% 11,895.00 12,993.50
F Harga Satuan Pekerjaan (D+E) 130,845.00 142,928.50

28 A.4.5.2.37 1 m' Pemasangan Nok Genteng Metal 70,757.50 78,628.00


A Tenaga 41,575.00 45,855.00
L.01 0.250 OH Pekerja 80,000.00 90,000.00 20,000.00 22,500.00
L.02 0.150 OH Tukang Kayu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00
B Bahan 22,750.00 25,625.00
1.1 Buah Nok Genteng 20,000.00 22,500.00 22,000.00 24,750.00
0.05 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 750.00 875.00

C PERALATAN
D Jumlah A + B + C 64,325.00 71,480.00
E Overhead & Profit (contoh 10%) 10% 6,432.50 7,148.00
F Harga Satuan Pekerjaan (D+E) 70,757.50 78,628.00

29 A.4.5.2.38 1 m' Pemasangan Nok Sirap 61,655.00 68,183.50


A Tenaga 44,000.00 48,060.00
L.01 0.125 OH Pekerja 80,000.00 90,000.00 10,000.00 11,250.00
L.02 0.25 OH Tukang Kayu 120,000.00 130,000.00 30,000.00 32,500.00
L.03 0.025 OH Kepala Tukang 130,000.00 140,000.00 3,250.00 3,500.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 12,050.00 13,925.00
0.4 Lbr Seng Plaat 3" x 6" BJLS 28 26,000.00 30,000.00 10,400.00 12,000.00
0.06 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 900.00 1,050.00
0.05 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 750.00 875.00

C PERALATAN
D Jumlah A + B + C 56,050.00 61,985.00
E Overhead & Profit (contoh 10%) 10% 5,605.00 6,198.50
F Harga Satuan Pekerjaan (D+E) 61,655.00 68,183.50

30 A.4.5.2.39 1 m2 Pemasangan Atap Seng Gelombang 40,513.00 45,760.00


A Tenaga 18,330.00 20,250.00
L.01 0.12 OH Pekerja 80,000.00 90,000.00 9,600.00 10,800.00
L.02 0.06 OH Tukang Kayu 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 18,500.00 21,350.00
0.7 Lbr Seng Gelombang 3" x 6" BJLS 28 26,000.00 30,000.00 18,200.00 21,000.00
0.02 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 300.00 350.00
C PERALATAN
D Jumlah A + B + C 36,830.00 41,600.00
E Overhead & Profit (contoh 10%) 10% 3,683.00 4,160.00
F Harga Satuan Pekerjaan (D+E) 40,513.00 45,760.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/103 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
31 A.4.5.2.40 1 m' Pemasangan Atap Nok Seng 33,506.00 37,499.00
A Tenaga 22,060.00 24,390.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.02 0.07 OH Tukang Kayu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 8,400.00 9,700.00
0.3 Lbr Seng Plaat 3" x 6" BJLS 28 26,000.00 30,000.00 7,800.00 9,000.00
0.04 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 600.00 700.00
C PERALATAN
D Jumlah A + B + C 30,460.00 34,090.00
E Overhead & Profit (contoh 10%) 10% 3,046.00 3,409.00
F Harga Satuan Pekerjaan (D+E) 33,506.00 37,499.00

32 A.4.5.2.43 1 m2 Pasang Allumunium Foil / Sisalation 35,475.00 41,283.00


A Tenaga 19,650.00 21,780.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.02 0.05 OH Tukang Kayu 120,000.00 130,000.00 6,000.00 6,500.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 12,600.00 15,750.00
1.05 m2 Sisalation / Allumunium Foil 12,000.00 15,000.00 12,600.00 15,750.00
C PERALATAN
D Jumlah A + B + C 32,250.00 37,530.00
E Overhead & Profit (contoh 10%) 10% 3,225.00 3,753.00
F Harga Satuan Pekerjaan (D+E) 35,475.00 41,283.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/104 10-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
Pembuatan & Pemasangan Kosen Pintu & Jendela
1 A.4.6.1.1 1 m3 27,970,800.00 28,922,437.50
Kayu klas I
A Tenaga 3,396,750.00 3,701,250.00
L.01 7 OH Pekerja 80,000.00 90,000.00 560,000.00 630,000.00
L.02 21 OH Tukang Kayu 120,000.00 130,000.00 2,520,000.00 2,730,000.00
L.03 2.10 OH Kepala Tukang 130,000.00 140,000.00 273,000.00 294,000.00
L.04 0.35 OH Mandor 125,000.00 135,000.00 43,750.00 47,250.00
B Bahan 22,031,250.00 22,591,875.00
1.1 m3 Kayu Klas I (Jati) , Balok 20,000,000.00 20,500,000.00 22,000,000.00 22,550,000.00
1.25 kg Paku Biasa 2" - 5 " 15,000.00 17,500.00 18,750.00 21,875.00
1 kg Lem Kayu 12,500.00 20,000.00 12,500.00 20,000.00
C PERALATAN
D Jumlah A + B + C 25,428,000.00 26,293,125.00
E Overhead & Profit (contoh 10%) 10% 2,542,800.00 2,629,312.50
F Harga Satuan Pekerjaan (D+E) 27,970,800.00 28,922,437.50

Pembuatan & Pemasangan Kosen Pintu & Jendela


2 A.4.6.1.2 1 m3 11,289,025.00 13,435,812.50
Kayu klas II atau III
Tenaga 2,911,500.00 3,172,500.00
L.01 6.00 OH Pekerja 80,000.00 90,000.00 480,000.00 540,000.00
L.02 18.00 OH Tukang Kayu 120,000.00 130,000.00 2,160,000.00 2,340,000.00
L.03 1.80 OH Kepala Tukang 130,000.00 140,000.00 234,000.00 252,000.00
L.04 0.30 OH Mandor 125,000.00 135,000.00 37,500.00 40,500.00
Bahan 7,351,250.00 9,041,875.00
1.2 m3 Kayu Klas II (Kamfer) , Balok 6,100,000.00 7,500,000.00 7,320,000.00 9,000,000.00
1.25 kg Paku Biasa 2" - 5 " 15,000.00 17,500.00 18,750.00 21,875.00
1 kg Lem Kayu 12,500.00 20,000.00 12,500.00 20,000.00
C PERALATAN
D Jumlah A + B + C 10,262,750.00 12,214,375.00
E Overhead & Profit (contoh 10%) 10% 1,026,275.00 1,221,437.50
F Harga Satuan Pekerjaan (D+E) 11,289,025.00 13,435,812.50

Pembuatan & Pemasangan Pintu KlampStandard


3 A.4.6.1.3 1 m2 504,515.00 547,805.50
Kayu Klas II (Kayu Kamfer)
A Tenaga 169,900.00 185,130.00
L.01 0.35 OH Pekerja 80,000.00 90,000.00 28,000.00 31,500.00
L.02 1.05 OH Tukang Kayu 120,000.00 130,000.00 126,000.00 136,500.00
L.03 0.105 OH Kepala Tukang 130,000.00 140,000.00 13,650.00 14,700.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
B Bahan 288,750.00 312,875.00
0.040 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 288,000.00 312,000.00
0.05 Kg Paku Biasa 2" - 5 " 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 458,650.00 498,005.00
E Overhead & Profit (contoh 10%) 10% 45,865.00 49,800.50
F Harga Satuan Pekerjaan (D+E) 504,515.00 547,805.50

Pembuatan & Pemasangan Daun Pintu Klamp


4 A.4.6.1.4 1 m2 504,515.00 547,805.50
Sederhana Kayu Klas III
Tenaga 169,900.00 185,130.00
L.01 0.35 OH Pekerja 80,000.00 90,000.00 28,000.00 31,500.00
L.02 1.05 OH Tukang Kayu 120,000.00 130,000.00 126,000.00 136,500.00
L.03 0.105 OH Kepala Tukang 130,000.00 140,000.00 13,650.00 14,700.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
Bahan 288,750.00 312,875.00
0.040 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 288,000.00 312,000.00
0.05 Kg Paku Biasa 2" - 5 " 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 458,650.00 498,005.00
E Overhead & Profit (contoh 10%) 10% 45,865.00 49,800.50
F Harga Satuan Pekerjaan (D+E) 504,515.00 547,805.50

Pembuatan & Pemasangan Daun Pintu Panel, Kayu


5 A.4.6.1.5 1 m2 851,262.50 925,925.00
Klas I atau II
A Tenaga 485,250.00 528,750.00
L.01 1.00 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00
L.02 3.00 OH Tukang Kayu 120,000.00 130,000.00 360,000.00 390,000.00
L.03 0.30 OH Kepala Tukang 130,000.00 140,000.00 39,000.00 42,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 288,625.00 313,000.00
0.04 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 288,000.00 312,000.00
0.050 kg Lem Kayu 12,500.00 20,000.00 625.00 1,000.00
C PERALATAN
D Jumlah A + B + C 773,875.00 841,750.00
E Overhead & Profit (contoh 10%) 10% 77,387.50 84,175.00
F Harga Satuan Pekerjaan (D+E) 851,262.50 925,925.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/105 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pembuatan & Pemasangan Pintu & Jendela Kaca
6 A.4.6.1.6 1 m2 621,225.00 677,820.00
Kayu Klas I atau II
A Tenaga 388,200.00 423,000.00
L.01 0.800 OH Pekerja 80,000.00 90,000.00 64,000.00 72,000.00
L.02 2.400 OH Tukang Kayu 120,000.00 130,000.00 288,000.00 312,000.00
L.03 0.240 OH Kepala Tukang 130,000.00 140,000.00 31,200.00 33,600.00
L.04 0.040 OH Mandor 125,000.00 135,000.00 5,000.00 5,400.00
B Bahan 176,550.00 193,200.00
0.024 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 172,800.00 187,200.00
0.300 kg Lem Kayu 12,500.00 20,000.00 3,750.00 6,000.00
C PERALATAN
D Jumlah A + B + C 564,750.00 616,200.00
E Overhead & Profit (contoh 10%) 10% 56,475.00 61,620.00
F Harga Satuan Pekerjaan (D+E) 621,225.00 677,820.00

Pembuatan & Pemasangan Pintu & Jendela Jalusi


7 A.4.6.1.7 1 m2 2,089,450.00 2,211,825.00
Kayu Klas I atau II (jati)
A Tenaga 485,250.00 528,750.00
L.01 1 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00
L.02 3 OH Tukang Kayu 120,000.00 130,000.00 360,000.00 390,000.00
L.03 0.3 OH Kepala Tukang 130,000.00 140,000.00 39,000.00 42,000.00
L.04 0.05 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00
B Bahan 1,414,250.00 1,482,000.00
0.064 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 1,408,000.00 1,472,000.00
0.5 kg Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
C PERALATAN
D Jumlah A + B + C 1,899,500.00 2,010,750.00
E Overhead & Profit (contoh 10%) 10% 189,950.00 201,075.00
F Harga Satuan Pekerjaan (D+E) 2,089,450.00 2,211,825.00

Pembuatan&Pemasangan Pintu kayu lapis (Plywood)


8 A.4.6.1.8 1 m2 650,512.50 726,715.00
Rangkap rangka Kayu Klas II (lbr s/d 90 cm)

A Tenaga 339,675.00 370,125.00


L.01 0.700 OH Pekerja 80,000.00 90,000.00 56,000.00 63,000.00
L.02 2.100 OH Tukang Kayu 120,000.00 130,000.00 252,000.00 273,000.00
L.03 0.210 OH Kepala Tukang 130,000.00 140,000.00 27,300.00 29,400.00
L.04 0.035 OH Mandor 125,000.00 135,000.00 4,375.00 4,725.00
B Bahan 251,700.00 290,525.00
0.025 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 180,000.00 195,000.00
0.030 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 450.00 525.00
0.500 Ltr Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
1.000 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 85,000.00 65,000.00 85,000.00
C PERALATAN
D Jumlah A + B + C 591,375.00 660,650.00
E Overhead & Profit (contoh 10%) 10% 59,137.50 66,065.00
F Harga Satuan Pekerjaan (D+E) 650,512.50 726,715.00

Pembuatan&Pemasangan Pintu Plywood rangkap,


9 A.4.6.1.9 1 m2 708,642.00 790,025.50
rangka expose kayu klas I atau II
A Tenaga 388,200.00 423,000.00
L.01 0.800 OH Pekerja 80,000.00 90,000.00 64,000.00 72,000.00
L.02 2.400 OH Tukang Kayu 120,000.00 130,000.00 288,000.00 312,000.00
L.03 0.240 OH Kepala Tukang 130,000.00 140,000.00 31,200.00 33,600.00
L.04 0.040 OH Mandor 125,000.00 135,000.00 5,000.00 5,400.00
B Bahan 256,020.00 295,205.00
0.0256 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 184,320.00 199,680.00
0.03 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 450.00 525.00
0.5 Ltr Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
1 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 85,000.00 65,000.00 85,000.00
C PERALATAN
D Jumlah A + B + C 644,220.00 718,205.00
E Overhead & Profit (contoh 10%) 10% 64,422.00 71,820.50
F Harga Satuan Pekerjaan (D+E) 708,642.00 790,025.50

Pembuatan & Pemasangan Jalusi mati Kosen Kayu


10 A.4.6.1.10 1 m2 1,852,097.50 1,953,765.00
Klas I atau II
A Tenaga 361,475.00 393,525.00
L.01 0.670 OH Pekerja 80,000.00 90,000.00 53,600.00 60,300.00
L.02 2.000 OH Tukang Kayu 120,000.00 130,000.00 240,000.00 260,000.00
L.03 0.200 OH Kepala Tukang 130,000.00 140,000.00 26,000.00 28,000.00
L.04 0.335 OH Mandor 125,000.00 135,000.00 41,875.00 45,225.00
B Bahan 1,322,250.00 1,382,625.00
0.06 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 1,320,000.00 1,380,000.00
0.15 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 2,250.00 2,625.00
C PERALATAN
D Jumlah A + B + C 1,683,725.00 1,776,150.00
E Overhead & Profit (contoh 10%) 10% 168,372.50 177,615.00
F Harga Satuan Pekerjaan (D+E) 1,852,097.50 1,953,765.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/106 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pembuatan & Pemasangan Pintu Teakwood
11 A.4.6.1.11 1 m2 1,108,140.00 1,198,477.50
Rangkap, Rangka Expose Kayu Klas I
A Tenaga 388,200.00 423,000.00
L.01 0.80 OH Pekerja 80,000.00 90,000.00 64,000.00 72,000.00
L.02 2.40 OH Tukang Kayu 120,000.00 130,000.00 288,000.00 312,000.00
L.03 0.24 OH Kepala Tukang 130,000.00 140,000.00 31,200.00 33,600.00
L.04 0.04 OH Mandor 125,000.00 135,000.00 5,000.00 5,400.00
B Bahan 619,200.00 666,525.00
0.025 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 550,000.00 575,000.00
0.03 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 450.00 525.00
0.3 kg Lem Kayu 12,500.00 20,000.00 3,750.00 6,000.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 65,000.00 85,000.00 65,000.00 85,000.00
C PERALATAN
D Jumlah A + B + C 1,007,400.00 1,089,525.00
E Overhead & Profit (contoh 10%) 10% 100,740.00 108,952.50
F Harga Satuan Pekerjaan (D+E) 1,108,140.00 1,198,477.50

Pembuatan & Pemasangan Pintu Teakwood Rangkap


12 A.4.6.1.12 1 m2 763,372.50 846,043.00
Lapis Formika, Rangka expose Kayu Klas II

A Tenaga 412,525.00 449,505.00


L.01 0.850 OH Pekerja 80,000.00 90,000.00 68,000.00 76,500.00
L.02 2.550 OH Tukang Kayu 120,000.00 130,000.00 306,000.00 331,500.00
L.03 0.255 OH Kepala Tukang 130,000.00 140,000.00 33,150.00 35,700.00
L.04 0.043 OH Mandor 125,000.00 135,000.00 5,375.00 5,805.00
B Bahan 281,450.00 319,625.00
0.025 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 180,000.00 195,000.00
0.03 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 450.00 525.00
0.08 kg Lem Kayu 12,500.00 20,000.00 1,000.00 1,600.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 65,000.00 85,000.00 65,000.00 85,000.00
0.5 Lbr Formika 70,000.00 75,000.00 35,000.00 37,500.00
C PERALATAN
D Jumlah A + B + C 693,975.00 769,130.00
E Overhead & Profit (contoh 10%) 10% 69,397.50 76,913.00
F Harga Satuan Pekerjaan (D+E) 763,372.50 846,043.00

Pembuatan&Memasang Konstruksi Kuda-kuda


13 A.4.6.1.13 1 m3 9,839,500.00 11,744,425.00
Konvensional Kayu I; II & III Bentang 6 meter
A Tenaga 1,941,000.00 2,115,000.00
L.01 4 OH Pekerja 80,000.00 90,000.00 320,000.00 360,000.00
L.02 12 OH Tukang Kayu 120,000.00 130,000.00 1,440,000.00 1,560,000.00
L.03 1.2 OH Kepala Tukang 130,000.00 140,000.00 156,000.00 168,000.00
L.04 0.2 OH Mandor 125,000.00 135,000.00 25,000.00 27,000.00
B Bahan 7,004,000.00 8,561,750.00
1.1 m3 Kayu Kamfer, balok 6,100,000.00 7,500,000.00 6,710,000.00 8,250,000.00
15 Kg Besi Strip 14,000.00 14,250.00 210,000.00 213,750.00
5.6 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 84,000.00 98,000.00
C PERALATAN
D Jumlah A + B + C 8,945,000.00 10,676,750.00
E Overhead & Profit (contoh 10%) 10% 894,500.00 1,067,675.00
F Harga Satuan Pekerjaan (D+E) 9,839,500.00 11,744,425.00

Pembuatan&Pemasangan Konstruksi Kuda-kuda


14 A.4.6.1.14 1 m3 30,299,692.50 31,299,812.50
Expose, Kayu Klas I
A Tenaga 3,251,175.00 3,542,625.00
L.01 6.7 OH Pekerja 80,000.00 90,000.00 536,000.00 603,000.00
L.02 20.1 OH Tukang Kayu 120,000.00 130,000.00 2,412,000.00 2,613,000.00
L.03 2.01 OH Kepala Tukang 130,000.00 140,000.00 261,300.00 281,400.00
L.04 0.335 OH Mandor 125,000.00 135,000.00 41,875.00 45,225.00
B Bahan 24,294,000.00 24,911,750.00
1.2 m3 Kayu Klas I (jati), balok 20,000,000.00 20,500,000.00 24,000,000.00 24,600,000.00
15 Kg Besi Strip 14,000.00 14,250.00 210,000.00 213,750.00
5.6 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 84,000.00 98,000.00
C PERALATAN
D Jumlah A + B + C 27,545,175.00 28,454,375.00
E Overhead & Profit (contoh 10%) 10% 2,754,517.50 2,845,437.50
F Harga Satuan Pekerjaan (D+E) 30,299,692.50 31,299,812.50

15 A.4.6.1.15 1 m3 Pemasangan konstruksi Gording, Kayu Klas II 8,942,560.00 10,763,775.00


A Tenaga 1,164,600.00 1,269,000.00
L.01 2.4 OH Pekerja 80,000.00 90,000.00 192,000.00 216,000.00
L.02 7.2 OH Tukang Kayu 120,000.00 130,000.00 864,000.00 936,000.00
L.03 0.72 OH Kepala Tukang 130,000.00 140,000.00 93,600.00 100,800.00
L.04 0.12 OH Mandor 125,000.00 135,000.00 15,000.00 16,200.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/107 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 6,965,000.00 8,516,250.00
1.1 m3 Kayu Klas I (Kamfer), balok 6,100,000.00 7,500,000.00 6,710,000.00 8,250,000.00
15 Kg Besi Strip 14,000.00 14,250.00 210,000.00 213,750.00
3 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 45,000.00 52,500.00
C PERALATAN
D Jumlah A + B + C 8,129,600.00 9,785,250.00
E Overhead & Profit (contoh 10%) 10% 812,960.00 978,525.00
F Harga Satuan Pekerjaan (D+E) 8,942,560.00 10,763,775.00

Pemasangan Rangka Atap Genteng Keramik, Kayu


16 A.4.6.1.16 1 m2 146,338.50 176,495.00
Klas II
A Tenaga 21,925.00 24,075.00
L.01 0.1 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 111,110.00 136,375.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 6,100,000.00 7,500,000.00 85,400.00 105,000.00
0.0036 m3 Reng (2x3) cm 6,100,000.00 7,500,000.00 21,960.00 27,000.00
0.25 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 3,750.00 4,375.00
C PERALATAN
D Jumlah A + B + C 133,035.00 160,450.00
E Overhead & Profit (contoh 10%) 10% 13,303.50 16,045.00
F Harga Satuan Pekerjaan (D+E) 146,338.50 176,495.00

Pemasangan Rangka Atap Genteng Beton, Kayu


17 A.4.6.1.17 1 m2 170,494.50 206,195.00
Klas II
A Tenaga 21,925.00 24,075.00
L.01 0.1 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 133,070.00 163,375.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 6,100,000.00 7,500,000.00 85,400.00 105,000.00
0.0072 m3 Reng (2x3) cm 6,100,000.00 7,500,000.00 43,920.00 54,000.00
0.25 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 3,750.00 4,375.00
C PERALATAN
D Jumlah A + B + C 154,995.00 187,450.00
E Overhead & Profit (contoh 10%) 10% 15,499.50 18,745.00
F Harga Satuan Pekerjaan (D+E) 170,494.50 206,195.00

18 A.4.6.1.18 1 m2 Pemasangan Rangka Atap Sirap, Kayu Klas II 126,181.00 151,129.00


A Tenaga 26,310.00 28,890.00
L.01 0.12 OH Pekerja 80,000.00 90,000.00 9,600.00 10,800.00
L.02 0.12 OH Tukang Kayu 120,000.00 130,000.00 14,400.00 15,600.00
L.03 0.012 OH Kepala Tukang 130,000.00 140,000.00 1,560.00 1,680.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 88,400.00 108,500.00
0.014 m3 Kayu Klas II (Kamfer), balok 6,100,000.00 7,500,000.00 85,400.00 105,000.00
0.2 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 114,710.00 137,390.00
E Overhead & Profit (contoh 10%) 10% 11,471.00 13,739.00
F Harga Satuan Pekerjaan (D+E) 126,181.00 151,129.00

Pemasangan Rangka Langit-langit (50x1,00) m, kayu


19 A.4.6.1.19 1 m2 174,036.50 204,407.50
Klas II atau III
A Tenaga 61,275.00 66,825.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.02 0.30 OH Tukang Kayu 120,000.00 130,000.00 36,000.00 39,000.00
L.03 0.030 OH Kepala Tukang 130,000.00 140,000.00 3,900.00 4,200.00
L.04 0.075 OH Mandor 125,000.00 135,000.00 9,375.00 10,125.00
B Bahan 96,940.00 119,000.00
0.0154 m3 Kayu Klas II (Kamfer), balok 6,100,000.00 7,500,000.00 93,940.00 115,500.00
0.2 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 158,215.00 185,825.00
E Overhead & Profit (contoh 10%) 10% 15,821.50 18,582.50
F Harga Satuan Pekerjaan (D+E) 174,036.50 204,407.50

Pemasangan Rangka Langit-langit (60x60) cm, kayu


20 A.4.6.1.20 1 m2 176,363.00 208,092.50
Klas II atau III
A Tenaga 57,150.00 62,550.00
L.01 0.2 OH Pekerja 80,000.00 90,000.00 16,000.00 18,000.00
L.02 0.3 OH Tukang Kayu 120,000.00 130,000.00 36,000.00 39,000.00
L.03 0.03 OH Kepala Tukang 130,000.00 140,000.00 3,900.00 4,200.00
L.04 0.01 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/108 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 103,180.00 126,625.00
0.0163 m3 Kayu Klas II (Kamfer), balok 6,100,000.00 7,500,000.00 99,430.00 122,250.00
0.25 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 3,750.00 4,375.00
C PERALATAN
D Jumlah A + B + C 160,330.00 189,175.00
E Overhead & Profit (contoh 10%) 10% 16,033.00 18,917.50
F Harga Satuan Pekerjaan (D+E) 176,363.00 208,092.50

Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau


21 A.4.6.1.21 1 m' 301,757.50 317,487.50
II
A Tenaga 35,225.00 38,475.00
L.01 0.1 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.020 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 239,100.00 250,150.00
0.0108 m3 Kayu klas I (Jati), papan 22,000,000.00 23,000,000.00 237,600.00 248,400.00
0.10 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 1,500.00 1,750.00
C PERALATAN
D Jumlah A + B + C 274,325.00 288,625.00
E Overhead & Profit (contoh 10%) 10% 27,432.50 28,862.50
F Harga Satuan Pekerjaan (D+E) 301,757.50 317,487.50

Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau


22 A.4.6.1.22 1 m' 126,692.50 137,665.00
klas II
A Tenaga 35,225.00 38,475.00
L.01 0.1 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 79,950.00 86,675.00
0.011 m3 Kayu klas II (Kamfer), papan 7,200,000.00 7,800,000.00 79,200.00 85,800.00
0.05 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 115,175.00 125,150.00
E Overhead & Profit (contoh 10%) 10% 11,517.50 12,515.00
F Harga Satuan Pekerjaan (D+E) 126,692.50 137,665.00

Pemasangan Rangka Dinding Pemisah (60x120) cm


23 A.4.6.1.23 1 m2 270,490.00 321,205.50
Kayu klas II atau III
A Tenaga 72,850.00 79,380.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.02 0.45 OH Tukang Kayu 120,000.00 130,000.00 54,000.00 58,500.00
L.03 0.045 OH Kepala Tukang 130,000.00 140,000.00 5,850.00 6,300.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 173,050.00 212,625.00
0.028 m3 Kayu klas II (Kamfer), balok 6,100,000.00 7,500,000.00 170,800.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 2,250.00 2,625.00
C PERALATAN
D Jumlah A + B + C 245,900.00 292,005.00
E Overhead & Profit (contoh 10%) 10% 24,590.00 29,200.50
F Harga Satuan Pekerjaan (D+E) 270,490.00 321,205.50

Pemasangan Dinding Pemisah Teakwood Rangkap


24 A.4.6.1.24 1 m2 339,680.00 413,935.50
Rangka Kayu Klas II
A Tenaga 72,850.00 79,380.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.02 0.45 OH Tukang Kayu 120,000.00 130,000.00 54,000.00 58,500.00
L.03 0.045 OH Kepala Tukang 130,000.00 140,000.00 5,850.00 6,300.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 235,950.00 296,925.00
0.028 m3 Kayu klas II (Kamfer), balok 6,100,000.00 7,500,000.00 170,800.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 2,250.00 2,625.00
0.86 Lbr Teakwood 120 x 240 cm tebal 4mm 65,000.00 85,000.00 55,900.00 73,100.00
0.56 Ltr Lem 12,500.00 20,000.00 7,000.00 11,200.00
C PERALATAN
D Jumlah A + B + C 308,800.00 376,305.00
E Overhead & Profit (contoh 10%) 10% 30,880.00 37,630.50
F Harga Satuan Pekerjaan (D+E) 339,680.00 413,935.50

Pemasangan Dinding Pemisah Plywood Rangkap


25 A.4.6.1.25 1 m2 350,460.00 425,122.50
Rangka Kayu Klas II
A Tenaga 82,650.00 89,550.00
L.01 0.020 OH Pekerja 80,000.00 90,000.00 1,600.00 1,800.00
L.02 0.600 OH Tukang Kayu 120,000.00 130,000.00 72,000.00 78,000.00
L.03 0.060 OH Kepala Tukang 130,000.00 140,000.00 7,800.00 8,400.00
L.04 0.010 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/109 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 235,950.00 296,925.00
0.028 m3 Kayu klas II (Kamfer), balok 6,100,000.00 7,500,000.00 170,800.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 2,250.00 2,625.00
0.86 Lbr Plywood 120 x 240 cm tebal 4mm 65,000.00 85,000.00 55,900.00 73,100.00
0.56 Ltr Lem 12,500.00 20,000.00 7,000.00 11,200.00
C PERALATAN
D Jumlah A + B + C 318,600.00 386,475.00
E Overhead & Profit (contoh 10%) 10% 31,860.00 38,647.50
F Harga Satuan Pekerjaan (D+E) 350,460.00 425,122.50

26 A.4.6.1.26 1 m2 Pemasangan Dinding Lambriziring dari Papan Kelas I 492,470.00 529,320.00

A Tenaga 291,150.00 317,250.00


L.01 0.6 OH Pekerja 80,000.00 90,000.00 48,000.00 54,000.00
L.02 1.8 OH Tukang Kayu 120,000.00 130,000.00 216,000.00 234,000.00
L.03 0.18 OH Kepala Tukang 130,000.00 140,000.00 23,400.00 25,200.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 156,550.00 163,950.00
0.007 m3 Kayu klas I (Jati), papan 22,000,000.00 23,000,000.00 154,000.00 161,000.00
0.1 Kg Paku Biasa 2" - 5" 15,000.00 17,500.00 1,500.00 1,750.00
0.15 Kg Paku Sekrup 3,5" 7,000.00 8,000.00 1,050.00 1,200.00
C PERALATAN
D Jumlah A + B + C 447,700.00 481,200.00
E Overhead & Profit (contoh 10%) 10% 44,770.00 48,120.00
F Harga Satuan Pekerjaan (D+E) 492,470.00 529,320.00

Pemasangan Dinding Lambriziring dari Plywood


27 A.4.6.1.27 1 m2 42,806.50 48,543.00
ukuran (120x240) cm
A Tenaga 12,165.00 13,255.00
L.01 0.025 OH Pekerja 80,000.00 90,000.00 2,000.00 2,250.00
L.02 0.075 OH Tukang Kayu 120,000.00 130,000.00 9,000.00 9,750.00
L.03 0.0080 OH Kepala Tukang 130,000.00 140,000.00 1,040.00 1,120.00
L.04 0.0010 OH Mandor 125,000.00 135,000.00 125.00 135.00
B Bahan 26,750.00 30,875.00
0.4 Lbr Plywood (120 X 240) cm x 4mm 65,000.00 75,000.00 26,000.00 30,000.00
0.05 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 750.00 875.00
C PERALATAN
D Jumlah A + B + C 38,915.00 44,130.00
E Overhead & Profit (contoh 10%) 10% 3,891.50 4,413.00
F Harga Satuan Pekerjaan (D+E) 42,806.50 48,543.00

Pemasangan Dinding Bilik, Rangka Kayu Klas III atau


28 A.4.6.1.28 1 m2 123,936.34 143,715.00
IV
A Tenaga 15,275.00 16,875.00
L.01 0.1 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.02 0.05 OH Tukang Kayu 120,000.00 130,000.00 6,000.00 6,500.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 97,394.40 113,775.00
1.500 m2 Bilik Bambu 20,000.00 22,500.00 30,000.00 33,750.00
0.014 m3 Kayu Klas III (Meranti) 4,800,000.00 5,700,000.00 67,200.00 79,800.00
0.012 Kg Paku Biasa 1/2" - 1" 15,000.00 17,500.00 180.00 210.00
0.003 m' List Kayu 2/4 4,800.00 5,000.00 14.40 15.00
C PERALATAN
D Jumlah A + B + C 112,669.40 130,650.00
E Overhead & Profit (contoh 10%) 10% 11,266.94 13,065.00
F Harga Satuan Pekerjaan (D+E) 123,936.34 143,715.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/110 11-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA
1 A.4.6.2.2 1 Buah Pemasangan Kunci Tanam Biasa 211,997.50 261,772.50
A Tenaga 62,725.00 67,975.00
L.01 0.01 OH Pekerja 80,000.00 90,000.00 800.00 900.00
L.02 0.5 OH Tukang Kayu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 130,000.00 170,000.00
1 Buah Kunci Tanam Biasa 130,000.00 170,000.00 130,000.00 170,000.00
C PERALATAN
D Jumlah A + B + C 192,725.00 237,975.00
E Overhead & Profit (contoh 10%) 10% 19,272.50 23,797.50
F Harga Satuan Pekerjaan (D+E) 211,997.50 261,772.50
Overhead & Profit (contoh 10%)
2 A.4.6.2.3 1 Buah Pemasangan Kunci Kamar Mandi 171,998.75 238,136.25
A Tenaga 61,362.50 66,487.50
L.01 0.005 OH Pekerja 80,000.00 90,000.00 400.00 450.00
L.02 0.5 OH Tukang Kayu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.0025 OH Mandor 125,000.00 135,000.00 312.50 337.50
B Bahan 95,000.00 150,000.00
1 Buah Kunci Tanam Kamar Mandi 95,000.00 150,000.00 95,000.00 150,000.00
C PERALATAN
D Jumlah A + B + C 156,362.50 216,487.50
E Overhead & Profit (contoh 10%) 10% 15,636.25 21,648.75
F Harga Satuan Pekerjaan (D+E) 171,998.75 238,136.25

3 A.4.6.2.4 1 Buah Pemasangan Kunci Selinder 210,498.75 260,136.25


A Tenaga 61,362.50 66,487.50
L.01 0.005 OH Pekerja 80,000.00 90,000.00 400.00 450.00
L.02 0.5 OH Tukang Kayu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.005 OH Kepala Tukang 130,000.00 140,000.00 650.00 700.00
L.04 0.0025 OH Mandor 125,000.00 135,000.00 312.50 337.50
B Bahan 130,000.00 170,000.00
1 Buah Kunci Selinder 130,000.00 170,000.00 130,000.00 170,000.00
C PERALATAN
D Jumlah A + B + C 191,362.50 236,487.50
E Overhead & Profit (contoh 10%) 10% 19,136.25 23,648.75
F Harga Satuan Pekerjaan (D+E) 210,498.75 260,136.25

4 A.4.6.2.5 1 Buah Pemasangan Engsel Pintu 32,546.25 36,258.75


A Tenaga 22,087.50 23,962.50
L.01 0.015 OH Pekerja 80,000.00 90,000.00 1,200.00 1,350.00
L.02 0.15 OH Tukang Kayu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.0075 OH Mandor 125,000.00 135,000.00 937.50 1,012.50
B Bahan 7,500.00 9,000.00
1 Buah Engsel pintu 7,500.00 9,000.00 7,500.00 9,000.00
C PERALATAN
D Jumlah A + B + C 29,587.50 32,962.50
E Overhead & Profit (contoh 10%) 10% 2,958.75 3,296.25
F Harga Satuan Pekerjaan (D+E) 32,546.25 36,258.75

5 A.4.6.2.6 1 Buah Pemasangan Engsel Jendela Kupu-kupu 21,147.50 24,172.50


A Tenaga 14,725.00 15,975.00
L.01 0.01 OH Pekerja 80,000.00 90,000.00 800.00 900.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 4,500.00 6,000.00
1 Buah Engsel Jendela 4,500.00 6,000.00 4,500.00 6,000.00
C PERALATAN
D Jumlah A + B + C 19,225.00 21,975.00
E Overhead & Profit (contoh 10%) 10% 1,922.50 2,197.50
F Harga Satuan Pekerjaan (D+E) 21,147.50 24,172.50

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/111 12-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
6 A.4.6.2.7 1 Buah Pemasangan Engsel Angin 55,728.75 74,654.25
A Tenaga 34,662.50 37,867.50
L.01 0.10 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.02 0.20 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.0005 OH Mandor 125,000.00 135,000.00 62.50 67.50
B Bahan 16,000.00 30,000.00
1 Buah Engsel Angin 16,000.00 30,000.00 16,000.00 30,000.00
C PERALATAN
D Jumlah A + B + C 50,662.50 67,867.50
E Overhead & Profit (contoh 10%) 10% 5,066.25 6,786.75
F Harga Satuan Pekerjaan (D+E) 55,728.75 74,654.25

7 A.4.6.2.9 1 Buah Pemasangan Kait Angin 43,615.00 48,433.00


A Tenaga 22,150.00 24,030.00
L.01 0.015 OH Pekerja 80,000.00 90,000.00 1,200.00 1,350.00
L.02 0.15 OH Tukang Kayu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 17,500.00 20,000.00
1 Buah Kait Angin 17,500.00 20,000.00 17,500.00 20,000.00
C PERALATAN
D Jumlah A + B + C 39,650.00 44,030.00
E Overhead & Profit (contoh 10%) 10% 3,965.00 4,403.00
F Harga Satuan Pekerjaan (D+E) 43,615.00 48,433.00

8 A.4.6.2.10 1 Buah Pasang Door Closer 380,393.75 469,521.25


A Tenaga 70,812.50 76,837.50
L.01 0.05 OH Pekerja 80,000.00 90,000.00 4,000.00 4,500.00
L.02 0.5 OH Tukang Kayu 120,000.00 130,000.00 60,000.00 65,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.0025 OH Mandor 125,000.00 135,000.00 312.50 337.50
B Bahan 275,000.00 350,000.00
1 Buah Door Closer 275,000.00 350,000.00 275,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 345,812.50 426,837.50
E Overhead & Profit (contoh 10%) 10% 34,581.25 42,683.75
F Harga Satuan Pekerjaan (D+E) 380,393.75 469,521.25

9 A.4.6.2.11 1 Buah Pemasangan Kunci Selot 39,957.50 44,808.50


A Tenaga 28,325.00 30,735.00
L.01 0.02 OH Pekerja 80,000.00 90,000.00 1,600.00 1,800.00
L.02 0.2 OH Tukang Kayu 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.02 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00
B Bahan 8,000.00 10,000.00
1 Buah Kunci Selot 8,000.00 10,000.00 8,000.00 10,000.00
C PERALATAN
D Jumlah A + B + C 36,325.00 40,735.00
E Overhead & Profit (contoh 10%) 10% 3,632.50 4,073.50
F Harga Satuan Pekerjaan (D+E) 39,957.50 44,808.50

10 A.4.6.2.13 1 Buah Pemasangan Door Stop 318,078.75 401,904.25


A Tenaga 14,162.50 15,367.50
L.01 0.01 OH Pekerja 80,000.00 90,000.00 800.00 900.00
L.02 0.1 OH Tukang Kayu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.01 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.0005 OH Mandor 125,000.00 135,000.00 62.50 67.50
B Bahan 275,000.00 350,000.00
1 Buah Door Stop 275,000.00 350,000.00 275,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 289,162.50 365,367.50
E Overhead & Profit (contoh 10%) 10% 28,916.25 36,536.75
F Harga Satuan Pekerjaan (D+E) 318,078.75 401,904.25

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/112 12-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
11 A.4.6.2.14 1 Buah Pemasangan Rel Pintu Dorong 313,472.50 359,925.50
A Tenaga 84,975.00 92,205.00
L.01 0.06 OH Pekerja 80,000.00 90,000.00 4,800.00 5,400.00
L.02 0.6 OH Tukang Kayu 120,000.00 130,000.00 72,000.00 78,000.00
L.03 0.06 OH Kepala Tukang 130,000.00 140,000.00 7,800.00 8,400.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 200,000.00 235,000.00
1 Buah Rel Pintu Dorong 200,000.00 235,000.00 200,000.00 235,000.00
C PERALATAN
D Jumlah A + B + C 284,975.00 327,205.00
E Overhead & Profit (contoh 10%) 10% 28,497.50 32,720.50
F Harga Satuan Pekerjaan (D+E) 313,472.50 359,925.50

12 A.4.6.2.15 1 Buah Pemasangan Kunci Lemari 52,703.75 58,768.05


A Tenaga 35,412.50 38,425.50
L.01 0.025 OH Pekerja 80,000.00 90,000.00 2,000.00 2,250.00
L.02 0.25 OH Tukang Kayu 120,000.00 130,000.00 30,000.00 32,500.00
L.03 0.025 OH Kepala Tukang 130,000.00 140,000.00 3,250.00 3,500.00
L.04 0.00130 OH Mandor 125,000.00 135,000.00 162.50 175.50
B Bahan 12,500.00 15,000.00
1 Buah Kunci Lemari 12,500.00 15,000.00 12,500.00 15,000.00
C PERALATAN
D Jumlah A + B + C 47,912.50 53,425.50
E Overhead & Profit (contoh 10%) 10% 4,791.25 5,342.55
F Harga Satuan Pekerjaan (D+E) 52,703.75 58,768.05

13 A.4.6.2.16 1 m2 Pemasangan Kaca tebal 3 mm 114,118.13 128,206.38


A Tenaga 21,243.75 23,051.25
L.01 0.015 OH Pekerja 80,000.00 90,000.00 1,200.00 1,350.00
L.02 0.15 OH Tukang Kayu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.00075 OH Mandor 125,000.00 135,000.00 93.75 101.25
B Bahan 82,500.00 93,500.00
1.1 m2 Kaca tebal 3mm 75,000.00 85,000.00 82,500.00 93,500.00
C PERALATAN
D Jumlah A + B + C 103,743.75 116,551.25
E Overhead & Profit (contoh 10%) 10% 10,374.38 11,655.13
F Harga Satuan Pekerjaan (D+E) 114,118.13 128,206.38

14 A.4.6.2.17 1 m2 Pemasangan Kaca tebal 5 mm 132,268.13 140,306.38


A Tenaga 21,243.75 23,051.25
L.01 0.015 OH Pekerja 80,000.00 90,000.00 1,200.00 1,350.00
L.02 0.15 OH Tukang Kayu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.00075 OH Mandor 125,000.00 135,000.00 93.75 101.25
B Bahan 99,000.00 104,500.00
1.1 m2 Kaca tebal 5mm 90,000.00 95,000.00 99,000.00 104,500.00
C PERALATAN
D Jumlah A + B + C 120,243.75 127,551.25
E Overhead & Profit (contoh 10%) 10% 12,024.38 12,755.13
F Harga Satuan Pekerjaan (D+E) 132,268.13 140,306.38

15 A.4.6.2.18 1 m2 Pemasangan Kaca Cermin tebal 5 mm 356,118.13 418,606.38


A Tenaga 21,243.75 23,051.25
L.01 0.015 OH Pekerja 80,000.00 90,000.00 1,200.00 1,350.00
L.02 0.15 OH Tukang Kayu 120,000.00 130,000.00 18,000.00 19,500.00
L.03 0.015 OH Kepala Tukang 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.00075 OH Mandor 125,000.00 135,000.00 93.75 101.25
B Bahan 302,500.00 357,500.00
1.1 m2 Kaca Cermin 275,000.00 325,000.00 302,500.00 357,500.00
C PERALATAN
D Jumlah A + B + C 323,743.75 380,551.25
E Overhead & Profit (contoh 10%) 10% 32,374.38 38,055.13
F Harga Satuan Pekerjaan (D+E) 356,118.13 418,606.38

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/113 12-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

Pengikisan / pengerokan Permukaan Cat Tembok


1 A.4.7.1.1 1 m2 14,327.50 16,120.50
Lama
A Tenaga 12,375.00 13,905.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 650.00 750.00
0.05 Kg Soda Api 13,000.00 15,000.00 650.00 750.00
C PERALATAN
D Jumlah A + B + C 13,025.00 14,655.00
E Overhead & Profit (contoh 10%) 10% 1,302.50 1,465.50
F Harga Satuan Pekerjaan (D+E) 14,327.50 16,120.50

Pencucian Bidang Permukaan Tembok yang Pernah


2 A.4.7.1.2 1 m2 14,300.00 16,120.50
dicat
A Tenaga 12,375.00 13,905.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 625.00 750.00
0.05 Kg Sabun 12,500.00 15,000.00 625.00 750.00
C PERALATAN
D Jumlah A + B + C 13,000.00 14,655.00
E Overhead & Profit (contoh 10%) 10% 1,300.00 1,465.50
F Harga Satuan Pekerjaan (D+E) 14,300.00 16,120.50

Pengerokan Karat Cat Lama permukaan Baja dg cara


3 A.4.7.1.3 1 m2 14,987.50 16,863.00
manual
A Tenaga 13,000.00 14,580.00
L.01 0.15 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.04 0.0080 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 625.00 750.00
0.05 Kg Sabun 12,500.00 15,000.00 625.00 750.00
C PERALATAN
D Jumlah A + B + C 13,625.00 15,330.00
E Overhead & Profit (contoh 10%) 10% 1,362.50 1,533.00
F Harga Satuan Pekerjaan (D+E) 14,987.50 16,863.00

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


4 A.4.7.1.4 1 m2 44,302.50 51,144.50
dasar, 2 Lp Cat Penutup)
A Tenaga 7,835.00 8,715.00
L.01 0.070 OH Pekerja 80,000.00 90,000.00 5,600.00 6,300.00
L.02 0.009 OH Tukang Cat 120,000.00 130,000.00 1,080.00 1,170.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 32,440.00 37,780.00
0.2000 kg Cat Menie 25,000.00 30,000.00 5,000.00 6,000.00
0.1500 kg Plamuur 25,000.00 30,000.00 3,750.00 4,500.00
0.1700 kg Cat Dasar 40,000.00 42,500.00 6,800.00 7,225.00
0.2600 kg Cat Penutup 60,000.00 71,000.00 15,600.00 18,460.00
0.0100 bh Kuas 14,000.00 17,500.00 140.00 175.00
0.0300 kg Pengencer 15,000.00 20,000.00 450.00 600.00
0.2000 lbr Amplas 3,500.00 4,100.00 700.00 820.00
C PERALATAN
D Jumlah A + B + C 40,275.00 46,495.00
E Overhead & Profit (contoh 10%) 10% 4,027.50 4,649.50
F Harga Satuan Pekerjaan (D+E) 44,302.50 51,144.50

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


5 A.4.7.1.5 1 m2 62,628.50 71,593.50
dasar, 3 Lp Cat Penutup)
A Tenaga 19,095.00 20,915.00
L.01 0.070 OH Pekerja 80,000.00 90,000.00 5,600.00 6,300.00
L.02 0.105 OH Tukang Cat 120,000.00 130,000.00 12,600.00 13,650.00
L.03 0.004 OH Kepala Tukang 130,000.00 140,000.00 520.00 560.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/114 13-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 37,840.00 44,170.00
0.2000 kg Cat Menie 25,000.00 30,000.00 5,000.00 6,000.00
0.1500 kg Plamuur 25,000.00 30,000.00 3,750.00 4,500.00
0.1700 kg Cat Dasar 40,000.00 42,500.00 6,800.00 7,225.00
0.3500 kg Cat Penutup 60,000.00 71,000.00 21,000.00 24,850.00
0.0100 bh Kuas 14,000.00 17,500.00 140.00 175.00
0.0300 kg Pengencer 15,000.00 20,000.00 450.00 600.00
0.2000 lbr Amplas 3,500.00 4,100.00 700.00 820.00
C PERALATAN
D Jumlah A + B + C 56,935.00 65,085.00
E Overhead & Profit (contoh 10%) 10% 5,693.50 6,508.50
F Harga Satuan Pekerjaan (D+E) 62,628.50 71,593.50

6 A.4.7.1.6 1 m2 Pelaburan Bidang Kayu dg Teak Oil 37,493.50 39,748.50


A Tenaga 19,325.00 21,015.00
L.01 0.04 OH Pekerja 80,000.00 90,000.00 3,200.00 3,600.00
L.02 0.063 OH Tukang Cat 120,000.00 130,000.00 7,560.00 8,190.00
L.03 0.063 OH Kepala Tukang 130,000.00 140,000.00 8,190.00 8,820.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 14,760.00 15,120.00
0.36 Ltr Teak Oil 41,000.00 42,000.00 14,760.00 15,120.00
C PERALATAN
D Jumlah A + B + C 34,085.00 36,135.00
E Overhead & Profit (contoh 10%) 10% 3,408.50 3,613.50
F Harga Satuan Pekerjaan (D+E) 37,493.50 39,748.50

7 A.4.7.1.7 1 m2 Pelaburan Bidang Kayu dg Politur 59,163.50 61,792.50


A Tenaga 12,855.00 14,045.00
L.01 0.04 OH Pekerja 80,000.00 90,000.00 3,200.00 3,600.00
L.02 0.06 OH Tukang Cat 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.016 OH Kepala Tukang 130,000.00 140,000.00 2,080.00 2,240.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 40,930.00 42,130.00
0.15 Ltr Politur 65,000.00 65,000.00 9,750.00 9,750.00
0.372 Ltr Politur Jadi 65,000.00 65,000.00 24,180.00 24,180.00
2 Lbr Ampelas 3,500.00 4,100.00 7,000.00 8,200.00
C PERALATAN
D Jumlah A + B + C 53,785.00 56,175.00
E Overhead & Profit (contoh 10%) 10% 5,378.50 5,617.50
F Harga Satuan Pekerjaan (D+E) 59,163.50 61,792.50

8 A.4.7.1.8 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter 10,683.75 11,946.00
A Tenaga 8,750.00 9,810.00
L.01 0.1 OH Pekerja 80,000.00 90,000.00 8,000.00 9,000.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 962.50 1,050.00
0.35 Ltr Residu atau Ter 2,750.00 3,000.00 962.50 1,050.00
C PERALATAN
D Jumlah A + B + C 9,712.50 10,860.00
E Overhead & Profit (contoh 10%) 10% 971.25 1,086.00
F Harga Satuan Pekerjaan (D+E) 10,683.75 11,946.00

9 A.4.7.1.9 1 m2 Pelaburan Bidang Kayu dg Vernis 43,785.50 47,855.50


A Tenaga 34,455.00 37,845.00
L.01 0.16 OH Pekerja 80,000.00 90,000.00 12,800.00 14,400.00
L.02 0.16 OH Tukang Cat 120,000.00 130,000.00 19,200.00 20,800.00
L.03 0.016 OH Kepala Tukang 130,000.00 140,000.00 2,080.00 2,240.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 5,350.00 5,660.00
0.15 Ltr Vernis 25,000.00 25,000.00 3,750.00 3,750.00
0.05 Ltr Dempul 25,000.00 30,000.00 1,250.00 1,500.00
0.1 Lbr Ampelas 3,500.00 4,100.00 350.00 410.00
C PERALATAN
D Jumlah A + B + C 39,805.00 43,505.00
E Overhead & Profit (contoh 10%) 10% 3,980.50 4,350.50
F Harga Satuan Pekerjaan (D+E) 43,785.50 47,855.50

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/115 13-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2
10 A.4.7.1.10 1 m2 22,037.40 25,010.70
Lap.Cat Penutup)
A Tenaga 10,354.00 11,277.00
L.01 0.02 OH Pekerja 80,000.00 90,000.00 1,600.00 1,800.00
L.02 0.063 OH Tukang Cat 120,000.00 130,000.00 7,560.00 8,190.00
L.03 0.0063 OH Kepala Tukang 130,000.00 140,000.00 819.00 882.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 9,680.00 11,460.00
0.1 Kg Plamir 25,000.00 32,000.00 2,500.00 3,200.00
0.1 Kg Cat Dasar 12,000.00 15,000.00 1,200.00 1,500.00
0.26 Kg Cat Penutup 2 kali 23,000.00 26,000.00 5,980.00 6,760.00
C PERALATAN
D Jumlah A + B + C 20,034.00 22,737.00
E Overhead & Profit (contoh 10%) 10% 2,003.40 2,273.70
F Harga Satuan Pekerjaan (D+E) 22,037.40 25,010.70

Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat


11 A.4.7.1.11 1 m2 15,159.10 16,998.30
Penutup)
A Tenaga 8,201.00 8,973.00
L.01 0.028 OH Pekerja 80,000.00 90,000.00 2,240.00 2,520.00
L.02 0.042 OH Tukang Cat 120,000.00 130,000.00 5,040.00 5,460.00
L.03 0.0042 OH Kepala Tukang 130,000.00 140,000.00 546.00 588.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 5,580.00 6,480.00
0.12 Kg Cat Dasar 12,000.00 15,000.00 1,440.00 1,800.00
0.18 Kg Cat Penutup 2 kali 23,000.00 26,000.00 4,140.00 4,680.00
C PERALATAN
D Jumlah A + B + C 13,781.00 15,453.00
E Overhead & Profit (contoh 10%) 10% 1,378.10 1,545.30
F Harga Satuan Pekerjaan (D+E) 15,159.10 16,998.30

12 A.4.7.1.12 1 m2 Pengecatan Tembok dengan Kalkarium 9,516.10 10,420.30


A Tenaga 8,201.00 8,973.00
L.01 0.028 OH Pekerja 80,000.00 90,000.00 2,240.00 2,520.00
L.02 0.042 OH Tukang Cat 120,000.00 130,000.00 5,040.00 5,460.00
L.03 0.0042 OH Kepala Tukang 130,000.00 140,000.00 546.00 588.00
L.04 0.0030 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 450.00 500.00
0.1 Kg Kalkarium 4,500.00 5,000.00 450.00 500.00
- -
C PERALATAN
D Jumlah A + B + C 8,651.00 9,473.00
E Overhead & Profit (contoh 10%) 10% 865.10 947.30
F Harga Satuan Pekerjaan (D+E) 9,516.10 10,420.30

13 A.4.7.1.13 1 m2 Pelaburan Tembok dengan Kapur Sirih 15,862.55 17,838.15


A Tenaga 12,445.50 13,981.50
L.01 0.150 OH Pekerja 80,000.00 90,000.00 12,000.00 13,500.00
L.02 0.001 OH Tukang Cat 120,000.00 130,000.00 120.00 130.00
L.03 0.0001 OH Kepala Tukang 130,000.00 140,000.00 13.00 14.00
L.04 0.0025 OH Mandor 125,000.00 135,000.00 312.50 337.50
B Bahan 1,975.00 2,235.00
0.15 Kg Kapur Sirih 7,500.00 8,000.00 1,125.00 1,200.00
0.1 lbr Amplas 3,500.00 4,100.00 350.00 410.00
0.25 ikat Alang-alang 2,000.00 2,500.00 500.00 625.00
C PERALATAN
D Jumlah A + B + C 14,420.50 16,216.50
E Overhead & Profit (contoh 10%) 10% 1,442.05 1,621.65
F Harga Satuan Pekerjaan (D+E) 15,862.55 17,838.15

Pelaburan Tembok lama dengan Kapur Sirih


14 A.4.7.1.14 1 m2 7,317.75 8,280.25
(pemeliharaan)
A Tenaga 4,177.50 4,657.50
L.01 0.040 OH Pekerja 80,000.00 90,000.00 3,200.00 3,600.00
L.02 0.005 OH Tukang Cat 120,000.00 130,000.00 600.00 650.00
L.03 0.0005 OH Kepala Tukang 130,000.00 140,000.00 65.00 70.00
L.04 0.0025 OH Mandor 125,000.00 135,000.00 312.50 337.50

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/116 13-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 2,475.00 2,870.00
0.30 Kg Kapur Sirih 4,250.00 4,750.00 1,275.00 1,425.00
0.2 lbr Amplas 3,500.00 4,100.00 700.00 820.00
0.25 ikat Alang-alang 2,000.00 2,500.00 500.00 625.00
C PERALATAN
D Jumlah A + B + C 6,652.50 7,527.50
E Overhead & Profit (contoh 10%) 10% 665.25 752.75
F Harga Satuan Pekerjaan (D+E) 7,317.75 8,280.25

15 A.4.7.1.15 1 m2 Pemasangan Wallpaper 89,663.75 101,131.25


A Tenaga 28,512.50 30,937.50
L.01 0.020 OH Pekerja 80,000.00 90,000.00 1,600.00 1,800.00
L.02 0.200 OH Tukang Cat 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.0200 OH Kepala Tukang 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.0025 OH Mandor 125,000.00 135,000.00 312.50 337.50
B Bahan 53,000.00 61,000.00
1.20 lbr Wall Paper 35,000.00 40,000.00 42,000.00 48,000.00
0.2 kg Lem 55,000.00 65,000.00 11,000.00 13,000.00

C PERALATAN
D Jumlah A + B + C 81,512.50 91,937.50
E Overhead & Profit (contoh 10%) 10% 8,151.25 9,193.75
F Harga Satuan Pekerjaan (D+E) 89,663.75 101,131.25

16 A.4.7.1.16 1 m2 Pengecatan Permukaan Baja dg Meni Besi 32,144.75 35,934.25


A Tenaga 26,172.50 28,417.50
L.01 0.02 OH Pekerja 80,000.00 90,000.00 1,600.00 1,800.00
L.02 0.2 OH Tukang Cat 120,000.00 130,000.00 24,000.00 26,000.00
L.03 0.002 OH Kepala Tukang 130,000.00 140,000.00 260.00 280.00
L.04 0.0025 OH Mandor 125,000.00 135,000.00 312.50 337.50
B Bahan 3,050.00 4,250.00
0.1 Kg Meni Besi 25,000.00 36,000.00 2,500.00 3,600.00
0.01 Kg Perekat / Lem 55,000.00 65,000.00 550.00 650.00
C PERALATAN
D Jumlah A + B + C 29,222.50 32,667.50
E Overhead & Profit (contoh 10%) 10% 2,922.25 3,266.75
F Harga Satuan Pekerjaan (D+E) 32,144.75 35,934.25

Pengecatan Permukaan Baja dg Meni Besi &


17 A.4.7.1.17 1 m2 60,486.25 67,553.75
Perancah
A Tenaga 47,937.50 52,762.50
L.01 0.25 OH Pekerja 80,000.00 90,000.00 20,000.00 22,500.00
L.02 0.225 OH Tukang Cat 120,000.00 130,000.00 27,000.00 29,250.00
L.04 0.0075 OH Mandor 125,000.00 135,000.00 937.50 1,012.50
B Bahan 7,050.00 8,650.00
0.1 Kg Meni Besi 25,000.00 36,000.00 2,500.00 3,600.00
0.01 Kg Perekat / Lem 55,000.00 65,000.00 550.00 650.00
0.002 m3 Perancah Kayu 2,000,000.00 2,200,000.00 4,000.00 4,400.00
C PERALATAN
D Jumlah A + B + C 54,987.50 61,412.50
E Overhead & Profit (contoh 10%) 10% 5,498.75 6,141.25
F Harga Satuan Pekerjaan (D+E) 60,486.25 67,553.75

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/117 13-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
HARGA SATUAN PEKERJAAN SANITASI DALAM
XIV A.5.1.1
GEDUNG
1 A.5.1.1.1 1 Unit Pemasangan Closet Duduk / Mono Blok 2,323,343.00 2,665,014.00
A Tenaga 416,130.00 461,740.00
L.01 3.3 OH Pekerja 80,000.00 90,000.00 264,000.00 297,000.00
L.02 1.1 OH Tukang Batu 120,000.00 130,000.00 132,000.00 143,000.00
L.03 0.001 OH Kepala Tukang 130,000.00 140,000.00 130.00 140.00
L.04 0.16 OH Mandor 125,000.00 135,000.00 20,000.00 21,600.00
Buah Bahan 1,696,000.00 1,961,000.00
1 Buah Kloset Duduk / Monoblok 1,600,000.00 1,850,000.00 1,600,000.00 1,850,000.00
0.06 Kelengkapan 6% dari harga Kloset 1,600,000.00 1,850,000.00 96,000.00 111,000.00
C PERALATAN
D Jumlah A + B + C 2,112,130.00 2,422,740.00
E Overhead & Profit (contoh 10%) 10% 211,213.00 242,274.00
F Harga Satuan Pekerjaan (D+E) 2,323,343.00 2,665,014.00
Overhead & Profit (contoh 10%)
2 A.5.1.1.2 1 Unit Pemasangan Closet Jongkok Porselen 693,165.00 756,250.00
A Tenaga 475,000.00 516,600.00
L.01 1 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00
L.02 1.5 OH Tukang Batu 120,000.00 130,000.00 180,000.00 195,000.00
L.03 1.5 OH Kepala Tukang 130,000.00 140,000.00 195,000.00 210,000.00
L.04 0.16 OH Mandor 125,000.00 135,000.00 20,000.00 21,600.00
B Bahan 155,150.00 170,900.00
1 Buah Kloset Jongkok 145,000.00 160,000.00 145,000.00 160,000.00
6 Kg Portland Semen 1,125.00 1,200.00 6,750.00 7,200.00
0.01 m3 Pasir Pasang 340,000.00 370,000.00 3,400.00 3,700.00
C PERALATAN
D Jumlah A + B + C 630,150.00 687,500.00
E Overhead & Profit (contoh 10%) 10% 63,015.00 68,750.00
F Harga Satuan Pekerjaan (D+E) 693,165.00 756,250.00

3 A.5.1.1.4 1 Unit Pemasangan Urinoir 759,715.00 820,490.00


A Tenaga 225,500.00 247,500.00
L.01 1 OH Pekerja 80,000.00 90,000.00 80,000.00 90,000.00
L.02 1 OH Tukang Batu 120,000.00 130,000.00 120,000.00 130,000.00
L.03 0.1 OH Kepala Tukang 130,000.00 140,000.00 13,000.00 14,000.00
L.04 0.1 OH Mandor 125,000.00 135,000.00 12,500.00 13,500.00
B Bahan 465,150.00 498,400.00
1 Buah Urinoir 350,000.00 375,000.00 350,000.00 375,000.00
0.3 - Perlengkapan 30% Harga Urinoir 350,000.00 375,000.00 105,000.00 112,500.00
6 Kg Portland Semen 1,125.00 1,200.00 6,750.00 7,200.00
0.01 m3 Pasir Pasang 340,000.00 370,000.00 3,400.00 3,700.00
C PERALATAN
D Jumlah A + B + C 690,650.00 745,900.00
E Overhead & Profit (contoh 10%) 10% 69,065.00 74,590.00
F Harga Satuan Pekerjaan (D+E) 759,715.00 820,490.00

4 A.5.1.1.5 1 Unit Pemasangan Wastafel 600,105.00 654,225.00


A Tenaga 145,400.00 161,350.00
L.01 1.2 OH Pekerja 80,000.00 90,000.00 96,000.00 108,000.00
L.02 0.145 OH Tukang Batu 120,000.00 130,000.00 17,400.00 18,850.00
L.03 0.15 OH Kepala Tukang 130,000.00 140,000.00 19,500.00 21,000.00
L.04 0.1 OH Mandor 125,000.00 135,000.00 12,500.00 13,500.00
B Bahan 400,150.00 433,400.00
1 Buah Wastafel 300,000.00 325,000.00 300,000.00 325,000.00
0.3 - Perlengkapan 30% Harga Wastafel 300,000.00 325,000.00 90,000.00 97,500.00
6 Kg Portland Semen 1,125.00 1,200.00 6,750.00 7,200.00
0.01 m3 Pasir Pasang 340,000.00 370,000.00 3,400.00 3,700.00
C PERALATAN
D Jumlah A + B + C 545,550.00 594,750.00
E Overhead & Profit (contoh 10%) 10% 54,555.00 59,475.00
F Harga Satuan Pekerjaan (D+E) 600,105.00 654,225.00

5 A.5.1.1.6 1 Unit Pemasangan Bathcuip porselen 1,106,737.50 1,182,670.50


A Tenaga 106,125.00 115,155.00
L.01 0.075 OH Pekerja 80,000.00 90,000.00 6,000.00 6,750.00
L.02 0.75 OH Tukang Batu 120,000.00 130,000.00 90,000.00 97,500.00
L.03 0.075 OH Kepala Tukang 130,000.00 140,000.00 9,750.00 10,500.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/118 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 900,000.00 960,000.00
1 Buah Batchuip 750,000.00 800,000.00 750,000.00 800,000.00
0.2 - Perlengkapan 20% Harga Bathcuip 750,000.00 800,000.00 150,000.00 160,000.00
C PERALATAN
D Jumlah A + B + C 1,006,125.00 1,075,155.00
E Overhead & Profit (contoh 10%) 10% 100,612.50 107,515.50
F Harga Satuan Pekerjaan (D+E) 1,106,737.50 1,182,670.50

6 A.5.1.1.7 1 Unit Pemasangan Bak Fibreglass vol.1 m3 1,327,700.00 1,451,450.00


A Tenaga 899,000.00 983,500.00

L.01 3 OH Pekerja 80,000.00 90,000.00 240,000.00 270,000.00


L.02 4.5 OH Tukang Batu 120,000.00 130,000.00 540,000.00 585,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.9 OH Mandor 125,000.00 135,000.00 112,500.00 121,500.00
B Tukang Batu 308,000.00 336,000.00
1 Buah Bak Fibreglass 275,000.00 300,000.00 275,000.00 300,000.00
0.12 - Perlengkapan 12% Bak Fibreglass 275,000.00 300,000.00 33,000.00 36,000.00
C PERALATAN
D Jumlah A + B + C 1,207,000.00 1,319,500.00
E Overhead & Profit (contoh 10%) 10% 120,700.00 131,950.00
F Harga Satuan Pekerjaan (D+E) 1,327,700.00 1,451,450.00

7 A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 1,606,154.27 1,768,063.54
A Tenaga 882,750.00 976,050.00
L.01 6.00 OH Pekerja 80,000.00 90,000.00 480,000.00 540,000.00
L.02 3.00 OH Tukang Batu 120,000.00 130,000.00 360,000.00 390,000.00
L.03 0.30 OH Kepala Tukang 130,000.00 140,000.00 39,000.00 42,000.00
L.04 0.03 OH Mandor 125,000.00 135,000.00 3,750.00 4,050.00
B Bahan 577,390.24 631,280.49
150.0 bh Batu Bata 600.00 650.00 90,000.00 97,500.00
120 Kg Portland Semen 0.11 1,125.00 1,200.00 135,000.00 144,000.00
0.3 m3 Pasir Pasang 0.0121 340,000.00 370,000.00 102,000.00 111,000.00
360 buah Porselen 11 x 11 cm 82.6446 512.20 524.39 184,390.24 188,780.49
6 Kg Semen Nat 11,000.00 15,000.00 66,000.00 90,000.00
C PERALATAN
D Jumlah A + B + C 1,460,140.24 1,607,330.49
E Overhead & Profit (contoh 10%) 10% 146,014.02 160,733.05
F Harga Satuan Pekerjaan (D+E) 1,606,154.27 1,768,063.54

8 A.5.1.1.11 1 Unit Pemasangan Bak Beton Bertulang Vol. 1 m3 6,472,506.25 7,448,583.37


A Tenaga 828,750.00 909,430.00
L.01 3.50 OH Pekerja 80,000.00 90,000.00 280,000.00 315,000.00
L.02 4.50 OH Tukang Batu 120,000.00 130,000.00 540,000.00 585,000.00
L.03 0.05 OH Kepala Tukang 130,000.00 140,000.00 6,500.00 7,000.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
B Bahan 1,179,432.09 1,325,827.04 5,055,346.59 5,862,009.43
0.9 m3 Beton K.150 1,054,548.52 1,173,356.90 949,093.67 1,056,021.21
180 Kg Baja Tulangan 0.11 13,542.10 16,067.70 2,437,578.00 2,892,186.00
8.0 m2 Kayu Bekisting 0.05 0.0121 110,000.00 135,000.00 880,000.00 1,080,000.00
500 buah Porselen 11 x 11 cm 20 82.6446 1,341.46 1,402.44 670,731.71 701,219.51
10 % Perlengkapan 1,179,432.09 1,325,827.04 117,943.21 132,582.70
C PERALATAN
D Jumlah A + B + C 5,884,096.59 6,771,439.43
E Overhead & Profit (contoh 10%) 10% 588,409.66 677,143.94
F Harga Satuan Pekerjaan (D+E) 6,472,506.25 7,448,583.37

9 A.5.1.1.12 1 buah Pemasangan Bak Cuci Piring Stainless stell 351,092.50 393,717.50
A Tenaga 44,175.00 47,925.00
L.01 0.030 OH Pekerja 80,000.00 90,000.00 2,400.00 2,700.00
L.02 0.300 OH Tukang Batu 120,000.00 130,000.00 36,000.00 39,000.00
L.03 0.030 OH Kepala Tukang 130,000.00 140,000.00 3,900.00 4,200.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00
B Bahan 275,000.00 310,000.00
1 unit Bak Cuci Piring 225,000.00 250,000.00 225,000.00 250,000.00
1 bh Water drain 50,000.00 60,000.00 50,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 319,175.00 357,925.00
E Overhead & Profit (contoh 10%) 10% 31,917.50 35,792.50
F Harga Satuan Pekerjaan (D+E) 351,092.50 393,717.50

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/119 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
10 A.5.1.1.14 1 buah Pemasangan Floor Drain 54,697.50 64,322.50
A Tenaga 14,725.00 15,975.00
L.01 0.010 OH Pekerja 80,000.00 90,000.00 800.00 900.00
L.02 0.100 OH Tukang Batu 120,000.00 130,000.00 12,000.00 13,000.00
L.03 0.010 OH Kepala Tukang 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 35,000.00 42,500.00
1 bh Floor Drain 35,000.00 42,500.00 35,000.00 42,500.00

C PERALATAN
D Jumlah A + B + C 49,725.00 58,475.00
E Overhead & Profit (contoh 10%) 10% 4,972.50 5,847.50
F Harga Satuan Pekerjaan (D+E) 54,697.50 64,322.50

Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi


11 A.5.1.1.15 1 bh 470,032.60 518,070.65
35 cm
A Tenaga 269,935.00 299,565.00
L.01 2.160 OH Pekerja 80,000.00 90,000.00 172,800.00 194,400.00
L.02 0.720 OH Tukang Batu 120,000.00 130,000.00 86,400.00 93,600.00
L.03 0.072 OH Kepala Tukang 130,000.00 140,000.00 9,360.00 10,080.00
L.04 0.011 OH Mandor 125,000.00 135,000.00 1,375.00 1,485.00
B Bahan 157,367.36 171,408.32
40.00 bh Batu Bata 600.00 650.00 24,000.00 26,000.00
44.00 kg Semen Portland 1,125.00 1,200.00 49,500.00 52,800.00
0.07 m3 Pasir Pasang 340,000.00 370,000.00 23,800.00 25,900.00
0.06 m3 Pasir Beton 360,000.00 380,000.00 21,600.00 22,800.00
0.07 m3 Kerikil 240,000.00 260,000.00 16,800.00 18,200.00
1.60 kg Baja Tulangan 13,542.10 16,067.70 21,667.36 25,708.32
C PERALATAN
D Jumlah A + B + C 427,302.36 470,973.32
E Overhead & Profit (contoh 10%) 10% 42,730.24 47,097.33
F Harga Satuan Pekerjaan (D+E) 470,032.60 518,070.65

Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45


12 A.5.1.1.16 1 bh 692,034.60 761,539.15
tinggi 50 cm
A Tenaga 397,430.00 441,200.00
L.01 3.200 OH Pekerja 80,000.00 90,000.00 256,000.00 288,000.00
L.02 1.150 OH Tukang Batu 120,000.00 130,000.00 138,000.00 149,500.00
L.03 0.011 OH Kepala Tukang 130,000.00 140,000.00 1,430.00 1,540.00
L.04 0.016 OH Mandor 125,000.00 135,000.00 2,000.00 2,160.00
B Bahan 231,692.36 251,108.32
70.00 bh Batu Bata 600.00 650.00 42,000.00 45,500.00
77.00 kg Semen Portland 1,125.00 1,200.00 86,625.00 92,400.00
0.13 m3 Pasir Pasang 340,000.00 370,000.00 44,200.00 48,100.00
0.09 m3 Pasir Beton 360,000.00 380,000.00 32,400.00 34,200.00
0.02 m3 Kerikil 240,000.00 260,000.00 4,800.00 5,200.00
1.60 kg Baja Tulangan 13,542.10 16,067.70 21,667.36 25,708.32
C PERALATAN
D Jumlah A + B + C 629,122.36 692,308.32
E Overhead & Profit (contoh 10%) 10% 62,912.24 69,230.83
F Harga Satuan Pekerjaan (D+E) 692,034.60 761,539.15

Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi


13 A.5.1.1.17 1 bh 832,171.10 918,674.18
60 cm
A Tenaga 397,430.00 441,200.00
L.01 3.200 OH Pekerja 80,000.00 90,000.00 256,000.00 288,000.00
L.02 1.150 OH Tukang Batu 120,000.00 130,000.00 138,000.00 149,500.00
L.03 0.011 OH Kepala Tukang 130,000.00 140,000.00 1,430.00 1,540.00
L.04 0.016 OH Mandor 125,000.00 135,000.00 2,000.00 2,160.00
B Bahan 359,089.19 393,958.35
123.00 bh Batu Bata 600.00 650.00 73,800.00 79,950.00
114.00 kg Semen Portland 1,125.00 1,200.00 128,250.00 136,800.00
0.18 m3 Pasir Pasang 340,000.00 370,000.00 62,560.00 68,080.00
0.12 m3 Pasir Beton 240,000.00 260,000.00 28,800.00 31,200.00
4.85 kg Baja Tulangan 13,542.10 16,067.70 65,679.19 77,928.35
C PERALATAN
D Jumlah A + B + C 756,519.19 835,158.35
E Overhead & Profit (contoh 10%) 10% 75,651.92 83,515.83
F Harga Satuan Pekerjaan (D+E) 832,171.10 918,674.18

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/120 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
14 A.5.1.1.18 1 m' Pemasangan Pipa Galvanis Ø ½" 65,677.33 69,078.17
A Tenaga 19,665.00 21,465.00
L.01 0.054 OH Pekerja 80,000.00 90,000.00 4,320.00 4,860.00
L.02 0.090 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.027 OH Mandor 125,000.00 135,000.00 3,375.00 3,645.00
B Bahan 40,041.67 41,333.33
1.20 m' Pipa Galvanis Ø ½" 25,833.33 26,666.67 31,000.00 32,000.00
0.35 Ls Perlengkapan 35% x pipa 25,833.33 26,666.67 9,041.67 9,333.33
C PERALATAN
D Jumlah A + B + C 59,706.67 62,798.33
E Overhead & Profit (contoh 10%) 10% 5,970.67 6,279.83
F Harga Satuan Pekerjaan (D+E) 65,677.33 69,078.17

15 A.5.1.1.19 1 bh Pemasangan Kran Ø ½" atau Ø ¾" 87,597.13 114,604.88


A Tenaga 54,625.00 59,175.00
L.01 0.010 OH Pekerja 80,000.00 90,000.00 800.00 900.00
L.02 0.400 OH Tukang Batu 120,000.00 130,000.00 48,000.00 52,000.00
L.03 0.040 OH Kepala Tukang 130,000.00 140,000.00 5,200.00 5,600.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 25,008.75 45,011.25
1.00 bh Kran Air 25,000.00 45,000.00 25,000.00 45,000.00
0.0025 bh Sealtape 3,500.00 4,500.00 8.75 11.25
C PERALATAN
D Jumlah A + B + C 79,633.75 104,186.25
E Overhead & Profit (contoh 10%) 10% 7,963.38 10,418.63
F Harga Satuan Pekerjaan (D+E) 87,597.13 114,604.88

16 A.5.1.1.20 1 m' Pemasangan Pipa Galvanis Ø ¾" 77,044.00 80,444.83


A Tenaga 19,665.00 21,465.00
L.01 0.054 OH Pekerja 80,000.00 90,000.00 4,320.00 4,860.00
L.02 0.090 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.027 OH Mandor 125,000.00 135,000.00 3,375.00 3,645.00
B Bahan 50,375.00 51,666.67
1.20 m' Pipa Galvanis Ø ¾" 32,500.00 33,333.33 39,000.00 40,000.00
0.35 Ls Perlengkapan 35% x pipa 32,500.00 33,333.33 11,375.00 11,666.67
C PERALATAN
D Jumlah A + B + C 70,040.00 73,131.67
E Overhead & Profit (contoh 10%) 10% 7,004.00 7,313.17
F Harga Satuan Pekerjaan (D+E) 77,044.00 80,444.83

17 A.5.1.1.21 1 m' Pemasangan Pipa Galvanis Ø 1" 108,302.33 113,124.00


A Tenaga 19,665.00 21,465.00
L.01 0.054 OH Pekerja 80,000.00 90,000.00 4,320.00 4,860.00
L.02 0.090 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.027 OH Mandor 125,000.00 135,000.00 3,375.00 3,645.00
B Bahan 78,791.67 81,375.00
1.20 m' Pipa Galvanis Ø 1" 50,833.33 52,500.00 61,000.00 63,000.00
0.35 Ls Perlengkapan 35% x pipa 50,833.33 52,500.00 17,791.67 18,375.00
C PERALATAN
D Jumlah A + B + C 98,456.67 102,840.00
E Overhead & Profit (contoh 10%) 10% 9,845.67 10,284.00
F Harga Satuan Pekerjaan (D+E) 108,302.33 113,124.00

18 A.5.1.1.22 1 m' Pemasangan Pipa Galvanis Ø 1½ " 144,508.83 150,771.50


A Tenaga 33,205.00 36,315.00
L.01 0.108 OH Pekerja 80,000.00 90,000.00 8,640.00 9,720.00
L.02 0.180 OH Tukang Batu 120,000.00 130,000.00 21,600.00 23,400.00
L.03 0.018 OH Kepala Tukang 130,000.00 140,000.00 2,340.00 2,520.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 98,166.67 100,750.00
1.20 m' Pipa Galvanis Ø 1½" 63,333.33 65,000.00 76,000.00 78,000.00
0.35 Ls Perlengkapan 35% x pipa 63,333.33 65,000.00 22,166.67 22,750.00
C PERALATAN
D Jumlah A + B + C 131,371.67 137,065.00
E Overhead & Profit (contoh 10%) 10% 13,137.17 13,706.50
F Harga Satuan Pekerjaan (D+E) 144,508.83 150,771.50

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/121 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
19 A.5.1.1.23 1 m' Pemasangan Pipa Galvanis Ø 3" 256,114.83 263,814.83
A Tenaga 41,665.00 45,565.00
L.01 0.135 OH Pekerja 80,000.00 90,000.00 10,800.00 12,150.00
L.02 0.225 OH Tukang Batu 120,000.00 130,000.00 27,000.00 29,250.00
L.03 0.023 OH Kepala Tukang 130,000.00 140,000.00 2,990.00 3,220.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 191,166.67 194,266.67
1.20 m' Pipa Galvanis Ø 3" 123,333.33 125,333.33 148,000.00 150,400.00
0.35 Ls Perlengkapan 35% x pipa 123,333.33 125,333.33 43,166.67 43,866.67
C PERALATAN
D Jumlah A + B + C 232,831.67 239,831.67
E Overhead & Profit (contoh 10%) 10% 23,283.17 23,983.17
F Harga Satuan Pekerjaan (D+E) 256,114.83 263,814.83

20 A.5.1.1.24 1 m' Pemasangan Pipa Galvanis Ø 4" 459,294.00 465,715.25


A Tenaga 41,665.00 45,565.00
L.01 0.135 OH Pekerja 80,000.00 90,000.00 10,800.00 12,150.00
L.02 0.225 OH Tukang Batu 120,000.00 130,000.00 27,000.00 29,250.00
L.03 0.023 OH Kepala Tukang 130,000.00 140,000.00 2,990.00 3,220.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 375,875.00 377,812.50
1.20 m' Pipa Galvanis Ø 4" 242,500.00 243,750.00 291,000.00 292,500.00
0.35 Ls Perlengkapan 35% x pipa 242,500.00 243,750.00 84,875.00 85,312.50
C PERALATAN
D Jumlah A + B + C 417,540.00 423,377.50
E Overhead & Profit (contoh 10%) 10% 41,754.00 42,337.75
F Harga Satuan Pekerjaan (D+E) 459,294.00 465,715.25

21 A.5.1.1.25 1 m' Pemasangan Pipa PVC tipe AW Ø ½" 24,156.00 26,578.75


A Tenaga 11,110.00 12,150.00
L.01 0.036 OH Pekerja 80,000.00 90,000.00 2,880.00 3,240.00
L.02 0.060 OH Tukang Batu 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 10,850.00 12,012.50
1.20 m' Pipa PVC Ø ½" 7,000.00 7,750.00 8,400.00 9,300.00
0.35 Ls Perlengkapan 35% x pipa 7,000.00 7,750.00 2,450.00 2,712.50
C PERALATAN
D Jumlah A + B + C 21,960.00 24,162.50
E Overhead & Profit (contoh 10%) 10% 2,196.00 2,416.25
F Harga Satuan Pekerjaan (D+E) 24,156.00 26,578.75

22 A.5.1.1.26 1 m' Pemasangan Pipa PVC tipe AW Ø ¾" 26,713.50 28,923.13


A Tenaga 11,110.00 12,150.00
L.01 0.036 OH Pekerja 80,000.00 90,000.00 2,880.00 3,240.00
L.02 0.060 OH Tukang Batu 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 13,175.00 14,143.75
1.20 m' Pipa PVC Ø ¾" 8,500.00 9,125.00 10,200.00 10,950.00
0.35 Ls Perlengkapan 35% x pipa 8,500.00 9,125.00 2,975.00 3,193.75
C PERALATAN
D Jumlah A + B + C 24,285.00 26,293.75
E Overhead & Profit (contoh 10%) 10% 2,428.50 2,629.38
F Harga Satuan Pekerjaan (D+E) 26,713.50 28,923.13

23 A.5.1.1.27 1 m' Pemasangan Pipa PVC tipe AW Ø 1" 31,402.25 36,808.75


A Tenaga 11,110.00 12,150.00
L.01 0.036 OH Pekerja 80,000.00 90,000.00 2,880.00 3,240.00
L.02 0.060 OH Tukang Batu 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 17,437.50 21,312.50
1.20 m' Pipa PVC Ø 1" 11,250.00 13,750.00 13,500.00 16,500.00
0.35 Ls Perlengkapan 35% x pipa 11,250.00 13,750.00 3,937.50 4,812.50
C PERALATAN
D Jumlah A + B + C 28,547.50 33,462.50
E Overhead & Profit (contoh 10%) 10% 2,854.75 3,346.25
F Harga Satuan Pekerjaan (D+E) 31,402.25 36,808.75

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/122 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
24 A.5.1.1.28 1 m' Pemasangan Pipa PVC tipe AW Ø 1½" 34,244.83 39,939.17
A Tenaga 16,665.00 18,225.00
L.01 0.054 OH Pekerja 80,000.00 90,000.00 4,320.00 4,860.00
L.02 0.090 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 14,466.67 18,083.33
1.20 m' Pipa PVC Ø 1½" 9,333.33 11,666.67 11,200.00 14,000.00
0.35 Ls Perlengkapan 35% x pipa 9,333.33 11,666.67 3,266.67 4,083.33
C PERALATAN
D Jumlah A + B + C 31,131.67 36,308.33
E Overhead & Profit (contoh 10%) 10% 3,113.17 3,630.83
F Harga Satuan Pekerjaan (D+E) 34,244.83 39,939.17

25 A.5.1.1.29 1 m' Pemasangan Pipa PVC tipe AW Ø 2" 38,223.17 49,885.00


A Tenaga 16,665.00 18,225.00
L.01 0.054 OH Pekerja 80,000.00 90,000.00 4,320.00 4,860.00
L.02 0.090 OH Tukang Batu 120,000.00 130,000.00 10,800.00 11,700.00
L.03 0.009 OH Kepala Tukang 130,000.00 140,000.00 1,170.00 1,260.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 18,083.33 27,125.00
1.20 m' Pipa PVC Ø 2" 11,666.67 17,500.00 14,000.00 21,000.00
0.35 Ls Perlengkapan 35% x pipa 11,666.67 17,500.00 4,083.33 6,125.00
C PERALATAN
D Jumlah A + B + C 34,748.33 45,350.00
E Overhead & Profit (contoh 10%) 10% 3,474.83 4,535.00
F Harga Satuan Pekerjaan (D+E) 38,223.17 49,885.00

26 A.5.1.1.31 1 m' Pemasangan Pipa PVC tipe AW Ø 3" 62,949.33 82,567.83


A Tenaga 24,935.00 27,270.00
L.01 0.081 OH Pekerja 80,000.00 90,000.00 6,480.00 7,290.00
L.02 0.135 OH Tukang Batu 120,000.00 130,000.00 16,200.00 17,550.00
L.03 0.0135 OH Kepala Tukang 130,000.00 140,000.00 1,755.00 1,890.00
L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00
B Bahan 32,291.67 47,791.67
1.20 m' Pipa PVC Ø 3" 20,833.33 30,833.33 25,000.00 37,000.00
0.35 Ls Perlengkapan 35% x pipa 20,833.33 30,833.33 7,291.67 10,791.67
C PERALATAN
D Jumlah A + B + C 57,226.67 75,061.67
E Overhead & Profit (contoh 10%) 10% 5,722.67 7,506.17
F Harga Satuan Pekerjaan (D+E) 62,949.33 82,567.83

27 A.5.1.1.32 1 m' Pemasangan Pipa PVC tipe AW Ø 4" 88,946.00 92,931.67


A Tenaga 11,110.00 12,150.00
L.01 0.036 OH Pekerja 80,000.00 90,000.00 2,880.00 3,240.00
L.02 0.060 OH Tukang Batu 120,000.00 130,000.00 7,200.00 7,800.00
L.03 0.006 OH Kepala Tukang 130,000.00 140,000.00 780.00 840.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan 69,750.00 72,333.33
1.20 m' Pipa PVC Ø 4" 45,000.00 46,666.67 54,000.00 56,000.00
0.35 Ls Perlengkapan 35% x pipa 45,000.00 46,666.67 15,750.00 16,333.33
C PERALATAN
D Jumlah A + B + C 80,860.00 84,483.33
E Overhead & Profit (contoh 10%) 10% 8,086.00 8,448.33
F Harga Satuan Pekerjaan (D+E) 88,946.00 92,931.67

28 A.5.1.1.33 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 82,054.50 91,256.00
cm
A Tenaga 12,220.00 13,500.00
L.01 0.080 OH Pekerja 80,000.00 90,000.00 6,400.00 7,200.00
L.02 0.040 OH Tukang Batu 120,000.00 130,000.00 4,800.00 5,200.00
L.03 0.004 OH Kepala Tukang 130,000.00 140,000.00 520.00 560.00
L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00
B Bahan 62,375.00 69,460.00
1.60 bh pipa tanah 10,000.00 12,000.00 16,000.00 19,200.00
35.00 kg Semen Portlan 1,125.00 1,200.00 39,375.00 42,000.00
0.014 m3 Pasir Pasang 340,000.00 370,000.00 4,760.00 5,180.00
0.014 m3 Pasir Urug 160,000.00 220,000.00 2,240.00 3,080.00
- -

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/123 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 74,595.00 82,960.00
E Overhead & Profit (contoh 10%) 10% 7,459.50 8,296.00
F Harga Satuan Pekerjaan (D+E) 82,054.50 91,256.00

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15


29 A.5.1.1.34 1 m' 39,374.50 44,786.50
cm
A Tenaga 9,165.00 10,125.00
L.01 0.060 OH Pekerja 80,000.00 90,000.00 4,800.00 5,400.00
L.02 0.030 OH Tukang Batu 120,000.00 130,000.00 3,600.00 3,900.00
L.03 0.003 OH Kepala Tukang 130,000.00 140,000.00 390.00 420.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 26,630.00 30,590.00
1.60 bh pipa tanah 8,000.00 9,500.00 12,800.00 15,200.00
6.80 kg Semen Portlan 1,125.00 1,200.00 7,650.00 8,160.00
0.013 m3 Pasir Pasang 340,000.00 370,000.00 4,420.00 4,810.00
0.011 m3 Pasir Urug 160,000.00 220,000.00 1,760.00 2,420.00
,
C PERALATAN
D Jumlah A + B + C 35,795.00 40,715.00
E Overhead & Profit (contoh 10%) 10% 3,579.50 4,071.50
F Harga Satuan Pekerjaan (D+E) 39,374.50 44,786.50

30 A.5.1.1.35 1 m' Pemasangan Pipa Beton Ø 15 - 20 cm 117,727.50 134,740.65


A Tenaga 21,385.00 23,625.00
L.01 0.140 OH Pekerja 80,000.00 90,000.00 11,200.00 12,600.00
L.02 0.070 OH Tukang Batu 120,000.00 130,000.00 8,400.00 9,100.00
L.03 0.007 OH Kepala Tukang 130,000.00 140,000.00 910.00 980.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
B Bahan 85,640.00 98,866.50
1.10 bh pipa beton 42,000.00 50,000.00 46,200.00 55,000.00
0.027 m3 Batu Bata 450,000.00 487,500.00 12,150.00 13,162.50
3.920 kg Semen Portlan 1,125.00 1,200.00 4,410.00 4,704.00
0.056 m3 Pasir Pasang 340,000.00 370,000.00 19,040.00 20,720.00
0.024 m3 Pasir Urug 160,000.00 220,000.00 3,840.00 5,280.00
C PERALATAN
D Jumlah A + B + C 107,025.00 122,491.50
E Overhead & Profit (contoh 10%) 10% 10,702.50 12,249.15
F Harga Satuan Pekerjaan (D+E) 117,727.50 134,740.65

31 A.5.1.1.36 1 m' Pemasangan Pipa Beton Ø 30 - 100 cm 589,459.75 633,798.00


A Tenaga 58,045.00 64,125.00
L.01 0.380 OH Pekerja 80,000.00 90,000.00 30,400.00 34,200.00
L.02 0.190 OH Tukang Batu 120,000.00 130,000.00 22,800.00 24,700.00
L.03 0.019 OH Kepala Tukang 130,000.00 140,000.00 2,470.00 2,660.00
L.04 0.019 OH Mandor 125,000.00 135,000.00 2,375.00 2,565.00
B Bahan 477,827.50 512,055.00
1.10 bh pipa beton 180,000.00 190,000.00 198,000.00 209,000.00
0.55 m3 Batu Bata 450,000.00 487,500.00 247,500.00 268,125.00
10.300 kg Semen Portlan 1,125.00 1,200.00 11,587.50 12,360.00
0.061 m3 Pasir Pasang 340,000.00 370,000.00 20,740.00 22,570.00
0.069 m3 Pasir Urug 160,000.00 220,000.00 11,040.00 15,180.00
C PERALATAN
D Jumlah A + B + C 535,872.50 576,180.00
E Overhead & Profit (contoh 10%) 10% 53,587.25 57,618.00
F Harga Satuan Pekerjaan (D+E) 589,459.75 633,798.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/124 14-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XV A.8.4.6 HARGA SATUAN PEKERJAAN ELEKTRIKAL

1 A.8.4.6.1 1 Titik Pemasangan Lampu 385,880.00 431,508.00


A Tenaga 175,400.00 196,140.00
100 % Pekerja 175,400.00 196,140.00 175,400.00 196,140.00

Bahan 175,400.00 196,140.00


3.00 btg Pipa Listrik 5/8" **) 4,000.00 4,200.00 12,000.00 12,600.00
24.00 m Kabel **) 5,500.00 6,200.00 132,000.00 148,800.00
3.00 buah T.Dus 500.00 600.00 1,500.00 1,800.00
4.00 buah L.Bow 500.00 600.00 2,000.00 2,400.00
3.00 buah Las Dop 500.00 600.00 1,500.00 1,800.00
24.00 buah Klem 50.00 60.00 1,200.00 1,440.00
1.00 buah Mongkok 1,200.00 1,300.00 1,200.00 1,300.00
1.00 buah Saklar 12,000.00 13,000.00 12,000.00 13,000.00

1.00 buah Pitting 12,000.00 13,000.00 12,000.00 13,000.00

C PERALATAN
D Jumlah A + B + C 350,800.00 392,280.00
E Overhead & Profit (contoh 10%) 10% 35,080.00 39,228.00
F Harga Satuan Pekerjaan (D+E) 385,880.00 431,508.00
Overhead & Profit (contoh 10%)
2 A.8.4.6.2 1 buah Pemasangan MCB 488,840.00 536,448.00
A Tenaga 222,200.00 243,840.00
L.01 100 % Pekerja 222,200.00 243,840.00 222,200.00 243,840.00

B Bahan 222,200.00 243,840.00


3 Kg Pipa Listrik 5/8" **) 4,000.00 4,200.00 12,000.00 12,600.00
15 m Kabel **) 5,500.00 6,200.00 82,500.00 93,000.00
1 buah T.Dus 500.00 600.00 500.00 600.00
2 buah L.Bow 500.00 600.00 1,000.00 1,200.00
24 buah Klem 50.00 60.00 1,200.00 1,440.00
1 buah MCB 125,000.00 135,000.00 125,000.00 135,000.00
C PERALATAN
D Jumlah A + B + C 444,400.00 487,680.00
E Overhead & Profit (contoh 10%) 10% 44,440.00 48,768.00
F Harga Satuan Pekerjaan (D+E) 488,840.00 536,448.00

file:///conversion/tmp/activity_task_scratch/668638447.xls 177/125 15-20


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
HARGA SATUAN PEKERJAAN PEMASANGAN
XVI A.8.4.1
PIPA
1 A.8.4.1.1 1 m' Pemasangan Pipa PVC Ø 63 mm 15,755.30 18,167.60
A Tenaga 8,013.00 8,944.00
L.01 0.081 OH Pekerja 80,000.00 90,000.00 6,480.00 7,290.00
L.02 0.0041 OH Tukang Pipa 130,000.00 140,000.00 533.00 574.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00
B Bahan 6,250.00 7,500.00
1 m' Pipa PVC Ø 63 mm 6,250.00 7,500.00 6,250.00 7,500.00
C PERALATAN 60.00 72.00
0.006 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 60.00 72.00
D Jumlah A + B + C 14,323.00 16,516.00
E Overhead & Profit (contoh 10%) 10% 1,432.30 1,651.60
F Harga Satuan Pekerjaan (D+E) 15,755.30 18,167.60

2 A.8.4.1.2 1 m' Pemasangan Pipa PVC Ø 90 mm 24,568.50 27,611.10


A Tenaga 14,755.00 16,255.00
L.01 0.094 OH Pekerja 80,000.00 90,000.00 7,520.00 8,460.00
L.02 0.047 OH Tukang Pipa 130,000.00 140,000.00 6,110.00 6,580.00
L.04 0.009 OH Mandor 125,000.00 135,000.00 1,125.00 1,215.00
B Bahan 7,500.00 8,750.00
1 m' Pipa PVC Ø 90 mm 7,500.00 8,750.00 7,500.00 8,750.00
C PERALATAN 80.00 96.00
0.008 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 80.00 96.00
D Jumlah A + B + C 22,335.00 25,101.00
E Overhead & Profit (contoh 10%) 10% 2,233.50 2,510.10
F Harga Satuan Pekerjaan (D+E) 24,568.50 27,611.10

3 A.8.4.1.3 1 m' Pemasangan Pipa PVC Ø 110 mm 28,616.50 34,622.50


A Tenaga 16,665.00 18,355.00
L.01 0.105 OH Pekerja 80,000.00 90,000.00 8,400.00 9,450.00
L.02 0.053 OH Tukang Pipa 130,000.00 140,000.00 6,890.00 7,420.00
L.04 0.011 OH Mandor 125,000.00 135,000.00 1,375.00 1,485.00
B Bahan 9,250.00 13,000.00
1 m' Pipa PVC Ø 110 mm 9,250.00 13,000.00 9,250.00 13,000.00
C PERALATAN 100.00 120.00
0.01 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 100.00 120.00
D Jumlah A + B + C 26,015.00 31,475.00
E Overhead & Profit (contoh 10%) 10% 2,601.50 3,147.50
F Harga Satuan Pekerjaan (D+E) 28,616.50 34,622.50

4 A.8.4.1.4 1 m' Pemasangan Pipa PVC Ø 150 mm 33,253.00 41,408.40


A Tenaga 18,610.00 20,500.00
L.01 0.118 OH Pekerja 80,000.00 90,000.00 9,440.00 10,620.00
L.02 0.059 OH Tukang Pipa 130,000.00 140,000.00 7,670.00 8,260.00
L.04 0.012 OH Mandor 125,000.00 135,000.00 1,500.00 1,620.00
B Bahan 11,500.00 17,000.00
1 m' Pipa PVC Ø 150 mm 11,500.00 17,000.00 11,500.00 17,000.00
C PERALATAN 120.00 144.00
0.012 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 120.00 144.00
D Jumlah A + B + C 30,230.00 37,644.00
E Overhead & Profit (contoh 10%) 10% 3,023.00 3,764.40
F Harga Satuan Pekerjaan (D+E) 33,253.00 41,408.40

5 A.8.4.1.5 1 m' Pemasangan Pipa PVC Ø 200 mm 49,593.50 65,354.30


A Tenaga 29,845.00 32,875.00
L.01 0.189 OH Pekerja 80,000.00 90,000.00 15,120.00 17,010.00
L.02 0.095 OH Tukang Pipa 130,000.00 140,000.00 12,350.00 13,300.00
L.04 0.019 OH Mandor 125,000.00 135,000.00 2,375.00 2,565.00
B Bahan 15,000.00 26,250.00
1 m' Pipa PVC Ø 200 mm 15,000.00 26,250.00 15,000.00 26,250.00
C PERALATAN 240.00 288.00
0.024 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 240.00 288.00
D Jumlah A + B + C 45,085.00 59,413.00
E Overhead & Profit (contoh 10%) 10% 4,508.50 5,941.30
F Harga Satuan Pekerjaan (D+E) 49,593.50 65,354.30

6 A.8.4.1.6 1 m' Pemasangan Pipa PVC Ø 250 mm 66,781.00 100,240.80


A Tenaga 40,370.00 44,470.00
L.01 0.256 OH Pekerja 80,000.00 90,000.00 20,480.00 23,040.00
L.02 0.128 OH Tukang Pipa 130,000.00 140,000.00 16,640.00 17,920.00
L.04 0.026 OH Mandor 125,000.00 135,000.00 3,250.00 3,510.00
B Bahan 20,000.00 46,250.00
1 m' Pipa PVC Ø 250 mm 20,000.00 46,250.00 20,000.00 46,250.00
C PERALATAN 340.00 408.00
0.034 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 340.00 408.00
D Jumlah A + B + C 60,710.00 91,128.00
E Overhead & Profit (contoh 10%) 10% 6,071.00 9,112.80
F Harga Satuan Pekerjaan (D+E) 66,781.00 100,240.80

7 A.8.4.1.7 1 m' Pemasangan Pipa PVC Ø 300 mm 100,820.50 133,578.50


A Tenaga 46,255.00 50,955.00
L.01 0.294 OH Pekerja 80,000.00 90,000.00 23,520.00 26,460.00
L.02 0.147 OH Tukang Pipa 130,000.00 140,000.00 19,110.00 20,580.00
L.04 0.029 OH Mandor 125,000.00 135,000.00 3,625.00 3,915.00
B Bahan 45,000.00 70,000.00
1 m' Pipa PVC Ø 300 mm 45,000.00 70,000.00 45,000.00 70,000.00
C PERALATAN 400.00 480.00
0.040 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 400.00 480.00
D Jumlah A + B + C 91,655.00 121,435.00
E Overhead & Profit (contoh 10%) 10% 9,165.50 12,143.50
F Harga Satuan Pekerjaan (D+E) 100,820.50 133,578.50

8 A.8.4.1.8 1 m' Pemasangan Pipa PVC Ø 400 mm 191,323.00 256,069.00


A Tenaga 85,630.00 94,330.00
L.01 0.544 OH Pekerja 80,000.00 90,000.00 43,520.00 48,960.00
L.02 0.272 OH Tukang Pipa 130,000.00 140,000.00 35,360.00 38,080.00
L.04 0.054 OH Mandor 125,000.00 135,000.00 6,750.00 7,290.00
B Bahan 87,500.00 137,500.00
1 m' Pipa PVC Ø 400 mm 87,500.00 137,500.00 87,500.00 137,500.00
C PERALATAN 800.00 960.00
0.080 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 800.00 960.00
D Jumlah A + B + C 173,930.00 232,790.00
E Overhead & Profit (contoh 10%) 10% 17,393.00 23,279.00
F Harga Satuan Pekerjaan (D+E) 191,323.00 256,069.00

9 A.8.4.1.9 1 m' Pemasangan Pipa PVC Ø 450 mm 364,589.50 417,840.50


A Tenaga 105,445.00 116,155.00
L.01 0.669 OH Pekerja 80,000.00 90,000.00 53,520.00 60,210.00
L.02 0.335 OH Tukang Pipa 130,000.00 140,000.00 43,550.00 46,900.00
L.04 0.067 OH Mandor 125,000.00 135,000.00 8,375.00 9,045.00
B Bahan 225,000.00 262,500.00
1 m' Pipa PVC Ø 450 mm 225,000.00 262,500.00 225,000.00 262,500.00
C PERALATAN 1,000.00 1,200.00
0.100 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,000.00 1,200.00
D Jumlah A + B + C 331,445.00 379,855.00
E Overhead & Profit (contoh 10%) 10% 33,144.50 37,985.50
F Harga Satuan Pekerjaan (D+E) 364,589.50 417,840.50

10 A.8.4.1.10 1 m' Pemasangan Pipa PVC Ø 500 mm 449,586.50 469,599.90


A Tenaga 127,495.00 140,445.00
L.01 0.809 OH Pekerja 80,000.00 90,000.00 64,720.00 72,810.00
L.02 0.405 OH Tukang Pipa 130,000.00 140,000.00 52,650.00 56,700.00
L.04 0.081 OH Mandor 125,000.00 135,000.00 10,125.00 10,935.00
B Bahan 280,000.00 285,000.00
1 m' Pipa PVC Ø 500 mm 280,000.00 285,000.00 280,000.00 285,000.00
C PERALATAN 1,220.00 1,464.00
0.122 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,220.00 1,464.00
D Jumlah A + B + C 408,715.00 426,909.00
E Overhead & Profit (contoh 10%) 10% 40,871.50 42,690.90
F Harga Satuan Pekerjaan (D+E) 449,586.50 469,599.90

11 A.8.4.1.11 1 m' Pemasangan Pipa PVC Ø 600 mm 524,579.00 563,717.00


A Tenaga 150,440.00 165,730.00
L.01 0.957 OH Pekerja 80,000.00 90,000.00 76,560.00 86,130.00
L.02 0.476 OH Tukang Pipa 130,000.00 140,000.00 61,880.00 66,640.00
L.04 0.096 OH Mandor 125,000.00 135,000.00 12,000.00 12,960.00
B Bahan 325,000.00 345,000.00
1 m' Pipa PVC Ø 600 mm 325,000.00 345,000.00 325,000.00 345,000.00
C PERALATAN 1,450.00 1,740.00
0.145 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,450.00 1,740.00
D Jumlah A + B + C 476,890.00 512,470.00
E Overhead & Profit (contoh 10%) 10% 47,689.00 51,247.00
F Harga Satuan Pekerjaan (D+E) 524,579.00 563,717.00

12 A.8.4.1.12 1 m' Pemasangan Pipa PVC Ø 800 mm 750,596.00 807,125.00


A Tenaga 254,860.00 280,750.00
L.01 1.618 OH Pekerja 80,000.00 90,000.00 129,440.00 145,620.00
L.02 0.809 OH Tukang Pipa 130,000.00 140,000.00 105,170.00 113,260.00
L.04 0.162 OH Mandor 125,000.00 135,000.00 20,250.00 21,870.00
B Bahan 425,000.00 450,000.00
1 m' Pipa PVC Ø 800 mm 425,000.00 450,000.00 425,000.00 450,000.00
C PERALATAN 2,500.00 3,000.00
0.250 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,500.00 3,000.00
D Jumlah A + B + C 682,360.00 733,750.00
E Overhead & Profit (contoh 10%) 10% 68,236.00 73,375.00
F Harga Satuan Pekerjaan (D+E) 750,596.00 807,125.00

13 A.8.4.1.13 1 m' Pemasangan Pipa PVC Ø 900 mm 983,405.50 1,041,247.90


A Tenaga 266,385.00 293,445.00
L.01 1.691 OH Pekerja 80,000.00 90,000.00 135,280.00 152,190.00
L.02 0.846 OH Tukang Pipa 130,000.00 140,000.00 109,980.00 118,440.00
L.04 0.169 OH Mandor 125,000.00 135,000.00 21,125.00 22,815.00
B Bahan 625,000.00 650,000.00
1 m' Pipa PVC Ø 900 mm 625,000.00 650,000.00 625,000.00 650,000.00
C PERALATAN 2,620.00 3,144.00
0.262 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,620.00 3,144.00
D Jumlah A + B + C 894,005.00 946,589.00
E Overhead & Profit (contoh 10%) 10% 89,400.50 94,658.90
F Harga Satuan Pekerjaan (D+E) 983,405.50 1,041,247.90

14 A.8.4.1.14 1 m' Pemasangan Pipa PVC Ø 1.000 mm 1,134,683.00 1,190,692.80


A Tenaga 298,590.00 328,920.00
L.01 1.895 OH Pekerja 80,000.00 90,000.00 151,600.00 170,550.00
L.02 0.948 OH Tukang Pipa 130,000.00 140,000.00 123,240.00 132,720.00
L.04 0.190 OH Mandor 125,000.00 135,000.00 23,750.00 25,650.00
B Bahan 730,000.00 750,000.00
1 m' Pipa PVC Ø 1.000 mm 730,000.00 750,000.00 730,000.00 750,000.00
C PERALATAN 2,940.00 3,528.00
0.294 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,940.00 3,528.00
D Jumlah A + B + C 1,031,530.00 1,082,448.00
E Overhead & Profit (contoh 10%) 10% 103,153.00 108,244.80
F Harga Satuan Pekerjaan (D+E) 1,134,683.00 1,190,692.80

15 A.8.4.1.15 1 m' Pemasangan Pipa PVC Ø 1.100 mm 1,247,334.00 1,340,002.40


A Tenaga 330,670.00 364,260.00
L.01 2.099 OH Pekerja 80,000.00 90,000.00 167,920.00 188,910.00
L.02 1.050 OH Tukang Pipa 130,000.00 140,000.00 136,500.00 147,000.00
L.04 0.210 OH Mandor 125,000.00 135,000.00 26,250.00 28,350.00
B Bahan 800,000.00 850,000.00
1 m' Pipa PVC Ø 1.100 mm 800,000.00 850,000.00 800,000.00 850,000.00
C PERALATAN 3,270.00 3,924.00
0.327 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,270.00 3,924.00
D Jumlah A + B + C 1,133,940.00 1,218,184.00
E Overhead & Profit (contoh 10%) 10% 113,394.00 121,818.40
F Harga Satuan Pekerjaan (D+E) 1,247,334.00 1,340,002.40

16 A.8.4.1.16 1 m' Pemasangan Pipa PVC Ø 1.200 mm 1,337,974.00 1,434,298.80


A Tenaga 362,750.00 399,600.00
L.01 2.303 OH Pekerja 80,000.00 90,000.00 184,240.00 207,270.00
L.02 1.152 OH Tukang Pipa 130,000.00 140,000.00 149,760.00 161,280.00
L.04 0.230 OH Mandor 125,000.00 135,000.00 28,750.00 31,050.00
B Bahan 850,000.00 900,000.00
1 m' Pipa PVC Ø 1.200 mm 850,000.00 900,000.00 850,000.00 900,000.00
C PERALATAN 3,590.00 4,308.00
0.359 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,590.00 4,308.00
D Jumlah A + B + C 1,216,340.00 1,303,908.00
E Overhead & Profit (contoh 10%) 10% 121,634.00 130,390.80
F Harga Satuan Pekerjaan (D+E) 1,337,974.00 1,434,298.80

17 A.8.4.1.17 1 m' Pemasangan Pipa HDPE Ø 63 mm 33,632.50 39,779.30


A Tenaga 5,385.00 5,935.00
L.01 0.035 OH Pekerja 80,000.00 90,000.00 2,800.00 3,150.00
L.02 0.017 OH Tukang Pipa 130,000.00 140,000.00 2,210.00 2,380.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan 25,000.00 30,000.00
1 m' Pipa HDPE Ø 63 mm 25,000.00 30,000.00 25,000.00 30,000.00
C PERALATAN 190.00 228.00
0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00
D Jumlah A + B + C 30,575.00 36,163.00
E Overhead & Profit (contoh 10%) 10% 3,057.50 3,616.30
F Harga Satuan Pekerjaan (D+E) 33,632.50 39,779.30

18 A.8.4.1.18 1 m' Pemasangan Pipa HDPE Ø 100 mm 45,639.00 51,884.80


A Tenaga 6,300.00 6,940.00
L.01 0.040 OH Pekerja 80,000.00 90,000.00 3,200.00 3,600.00
L.02 0.020 OH Tukang Pipa 130,000.00 140,000.00 2,600.00 2,800.00
L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00
B Bahan 35,000.00 40,000.00
1 m' Pipa HDPE Ø 100 mm 35,000.00 40,000.00 35,000.00 40,000.00
C PERALATAN 190.00 228.00
0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00
D Jumlah A + B + C 41,490.00 47,168.00
E Overhead & Profit (contoh 10%) 10% 4,149.00 4,716.80
F Harga Satuan Pekerjaan (D+E) 45,639.00 51,884.80

19 A.8.4.1.19 1 m' Pemasangan Pipa HDPE Ø 125 mm 57,645.50 63,990.30


A Tenaga 7,215.00 7,945.00
L.01 0.045 OH Pekerja 80,000.00 90,000.00 3,600.00 4,050.00
L.02 0.023 OH Tukang Pipa 130,000.00 140,000.00 2,990.00 3,220.00
L.04 0.005 OH Mandor 125,000.00 135,000.00 625.00 675.00
B Bahan 45,000.00 50,000.00
1 m' Pipa HDPE Ø 125 mm 45,000.00 50,000.00 45,000.00 50,000.00
C PERALATAN 190.00 228.00
0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00
D Jumlah A + B + C 52,405.00 58,173.00
E Overhead & Profit (contoh 10%) 10% 5,240.50 5,817.30
F Harga Satuan Pekerjaan (D+E) 57,645.50 63,990.30

20 A.8.4.1.20 1 m' Pemasangan Pipa HDPE Ø 150 mm 82,423.00 89,053.80


A Tenaga 9,740.00 10,730.00
L.01 0.062 OH Pekerja 80,000.00 90,000.00 4,960.00 5,580.00
L.02 0.031 OH Tukang Pipa 130,000.00 140,000.00 4,030.00 4,340.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00
B Bahan 65,000.00 70,000.00
1 m' Pipa HDPE Ø 150 mm 65,000.00 70,000.00 65,000.00 70,000.00
C PERALATAN 190.00 228.00
0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00
D Jumlah A + B + C 74,930.00 80,958.00
E Overhead & Profit (contoh 10%) 10% 7,493.00 8,095.80
F Harga Satuan Pekerjaan (D+E) 82,423.00 89,053.80

21 A.8.4.1.21 1 m' Pemasangan Pipa HDPE Ø 200 mm 138,853.00 151,687.80


A Tenaga 16,040.00 17,670.00
L.01 0.102 OH Pekerja 80,000.00 90,000.00 8,160.00 9,180.00
L.02 0.051 OH Tukang Pipa 130,000.00 140,000.00 6,630.00 7,140.00
L.04 0.010 OH Mandor 125,000.00 135,000.00 1,250.00 1,350.00
B Bahan 110,000.00 120,000.00
1 m' Pipa HDPE Ø 200 mm 110,000.00 120,000.00 110,000.00 120,000.00
C PERALATAN 190.00 228.00
0.019 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 190.00 228.00
D Jumlah A + B + C 126,230.00 137,898.00
E Overhead & Profit (contoh 10%) 10% 12,623.00 13,789.80
F Harga Satuan Pekerjaan (D+E) 138,853.00 151,687.80

22 A.8.4.1.22 1 m' Pemasangan Pipa HDPE Ø 250 mm 172,034.50 179,969.90


A Tenaga 20,975.00 23,105.00
L.01 0.133 OH Pekerja 80,000.00 90,000.00 10,640.00 11,970.00
L.02 0.067 OH Tukang Pipa 130,000.00 140,000.00 8,710.00 9,380.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00
B Bahan 135,000.00 140,000.00
1 m' Pipa HDPE Ø 250 mm 135,000.00 140,000.00 135,000.00 140,000.00
C PERALATAN 420.00 504.00
0.042 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 420.00 504.00
D Jumlah A + B + C 156,395.00 163,609.00
E Overhead & Profit (contoh 10%) 10% 15,639.50 16,360.90
F Harga Satuan Pekerjaan (D+E) 172,034.50 179,969.90

23 A.8.4.1.23 1 m' Pemasangan Pipa HDPE Ø 300 mm 206,167.50 220,302.50


A Tenaga 26,775.00 29,495.00
L.01 0.170 OH Pekerja 80,000.00 90,000.00 13,600.00 15,300.00
L.02 0.085 OH Tukang Pipa 130,000.00 140,000.00 11,050.00 11,900.00
L.04 0.017 OH Mandor 125,000.00 135,000.00 2,125.00 2,295.00
B Bahan 160,000.00 170,000.00
1 m' Pipa HDPE Ø 300 mm 160,000.00 170,000.00 160,000.00 170,000.00
C PERALATAN 650.00 780.00
0.065 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 650.00 780.00
D Jumlah A + B + C 187,425.00 200,275.00
E Overhead & Profit (contoh 10%) 10% 18,742.50 20,027.50
F Harga Satuan Pekerjaan (D+E) 206,167.50 220,302.50

24 A.8.4.1.24 1 m' Pemasangan Pipa HDPE Ø 400 mm 271,914.50 288,352.90


A Tenaga 45,675.00 50,315.00
L.01 0.290 OH Pekerja 80,000.00 90,000.00 23,200.00 26,100.00
L.02 0.145 OH Tukang Pipa 130,000.00 140,000.00 18,850.00 20,300.00
L.04 0.029 OH Mandor 125,000.00 135,000.00 3,625.00 3,915.00
B Bahan 200,000.00 210,000.00
1 m' Pipa HDPE Ø 400 mm 200,000.00 210,000.00 200,000.00 210,000.00
C PERALATAN 1,520.00 1,824.00
0.152 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,520.00 1,824.00
D Jumlah A + B + C 247,195.00 262,139.00
E Overhead & Profit (contoh 10%) 10% 24,719.50 26,213.90
F Harga Satuan Pekerjaan (D+E) 271,914.50 288,352.90

25 A.8.4.1.25 1 m' Pemasangan Pipa HDPE Ø 450 mm 328,482.00 346,247.00


A Tenaga 56,620.00 62,370.00
L.01 0.359 OH Pekerja 80,000.00 90,000.00 28,720.00 32,310.00
L.02 0.180 OH Tukang Pipa 130,000.00 140,000.00 23,400.00 25,200.00
L.04 0.036 OH Mandor 125,000.00 135,000.00 4,500.00 4,860.00
B Bahan 240,000.00 250,000.00
1 m' Pipa HDPE Ø 450 mm 240,000.00 250,000.00 240,000.00 250,000.00
C PERALATAN 2,000.00 2,400.00
0.200 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,000.00 2,400.00
D Jumlah A + B + C 298,620.00 314,770.00
E Overhead & Profit (contoh 10%) 10% 29,862.00 31,477.00
F Harga Satuan Pekerjaan (D+E) 328,482.00 346,247.00

26 A.8.4.1.26 1 m' Pemasangan Pipa HDPE Ø 500 mm 407,665.50 437,829.70


A Tenaga 68,095.00 75,015.00
L.01 0.433 OH Pekerja 80,000.00 90,000.00 34,640.00 38,970.00
L.02 0.216 OH Tukang Pipa 130,000.00 140,000.00 28,080.00 30,240.00
L.04 0.043 OH Mandor 125,000.00 135,000.00 5,375.00 5,805.00

B Bahan 300,000.00 320,000.00


1 m' Pipa HDPE Ø 500 mm 300,000.00 320,000.00 300,000.00 320,000.00

C PERALATAN 2,510.00 3,012.00


0.251 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,510.00 3,012.00

D Jumlah A + B + C 370,605.00 398,027.00


E Overhead & Profit (contoh 10%) 10% 37,060.50 39,802.70
F Harga Satuan Pekerjaan (D+E) 407,665.50 437,829.70

27 A.8.4.1.27 1 m' Pemasangan Pipa HDPE Ø 600 mm 565,053.50 596,737.90


A Tenaga 80,615.00 88,805.00
L.01 0.512 OH Pekerja 80,000.00 90,000.00 40,960.00 46,080.00
L.02 0.256 OH Tukang Pipa 130,000.00 140,000.00 33,280.00 35,840.00
L.04 0.051 OH Mandor 125,000.00 135,000.00 6,375.00 6,885.00

B Bahan 430,000.00 450,000.00


1 m' Pipa HDPE Ø 600 mm 430,000.00 450,000.00 430,000.00 450,000.00

C PERALATAN 3,070.00 3,684.00


0.307 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,070.00 3,684.00

D Jumlah A + B + C 513,685.00 542,489.00


E Overhead & Profit (contoh 10%) 10% 51,368.50 54,248.90
F Harga Satuan Pekerjaan (D+E) 565,053.50 596,737.90

28 A.8.4.1.28 1 m' Pemasangan Pipa HDPE Ø 800 mm 875,902.50 920,371.10


A Tenaga 140,545.00 154,825.00
L.01 0.893 OH Pekerja 80,000.00 90,000.00 71,440.00 80,370.00
L.02 0.446 OH Tukang Pipa 130,000.00 140,000.00 57,980.00 62,440.00
L.04 0.089 OH Mandor 125,000.00 135,000.00 11,125.00 12,015.00

B Bahan 650,000.00 675,000.00


1 m' Pipa HDPE Ø 800 mm 650,000.00 675,000.00 650,000.00 675,000.00

C PERALATAN 5,730.00 6,876.00


0.573 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,730.00 6,876.00

D Jumlah A + B + C 796,275.00 836,701.00


E Overhead & Profit (contoh 10%) 10% 79,627.50 83,670.10
F Harga Satuan Pekerjaan (D+E) 875,902.50 920,371.10

29 A.8.4.1.29 1 m' Pemasangan Pipa HDPE Ø 900 mm 1,069,150.50 1,149,908.10


A Tenaga 213,125.00 234,775.00
L.01 1.353 OH Pekerja 80,000.00 90,000.00 108,240.00 121,770.00
L.02 0.677 OH Tukang Pipa 130,000.00 140,000.00 88,010.00 94,780.00
L.04 0.135 OH Mandor 125,000.00 135,000.00 16,875.00 18,225.00

B Bahan 750,000.00 800,000.00


1 m' Pipa HDPE Ø 900 mm 750,000.00 800,000.00 750,000.00 800,000.00
C PERALATAN 8,830.00 10,596.00
0.883 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 8,830.00 10,596.00

D Jumlah A + B + C 971,955.00 1,045,371.00


E Overhead & Profit (contoh 10%) 10% 97,195.50 104,537.10
F Harga Satuan Pekerjaan (D+E) 1,069,150.50 1,149,908.10

30 A.8.4.1.30 1 m' Pemasangan Pipa HDPE Ø 1.000 mm 1,289,530.00 1,348,639.60


A 261,370.00 287,920.00
L.01 1.659 OH Pekerja 80,000.00 90,000.00 132,720.00 149,310.00
L.02 0.830 OH Tukang Pipa 130,000.00 140,000.00 107,900.00 116,200.00
L.04 0.166 OH Mandor 125,000.00 135,000.00 20,750.00 22,410.00

B Bahan 900,000.00 925,000.00


1 m' Pipa HDPE Ø 1.000 mm 900,000.00 925,000.00 900,000.00 925,000.00

C PERALATAN 10,930.00 13,116.00


1.093 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,930.00 13,116.00

D Jumlah A + B + C 1,172,300.00 1,226,036.00


E Overhead & Profit (contoh 10%) 10% 117,230.00 122,603.60
F Harga Satuan Pekerjaan (D+E) 1,289,530.00 1,348,639.60

31 A.8.4.1.31 1 m' Pemasangan Pipa HDPE Ø 1.100 mm 1,428,251.00 1,517,901.00


A Tenaga 286,360.00 315,450.00
L.01 1.818 OH Pekerja 80,000.00 90,000.00 145,440.00 163,620.00
L.02 0.909 OH Tukang Pipa 130,000.00 140,000.00 118,170.00 127,260.00
L.04 0.182 OH Mandor 125,000.00 135,000.00 22,750.00 24,570.00

B Bahan 1,000,000.00 1,050,000.00


1 m' Pipa HDPE Ø 1.100 mm 1,000,000.00 1,050,000.00 1,000,000.00 1,050,000.00

C PERALATAN 12,050.00 14,460.00


1.205 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 12,050.00 14,460.00

D Jumlah A + B + C 1,298,410.00 1,379,910.00


E Overhead & Profit (contoh 10%) 10% 129,841.00 137,991.00
F Harga Satuan Pekerjaan (D+E) 1,428,251.00 1,517,901.00

32 A.8.4.1.32 1 m' Pemasangan Pipa HDPE Ø 1.200 mm 1,638,026.50 1,738,223.30


A Tenaga 373,275.00 411,195.00
L.01 2.370 OH Pekerja 80,000.00 90,000.00 189,600.00 213,300.00
L.02 1.185 OH Tukang Pipa 130,000.00 140,000.00 154,050.00 165,900.00
L.04 0.237 OH Mandor 125,000.00 135,000.00 29,625.00 31,995.00

B Bahan 1,100,000.00 1,150,000.00


1 m' Pipa HDPE Ø 1.200 mm 1,100,000.00 1,150,000.00 1,100,000.00 1,150,000.00
C PERALATAN 15,840.00 19,008.00
1.584 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 15,840.00 19,008.00
D Jumlah A + B + C 1,489,115.00 1,580,203.00
E Overhead & Profit (contoh 10%) 10% 148,911.50 158,020.30
F Harga Satuan Pekerjaan (D+E) 1,638,026.50 1,738,223.30

33 A.8.4.1.33 1 m' Pemasangan Pipa GIP Ø 63 mm 76,131.00 84,942.00


A Tenaga 54,210.00 59,720.00
L.01 0.345 OH Pekerja 80,000.00 90,000.00 27,600.00 31,050.00
L.02 0.172 OH Tukang Pipa 130,000.00 140,000.00 22,360.00 24,080.00
L.04 0.034 OH Mandor 125,000.00 135,000.00 4,250.00 4,590.00
B Bahan 15,000.00 17,500.00
1 m' Pipa GIP Ø 63 mm 15,000.00 17,500.00 15,000.00 17,500.00
C PERALATAN - -

hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
D Jumlah A + B + C 69,210.00 77,220.00
E Overhead & Profit (contoh 10%) 10% 6,921.00 7,722.00
F Harga Satuan Pekerjaan (D+E) 76,131.00 84,942.00
34 A.8.4.1.34 1 m' Pemasangan Pipa GIP Ø 100 mm 90,383.33 103,840.00
A Tenaga 63,000.00 69,400.00
L.01 0.400 OH Pekerja 80,000.00 90,000.00 32,000.00 36,000.00
L.02 0.200 OH Tukang Pipa 130,000.00 140,000.00 26,000.00 28,000.00
L.04 0.040 OH Mandor 125,000.00 135,000.00 5,000.00 5,400.00

B Bahan 19,166.67 25,000.00


1 m' Pipa GIP Ø 100 mm 19,166.67 25,000.00 19,166.67 25,000.00

C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -

D Jumlah A + B + C 82,166.67 94,400.00


E Overhead & Profit (contoh 10%) 10% 8,216.67 9,440.00
F Harga Satuan Pekerjaan (D+E) 90,383.33 103,840.00

35 A.8.4.1.35 1 m' Pemasangan Pipa GIP Ø 125 mm 102,393.50 118,530.50


A Tenaga 70,585.00 77,755.00
L.01 0.448 OH Pekerja 80,000.00 90,000.00 35,840.00 40,320.00
L.02 0.224 OH Tukang Pipa 130,000.00 140,000.00 29,120.00 31,360.00
L.04 0.045 OH Mandor 125,000.00 135,000.00 5,625.00 6,075.00

B Bahan 22,500.00 30,000.00


1 m' Pipa GIP Ø 125 mm 22,500.00 30,000.00 22,500.00 30,000.00

C PERALATAN
D Jumlah A + B + C 93,085.00 107,755.00
E Overhead & Profit (contoh 10%) 10% 9,308.50 10,775.50
F Harga Satuan Pekerjaan (D+E) 102,393.50 118,530.50

36 A.8.4.1.36 1 m' Pemasangan Pipa GIP Ø 150 mm 118,886.17 136,962.83


A Tenaga 79,745.00 87,845.00
L.01 0.506 OH Pekerja 80,000.00 90,000.00 40,480.00 45,540.00
L.02 0.253 OH Tukang Pipa 130,000.00 140,000.00 32,890.00 35,420.00
L.04 0.051 OH Mandor 125,000.00 135,000.00 6,375.00 6,885.00

B Bahan 28,333.33 36,666.67


1 m' Pipa GIP Ø 150 mm 28,333.33 36,666.67 28,333.33 36,666.67

C PERALATAN
D Jumlah A + B + C 108,078.33 124,511.67
E Overhead & Profit (contoh 10%) 10% 10,807.83 12,451.17
F Harga Satuan Pekerjaan (D+E) 118,886.17 136,962.83

37 A.8.4.1.37 1 m' Pemasangan Pipa GIP Ø 200 mm 179,212.00 205,142.67


A Tenaga 125,420.00 138,160.00
L.01 0.796 OH Pekerja 80,000.00 90,000.00 63,680.00 71,640.00
L.02 0.398 OH Tukang Pipa 130,000.00 140,000.00 51,740.00 55,720.00
L.04 0.080 OH Mandor 125,000.00 135,000.00 10,000.00 10,800.00

B Bahan 37,500.00 48,333.33


1 m' Pipa GIP Ø 200 mm 37,500.00 48,333.33 37,500.00 48,333.33

C PERALATAN
D Jumlah A + B + C 162,920.00 186,493.33
E Overhead & Profit (contoh 10%) 10% 16,292.00 18,649.33
F Harga Satuan Pekerjaan (D+E) 179,212.00 205,142.67

38 A.8.4.1.38 1 m' Pemasangan Pipa GIP Ø 250 mm 213,999.50 245,375.17


A Tenaga 149,545.00 164,735.00
L.01 0.949 OH Pekerja 80,000.00 90,000.00 75,920.00 85,410.00
L.02 0.475 OH Tukang Pipa 130,000.00 140,000.00 61,750.00 66,500.00
L.04 0.095 OH Mandor 125,000.00 135,000.00 11,875.00 12,825.00
B Bahan 45,000.00 58,333.33
1 m' Pipa GIP Ø 250 mm 45,000.00 58,333.33 45,000.00 58,333.33

C PERALATAN
D Jumlah A + B + C 194,545.00 223,068.33
E Overhead & Profit (contoh 10%) 10% 19,454.50 22,306.83
F Harga Satuan Pekerjaan (D+E) 213,999.50 245,375.17

39 A.8.4.1.39 1 m' Pemasangan Pipa GIP Ø 300 mm 243,001.00 272,697.33


A Tenaga 150,910.00 166,240.00
L.01 0.958 OH Pekerja 80,000.00 90,000.00 76,640.00 86,220.00
L.02 0.479 OH Tukang Pipa 130,000.00 140,000.00 62,270.00 67,060.00
L.04 0.096 OH Mandor 125,000.00 135,000.00 12,000.00 12,960.00

B Bahan 70,000.00 81,666.67


1 m' Pipa GIP Ø 300 mm 70,000.00 81,666.67 70,000.00 81,666.67

C PERALATAN
D Jumlah A + B + C 220,910.00 247,906.67
E Overhead & Profit (contoh 10%) 10% 22,091.00 24,790.67
F Harga Satuan Pekerjaan (D+E) 243,001.00 272,697.33

40 A.8.4.1.40 1 m' Pemasangan Pipa GIP Ø 400 mm 312,618.17 337,613.83


A Tenaga 190,865.00 210,255.00
L.01 1.212 OH Pekerja 80,000.00 90,000.00 96,960.00 109,080.00
L.02 0.606 OH Tukang Pipa 130,000.00 140,000.00 78,780.00 84,840.00
L.04 0.121 OH Mandor 125,000.00 135,000.00 15,125.00 16,335.00

B Bahan 93,333.33 96,666.67


1 m' Pipa GIP Ø 400 mm 93,333.33 96,666.67 93,333.33 96,666.67

C PERALATAN
D Jumlah A + B + C 284,198.33 306,921.67
E Overhead & Profit (contoh 10%) 10% 28,419.83 30,692.17
F Harga Satuan Pekerjaan (D+E) 312,618.17 337,613.83

41 A.8.4.1.41 1 m' Pemasangan Pipa GIP Ø 450 mm 355,294.50 390,098.50


A Tenaga 212,995.00 234,635.00
L.01 1.353 OH Pekerja 80,000.00 90,000.00 108,240.00 121,770.00
L.02 0.676 OH Tukang Pipa 130,000.00 140,000.00 87,880.00 94,640.00
L.04 0.135 OH Mandor 125,000.00 135,000.00 16,875.00 18,225.00

B Bahan 110,000.00 120,000.00


1 m' Pipa GIP Ø 450 mm 110,000.00 120,000.00 110,000.00 120,000.00

C PERALATAN
D Jumlah A + B + C 322,995.00 354,635.00
E Overhead & Profit (contoh 10%) 10% 32,299.50 35,463.50
F Harga Satuan Pekerjaan (D+E) 355,294.50 390,098.50

42 A.8.4.1.42 1 m' Pemasangan Pipa GIP Ø 500 mm 408,589.50 445,450.50


A Tenaga 231,445.00 254,955.00
L.01 1.469 OH Pekerja 80,000.00 90,000.00 117,520.00 132,210.00
L.02 0.735 OH Tukang Pipa 130,000.00 140,000.00 95,550.00 102,900.00
L.04 0.147 OH Mandor 125,000.00 135,000.00 18,375.00 19,845.00

B Bahan 140,000.00 150,000.00


1 m' Pipa GIP Ø 500 mm 140,000.00 150,000.00 140,000.00 150,000.00

C PERALATAN
D Jumlah A + B + C 371,445.00 404,955.00
E Overhead & Profit (contoh 10%) 10% 37,144.50 40,495.50
F Harga Satuan Pekerjaan (D+E) 408,589.50 445,450.50
43 A.8.4.1.43 1 m' Pemasangan Pipa GIP Ø 600 mm 406,015.50 440,379.50
A Tenaga 209,105.00 230,345.00
L.01 1.327 OH Pekerja 80,000.00 90,000.00 106,160.00 119,430.00
L.02 0.664 OH Tukang Pipa 130,000.00 140,000.00 86,320.00 92,960.00
L.04 0.133 OH Mandor 125,000.00 135,000.00 16,625.00 17,955.00

B Bahan 160,000.00 170,000.00


1 m' Pipa GIP Ø 600 mm 160,000.00 170,000.00 160,000.00 170,000.00

C PERALATAN
D Jumlah A + B + C 369,105.00 400,345.00
E Overhead & Profit (contoh 10%) 10% 36,910.50 40,034.50
F Harga Satuan Pekerjaan (D+E) 406,015.50 440,379.50

44 A.8.4.1.44 1 m' Pemasangan Pipa GIP Ø 800 mm 623,122.50 675,075.50


A Tenaga 366,475.00 403,705.00
L.01 2.327 OH Pekerja 80,000.00 90,000.00 186,160.00 209,430.00
L.02 1.163 OH Tukang Pipa 130,000.00 140,000.00 151,190.00 162,820.00
L.04 0.233 OH Mandor 125,000.00 135,000.00 29,125.00 31,455.00

B Bahan 200,000.00 210,000.00


1 m' Pipa GIP Ø 800 mm 200,000.00 210,000.00 200,000.00 210,000.00

C PERALATAN
D Jumlah A + B + C 566,475.00 613,705.00
E Overhead & Profit (contoh 10%) 10% 56,647.50 61,370.50
F Harga Satuan Pekerjaan (D+E) 623,122.50 675,075.50

45 A.8.4.1.45 1 m' Pemasangan Pipa GIP Ø 900 mm 707,465.00 775,632.00


A Tenaga 413,150.00 455,120.00
L.01 2.623 OH Pekerja 80,000.00 90,000.00 209,840.00 236,070.00
L.02 1.312 OH Tukang Pipa 130,000.00 140,000.00 170,560.00 183,680.00
L.04 0.262 OH Mandor 125,000.00 135,000.00 32,750.00 35,370.00

B Bahan 230,000.00 250,000.00


1 m' Pipa GIP Ø 900 mm 230,000.00 250,000.00 230,000.00 250,000.00

C PERALATAN
D Jumlah A + B + C 643,150.00 705,120.00
E Overhead & Profit (contoh 10%) 10% 64,315.00 70,512.00
F Harga Satuan Pekerjaan (D+E) 707,465.00 775,632.00

46 A.8.4.1.46 1 m' Pemasangan Pipa GIP Ø 1.000 mm 790,388.50 852,626.50


A Tenaga 458,535.00 505,115.00
L.01 2.911 OH Pekerja 80,000.00 90,000.00 232,880.00 261,990.00
L.02 1.456 OH Tukang Pipa 130,000.00 140,000.00 189,280.00 203,840.00
L.04 0.291 OH Mandor 125,000.00 135,000.00 36,375.00 39,285.00
B Bahan 260,000.00 270,000.00
1 m' Pipa GIP Ø 1.000 mm 260,000.00 270,000.00 260,000.00 270,000.00
C PERALATAN
D Jumlah A + B + C 718,535.00 775,115.00
E Overhead & Profit (contoh 10%) 10% 71,853.50 77,511.50
F Harga Satuan Pekerjaan (D+E) 790,388.50 852,626.50

47 A.8.4.1.47 1 m' Pemasangan Pipa GIP Ø 1.100 mm 862,400.00 929,720.00


A Tenaga 504,000.00 555,200.00
L.01 3.200 OH Pekerja 80,000.00 90,000.00 256,000.00 288,000.00
L.02 1.600 OH Tukang Pipa 130,000.00 140,000.00 208,000.00 224,000.00
L.04 0.320 OH Mandor 125,000.00 135,000.00 40,000.00 43,200.00
B Bahan 280,000.00 290,000.00
1 m' Pipa GIP Ø 1.100 mm 280,000.00 290,000.00 280,000.00 290,000.00
C PERALATAN
D Jumlah A + B + C 784,000.00 845,200.00
E Overhead & Profit (contoh 10%) 10% 78,400.00 84,520.00
F Harga Satuan Pekerjaan (D+E) 862,400.00 929,720.00
48 A.8.4.1.48 1 m' Pemasangan Pipa GIP Ø 1.200 mm 945,323.50 1,017,714.50
A Tenaga 549,385.00 605,195.00
L.01 3.488 OH Pekerja 80,000.00 90,000.00 279,040.00 313,920.00
L.02 1.744 OH Tukang Pipa 130,000.00 140,000.00 226,720.00 244,160.00
L.04 0.349 OH Mandor 125,000.00 135,000.00 43,625.00 47,115.00

B Bahan 310,000.00 320,000.00


1 m' Pipa GIP Ø 1.200 mm 310,000.00 320,000.00 310,000.00 320,000.00
C PERALATAN
D Jumlah A + B + C 859,385.00 925,195.00
E Overhead & Profit (contoh 10%) 10% 85,938.50 92,519.50
F Harga Satuan Pekerjaan (D+E) 945,323.50 1,017,714.50

49 A.8.4.1.49 1 m' Pemasangan Pipa DCI Ø 100 mm 91,701.50 104,281.10


A Tenaga 57,985.00 64,345.00
L.01 0.489 OH Pekerja 80,000.00 90,000.00 39,120.00 44,010.00
L.02 0.098 OH Tukang Pipa 130,000.00 140,000.00 12,740.00 13,720.00
L.04 0.049 OH Mandor 125,000.00 135,000.00 6,125.00 6,615.00
B Bahan 25,000.00 30,000.00
1 m' Pipa DCI Ø 100 mm 25,000.00 30,000.00 25,000.00 30,000.00
C PERALATAN 380.00 456.00
0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00
D Jumlah A + B + C 83,365.00 94,801.00
E Overhead & Profit (contoh 10%) 10% 8,336.50 9,480.10
F Harga Satuan Pekerjaan (D+E) 91,701.50 104,281.10

50 A.8.4.1.50 1 m' Pemasangan Pipa DCI Ø 125 mm 115,703.50 129,108.10


A Tenaga 64,805.00 71,915.00
L.01 0.547 OH Pekerja 80,000.00 90,000.00 43,760.00 49,230.00
L.02 0.109 OH Tukang Pipa 130,000.00 140,000.00 14,170.00 15,260.00
L.04 0.055 OH Mandor 125,000.00 135,000.00 6,875.00 7,425.00
B Bahan 40,000.00 45,000.00
1 m' Pipa DCI Ø 125 mm 40,000.00 45,000.00 40,000.00 45,000.00
C PERALATAN 380.00 456.00
0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00
D Jumlah A + B + C 105,185.00 117,371.00
E Overhead & Profit (contoh 10%) 10% 10,518.50 11,737.10
F Harga Satuan Pekerjaan (D+E) 115,703.50 129,108.10

51 A.8.4.1.51 1 m' Pemasangan Pipa DCI Ø 150 mm 146,338.50 166,189.10


A Tenaga 72,655.00 80,625.00
L.01 0.613 OH Pekerja 80,000.00 90,000.00 49,040.00 55,170.00
L.02 0.123 OH Tukang Pipa 130,000.00 140,000.00 15,990.00 17,220.00
L.04 0.061 OH Mandor 125,000.00 135,000.00 7,625.00 8,235.00
B Bahan 60,000.00 70,000.00
1 m' Pipa DCI Ø 150 mm 60,000.00 70,000.00 60,000.00 70,000.00
C PERALATAN 380.00 456.00
0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00
D Jumlah A + B + C 133,035.00 151,081.00
E Overhead & Profit (contoh 10%) 10% 13,303.50 15,108.10
F Harga Satuan Pekerjaan (D+E) 146,338.50 166,189.10

52 A.8.4.1.52 1 m' Pemasangan Pipa DCI Ø 200 mm 199,798.50 223,103.10


A Tenaga 101,255.00 112,365.00
L.01 0.855 OH Pekerja 80,000.00 90,000.00 68,400.00 76,950.00
L.02 0.171 OH Tukang Pipa 130,000.00 140,000.00 22,230.00 23,940.00
L.04 0.085 OH Mandor 125,000.00 135,000.00 10,625.00 11,475.00
B Bahan 80,000.00 90,000.00
1 m' Pipa DCI Ø 200 mm 80,000.00 90,000.00 80,000.00 90,000.00
C PERALATAN 380.00 456.00
0.038 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 380.00 456.00
D Jumlah A + B + C 181,635.00 202,821.00
E Overhead & Profit (contoh 10%) 10% 18,163.50 20,282.10
F Harga Satuan Pekerjaan (D+E) 199,798.50 223,103.10
53 A.8.4.1.53 1 m' Pemasangan Pipa DCI Ø 250 mm 234,470.50 259,176.50
A Tenaga 112,655.00 125,015.00
L.01 0.951 OH Pekerja 80,000.00 90,000.00 76,080.00 85,590.00
L.02 0.190 OH Tukang Pipa 130,000.00 140,000.00 24,700.00 26,600.00
L.04 0.095 OH Mandor 125,000.00 135,000.00 11,875.00 12,825.00

B Bahan 100,000.00 110,000.00


1 m' Pipa DCI Ø 250 mm 100,000.00 110,000.00 100,000.00 110,000.00

C PERALATAN 500.00 600.00


0.050 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 500.00 600.00

D Jumlah A + B + C 213,155.00 235,615.00


E Overhead & Profit (contoh 10%) 10% 21,315.50 23,561.50
F Harga Satuan Pekerjaan (D+E) 234,470.50 259,176.50

54 A.8.4.1.54 1 m' Pemasangan Pipa DCI Ø 300 mm 259,627.50 284,698.70


A Tenaga 115,315.00 127,965.00
L.01 0.973 OH Pekerja 80,000.00 90,000.00 77,840.00 87,570.00
L.02 0.195 OH Tukang Pipa 130,000.00 140,000.00 25,350.00 27,300.00
L.04 0.097 OH Mandor 125,000.00 135,000.00 12,125.00 13,095.00

B Bahan 120,000.00 130,000.00


1 m' Pipa DCI Ø 300 mm 120,000.00 130,000.00 120,000.00 130,000.00

C PERALATAN 710.00 852.00


0.071 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 710.00 852.00

D Jumlah A + B + C 236,025.00 258,817.00


E Overhead & Profit (contoh 10%) 10% 23,602.50 25,881.70
F Harga Satuan Pekerjaan (D+E) 259,627.50 284,698.70

55 A.8.4.1.55 1 m' Pemasangan Pipa DCI Ø 400 mm 391,253.50 426,070.70


A Tenaga 197,900.00 219,375.00
L.01 1.545 OH Pekerja 80,000.00 90,000.00 123,600.00 139,050.00
L.02 0.309 OH Tukang Pipa 130,000.00 140,000.00 40,170.00 43,260.00
L.08 0.093 OH Operator Alat Berat 160,000.00 175,000.00 14,880.00 16,275.00
L.04 0.154 OH Mandor 125,000.00 135,000.00 19,250.00 20,790.00
B Bahan 150,000.00 160,000.00
1 m' Pipa DCI Ø 400 mm 150,000.00 160,000.00 150,000.00 160,000.00

C PERALATAN 7,785.00 7,962.00


0.023 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 7,475.00 7,590.00
0.031 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 310.00 372.00
D Jumlah A + B + C 355,685.00 387,337.00
E Overhead & Profit (contoh 10%) 10% 35,568.50 38,733.70
F Harga Satuan Pekerjaan (D+E) 391,253.50 426,070.70

56 A.8.4.1.56 1 m' Pemasangan Pipa DCI Ø 450 mm 459,305.00 493,336.80


A Tenaga 237,735.00 263,450.00
L.01 1.813 OH Pekerja 80,000.00 90,000.00 145,040.00 163,170.00
L.02 0.363 OH Tukang Pipa 130,000.00 140,000.00 47,190.00 50,820.00
L.08 0.143 OH Operator Alat Berat 160,000.00 175,000.00 22,880.00 25,025.00
L.04 0.181 OH Mandor 125,000.00 135,000.00 22,625.00 24,435.00
B Bahan 170,000.00 175,000.00
1 m' Pipa DCI Ø 450 mm 170,000.00 175,000.00 170,000.00 175,000.00

C PERALATAN 9,815.00 10,038.00


0.029 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 9,425.00 9,570.00
0.039 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 390.00 468.00
D Jumlah A + B + C 417,550.00 448,488.00
E Overhead & Profit (contoh 10%) 10% 41,755.00 44,848.80
F Harga Satuan Pekerjaan (D+E) 459,305.00 493,336.80
57 A.8.4.1.57 1 m' Pemasangan Pipa DCI Ø 500 mm 522,428.50 566,170.00
A Tenaga 273,435.00 302,940.00
L.01 2.047 OH Pekerja 80,000.00 90,000.00 163,760.00 184,230.00
L.02 0.409 OH Tukang Pipa 130,000.00 140,000.00 53,170.00 57,260.00
L.08 0.193 OH Operator Alat Berat 160,000.00 175,000.00 30,880.00 33,775.00
L.04 0.205 OH Mandor 125,000.00 135,000.00 25,625.00 27,675.00
B Bahan 190,000.00 200,000.00
1 m' Pipa DCI Ø 500 mm 190,000.00 200,000.00 190,000.00 200,000.00

C PERALATAN 11,500.00 11,760.00


0.034 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 11,050.00 11,220.00
0.045 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 450.00 540.00
D Jumlah A + B + C 474,935.00 514,700.00
E Overhead & Profit (contoh 10%) 10% 47,493.50 51,470.00
F Harga Satuan Pekerjaan (D+E) 522,428.50 566,170.00

58 A.8.4.1.58 1 m' Pemasangan Pipa DCI Ø 600 mm 582,741.50 644,318.40


A Tenaga 285,145.00 315,680.00
L.01 2.011 OH Pekerja 80,000.00 90,000.00 160,880.00 180,990.00
L.02 0.402 OH Tukang Pipa 130,000.00 140,000.00 52,260.00 56,280.00
L.08 0.293 OH Operator Alat Berat 160,000.00 175,000.00 46,880.00 51,275.00
L.04 0.201 OH Mandor 125,000.00 135,000.00 25,125.00 27,135.00
B Bahan 225,000.00 250,000.00
1 m' Pipa DCI Ø 600 mm 225,000.00 250,000.00 225,000.00 250,000.00

C PERALATAN 19,620.00 20,064.00


0.058 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 18,850.00 19,140.00
0.077 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 770.00 924.00
D Jumlah A + B + C 529,765.00 585,744.00
E Overhead & Profit (contoh 10%) 10% 52,976.50 58,574.40
F Harga Satuan Pekerjaan (D+E) 582,741.50 644,318.40

59 A.8.4.1.59 1 m' Pemasangan Pipa DCI Ø 800 mm 897,336.00 978,114.50


A Tenaga 536,210.00 593,775.00
L.01 3.859 OH Pekerja 80,000.00 90,000.00 308,720.00 347,310.00
L.02 0.772 OH Tukang Pipa 130,000.00 140,000.00 100,360.00 108,080.00
L.08 0.493 OH Operator Alat Berat 160,000.00 175,000.00 78,880.00 86,275.00
L.04 0.386 OH Mandor 125,000.00 135,000.00 48,250.00 52,110.00
B Bahan 250,000.00 265,000.00
1 m' Pipa DCI Ø 800 mm 250,000.00 265,000.00 250,000.00 265,000.00

C PERALATAN 29,550.00 30,420.00


0.084 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 27,300.00 27,720.00
0.225 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 2,250.00 2,700.00
D Jumlah A + B + C 815,760.00 889,195.00
E Overhead & Profit (contoh 10%) 10% 81,576.00 88,919.50
F Harga Satuan Pekerjaan (D+E) 897,336.00 978,114.50

60 A.8.4.1.60 1 m' Pemasangan Pipa DCI Ø 900 mm 1,066,373.00 1,165,137.60


A Tenaga 686,725.00 760,550.00
L.01 4.995 OH Pekerja 80,000.00 90,000.00 399,600.00 449,550.00
L.02 0.999 OH Tukang Pipa 130,000.00 140,000.00 129,870.00 139,860.00
L.08 0.593 OH Operator Alat Berat 160,000.00 175,000.00 94,880.00 103,775.00
L.04 0.499 OH Mandor 125,000.00 135,000.00 62,375.00 67,365.00
B Bahan 250,000.00 265,000.00
1 m' Pipa DCI Ø 900 mm 250,000.00 265,000.00 250,000.00 265,000.00

C PERALATAN 32,705.00 33,666.00


0.093 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 30,225.00 30,690.00
0.248 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 2,480.00 2,976.00
D Jumlah A + B + C 969,430.00 1,059,216.00
E Overhead & Profit (contoh 10%) 10% 96,943.00 105,921.60
F Harga Satuan Pekerjaan (D+E) 1,066,373.00 1,165,137.60
61 A.8.4.1.61 1 m' Pemasangan Pipa DCI Ø 1.000 mm 1,277,699.50 1,388,965.60
A Tenaga 842,165.00 932,160.00
L.01 5.931 OH Pekerja 80,000.00 90,000.00 474,480.00 533,790.00
L.02 1.186 OH Tukang Pipa 130,000.00 140,000.00 154,180.00 166,040.00
L.08 0.793 OH Operator Alat Berat 160,000.00 175,000.00 126,880.00 138,775.00
L.04 0.693 OH Mandor 125,000.00 135,000.00 86,625.00 93,555.00
B Bahan 280,000.00 290,000.00
1 m' Pipa DCI Ø 1.000 mm 280,000.00 290,000.00 280,000.00 290,000.00

C PERALATAN 39,380.00 40,536.00


0.112 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 36,400.00 36,960.00
0.298 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 2,980.00 3,576.00
D Jumlah A + B + C 1,161,545.00 1,262,696.00
E Overhead & Profit (contoh 10%) 10% 116,154.50 126,269.60
F Harga Satuan Pekerjaan (D+E) 1,277,699.50 1,388,965.60

62 A.8.4.1.62 1 m' Pemasangan Pipa DCI Ø 1.100 mm 1,433,096.50 1,569,059.80


A Tenaga 950,375.00 1,052,610.00
L.01 6.949 OH Pekerja 80,000.00 90,000.00 555,920.00 625,410.00
L.02 1.390 OH Tukang Pipa 130,000.00 140,000.00 180,700.00 194,600.00
L.08 0.793 OH Operator Alat Berat 160,000.00 175,000.00 126,880.00 138,775.00
L.04 0.695 OH Mandor 125,000.00 135,000.00 86,875.00 93,825.00
B Bahan 300,000.00 320,000.00
1 m' Pipa DCI Ø 1.100 mm 300,000.00 320,000.00 300,000.00 320,000.00

C PERALATAN 52,440.00 53,808.00


0.152 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 49,400.00 50,160.00
0.304 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,040.00 3,648.00
D Jumlah A + B + C 1,302,815.00 1,426,418.00
E Overhead & Profit (contoh 10%) 10% 130,281.50 142,641.80
F Harga Satuan Pekerjaan (D+E) 1,433,096.50 1,569,059.80

63 A.8.4.1.63 1 m' Pemasangan Pipa DCI Ø 1.200 mm 1,627,604.00 1,781,323.50


A Tenaga 1,097,540.00 1,215,665.00
L.01 8.056 OH Pekerja 80,000.00 90,000.00 644,480.00 725,040.00
L.02 1.611 OH Tukang Pipa 130,000.00 140,000.00 209,430.00 225,540.00
L.08 0.893 OH Operator Alat Berat 160,000.00 175,000.00 142,880.00 156,275.00
L.04 0.806 OH Mandor 125,000.00 135,000.00 100,750.00 108,810.00
B Bahan 320,000.00 340,000.00
1 m' Pipa DCI Ø 1.200 mm 320,000.00 340,000.00 320,000.00 340,000.00

C PERALATAN 62,100.00 63,720.00


0.180 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 58,500.00 59,400.00
0.360 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,600.00 4,320.00
D Jumlah A + B + C 1,479,640.00 1,619,385.00
E Overhead & Profit (contoh 10%) 10% 147,964.00 161,938.50
F Harga Satuan Pekerjaan (D+E) 1,627,604.00 1,781,323.50

64 A.8.4.1.64 1 m' Pemasangan Baja PVC Ø 63 mm 78,331.00 86,578.80


A Tenaga 59,170.00 65,660.00
L.01 0.499 OH Pekerja 80,000.00 90,000.00 39,920.00 44,910.00
L.02 0.100 OH Tukang Pipa 130,000.00 140,000.00 13,000.00 14,000.00
L.04 0.050 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00

B Bahan 12,000.00 13,000.00


1 m' Pipa Baja Ø 63 mm 12,000.00 13,000.00 12,000.00 13,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 71,210.00 78,708.00


E Overhead & Profit (contoh 10%) 10% 7,121.00 7,870.80
F Harga Satuan Pekerjaan (D+E) 78,331.00 86,578.80
65 A.8.4.1.65 1 m' Pemasangan Pipa Baja Ø 100 mm 89,309.00 100,350.80
A Tenaga 68,650.00 76,180.00
L.01 0.579 OH Pekerja 80,000.00 90,000.00 46,320.00 52,110.00
L.02 0.116 OH Tukang Pipa 130,000.00 140,000.00 15,080.00 16,240.00
L.04 0.058 OH Mandor 125,000.00 135,000.00 7,250.00 7,830.00

B Bahan 12,500.00 15,000.00


1 m' Pipa Baja Ø 100 mm 12,500.00 15,000.00 12,500.00 15,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 81,190.00 91,228.00


E Overhead & Profit (contoh 10%) 10% 8,119.00 9,122.80
F Harga Satuan Pekerjaan (D+E) 89,309.00 100,350.80

66 A.8.4.1.66 1 m' Pemasangan Pipa Baja Ø 125 mm 101,095.50 112,577.30


A Tenaga 76,865.00 85,295.00
L.01 0.648 OH Pekerja 80,000.00 90,000.00 51,840.00 58,320.00
L.02 0.130 OH Tukang Pipa 130,000.00 140,000.00 16,900.00 18,200.00
L.04 0.065 OH Mandor 125,000.00 135,000.00 8,125.00 8,775.00

B Bahan 15,000.00 17,000.00


1 m' Pipa Baja Ø 125 mm 15,000.00 17,000.00 15,000.00 17,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 91,905.00 102,343.00


E Overhead & Profit (contoh 10%) 10% 9,190.50 10,234.30
F Harga Satuan Pekerjaan (D+E) 101,095.50 112,577.30

67 A.8.4.1.67 1 m' Pemasangan Pipa Baja Ø 150 mm 114,416.50 130,056.30


A Tenaga 83,975.00 93,185.00
L.01 0.708 OH Pekerja 80,000.00 90,000.00 56,640.00 63,720.00
L.02 0.142 OH Tukang Pipa 130,000.00 140,000.00 18,460.00 19,880.00
L.04 0.071 OH Mandor 125,000.00 135,000.00 8,875.00 9,585.00

B Bahan 20,000.00 25,000.00


1 m' Pipa Baja Ø 150 mm 20,000.00 25,000.00 20,000.00 25,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 104,015.00 118,233.00


E Overhead & Profit (contoh 10%) 10% 10,401.50 11,823.30
F Harga Satuan Pekerjaan (D+E) 114,416.50 130,056.30

68 A.8.4.1.68 1 m' Pemasangan Pipa Baja Ø 200 mm 178,139.50 199,565.30


A Tenaga 131,905.00 146,375.00
L.01 1.113 OH Pekerja 80,000.00 90,000.00 89,040.00 100,170.00
L.02 0.223 OH Tukang Pipa 130,000.00 140,000.00 28,990.00 31,220.00
L.04 0.111 OH Mandor 125,000.00 135,000.00 13,875.00 14,985.00

B Bahan 30,000.00 35,000.00


1 m' Pipa Baja Ø 200 mm 30,000.00 35,000.00 30,000.00 35,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 161,945.00 181,423.00


E Overhead & Profit (contoh 10%) 10% 16,194.50 18,142.30
F Harga Satuan Pekerjaan (D+E) 178,139.50 199,565.30
69 A.8.4.1.69 1 m' Pemasangan Pipa Baja Ø 250 mm 227,826.50 257,788.30
A Tenaga 157,075.00 174,305.00
L.01 1.325 OH Pekerja 80,000.00 90,000.00 106,000.00 119,250.00
L.02 0.265 OH Tukang Pipa 130,000.00 140,000.00 34,450.00 37,100.00
L.04 0.133 OH Mandor 125,000.00 135,000.00 16,625.00 17,955.00

B Bahan 50,000.00 60,000.00


1 m' Pipa Baja Ø 250 mm 50,000.00 60,000.00 50,000.00 60,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 207,115.00 234,353.00


E Overhead & Profit (contoh 10%) 10% 20,711.50 23,435.30
F Harga Satuan Pekerjaan (D+E) 227,826.50 257,788.30

70 A.8.4.1.70 1 m' Pemasangan Pipa Baja Ø 300 mm 261,420.50 287,158.30


A Tenaga 167,615.00 186,005.00
L.01 1.415 OH Pekerja 80,000.00 90,000.00 113,200.00 127,350.00
L.02 0.283 OH Tukang Pipa 130,000.00 140,000.00 36,790.00 39,620.00
L.04 0.141 OH Mandor 125,000.00 135,000.00 17,625.00 19,035.00

B Bahan 70,000.00 75,000.00


1 m' Pipa Baja Ø 300 mm 70,000.00 75,000.00 70,000.00 75,000.00

C PERALATAN 40.00 48.00


0.004 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 40.00 48.00

D Jumlah A + B + C 237,655.00 261,053.00


E Overhead & Profit (contoh 10%) 10% 23,765.50 26,105.30
F Harga Satuan Pekerjaan (D+E) 261,420.50 287,158.30

71 A.8.4.1.71 1 m' Pemasangan Pipa Baja Ø 400 mm 394,350.00 431,984.30


A Tenaga 264,335.00 293,335.00
L.01 2.231 OH Pekerja 80,000.00 90,000.00 178,480.00 200,790.00
L.02 0.446 OH Tukang Pipa 130,000.00 140,000.00 57,980.00 62,440.00
L.04 0.223 OH Mandor 125,000.00 135,000.00 27,875.00 30,105.00

B Bahan 85,000.00 90,000.00


1 m' Pipa Baja Ø 400 mm 85,000.00 90,000.00 85,000.00 90,000.00

C PERALATAN 9,165.00 9,378.00


0.027 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 8,775.00 8,910.00
0.039 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 390.00 468.00
D Jumlah A + B + C 358,500.00 392,713.00
E Overhead & Profit (contoh 10%) 10% 35,850.00 39,271.30
F Harga Satuan Pekerjaan (D+E) 394,350.00 431,984.30

72 A.8.4.1.72 1 m' Pemasangan Pipa Baja Ø 450 mm 410,470.50 453,594.90


A Tenaga 264,335.00 293,335.00
L.01 2.231 OH Pekerja 80,000.00 90,000.00 178,480.00 200,790.00
L.02 0.446 OH Tukang Pipa 130,000.00 140,000.00 57,980.00 62,440.00
L.04 0.223 OH Mandor 125,000.00 135,000.00 27,875.00 30,105.00

B Bahan 100,000.00 110,000.00


1 m' Pipa Baja Ø 450 mm 100,000.00 110,000.00 100,000.00 110,000.00

C PERALATAN 8,820.00 9,024.00


0.026 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 8,450.00 8,580.00
0.037 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 370.00 444.00
D Jumlah A + B + C 373,155.00 412,359.00
E Overhead & Profit (contoh 10%) 10% 37,315.50 41,235.90
F Harga Satuan Pekerjaan (D+E) 410,470.50 453,594.90
73 A.8.4.1.73 1 m' Pemasangan Pipa Baja Ø 500 mm 465,289.00 527,818.50
A Tenaga 288,115.00 319,725.00
L.01 2.432 OH Pekerja 80,000.00 90,000.00 194,560.00 218,880.00
L.02 0.486 OH Tukang Pipa 130,000.00 140,000.00 63,180.00 68,040.00
L.04 0.243 OH Mandor 125,000.00 135,000.00 30,375.00 32,805.00

B Bahan 125,000.00 150,000.00


1 m' Pipa Baja Ø 500 mm 125,000.00 150,000.00 125,000.00 150,000.00

C PERALATAN 9,875.00 10,110.00


0.029 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 9,425.00 9,570.00
0.045 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 450.00 540.00
D Jumlah A + B + C 422,990.00 479,835.00
E Overhead & Profit (contoh 10%) 10% 42,299.00 47,983.50
F Harga Satuan Pekerjaan (D+E) 465,289.00 527,818.50

74 A.8.4.1.74 1 m' Pemasangan Pipa Baja Ø 600 mm 495,979.00 549,794.30


A Tenaga 261,725.00 290,435.00
L.01 2.208 OH Pekerja 80,000.00 90,000.00 176,640.00 198,720.00
L.02 0.442 OH Tukang Pipa 130,000.00 140,000.00 57,460.00 61,880.00
L.04 0.221 OH Mandor 125,000.00 135,000.00 27,625.00 29,835.00

B Bahan 180,000.00 200,000.00


1 m' Pipa Baja Ø 600 mm 180,000.00 200,000.00 180,000.00 200,000.00

C PERALATAN 9,165.00 9,378.00


0.027 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 8,775.00 8,910.00
0.039 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 390.00 468.00
D Jumlah A + B + C 450,890.00 499,813.00
E Overhead & Profit (contoh 10%) 10% 45,089.00 49,981.30
F Harga Satuan Pekerjaan (D+E) 495,979.00 549,794.30

75 A.8.4.1.75 1 m' Pemasangan Pipa Baja Ø 800 mm 800,481.00 884,175.60


A Tenaga 461,780.00 512,440.00
L.01 3.897 OH Pekerja 80,000.00 90,000.00 311,760.00 350,730.00
L.02 0.779 OH Tukang Pipa 130,000.00 140,000.00 101,270.00 109,060.00
L.04 0.390 OH Mandor 125,000.00 135,000.00 48,750.00 52,650.00

B Bahan 250,000.00 275,000.00


1 m' Pipa Baja Ø 800 mm 250,000.00 275,000.00 250,000.00 275,000.00

C PERALATAN 15,930.00 16,356.00


0.046 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 14,950.00 15,180.00
0.098 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 980.00 1,176.00
D Jumlah A + B + C 727,710.00 803,796.00
E Overhead & Profit (contoh 10%) 10% 72,771.00 80,379.60
F Harga Satuan Pekerjaan (D+E) 800,481.00 884,175.60

76 A.8.4.1.76 1 m' Pemasangan Pipa Baja Ø 900 mm 913,649.00 998,371.00


A Tenaga 512,540.00 569,070.00
L.01 4.403 OH Pekerja 80,000.00 90,000.00 352,240.00 396,270.00
L.02 0.810 OH Tukang Pipa 130,000.00 140,000.00 105,300.00 113,400.00
L.04 0.440 OH Mandor 125,000.00 135,000.00 55,000.00 59,400.00

B Bahan 300,000.00 320,000.00


1 m' Pipa Baja Ø 900 mm 300,000.00 320,000.00 300,000.00 320,000.00

C PERALATAN 18,050.00 18,540.00


0.052 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 16,900.00 17,160.00
0.115 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,150.00 1,380.00
D Jumlah A + B + C 830,590.00 907,610.00
E Overhead & Profit (contoh 10%) 10% 83,059.00 90,761.00
F Harga Satuan Pekerjaan (D+E) 913,649.00 998,371.00
77 A.8.4.1.77 1 m' Pemasangan Pipa Baja Ø 1.000 mm 1,045,192.50 1,143,297.10
A Tenaga 579,995.00 643,625.00
L.01 4.895 OH Pekerja 80,000.00 90,000.00 391,600.00 440,550.00
L.02 0.979 OH Tukang Pipa 130,000.00 140,000.00 127,270.00 137,060.00
L.04 0.489 OH Mandor 125,000.00 135,000.00 61,125.00 66,015.00

B Bahan 350,000.00 375,000.00


1 m' Pipa Baja Ø 1.000 mm 350,000.00 375,000.00 350,000.00 375,000.00

C PERALATAN 20,180.00 20,736.00


0.058 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 18,850.00 19,140.00
0.133 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,330.00 1,596.00
D Jumlah A + B + C 950,175.00 1,039,361.00
E Overhead & Profit (contoh 10%) 10% 95,017.50 103,936.10
F Harga Satuan Pekerjaan (D+E) 1,045,192.50 1,143,297.10

78 A.8.4.1.78 1 m' Pemasangan Pipa Baja Ø 1.100 mm 1,166,709.50 1,271,924.50


A Tenaga 638,345.00 708,375.00
L.01 5.387 OH Pekerja 80,000.00 90,000.00 430,960.00 484,830.00
L.02 1.077 OH Tukang Pipa 130,000.00 140,000.00 140,010.00 150,780.00
L.04 0.539 OH Mandor 125,000.00 135,000.00 67,375.00 72,765.00

B Bahan 400,000.00 425,000.00


1 m' Pipa Baja Ø 1.100 mm 400,000.00 425,000.00 400,000.00 425,000.00

C PERALATAN 22,300.00 22,920.00


0.064 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 20,800.00 21,120.00
0.15 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,500.00 1,800.00
D Jumlah A + B + C 1,060,645.00 1,156,295.00
E Overhead & Profit (contoh 10%) 10% 106,064.50 115,629.50
F Harga Satuan Pekerjaan (D+E) 1,166,709.50 1,271,924.50

79 A.8.4.1.79 1 m' Pemasangan Pipa Baja Ø 1.200 mm 1,289,816.00 1,402,339.40


A Tenaga 698,140.00 774,750.00
L.01 5.897 OH Pekerja 80,000.00 90,000.00 471,760.00 530,730.00
L.02 1.176 OH Tukang Pipa 130,000.00 140,000.00 152,880.00 164,640.00
L.04 0.588 OH Mandor 125,000.00 135,000.00 73,500.00 79,380.00

B Bahan 450,000.00 475,000.00


1 m' Pipa Baja Ø 1.200 mm 450,000.00 475,000.00 450,000.00 475,000.00

C PERALATAN 24,420.00 25,104.00


0.070 hari Sewa Exavator Type 225 Kap.0,5 - 1,0 m3 325,000.00 330,000.00 22,750.00 23,100.00
0.167 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,670.00 2,004.00
D Jumlah A + B + C 1,172,560.00 1,274,854.00
E Overhead & Profit (contoh 10%) 10% 117,256.00 127,485.40
F Harga Satuan Pekerjaan (D+E) 1,289,816.00 1,402,339.40
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN


XVII A.8.4.2
PEMOTONGAN PIPA
1 A.8.4.2.1 1 bh Pemotongan Pipa PVC Ø 63 mm 821.15 910.25
A Tenaga 722.50 797.50
L.01 0.005 OH Pekerja 80,000.00 90,000.00 400.00 450.00
L.02 0.002 OH Tukang Pipa 130,000.00 140,000.00 260.00 280.00
L.04 0.0005 OH Mandor 125,000.00 135,000.00 62.50 67.50

B Bahan - -
- m' Pipa PVC Ø 63 mm 6,250.00 7,500.00 - -

C PERALATAN 24.00 30.00


0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00

D Jumlah A + B + C 746.50 827.50


E Overhead & Profit (contoh 10%) 10% 74.65 82.75
F Harga Satuan Pekerjaan (D+E) 821.15 910.25

2 A.8.4.2.2 1 bh Pemotongan Pipa PVC Ø 90 mm 2,396.90 2,645.50


A Tenaga 2,155.00 2,375.00
L.01 0.014 OH Pekerja 80,000.00 90,000.00 1,120.00 1,260.00
L.02 0.007 OH Tukang Pipa 130,000.00 140,000.00 910.00 980.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00

B Bahan - -
- m' Pipa PVC Ø 90 mm 7,500.00 8,750.00 - -

C PERALATAN 24.00 30.00


0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00

D Jumlah A + B + C 2,179.00 2,405.00


E Overhead & Profit (contoh 10%) 10% 217.90 240.50
F Harga Satuan Pekerjaan (D+E) 2,396.90 2,645.50

3 A.8.4.2.3 1 bh Pemotongan Pipa PVC Ø 110 mm 3,810.40 4,202.00


A Tenaga 3,440.00 3,790.00
L.01 0.022 OH Pekerja 80,000.00 90,000.00 1,760.00 1,980.00
L.02 0.011 OH Tukang Pipa 130,000.00 140,000.00 1,430.00 1,540.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
B Bahan - -
- m' Pipa PVC Ø 110 mm 9,250.00 13,000.00 - -

C PERALATAN 24.00 30.00


0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00
D Jumlah A + B + C 3,464.00 3,820.00
E Overhead & Profit (contoh 10%) 10% 346.40 382.00
F Harga Satuan Pekerjaan (D+E) 3,810.40 4,202.00

4 A.8.4.2.4 1 bh Pemotongan Pipa PVC Ø 150 mm 5,311.90 5,857.50


A Tenaga 4,805.00 5,295.00
L.01 0.031 OH Pekerja 80,000.00 90,000.00 2,480.00 2,790.00
L.02 0.015 OH Tukang Pipa 130,000.00 140,000.00 1,950.00 2,100.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00
B Bahan - -
- m' Pipa PVC Ø 150 mm 11,500.00 17,000.00 - -
C PERALATAN 24.00 30.00
0.003 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 24.00 30.00
D Jumlah A + B + C 4,829.00 5,325.00
E Overhead & Profit (contoh 10%) 10% 482.90 532.50
F Harga Satuan Pekerjaan (D+E) 5,311.90 5,857.50
5 A.8.4.2.5 1 bh Pemotongan Pipa PVC Ø 200 mm 14,097.60 15,554.00
A Tenaga 12,680.00 13,970.00
L.01 0.081 OH Pekerja 80,000.00 90,000.00 6,480.00 7,290.00
L.02 0.040 OH Tukang Pipa 130,000.00 140,000.00 5,200.00 5,600.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00

B Bahan - -
- m' Pipa PVC Ø 200 mm 15,000.00 26,250.00 - -

C PERALATAN 136.00 170.00


0.017 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 136.00 170.00

D Jumlah A + B + C 12,816.00 14,140.00


E Overhead & Profit (contoh 10%) 10% 1,281.60 1,414.00
F Harga Satuan Pekerjaan (D+E) 14,097.60 15,554.00

6 A.8.4.2.6 1 bh Pemotongan Pipa PVC Ø 250 mm 22,467.50 24,788.50


A Tenaga 20,185.00 22,235.00
L.01 0.128 OH Pekerja 80,000.00 90,000.00 10,240.00 11,520.00
L.02 0.064 OH Tukang Pipa 130,000.00 140,000.00 8,320.00 8,960.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00

B Bahan - -
- m' Pipa PVC Ø 250 mm 20,000.00 46,250.00 - -

C PERALATAN 240.00 300.00


0.03 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 240.00 300.00

D Jumlah A + B + C 20,425.00 22,535.00


E Overhead & Profit (contoh 10%) 10% 2,042.50 2,253.50
F Harga Satuan Pekerjaan (D+E) 22,467.50 24,788.50

7 A.8.4.2.7 1 bh Pemotongan Pipa PVC Ø 300 mm 27,039.10 29,837.50


A Tenaga 24,285.00 26,755.00
L.01 0.155 OH Pekerja 80,000.00 90,000.00 12,400.00 13,950.00
L.02 0.077 OH Tukang Pipa 130,000.00 140,000.00 10,010.00 10,780.00
L.04 0.015 OH Mandor 125,000.00 135,000.00 1,875.00 2,025.00

B Bahan - -
- m' Pipa PVC Ø 300 mm 45,000.00 70,000.00 - -

C PERALATAN 296.00 370.00


0.037 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 296.00 370.00

D Jumlah A + B + C 24,581.00 27,125.00


E Overhead & Profit (contoh 10%) 10% 2,458.10 2,712.50
F Harga Satuan Pekerjaan (D+E) 27,039.10 29,837.50

8 A.8.4.2.8 1 bh Pemotongan Pipa PVC Ø 400 mm 58,160.30 64,179.50


A Tenaga 52,185.00 57,485.00
L.01 0.331 OH Pekerja 80,000.00 90,000.00 26,480.00 29,790.00
L.02 0.166 OH Tukang Pipa 130,000.00 140,000.00 21,580.00 23,240.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00

B Bahan - -
- m' Pipa PVC Ø 400 mm 87,500.00 137,500.00 - -

C PERALATAN 688.00 860.00


0.086 hari Peralatan Potong Pipa T1/manual (gergaji) 8,000.00 10,000.00 688.00 860.00

D Jumlah A + B + C 52,873.00 58,345.00


E Overhead & Profit (contoh 10%) 10% 5,287.30 5,834.50
F Harga Satuan Pekerjaan (D+E) 58,160.30 64,179.50
9 A.8.4.2.9 1 bh Pemotongan Pipa PVC Ø 450 mm 74,250.00 81,939.00
A Tenaga 66,150.00 72,870.00
L.01 0.420 OH Pekerja 80,000.00 90,000.00 33,600.00 37,800.00
L.02 0.210 OH Tukang Pipa 130,000.00 140,000.00 27,300.00 29,400.00
L.04 0.042 OH Mandor 125,000.00 135,000.00 5,250.00 5,670.00

B Bahan - -
- m' Pipa PVC Ø 450 mm 225,000.00 262,500.00 - -

C PERALATAN 1,350.00 1,620.00


0.054 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,350.00 1,620.00

D Jumlah A + B + C 67,500.00 74,490.00


E Overhead & Profit (contoh 10%) 10% 6,750.00 7,449.00
F Harga Satuan Pekerjaan (D+E) 74,250.00 81,939.00

10 A.8.4.2.10 1 bh Pemotongan Pipa PVC Ø 500 mm 91,668.50 101,167.00


A Tenaga 81,610.00 89,900.00
L.01 0.518 OH Pekerja 80,000.00 90,000.00 41,440.00 46,620.00
L.02 0.259 OH Tukang Pipa 130,000.00 140,000.00 33,670.00 36,260.00
L.04 0.052 OH Mandor 125,000.00 135,000.00 6,500.00 7,020.00

B Bahan - -
- m' Pipa PVC Ø 500 mm 280,000.00 285,000.00 - -

C PERALATAN 1,725.00 2,070.00


0.069 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,725.00 2,070.00

D Jumlah A + B + C 83,335.00 91,970.00


E Overhead & Profit (contoh 10%) 10% 8,333.50 9,197.00
F Harga Satuan Pekerjaan (D+E) 91,668.50 101,167.00

11 A.8.4.2.11 1 bh Pemotongan Pipa PVC Ø 600 mm 110,187.00 121,616.00


A Tenaga 98,020.00 107,980.00
L.01 0.623 OH Pekerja 80,000.00 90,000.00 49,840.00 56,070.00
L.02 0.311 OH Tukang Pipa 130,000.00 140,000.00 40,430.00 43,540.00
L.04 0.062 OH Mandor 125,000.00 135,000.00 7,750.00 8,370.00

B Bahan - -
- m' Pipa PVC Ø 600 mm 325,000.00 345,000.00 - -

C PERALATAN 2,150.00 2,580.00


0.086 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 2,150.00 2,580.00

D Jumlah A + B + C 100,170.00 110,560.00


E Overhead & Profit (contoh 10%) 10% 10,017.00 11,056.00
F Harga Satuan Pekerjaan (D+E) 110,187.00 121,616.00

12 A.8.4.2.12 1 bh Pemasangan Pipa PVC Ø 800 mm 193,154.50 213,207.50


A Tenaga 171,595.00 189,025.00
L.01 1.089 OH Pekerja 80,000.00 90,000.00 87,120.00 98,010.00
L.02 0.545 OH Tukang Pipa 130,000.00 140,000.00 70,850.00 76,300.00
L.04 0.109 OH Mandor 125,000.00 135,000.00 13,625.00 14,715.00

B Bahan - -
- m' Pipa PVC Ø 800 mm 425,000.00 450,000.00 - -
C PERALATAN 4,000.00 4,800.00
0.160 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,000.00 4,800.00
D Jumlah A + B + C 175,595.00 193,825.00
E Overhead & Profit (contoh 10%) 10% 17,559.50 19,382.50
F Harga Satuan Pekerjaan (D+E) 193,154.50 213,207.50
13 A.8.4.2.13 1 bh Pemotongan Pipa PVC Ø 900 mm 202,356.00 223,366.00
A Tenaga 179,760.00 198,020.00
L.01 1.141 OH Pekerja 80,000.00 90,000.00 91,280.00 102,690.00
L.02 0.571 OH Tukang Pipa 130,000.00 140,000.00 74,230.00 79,940.00
L.04 0.114 OH Mandor 125,000.00 135,000.00 14,250.00 15,390.00

B Bahan - -
- m' Pipa PVC Ø 900 mm 625,000.00 650,000.00 - -

C PERALATAN 4,200.00 5,040.00


0.168 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,200.00 5,040.00

D Jumlah A + B + C 183,960.00 203,060.00


E Overhead & Profit (contoh 10%) 10% 18,396.00 20,306.00
F Harga Satuan Pekerjaan (D+E) 202,356.00 223,366.00

14 A.8.4.2.14 1 bh Pemotongan Pipa PVC Ø 1.000 mm 228,019.00 251,696.50


A , 202,515.00 223,085.00
L.01 1.285 OH Pekerja 80,000.00 90,000.00 102,800.00 115,650.00
L.02 0.643 OH Tukang Pipa 130,000.00 140,000.00 83,590.00 90,020.00
L.04 0.129 OH Mandor 125,000.00 135,000.00 16,125.00 17,415.00

B Bahan - -
- m' Pipa PVC Ø 1.000 mm 730,000.00 750,000.00 - -

C PERALATAN 4,775.00 5,730.00


0.191 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,775.00 5,730.00

D Jumlah A + B + C 207,290.00 228,815.00


E Overhead & Profit (contoh 10%) 10% 20,729.00 22,881.50
F Harga Satuan Pekerjaan (D+E) 228,019.00 251,696.50

15 A.8.4.2.15 1 bh Pemotongan Pipa PVC Ø 1.100 mm 253,517.00 279,845.50


A Tenaga 225,145.00 248,015.00
L.01 1.429 OH Pekerja 80,000.00 90,000.00 114,320.00 128,610.00
L.02 0.715 OH Tukang Pipa 130,000.00 140,000.00 92,950.00 100,100.00
L.04 0.143 OH Mandor 125,000.00 135,000.00 17,875.00 19,305.00

B Bahan - -
- m' Pipa PVC Ø 1.100 mm 800,000.00 850,000.00 - -

C PERALATAN 5,325.00 6,390.00


0.213 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 5,325.00 6,390.00

D Jumlah A + B + C 230,470.00 254,405.00


E Overhead & Profit (contoh 10%) 10% 23,047.00 25,440.50
F Harga Satuan Pekerjaan (D+E) 253,517.00 279,845.50

16 A.8.4.2.16 1 bh Pemotongan Pipa PVC Ø 1.200 mm 279,042.50 308,027.50


A Tenaga 247,775.00 272,945.00
L.01 1.573 OH Pekerja 80,000.00 90,000.00 125,840.00 141,570.00
L.02 0.787 OH Tukang Pipa 130,000.00 140,000.00 102,310.00 110,180.00
L.04 0.157 OH Mandor 125,000.00 135,000.00 19,625.00 21,195.00

B Bahan - -
- m' Pipa PVC Ø 1.200 mm 280,000.00 285,000.00 - -

C PERALATAN 5,900.00 7,080.00


0.236 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 5,900.00 7,080.00
D Jumlah A + B + C 253,675.00 280,025.00
E Overhead & Profit (contoh 10%) 10% 25,367.50 28,002.50
F Harga Satuan Pekerjaan (D+E) 279,042.50 308,027.50
17 A.8.4.2.17 1 bh Pemotongan Pipa HDPE Ø 63 mm 4,196.50 4,627.70
A Tenaga 3,715.00 4,087.00
L.01 0.002 OH Pekerja 80,000.00 90,000.00 160.00 180.00
L.02 0.001 OH Tukang Pipa 130,000.00 140,000.00 130.00 140.00
L.04 0.0002 OH Mandor 125,000.00 135,000.00 25.00 27.00
L.08 0.0340 OH Operator 100,000.00 110,000.00 3,400.00 3,740.00
B Bahan - -
- m' Pipa HDPE Ø 63 mm 25,000.00 30,000.00 - -

C PERALATAN 100.00 120.00


0.004 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 100.00 120.00

D Jumlah A + B + C 3,815.00 4,207.00


E Overhead & Profit (contoh 10%) 10% 381.50 420.70
F Harga Satuan Pekerjaan (D+E) 4,196.50 4,627.70

18 A.8.4.2.18 1 bh Pemotongan Pipa HDPE Ø 100 mm 9,042.00 9,960.50


A Tenaga 8,095.00 8,905.00
L.01 0.006 OH Pekerja 80,000.00 90,000.00 480.00 540.00
L.02 0.003 OH Tukang Pipa 130,000.00 140,000.00 390.00 420.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00
L.08 0.071 OH Operator 100,000.00 110,000.00 7,100.00 7,810.00
B Bahan - -
- m' Pipa HDPE Ø 100 mm 35,000.00 40,000.00 - -

C PERALATAN 125.00 150.00


0.005 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 125.00 150.00

D Jumlah A + B + C 8,220.00 9,055.00


E Overhead & Profit (contoh 10%) 10% 822.00 905.50
F Harga Satuan Pekerjaan (D+E) 9,042.00 9,960.50

19 A.8.4.2.19 1 bh Pemotongan Pipa HDPE Ø 125 mm 12,369.50 13,623.50


A Tenaga 11,095.00 12,205.00
L.01 0.009 OH Pekerja 80,000.00 90,000.00 720.00 810.00
L.02 0.005 OH Tukang Pipa 130,000.00 140,000.00 650.00 700.00
L.04 0.001 OH Mandor 125,000.00 135,000.00 125.00 135.00
L.08 0.096 OH Operator 100,000.00 110,000.00 9,600.00 10,560.00
B Bahan - -
- m' Pipa HDPE Ø 125 mm 45,000.00 50,000.00 - -

C PERALATAN 150.00 180.00


0.006 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 150.00 180.00

D Jumlah A + B + C 11,245.00 12,385.00


E Overhead & Profit (contoh 10%) 10% 1,124.50 1,238.50
F Harga Satuan Pekerjaan (D+E) 12,369.50 13,623.50

20 A.8.4.2.20 1 bh Pemotongan Pipa HDPE Ø 150 mm 16,384.50 18,051.00


A Tenaga 14,670.00 16,140.00
L.01 0.016 OH Pekerja 80,000.00 90,000.00 1,280.00 1,440.00
L.02 0.008 OH Tukang Pipa 130,000.00 140,000.00 1,040.00 1,120.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00
L.08 0.121 OH Operator 100,000.00 110,000.00 12,100.00 13,310.00
B Bahan - -
- m' Pipa HDPE Ø 150 mm 65,000.00 70,000.00 - -

C PERALATAN 225.00 270.00


0.009 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 225.00 270.00
D Jumlah A + B + C 14,895.00 16,410.00
E Overhead & Profit (contoh 10%) 10% 1,489.50 1,641.00
F Harga Satuan Pekerjaan (D+E) 16,384.50 18,051.00
21 A.8.4.2.21 1 bh Pemotongan Pipa HDPE Ø 200 mm 26,845.50 29,590.00
A Tenaga 23,980.00 26,390.00
L.01 0.044 OH Pekerja 80,000.00 90,000.00 3,520.00 3,960.00
L.02 0.022 OH Tukang Pipa 130,000.00 140,000.00 2,860.00 3,080.00
L.04 0.004 OH Mandor 125,000.00 135,000.00 500.00 540.00
L.08 0.171 OH Operator 100,000.00 110,000.00 17,100.00 18,810.00
B Bahan - -
m' Pipa HDPE Ø 200 mm 110,000.00 120,000.00 - -

C PERALATAN 425.00 510.00


0.017 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 425.00 510.00

D Jumlah A + B + C 24,405.00 26,900.00


E Overhead & Profit (contoh 10%) 10% 2,440.50 2,690.00
F Harga Satuan Pekerjaan (D+E) 26,845.50 29,590.00

22 A.8.4.2.22 1 bh Pemotongan Pipa HDPE Ø 250 mm 36,520.00 40,254.50


A Tenaga 32,625.00 35,905.00
L.01 0.067 OH Pekerja 80,000.00 90,000.00 5,360.00 6,030.00
L.02 0.033 OH Tukang Pipa 130,000.00 140,000.00 4,290.00 4,620.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00
L.08 0.221 OH Operator 100,000.00 110,000.00 22,100.00 24,310.00
B Bahan - -
- m' Pipa HDPE Ø 250 mm 135,000.00 140,000.00 - -

C PERALATAN 575.00 690.00


0.023 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 575.00 690.00

D Jumlah A + B + C 33,200.00 36,595.00


E Overhead & Profit (contoh 10%) 10% 3,320.00 3,659.50
F Harga Satuan Pekerjaan (D+E) 36,520.00 40,254.50

23 A.8.4.2.23 1 bh Pemotongan Pipa HDPE Ø 300 mm 46,227.50 50,957.50


A Tenaga 41,275.00 45,425.00
L.01 0.090 OH Pekerja 80,000.00 90,000.00 7,200.00 8,100.00
L.02 0.045 OH Tukang Pipa 130,000.00 140,000.00 5,850.00 6,300.00
L.04 0.009 OH Mandor 125,000.00 135,000.00 1,125.00 1,215.00
L.08 0.271 OH Operator 100,000.00 110,000.00 27,100.00 29,810.00
B Bahan - -
- m' Pipa HDPE Ø 300 mm 160,000.00 170,000.00 - -

C PERALATAN 750.00 900.00


0.030 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 750.00 900.00

D Jumlah A + B + C 42,025.00 46,325.00


E Overhead & Profit (contoh 10%) 10% 4,202.50 4,632.50
F Harga Satuan Pekerjaan (D+E) 46,227.50 50,957.50

24 A.8.4.2.24 1 bh Pemotongan Pipa HDPE Ø 400 mm 72,957.50 80,454.00


A Tenaga 64,950.00 71,490.00
L.01 0.177 OH Pekerja 80,000.00 90,000.00 14,160.00 15,930.00
L.02 0.088 OH Tukang Pipa 130,000.00 140,000.00 11,440.00 12,320.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00
L.08 0.371 OH Operator 100,000.00 110,000.00 37,100.00 40,810.00
B Bahan - -
- m' Pipa HDPE Ø 400 mm 200,000.00 210,000.00 - -
C PERALATAN 1,375.00 1,650.00
0.055 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,375.00 1,650.00

D Jumlah A + B + C 66,325.00 73,140.00


E Overhead & Profit (contoh 10%) 10% 6,632.50 7,314.00
F Harga Satuan Pekerjaan (D+E) 72,957.50 80,454.00
25 A.8.4.2.25 1 bh Pemotongan Pipa HDPE Ø 450 mm 87,356.50 96,343.50
A Tenaga 77,665.00 85,485.00
L.01 0.225 OH Pekerja 80,000.00 90,000.00 18,000.00 20,250.00
L.02 0.113 OH Tukang Pipa 130,000.00 140,000.00 14,690.00 15,820.00
L.04 0.023 OH Mandor 125,000.00 135,000.00 2,875.00 3,105.00
L.08 0.421 OH Operator 100,000.00 110,000.00 42,100.00 46,310.00
B Bahan - -
- m' Pipa HDPE Ø 450 mm 240,000.00 250,000.00 - -

C PERALATAN 1,750.00 2,100.00


0.070 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 1,750.00 2,100.00

D Jumlah A + B + C 79,415.00 87,585.00


E Overhead & Profit (contoh 10%) 10% 7,941.50 8,758.50
F Harga Satuan Pekerjaan (D+E) 87,356.50 96,343.50

26 A.8.4.2.26 1 bh Pemotongan Pipa HDPE Ø 500 mm 97,850.50 107,833.00


A Tenaga 86,830.00 95,480.00
L.01 0.227 OH Pekerja 80,000.00 90,000.00 18,160.00 20,430.00
L.02 0.139 OH Tukang Pipa 130,000.00 140,000.00 18,070.00 19,460.00
L.04 0.028 OH Mandor 125,000.00 135,000.00 3,500.00 3,780.00
L.08 0.471 OH Operator 100,000.00 110,000.00 47,100.00 51,810.00
B Bahan - -
- m' Pipa HDPE Ø 500 mm 300,000.00 320,000.00 - -

C PERALATAN 2,125.00 2,550.00


0.085 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 2,125.00 2,550.00
-
D Jumlah A + B + C 88,955.00 98,030.00
E Overhead & Profit (contoh 10%) 10% 8,895.50 9,803.00
F Harga Satuan Pekerjaan (D+E) 97,850.50 107,833.00

27 A.8.4.2.27 1 bh Pemotongan Pipa HDPE Ø 600 mm 123,310.00 136,009.50


A Tenaga 109,575.00 120,615.00
L.01 0.333 OH Pekerja 80,000.00 90,000.00 26,640.00 29,970.00
L.02 0.167 OH Tukang Pipa 130,000.00 140,000.00 21,710.00 23,380.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00
L.08 0.571 OH Operator 100,000.00 110,000.00 57,100.00 62,810.00
B Bahan - -
- m' Pipa HDPE Ø 600 mm 430,000.00 450,000.00 - -

C PERALATAN 2,525.00 3,030.00


0.101 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 2,525.00 3,030.00

D Jumlah A + B + C 112,100.00 123,645.00


E Overhead & Profit (contoh 10%) 10% 11,210.00 12,364.50
F Harga Satuan Pekerjaan (D+E) 123,310.00 136,009.50

28 A.8.4.2.28 1 bh Pemotongan Pipa HDPE Ø 800 mm 193,913.50 213,961.00


A Tenaga 171,810.00 189,140.00
L.01 0.601 OH Pekerja 80,000.00 90,000.00 48,080.00 54,090.00
L.02 0.301 OH Tukang Pipa 130,000.00 140,000.00 39,130.00 42,140.00
L.04 0.060 OH Mandor 125,000.00 135,000.00 7,500.00 8,100.00
L.08 0.771 OH Operator 100,000.00 110,000.00 77,100.00 84,810.00
B Bahan - -
- m' Pipa HDPE Ø 800 mm 650,000.00 675,000.00 - -

C PERALATAN 4,475.00 5,370.00


0.179 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,475.00 5,370.00
D Jumlah A + B + C 176,285.00 194,510.00
E Overhead & Profit (contoh 10%) 10% 17,628.50 19,451.00
F Harga Satuan Pekerjaan (D+E) 193,913.50 213,961.00
29 A.8.4.2.29 1 bh Pemotongan Pipa HDPE Ø 900 mm 261,299.50 288,425.50
A Tenaga 230,795.00 254,105.00
L.01 0.913 OH Pekerja 80,000.00 90,000.00 73,040.00 82,170.00
L.02 0.456 OH Tukang Pipa 130,000.00 140,000.00 59,280.00 63,840.00
L.04 0.091 OH Mandor 125,000.00 135,000.00 11,375.00 12,285.00
L.08 0.871 OH Operator 100,000.00 110,000.00 87,100.00 95,810.00
B Bahan - -
- m' Pipa HDPE Ø 900 mm 750,000.00 800,000.00 - -

C PERALATAN 6,750.00 8,100.00


0.270 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 6,750.00 8,100.00

D Jumlah A + B + C 237,545.00 262,205.00


E Overhead & Profit (contoh 10%) 10% 23,754.50 26,220.50
F Harga Satuan Pekerjaan (D+E) 261,299.50 288,425.50

30 A.8.4.2.30 1 bh Pemotongan Pipa HDPE Ø 1.000 mm 310,706.00 343,002.00


A Tenaga 274,160.00 301,860.00
L.01 1.125 OH Pekerja 80,000.00 90,000.00 90,000.00 101,250.00
L.02 0.562 OH Tukang Pipa 130,000.00 140,000.00 73,060.00 78,680.00
L.04 0.112 OH Mandor 125,000.00 135,000.00 14,000.00 15,120.00
L.08 0.971 OH Operator 100,000.00 110,000.00 97,100.00 106,810.00
B Bahan - -
- m' Pipa HDPE Ø 1.000 mm 900,000.00 925,000.00 - -

C PERALATAN 8,300.00 9,960.00


0.332 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 8,300.00 9,960.00

D Jumlah A + B + C 282,460.00 311,820.00


E Overhead & Profit (contoh 10%) 10% 28,246.00 31,182.00
F Harga Satuan Pekerjaan (D+E) 310,706.00 343,002.00

31 A.8.4.2.31 1 bh Pemotongan Pipa HDPE Ø 1.100 mm 342,358.50 377,938.00


A Tenaga 302,110.00 332,630.00
L.01 1.238 OH Pekerja 80,000.00 90,000.00 99,040.00 111,420.00
L.02 0.619 OH Tukang Pipa 130,000.00 140,000.00 80,470.00 86,660.00
L.04 0.124 OH Mandor 125,000.00 135,000.00 15,500.00 16,740.00
L.08 1.071 OH Operator 100,000.00 110,000.00 107,100.00 117,810.00
B Bahan - -
- m' Pipa HDPE Ø 1.100 mm 1,000,000.00 1,050,000.00 - -

C PERALATAN 9,125.00 10,950.00


0.365 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 9,125.00 10,950.00

D Jumlah A + B + C 311,235.00 343,580.00


E Overhead & Profit (contoh 10%) 10% 31,123.50 34,358.00
F Harga Satuan Pekerjaan (D+E) 342,358.50 377,938.00

32 A.8.4.2.32 1 bh Pemotongan Pipa HDPE Ø 1.200 mm 422,361.50 466,356.00


A Tenaga 372,040.00 409,650.00
L.01 1.619 OH Pekerja 80,000.00 90,000.00 129,520.00 145,710.00
L.02 0.809 OH Tukang Pipa 130,000.00 140,000.00 105,170.00 113,260.00
L.04 0.162 OH Mandor 125,000.00 135,000.00 20,250.00 21,870.00
L.08 1.171 OH Operator 100,000.00 110,000.00 117,100.00 128,810.00
B Bahan - -
- m' Pipa HDPE Ø 1.200 mm 1,100,000.00 1,150,000.00 - -

C PERALATAN 11,925.00 14,310.00


0.477 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 11,925.00 14,310.00
D Jumlah A + B + C 383,965.00 423,960.00
E Overhead & Profit (contoh 10%) 10% 38,396.50 42,396.00
F Harga Satuan Pekerjaan (D+E) 422,361.50 466,356.00
33 A.8.4.2.33 1 bh Pemotongan Pipa GIP Ø 63 mm 3,377.00 3,718.00
A Tenaga 3,070.00 3,380.00
L.01 0.019 OH Pekerja 80,000.00 90,000.00 1,520.00 1,710.00
L.02 0.010 OH Tukang Pipa 130,000.00 140,000.00 1,300.00 1,400.00
L.04 0.002 OH Mandor 125,000.00 135,000.00 250.00 270.00

B Bahan - -
- m' Pipa GIP Ø 63 mm 15,000.00 17,500.00 - -

C PERALATAN - -

hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 3,070.00 3,380.00


E Overhead & Profit (contoh 10%) 10% 307.00 338.00
F Harga Satuan Pekerjaan (D+E) 3,377.00 3,718.00

34 A.8.4.2.34 1 bh Pemotongan Pipa GIP Ø 100 mm 10,076.00 11,099.00


A Tenaga 9,160.00 10,090.00
L.01 0.058 OH Pekerja 80,000.00 90,000.00 4,640.00 5,220.00
L.02 0.029 OH Tukang Pipa 130,000.00 140,000.00 3,770.00 4,060.00
L.04 0.006 OH Mandor 125,000.00 135,000.00 750.00 810.00

B Bahan - -
- m' Pipa GIP Ø 100 mm 19,166.67 25,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 9,160.00 10,090.00


E Overhead & Profit (contoh 10%) 10% 916.00 1,009.00
F Harga Satuan Pekerjaan (D+E) 10,076.00 11,099.00

35 A.8.4.2.35 1 bh Pemotongan Pipa GIP Ø 125 mm 15,911.50 17,528.50


A Tenaga 14,465.00 15,935.00
L.01 0.092 OH Pekerja 80,000.00 90,000.00 7,360.00 8,280.00
L.02 0.046 OH Tukang Pipa 130,000.00 140,000.00 5,980.00 6,440.00
L.04 0.009 OH Mandor 125,000.00 135,000.00 1,125.00 1,215.00

B Bahan - -
- m' Pipa GIP Ø 125 mm 22,500.00 30,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 14,465.00 15,935.00


E Overhead & Profit (contoh 10%) 10% 1,446.50 1,593.50
F Harga Satuan Pekerjaan (D+E) 15,911.50 17,528.50

36 A.8.4.2.36 1 bh Pemotongan Pipa GIP Ø 150 mm 22,753.50 25,063.50


A Tenaga 20,685.00 22,785.00
L.01 0.131 OH Pekerja 80,000.00 90,000.00 10,480.00 11,790.00
L.02 0.066 OH Tukang Pipa 130,000.00 140,000.00 8,580.00 9,240.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00

B Bahan - -
- m' Pipa GIP Ø 150 mm 28,333.33 36,666.67 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
D Jumlah A + B + C 20,685.00 22,785.00
E Overhead & Profit (contoh 10%) 10% 2,068.50 2,278.50
F Harga Satuan Pekerjaan (D+E) 22,753.50 25,063.50
37 A.8.4.2.37 1 bh Pemotongan Pipa GIP Ø 200 mm 58,905.00 64,889.00
A Tenaga 53,550.00 58,990.00
L.01 0.340 OH Pekerja 80,000.00 90,000.00 27,200.00 30,600.00
L.02 0.170 OH Tukang Pipa 130,000.00 140,000.00 22,100.00 23,800.00
L.04 0.034 OH Mandor 125,000.00 135,000.00 4,250.00 4,590.00

B Bahan - -
- m' Pipa GIP Ø 200 mm 37,500.00 48,333.33 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 53,550.00 58,990.00


E Overhead & Profit (contoh 10%) 10% 5,355.00 5,899.00
F Harga Satuan Pekerjaan (D+E) 58,905.00 64,889.00

38 A.8.4.2.38 1 bh Pemotongan Pipa GIP Ø 250 mm 82,153.50 90,502.50


A Tenaga 74,685.00 82,275.00
L.01 0.475 OH Pekerja 80,000.00 90,000.00 38,000.00 42,750.00
L.02 0.237 OH Tukang Pipa 130,000.00 140,000.00 30,810.00 33,180.00
L.04 0.047 OH Mandor 125,000.00 135,000.00 5,875.00 6,345.00

B Bahan - -
- m' Pipa GIP Ø 250 mm 45,000.00 58,333.33 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 74,685.00 82,275.00


E Overhead & Profit (contoh 10%) 10% 7,468.50 8,227.50
F Harga Satuan Pekerjaan (D+E) 82,153.50 90,502.50

39 A.8.4.2.39 1 bh Pemotongan Pipa GIP Ø 300 mm 87,263.00 96,129.00


A Tenaga 79,330.00 87,390.00
L.01 0.504 OH Pekerja 80,000.00 90,000.00 40,320.00 45,360.00
L.02 0.252 OH Tukang Pipa 130,000.00 140,000.00 32,760.00 35,280.00
L.04 0.050 OH Mandor 125,000.00 135,000.00 6,250.00 6,750.00

B Bahan - -
- m' Pipa GIP Ø 300 mm 70,000.00 81,666.67 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 79,330.00 87,390.00


E Overhead & Profit (contoh 10%) 10% 7,933.00 8,739.00
F Harga Satuan Pekerjaan (D+E) 87,263.00 96,129.00

40 A.8.4.2.40 1 bh Pemotongan Pipa GIP Ø 400 mm 127,886.00 140,877.00


A Tenaga 116,260.00 128,070.00
L.01 0.738 OH Pekerja 80,000.00 90,000.00 59,040.00 66,420.00
L.02 0.369 OH Tukang Pipa 130,000.00 140,000.00 47,970.00 51,660.00
L.04 0.074 OH Mandor 125,000.00 135,000.00 9,250.00 9,990.00

B Bahan - -
- m' Pipa GIP Ø 400 mm 93,333.33 96,666.67 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 116,260.00 128,070.00


E Overhead & Profit (contoh 10%) 10% 11,626.00 12,807.00
F Harga Satuan Pekerjaan (D+E) 127,886.00 140,877.00
41 A.8.4.2.41 1 bh Pemotongan Pipa GIP Ø 450 mm 146,943.50 161,870.50
A Tenaga 133,585.00 147,155.00
L.01 0.848 OH Pekerja 80,000.00 90,000.00 67,840.00 76,320.00
L.02 0.424 OH Tukang Pipa 130,000.00 140,000.00 55,120.00 59,360.00
L.04 0.085 OH Mandor 125,000.00 135,000.00 10,625.00 11,475.00

B Bahan - -
- m' Pipa GIP Ø 450 mm 110,000.00 120,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 133,585.00 147,155.00


E Overhead & Profit (contoh 10%) 10% 13,358.50 14,715.50
F Harga Satuan Pekerjaan (D+E) 146,943.50 161,870.50

42 A.8.4.2.42 1 bh Pemotongan Pipa GIP Ø 500 mm 149,633.00 164,835.00


A Tenaga 136,030.00 149,850.00
L.01 0.864 OH Pekerja 80,000.00 90,000.00 69,120.00 77,760.00
L.02 0.432 OH Tukang Pipa 130,000.00 140,000.00 56,160.00 60,480.00
L.04 0.086 OH Mandor 125,000.00 135,000.00 10,750.00 11,610.00

B Bahan - -
- m' Pipa GIP Ø 500 mm 140,000.00 150,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 136,030.00 149,850.00


E Overhead & Profit (contoh 10%) 10% 13,603.00 14,985.00
F Harga Satuan Pekerjaan (D+E) 149,633.00 164,835.00

43 A.8.4.2.43 1 bh Pemotongan Pipa GIP Ø 600 mm 163,086.00 179,652.00


A Tenaga 148,260.00 163,320.00
L.01 0.941 OH Pekerja 80,000.00 90,000.00 75,280.00 84,690.00
L.02 0.471 OH Tukang Pipa 130,000.00 140,000.00 61,230.00 65,940.00
L.04 0.094 OH Mandor 125,000.00 135,000.00 11,750.00 12,690.00

B Bahan - -
- m' Pipa GIP Ø 600 mm 160,000.00 170,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 148,260.00 163,320.00


E Overhead & Profit (contoh 10%) 10% 14,826.00 16,332.00
F Harga Satuan Pekerjaan (D+E) 163,086.00 179,652.00

44 A.8.4.2.44 1 bh Pemotongan Pipa GIP Ø 800 mm 271,452.50 299,029.50


A Tenaga 246,775.00 271,845.00
L.01 1.567 OH Pekerja 80,000.00 90,000.00 125,360.00 141,030.00
L.02 0.783 OH Tukang Pipa 130,000.00 140,000.00 101,790.00 109,620.00
L.04 0.157 OH Mandor 125,000.00 135,000.00 19,625.00 21,195.00

B Bahan - -
- m' Pipa GIP Ø 800 mm 200,000.00 210,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
D Jumlah A + B + C 246,775.00 271,845.00
E Overhead & Profit (contoh 10%) 10% 24,677.50 27,184.50
F Harga Satuan Pekerjaan (D+E) 271,452.50 299,029.50
45 A.8.4.2.45 1 bh Pemotongan Pipa GIP Ø 900 mm 306,652.50 337,804.50
A Tenaga 278,775.00 307,095.00
L.01 1.770 OH Pekerja 80,000.00 90,000.00 141,600.00 159,300.00
L.02 0.885 OH Tukang Pipa 130,000.00 140,000.00 115,050.00 123,900.00
L.04 0.177 OH Mandor 125,000.00 135,000.00 22,125.00 23,895.00

B Bahan - -
- m' Pipa GIP Ø 900 mm 230,000.00 250,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 278,775.00 307,095.00


E Overhead & Profit (contoh 10%) 10% 27,877.50 30,709.50
F Harga Satuan Pekerjaan (D+E) 306,652.50 337,804.50

46 A.8.4.2.46 1 bh Pemotongan Pipa GIP Ø 1.000 mm 341,940.50 376,678.50


A Tenaga 310,855.00 342,435.00
L.01 1.974 OH Pekerja 80,000.00 90,000.00 157,920.00 177,660.00
L.02 0.987 OH Tukang Pipa 130,000.00 140,000.00 128,310.00 138,180.00
L.04 0.197 OH Mandor 125,000.00 135,000.00 24,625.00 26,595.00

B Bahan - -
- m' Pipa GIP Ø 1.000 mm 260,000.00 270,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 310,855.00 342,435.00


E Overhead & Profit (contoh 10%) 10% 31,085.50 34,243.50
F Harga Satuan Pekerjaan (D+E) 341,940.50 376,678.50

47 A.8.4.2.47 1 bh Pemotongan Pipa GIP Ø 1.100 mm 377,091.00 415,404.00


A Tenaga 342,810.00 377,640.00
L.01 2.178 OH Pekerja 80,000.00 90,000.00 174,240.00 196,020.00
L.02 1.089 OH Tukang Pipa 130,000.00 140,000.00 141,570.00 152,460.00
L.04 0.216 OH Mandor 125,000.00 135,000.00 27,000.00 29,160.00

B Bahan - -
- m' Pipa GIP Ø 1.100 mm 280,000.00 290,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -

D Jumlah A + B + C 342,810.00 377,640.00


E Overhead & Profit (contoh 10%) 10% 34,281.00 37,764.00
F Harga Satuan Pekerjaan (D+E) 377,091.00 415,404.00

48 A.8.4.2.48 1 bh Pemotongan Pipa GIP Ø 1.200 mm 412,654.00 454,575.00


A Tenaga 375,140.00 413,250.00
L.01 2.382 OH Pekerja 80,000.00 90,000.00 190,560.00 214,380.00
L.02 1.191 OH Tukang Pipa 130,000.00 140,000.00 154,830.00 166,740.00
L.04 0.238 OH Mandor 125,000.00 135,000.00 29,750.00 32,130.00

B Bahan - -
- m' Pipa GIP Ø 1.200 mm 310,000.00 320,000.00 - -

C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
D Jumlah A + B + C 375,140.00 413,250.00
E Overhead & Profit (contoh 10%) 10% 37,514.00 41,325.00
F Harga Satuan Pekerjaan (D+E) 412,654.00 454,575.00
49 A.8.4.2.49 1 bh Pemotongan Pipa DCI Ø 100 mm 9,245.50 10,264.10
A Tenaga 8,375.00 9,295.00
L.01 0.071 OH Pekerja 80,000.00 90,000.00 5,680.00 6,390.00
L.02 0.014 OH Tukang Pipa 130,000.00 140,000.00 1,820.00 1,960.00
L.04 0.007 OH Mandor 125,000.00 135,000.00 875.00 945.00

B Bahan - -
- m' Pipa DCI Ø 100 mm 25,000.00 30,000.00 - -

C PERALATAN 30.00 36.00


0.003 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 30.00 36.00

D Jumlah A + B + C 8,405.00 9,331.00


E Overhead & Profit (contoh 10%) 10% 840.50 933.10
F Harga Satuan Pekerjaan (D+E) 9,245.50 10,264.10

50 A.8.4.2.50 1 bh Pemotongan Pipa DCI Ø 125 mm 14,624.50 16,241.50


A Tenaga 13,195.00 14,645.00
L.01 0.112 OH Pekerja 80,000.00 90,000.00 8,960.00 10,080.00
L.02 0.022 OH Tukang Pipa 130,000.00 140,000.00 2,860.00 3,080.00
L.04 0.011 OH Mandor 125,000.00 135,000.00 1,375.00 1,485.00

B Bahan - -
- m' Pipa DCI Ø 125 mm 40,000.00 45,000.00 - -

C PERALATAN 100.00 120.00


0.010 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 100.00 120.00

D Jumlah A + B + C 13,295.00 14,765.00


E Overhead & Profit (contoh 10%) 10% 1,329.50 1,476.50
F Harga Satuan Pekerjaan (D+E) 14,624.50 16,241.50

51 A.8.4.2.51 1 bh Pemotongan Pipa DCI Ø 150 mm 20,966.00 23,282.60


A Tenaga 18,880.00 20,950.00
L.01 0.159 OH Pekerja 80,000.00 90,000.00 12,720.00 14,310.00
L.02 0.032 OH Tukang Pipa 130,000.00 140,000.00 4,160.00 4,480.00
L.04 0.016 OH Mandor 125,000.00 135,000.00 2,000.00 2,160.00

B Bahan - -
- m' Pipa DCI Ø 150 mm 60,000.00 70,000.00 - -

C PERALATAN 180.00 216.00


0.018 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 180.00 216.00

D Jumlah A + B + C 19,060.00 21,166.00


E Overhead & Profit (contoh 10%) 10% 1,906.00 2,116.60
F Harga Satuan Pekerjaan (D+E) 20,966.00 23,282.60

52 A.8.4.2.52 1 bh Pemotongan Pipa DCI Ø 200 mm 48,328.50 53,683.30


A Tenaga 43,395.00 48,155.00
L.01 0.366 OH Pekerja 80,000.00 90,000.00 29,280.00 32,940.00
L.02 0.073 OH Tukang Pipa 130,000.00 140,000.00 9,490.00 10,220.00
L.04 0.037 OH Mandor 125,000.00 135,000.00 4,625.00 4,995.00

B Bahan - -
- m' Pipa DCI Ø 200 mm 80,000.00 90,000.00 - -

C PERALATAN 540.00 648.00


0.054 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 540.00 648.00

D Jumlah A + B + C 43,935.00 48,803.00


E Overhead & Profit (contoh 10%) 10% 4,393.50 4,880.30
F Harga Satuan Pekerjaan (D+E) 48,328.50 53,683.30
53 A.8.4.2.53 1 bh Pemotongan Pipa DCI Ø 250 mm 62,876.00 69,845.60
A Tenaga 56,430.00 62,620.00
L.01 0.476 OH Pekerja 80,000.00 90,000.00 38,080.00 42,840.00
L.02 0.095 OH Tukang Pipa 130,000.00 140,000.00 12,350.00 13,300.00
L.04 0.048 OH Mandor 125,000.00 135,000.00 6,000.00 6,480.00

B Bahan - -
- m' Pipa DCI Ø 250 mm 100,000.00 110,000.00 - -

C PERALATAN 730.00 876.00


0.073 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 730.00 876.00

D Jumlah A + B + C 57,160.00 63,496.00


E Overhead & Profit (contoh 10%) 10% 5,716.00 6,349.60
F Harga Satuan Pekerjaan (D+E) 62,876.00 69,845.60

54 A.8.4.2.54 1 bh Pemotongan Pipa DCI Ø 300 mm 67,523.50 75,012.30


A Tenaga 60,595.00 67,245.00
L.01 0.512 OH Pekerja 80,000.00 90,000.00 40,960.00 46,080.00
L.02 0.102 OH Tukang Pipa 130,000.00 140,000.00 13,260.00 14,280.00
L.04 0.051 OH Mandor 125,000.00 135,000.00 6,375.00 6,885.00

B Bahan - -
m' Pipa DCI Ø 300 mm 120,000.00 130,000.00 - -

C PERALATAN 790.00 948.00


0.079 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 790.00 948.00

D Jumlah A + B + C 61,385.00 68,193.00


E Overhead & Profit (contoh 10%) 10% 6,138.50 6,819.30
F Harga Satuan Pekerjaan (D+E) 67,523.50 75,012.30

55 A.8.4.2.55 1 bh Pemotongan Pipa DCI Ø 400 mm 124,355.00 138,155.60


A Tenaga 111,470.00 123,700.00
L.01 0.941 OH Pekerja 80,000.00 90,000.00 75,280.00 84,690.00
L.02 0.188 OH Tukang Pipa 130,000.00 140,000.00 24,440.00 26,320.00
L.04 0.094 OH Mandor 125,000.00 135,000.00 11,750.00 12,690.00
- -
B Bahan - -
m' Pipa DCI Ø 400 mm 150,000.00 160,000.00 - -

C PERALATAN 1,580.00 1,896.00


0.158 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,580.00 1,896.00
- -
D Jumlah A + B + C 113,050.00 125,596.00
E Overhead & Profit (contoh 10%) 10% 11,305.00 12,559.60
F Harga Satuan Pekerjaan (D+E) 124,355.00 138,155.60

56 A.8.4.2.56 1 bh Pemotongan Pipa DCI Ø 450 mm 150,128.00 166,773.20


A Tenaga 134,720.00 149,500.00
L.01 1.137 OH Pekerja 80,000.00 90,000.00 90,960.00 102,330.00
L.02 0.227 OH Tukang Pipa 130,000.00 140,000.00 29,510.00 31,780.00
L.04 0.114 OH Mandor 125,000.00 135,000.00 14,250.00 15,390.00
- -
B Bahan - -
m' Pipa DCI Ø 450 mm 170,000.00 175,000.00 - -

C PERALATAN 1,760.00 2,112.00


0.176 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,760.00 2,112.00
- - - -
D Jumlah A + B + C 136,480.00 151,612.00
E Overhead & Profit (contoh 10%) 10% 13,648.00 15,161.20
F Harga Satuan Pekerjaan (D+E) 150,128.00 166,773.20
57 A.8.4.2.57 1 bh Pemotongan Pipa DCI Ø 500 mm 173,046.50 192,223.90
A Tenaga 155,395.00 172,445.00
L.01 1.312 OH Pekerja 80,000.00 90,000.00 104,960.00 118,080.00
L.02 0.262 OH Tukang Pipa 130,000.00 140,000.00 34,060.00 36,680.00
L.04 0.131 OH Mandor 125,000.00 135,000.00 16,375.00 17,685.00
- -
B Bahan - -
m' Pipa DCI Ø 500 mm 190,000.00 200,000.00 - -

C PERALATAN 1,920.00 2,304.00


0.192 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,920.00 2,304.00
- - - -
D Jumlah A + B + C 157,315.00 174,749.00
E Overhead & Profit (contoh 10%) 10% 15,731.50 17,474.90
F Harga Satuan Pekerjaan (D+E) 173,046.50 192,223.90

58 A.8.4.2.58 1 bh Pemotongan Pipa DCI Ø 600 mm 173,046.50 192,223.90


A Tenaga 155,395.00 172,445.00
L.01 1.312 OH Pekerja 80,000.00 90,000.00 104,960.00 118,080.00
L.02 0.262 OH Tukang Pipa 130,000.00 140,000.00 34,060.00 36,680.00
L.04 0.131 OH Mandor 125,000.00 135,000.00 16,375.00 17,685.00
- -
B Bahan - -
m' Pipa DCI Ø 600 mm 225,000.00 250,000.00 - -

C PERALATAN 1,920.00 2,304.00


0.192 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 1,920.00 2,304.00
- - - -
D Jumlah A + B + C 157,315.00 174,749.00
E Overhead & Profit (contoh 10%) 10% 15,731.50 17,474.90
F Harga Satuan Pekerjaan (D+E) 173,046.50 192,223.90

59 A.8.4.2.59 1 bh Pemotongan Pipa DCI Ø 800 mm 342,144.00 379,984.00


A Tenaga 307,940.00 341,720.00
L.01 2.598 OH Pekerja 80,000.00 90,000.00 207,840.00 233,820.00
L.02 0.520 OH Tukang Pipa 130,000.00 140,000.00 67,600.00 72,800.00
L.04 0.260 OH Mandor 125,000.00 135,000.00 32,500.00 35,100.00
- -
B Bahan - -
m' Pipa DCI Ø 800 mm 250,000.00 265,000.00 - -

C PERALATAN 3,100.00 3,720.00


0.310 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,100.00 3,720.00
- - - -
D Jumlah A + B + C 311,040.00 345,440.00
E Overhead & Profit (contoh 10%) 10% 31,104.00 34,544.00
F Harga Satuan Pekerjaan (D+E) 342,144.00 379,984.00

60 A.8.4.2.60 1 bh Pemotongan Pipa DCI Ø 900 mm 443,470.50 492,499.70


A Tenaga 399,345.00 443,155.00
L.01 3.370 OH Pekerja 80,000.00 90,000.00 269,600.00 303,300.00
L.02 0.674 OH Tukang Pipa 130,000.00 140,000.00 87,620.00 94,360.00
L.04 0.337 OH Mandor 125,000.00 135,000.00 42,125.00 45,495.00
- -
B Bahan - -
m' Pipa DCI Ø 900 mm 250,000.00 265,000.00 - -

C PERALATAN 3,810.00 4,572.00


0.381 hari Sewa Tripod / Tackel & handle crane 2 T 10,000.00 12,000.00 3,810.00 4,572.00
- - - -
D Jumlah A + B + C 403,155.00 447,727.00
E Overhead & Profit (contoh 10%) 10% 40,315.50 44,772.70
F Harga Satuan Pekerjaan (D+E) 443,470.50 492,499.70
61 A.8.4.2.61 1 bh Pemotongan Pipa DCI Ø 1.000 mm 528,946.00 587,413.20
A Tenaga 476,450.00 528,720.00
L.01 4.021 OH Pekerja 80,000.00 90,000.00 321,680.00 361,890.00
L.02 0.804 OH Tukang Pipa 130,000.00 140,000.00 104,520.00 112,560.00
L.04 0.402 OH Mandor 125,000.00 135,000.00 50,250.00 54,270.00
- -
B Bahan - -
m' Pipa DCI Ø 1.000 mm 280,000.00 290,000.00 - -

C PERALATAN 4,410.00 5,292.00


0.441 hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 4,410.00 5,292.00
- - - -
D Jumlah A + B + C 480,860.00 534,012.00
E Overhead & Profit (contoh 10%) 10% 48,086.00 53,401.20
F Harga Satuan Pekerjaan (D+E) 528,946.00 587,413.20

62 A.8.4.2.62 1 bh Pemotongan Pipa DCI Ø 1.100 mm 622,209.50 690,972.70


A Tenaga 560,585.00 622,085.00
L.01 4.731 OH Pekerja 80,000.00 90,000.00 378,480.00 425,790.00
L.02 0.946 OH Tukang Pipa 130,000.00 140,000.00 122,980.00 132,440.00
L.04 0.473 OH Mandor 125,000.00 135,000.00 59,125.00 63,855.00
- -
B Bahan - -
m' Pipa DCI Ø 1.100 mm 300,000.00 320,000.00 - -

C PERALATAN 5,060.00 6,072.00


0.506 hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 5,060.00 6,072.00
- - - -
D Jumlah A + B + C 565,645.00 628,157.00
E Overhead & Profit (contoh 10%) 10% 56,564.50 62,815.70
F Harga Satuan Pekerjaan (D+E) 622,209.50 690,972.70

63 A.8.4.2.63 1 bh Pemotongan Pipa DCI Ø 1.200 mm 723,437.00 803,376.20


A Tenaga 651,910.00 723,430.00
L.01 5.502 OH Pekerja 80,000.00 90,000.00 440,160.00 495,180.00
L.02 1.100 OH Tukang Pipa 130,000.00 140,000.00 143,000.00 154,000.00
L.04 0.550 OH Mandor 125,000.00 135,000.00 68,750.00 74,250.00
- -
B Bahan - -
m' Pipa DCI Ø 1.200 mm 320,000.00 340,000.00 - -

C PERALATAN 5,760.00 6,912.00


0.576 hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 5,760.00 6,912.00
- - - -
D Jumlah A + B + C 657,670.00 730,342.00
E Overhead & Profit (contoh 10%) 10% 65,767.00 73,034.20
F Harga Satuan Pekerjaan (D+E) 723,437.00 803,376.20

64 A.8.4.2.64 1 bh Pemotongan pipa Baja Ø 63 mm 4,955.50 5,566.00


A Tenaga 3,395.00 3,765.00
L.01 0.028 OH Pekerja 80,000.00 90,000.00 2,240.00 2,520.00
L.02 0.006 OH Tukang Pipa 130,000.00 140,000.00 780.00 840.00
L.04 0.003 OH Mandor 125,000.00 135,000.00 375.00 405.00

B Bahan - -
m' Pipa Baja Ø 63 mm 12,000.00 13,000.00 - -

C PERALATAN 1,110.00 1,295.00


0.037 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,110.00 1,295.00

D Jumlah A + B + C 4,505.00 5,060.00


E Overhead & Profit (contoh 10%) 10% 450.50 506.00
F Harga Satuan Pekerjaan (D+E) 4,955.50 5,566.00
65 A.8.4.2.65 1 bh Pemotongan Pipa Baja Ø 100 mm 12,331.00 13,761.00
A Tenaga 10,010.00 11,110.00
L.01 0.085 OH Pekerja 80,000.00 90,000.00 6,800.00 7,650.00
L.02 0.017 OH Tukang Pipa 130,000.00 140,000.00 2,210.00 2,380.00
L.04 0.008 OH Mandor 125,000.00 135,000.00 1,000.00 1,080.00

B Bahan - -
m' Pipa Baja Ø 100 mm 12,500.00 15,000.00 - -

C PERALATAN 1,200.00 1,400.00


0.04 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,200.00 1,400.00

D Jumlah A + B + C 11,210.00 12,510.00


E Overhead & Profit (contoh 10%) 10% 1,121.00 1,251.00
F Harga Satuan Pekerjaan (D+E) 12,331.00 13,761.00

66 A.8.4.2.66 1 bh Pemotongan Pipa Baja Ø 125 mm 18,738.50 20,872.50


A Tenaga 15,775.00 17,505.00
L.01 0.133 OH Pekerja 80,000.00 90,000.00 10,640.00 11,970.00
L.02 0.027 OH Tukang Pipa 130,000.00 140,000.00 3,510.00 3,780.00
L.04 0.013 OH Mandor 125,000.00 135,000.00 1,625.00 1,755.00

B Bahan - -
m' Pipa Baja Ø 125 mm 15,000.00 17,000.00 - -

C PERALATAN 1,260.00 1,470.00


0.042 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,260.00 1,470.00

D Jumlah A + B + C 17,035.00 18,975.00


E Overhead & Profit (contoh 10%) 10% 1,703.50 1,897.50
F Harga Satuan Pekerjaan (D+E) 18,738.50 20,872.50

67 A.8.4.2.67 1 bh Pemotongan Pipa Baja Ø 150 mm 25,443.00 28,319.50


A Tenaga 21,780.00 24,170.00
L.01 0.184 OH Pekerja 80,000.00 90,000.00 14,720.00 16,560.00
L.02 0.037 OH Tukang Pipa 130,000.00 140,000.00 4,810.00 5,180.00
L.04 0.018 OH Mandor 125,000.00 135,000.00 2,250.00 2,430.00

B Bahan - -
m' Pipa Baja Ø 150 mm 20,000.00 25,000.00 - -

C PERALATAN 1,350.00 1,575.00


0.045 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,350.00 1,575.00

D Jumlah A + B + C 23,130.00 25,745.00


E Overhead & Profit (contoh 10%) 10% 2,313.00 2,574.50
F Harga Satuan Pekerjaan (D+E) 25,443.00 28,319.50

68 A.8.4.2.68 1 bh Pemotongan Pipa Baja Ø 200 mm 64,053.00 71,192.00


A Tenaga 56,430.00 62,620.00
L.01 0.476 OH Pekerja 80,000.00 90,000.00 38,080.00 42,840.00
L.02 0.095 OH Tukang Pipa 130,000.00 140,000.00 12,350.00 13,300.00
L.04 0.048 OH Mandor 125,000.00 135,000.00 6,000.00 6,480.00

B Bahan - -
m' Pipa Baja Ø 200 mm 30,000.00 35,000.00 - -

C PERALATAN 1,800.00 2,100.00


0.06 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 1,800.00 2,100.00

D Jumlah A + B + C 58,230.00 64,720.00


E Overhead & Profit (contoh 10%) 10% 5,823.00 6,472.00
F Harga Satuan Pekerjaan (D+E) 64,053.00 71,192.00
69 A.8.4.2.69 1 bh Pemotongan Pipa Baja Ø 250 mm 88,682.00 98,538.00
A Tenaga 78,580.00 87,200.00
L.01 0.663 OH Pekerja 80,000.00 90,000.00 53,040.00 59,670.00
L.02 0.133 OH Tukang Pipa 130,000.00 140,000.00 17,290.00 18,620.00
L.04 0.066 OH Mandor 125,000.00 135,000.00 8,250.00 8,910.00

B Bahan - -
m' Pipa Baja Ø 250 mm 50,000.00 60,000.00 - -

C PERALATAN 2,040.00 2,380.00


0.068 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 2,040.00 2,380.00

D Jumlah A + B + C 80,620.00 89,580.00


E Overhead & Profit (contoh 10%) 10% 8,062.00 8,958.00
F Harga Satuan Pekerjaan (D+E) 88,682.00 98,538.00

70 A.8.4.2.70 1 bh Pemotongan Pipa Baja Ø 300 mm 99,418.00 110,462.00


A Tenaga 88,220.00 97,900.00
L.01 0.745 OH Pekerja 80,000.00 90,000.00 59,600.00 67,050.00
L.02 0.149 OH Tukang Pipa 130,000.00 140,000.00 19,370.00 20,860.00
L.04 0.074 OH Mandor 125,000.00 135,000.00 9,250.00 9,990.00

B Bahan - -
m' Pipa Baja Ø 300 mm 70,000.00 75,000.00 - -

C PERALATAN 2,160.00 2,520.00


0.072 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 2,160.00 2,520.00

D Jumlah A + B + C 90,380.00 100,420.00


E Overhead & Profit (contoh 10%) 10% 9,038.00 10,042.00
F Harga Satuan Pekerjaan (D+E) 99,418.00 110,462.00

71 A.8.4.2.71 1 bh Pemotongan Pipa Baja Ø 400 mm 191,169.00 212,338.50


A Tenaga 170,640.00 189,360.00
L.01 1.440 OH Pekerja 80,000.00 90,000.00 115,200.00 129,600.00
L.02 0.288 OH Tukang Pipa 130,000.00 140,000.00 37,440.00 40,320.00
L.04 0.144 OH Mandor 125,000.00 135,000.00 18,000.00 19,440.00

B Bahan - -
m' Pipa Baja Ø 400 mm 85,000.00 90,000.00 - -

C PERALATAN 3,150.00 3,675.00


0.105 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,150.00 3,675.00
- -
D Jumlah A + B + C 173,790.00 193,035.00
E Overhead & Profit (contoh 10%) 10% 17,379.00 19,303.50
F Harga Satuan Pekerjaan (D+E) 191,169.00 212,338.50

72 A.8.4.2.72 1 bh Pemotongan Pipa Baja Ø 450 mm 180,653.00 200,590.50


A Tenaga 161,020.00 178,610.00
L.01 1.339 OH Pekerja 80,000.00 90,000.00 107,120.00 120,510.00
L.02 0.280 OH Tukang Pipa 130,000.00 140,000.00 36,400.00 39,200.00
L.04 0.140 OH Mandor 125,000.00 135,000.00 17,500.00 18,900.00

B Bahan - -
m' Pipa Baja Ø 450 mm 100,000.00 110,000.00 - -

C PERALATAN 3,210.00 3,745.00


0.107 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,210.00 3,745.00
- - - -
D Jumlah A + B + C 164,230.00 182,355.00
E Overhead & Profit (contoh 10%) 10% 16,423.00 18,235.50
F Harga Satuan Pekerjaan (D+E) 180,653.00 200,590.50
73 A.8.4.2.73 1 bh Pemotongan Pipa Baja Ø 500 mm 193,996.00 215,528.50
A Tenaga 173,150.00 192,190.00
L.01 1.473 OH Pekerja 80,000.00 90,000.00 117,840.00 132,570.00
L.02 0.287 OH Tukang Pipa 130,000.00 140,000.00 37,310.00 40,180.00
L.04 0.144 OH Mandor 125,000.00 135,000.00 18,000.00 19,440.00

B Bahan - -
m' Pipa Baja Ø 500 mm 125,000.00 150,000.00 - -

C PERALATAN 3,210.00 3,745.00


0.107 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,210.00 3,745.00
- - - -
D Jumlah A + B + C 176,360.00 195,935.00
E Overhead & Profit (contoh 10%) 10% 17,636.00 19,593.50
F Harga Satuan Pekerjaan (D+E) 193,996.00 215,528.50

74 A.8.4.2.74 1 bh Pemotongan Pipa Baja Ø 600 mm 206,899.00 229,806.50


A Tenaga 184,700.00 204,960.00
L.01 1.558 OH Pekerja 80,000.00 90,000.00 124,640.00 140,220.00
L.02 0.312 OH Tukang Pipa 130,000.00 140,000.00 40,560.00 43,680.00
L.04 0.156 OH Mandor 125,000.00 135,000.00 19,500.00 21,060.00

B Bahan - -
m' Pipa Baja Ø 600 mm 180,000.00 200,000.00 - -

C PERALATAN 3,390.00 3,955.00


0.113 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 3,390.00 3,955.00
- - - -
D Jumlah A + B + C 188,090.00 208,915.00
E Overhead & Profit (contoh 10%) 10% 18,809.00 20,891.50
F Harga Satuan Pekerjaan (D+E) 206,899.00 229,806.50

75 A.8.4.2.75 1 bh Pemotongan Pipa Baja Ø 800 mm 347,490.00 385,924.00


A Tenaga 310,920.00 345,030.00
L.01 2.624 OH Pekerja 80,000.00 90,000.00 209,920.00 236,160.00
L.02 0.525 OH Tukang Pipa 130,000.00 140,000.00 68,250.00 73,500.00
L.04 0.262 OH Mandor 125,000.00 135,000.00 32,750.00 35,370.00

B Bahan - -
m' Pipa Baja Ø 800 mm 250,000.00 275,000.00 - -

C PERALATAN 4,980.00 5,810.00


0.166 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 4,980.00 5,810.00
- - - -
D Jumlah A + B + C 315,900.00 350,840.00
E Overhead & Profit (contoh 10%) 10% 31,590.00 35,084.00
F Harga Satuan Pekerjaan (D+E) 347,490.00 385,924.00

76 A.8.4.2.76 1 bh Pemotongan Pipa Baja Ø 900 mm 393,266.50 436,755.00


A Tenaga 352,025.00 390,645.00
L.01 2.971 OH Pekerja 80,000.00 90,000.00 237,680.00 267,390.00
L.02 0.594 OH Tukang Pipa 130,000.00 140,000.00 77,220.00 83,160.00
L.04 0.297 OH Mandor 125,000.00 135,000.00 37,125.00 40,095.00

B Bahan - -
m' Pipa Baja Ø 900 mm 300,000.00 320,000.00 - -

C PERALATAN 5,490.00 6,405.00


0.183 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 5,490.00 6,405.00
- - - -
D Jumlah A + B + C 357,515.00 397,050.00
E Overhead & Profit (contoh 10%) 10% 35,751.50 39,705.00
F Harga Satuan Pekerjaan (D+E) 393,266.50 436,755.00
77 A.8.4.2.77 1 bh Pemotongan Pipa Baja Ø 1.000 mm 439,307.00 487,877.50
A Tenaga 393,340.00 436,490.00
L.01 3.319 OH Pekerja 80,000.00 90,000.00 265,520.00 298,710.00
L.02 0.664 OH Tukang Pipa 130,000.00 140,000.00 86,320.00 92,960.00
L.04 0.332 OH Mandor 125,000.00 135,000.00 41,500.00 44,820.00

B Bahan - -
m' Pipa Baja Ø 1.000 mm 350,000.00 375,000.00 - -

C PERALATAN 6,030.00 7,035.00


0.201 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 6,030.00 7,035.00
- - - -
D Jumlah A + B + C 399,370.00 443,525.00
E Overhead & Profit (contoh 10%) 10% 39,937.00 44,352.50
F Harga Satuan Pekerjaan (D+E) 439,307.00 487,877.50

78 A.8.4.2.78 1 bh Pemotongan Pipa Baja Ø 1.100 mm 485,171.50 538,807.50


A Tenaga 434,525.00 482,195.00
L.01 3.667 OH Pekerja 80,000.00 90,000.00 293,360.00 330,030.00
L.02 0.733 OH Tukang Pipa 130,000.00 140,000.00 95,290.00 102,620.00
L.04 0.367 OH Mandor 125,000.00 135,000.00 45,875.00 49,545.00

B Bahan - -
m' Pipa Baja Ø 1.100 mm 400,000.00 425,000.00 - -

C PERALATAN 6,540.00 7,630.00


0.218 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 6,540.00 7,630.00
- - - -
D Jumlah A + B + C 441,065.00 489,825.00
E Overhead & Profit (contoh 10%) 10% 44,106.50 48,982.50
F Harga Satuan Pekerjaan (D+E) 485,171.50 538,807.50

79 A.8.4.2.79 1 bh Pemotongan Pipa Baja Ø 1.200 mm 531,212.00 589,930.00


A Tenaga 475,840.00 528,040.00
L.01 4.015 OH Pekerja 80,000.00 90,000.00 321,200.00 361,350.00
L.02 0.803 OH Tukang Pipa 130,000.00 140,000.00 104,390.00 112,420.00
L.04 0.402 OH Mandor 125,000.00 135,000.00 50,250.00 54,270.00

B Bahan - -
m' Pipa Baja Ø 1.200 mm 450,000.00 475,000.00 - -

C PERALATAN 7,080.00 8,260.00


0.236 hari Peralatan Potong pipa T2/mekanik/cilinder saw 30,000.00 35,000.00 7,080.00 8,260.00
- - - -
D Jumlah A + B + C 482,920.00 536,300.00
E Overhead & Profit (contoh 10%) 10% 48,292.00 53,630.00
F Harga Satuan Pekerjaan (D+E) 531,212.00 589,930.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN PEMASANGAN


XVIII A.8.4.3
AKSESORIS PIPA
1 A.8.4.3.1 1 bh Pemasangan Valve Ø 150 mm 303,759.50 345,636.50
A Tenaga 225,145.00 248,015.00
L.01 1.429 OH Pekerja 80,000.00 90,000.00 114,320.00 128,610.00
L.02 0.715 OH Tukang Pipa 130,000.00 140,000.00 92,950.00 100,100.00
L.04 0.143 OH Mandor 125,000.00 135,000.00 17,875.00 19,305.00
B Bahan 50,000.00 65,000.00
1 bh Valve Ø 150 mm 50,000.00 65,000.00 50,000.00 65,000.00
C PERALATAN 1,000.00 1,200.00
0.1 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,000.00 1,200.00

D Jumlah A + B + C 276,145.00 314,215.00


E Overhead & Profit (contoh 10%) 10% 27,614.50 31,421.50
F Harga Satuan Pekerjaan (D+E) 303,759.50 345,636.50

2 A.8.4.3.2 1 bh Pemasangan Valve Ø 200 mm 382,695.50 430,017.50


A Tenaga 269,905.00 297,325.00
L.01 1.714 OH Pekerja 80,000.00 90,000.00 137,120.00 154,260.00
L.02 0.857 OH Tukang Pipa 130,000.00 140,000.00 111,410.00 119,980.00
L.04 0.171 OH Mandor 125,000.00 135,000.00 21,375.00 23,085.00

B Bahan 75,000.00 90,000.00


1 bh Valve Ø 200 mm 75,000.00 90,000.00 75,000.00 90,000.00

C PERALATAN 3,000.00 3,600.00


0.3 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,000.00 3,600.00

D Jumlah A + B + C 347,905.00 390,925.00


E Overhead & Profit (contoh 10%) 10% 34,790.50 39,092.50
F Harga Satuan Pekerjaan (D+E) 382,695.50 430,017.50

3 A.8.4.3.3 1 bh Pemasangan Valve Ø 250 mm 438,795.50 480,837.50


A Tenaga 269,905.00 297,325.00
L.01 1.714 OH Pekerja 80,000.00 90,000.00 137,120.00 154,260.00
L.02 0.857 OH Tukang Pipa 130,000.00 140,000.00 111,410.00 119,980.00
L.04 0.171 OH Mandor 125,000.00 135,000.00 21,375.00 23,085.00

B Bahan 125,000.00 135,000.00


1 bh Valve Ø 250 mm 125,000.00 135,000.00 125,000.00 135,000.00

C PERALATAN 4,000.00 4,800.00


0.4 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 4,000.00 4,800.00

D Jumlah A + B + C 398,905.00 437,125.00


E Overhead & Profit (contoh 10%) 10% 39,890.50 43,712.50
F Harga Satuan Pekerjaan (D+E) 438,795.50 480,837.50

4 A.8.4.3.4 1 bh Pemasangan Valve Ø 300 mm 517,000.00 575,300.00


A Tenaga 315,000.00 347,000.00
L.01 2.000 OH Pekerja 80,000.00 90,000.00 160,000.00 180,000.00
L.02 1.000 OH Tukang Pipa 130,000.00 140,000.00 130,000.00 140,000.00
L.04 0.200 OH Mandor 125,000.00 135,000.00 25,000.00 27,000.00

B Bahan 150,000.00 170,000.00


1 bh Valve Ø 300 mm 150,000.00 170,000.00 150,000.00 170,000.00

C PERALATAN 5,000.00 6,000.00


0.5 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00
D Jumlah A + B + C 470,000.00 523,000.00
E Overhead & Profit (contoh 10%) 10% 47,000.00 52,300.00
F Harga Satuan Pekerjaan (D+E) 517,000.00 575,300.00
5 A.8.4.3.5 1 bh Pemasangan Valve Ø 400 mm 907,659.50 997,716.50
A Tenaga 540,145.00 595,015.00
L.01 3.429 OH Pekerja 80,000.00 90,000.00 274,320.00 308,610.00
L.02 1.715 OH Tukang Pipa 130,000.00 140,000.00 222,950.00 240,100.00
L.04 0.343 OH Mandor 125,000.00 135,000.00 42,875.00 46,305.00

B Bahan 275,000.00 300,000.00


1 bh Valve Ø 400 mm 275,000.00 300,000.00 275,000.00 300,000.00

C PERALATAN 10,000.00 12,000.00


1 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00

D Jumlah A + B + C 825,145.00 907,015.00


E Overhead & Profit (contoh 10%) 10% 82,514.50 90,701.50
F Harga Satuan Pekerjaan (D+E) 907,659.50 997,716.50

6 A.8.4.3.6 1 bh Pemasangan Valve Ø 450 mm 962,659.50 1,052,716.50


A Tenaga 540,145.00 595,015.00
L.01 3.429 OH Pekerja 80,000.00 90,000.00 274,320.00 308,610.00
L.02 1.715 OH Tukang Pipa 130,000.00 140,000.00 222,950.00 240,100.00
L.04 0.343 OH Mandor 125,000.00 135,000.00 42,875.00 46,305.00

B Bahan 325,000.00 350,000.00


1 bh Valve Ø 450 mm 325,000.00 350,000.00 325,000.00 350,000.00

C PERALATAN 10,000.00 12,000.00


1 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00

D Jumlah A + B + C 875,145.00 957,015.00


E Overhead & Profit (contoh 10%) 10% 87,514.50 95,701.50
F Harga Satuan Pekerjaan (D+E) 962,659.50 1,052,716.50

7 A.8.4.3.7 1 bh Pemasangan Valve Ø 500 mm 1,116,500.00 1,216,600.00


A Tenaga 630,000.00 694,000.00
L.01 4.000 OH Pekerja 80,000.00 90,000.00 320,000.00 360,000.00
L.02 2.000 OH Tukang Pipa 130,000.00 140,000.00 260,000.00 280,000.00
L.04 0.400 OH Mandor 125,000.00 135,000.00 50,000.00 54,000.00

B Bahan 375,000.00 400,000.00


1 bh Valve Ø 500 mm 375,000.00 400,000.00 375,000.00 400,000.00

C PERALATAN 10,000.00 12,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00

D Jumlah A + B + C 1,015,000.00 1,106,000.00


E Overhead & Profit (contoh 10%) 10% 101,500.00 110,600.00
F Harga Satuan Pekerjaan (D+E) 1,116,500.00 1,216,600.00

8 A.8.4.3.8 1 bh Pemasangan Valve Ø 600 mm 769,846.00 830,280.00


A Tenaga 223,860.00 246,600.00
L.01 1.421 OH Pekerja 80,000.00 90,000.00 113,680.00 127,890.00
L.02 0.711 OH Tukang Pipa 130,000.00 140,000.00 92,430.00 99,540.00
L.04 0.142 OH Mandor 125,000.00 135,000.00 17,750.00 19,170.00

B Bahan 425,000.00 450,000.00


1 bh Valve Ø 600 mm 425,000.00 450,000.00 425,000.00 450,000.00

C PERALATAN 51,000.00 58,200.00


0.600 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 6,000.00 7,200.00
0.300 hari Mobile crane = < 3 ton 150,000.00 170,000.00 45,000.00 51,000.00
D Jumlah A + B + C 699,860.00 754,800.00
E Overhead & Profit (contoh 10%) 10% 69,986.00 75,480.00
F Harga Satuan Pekerjaan (D+E) 769,846.00 830,280.00
9 A.8.4.3.9 1 bh Pemasangan Valve Ø 700 mm 885,659.50 944,916.50
A Tenaga 225,145.00 248,015.00
L.01 1.429 OH Pekerja 80,000.00 90,000.00 114,320.00 128,610.00
L.02 0.715 OH Tukang Pipa 130,000.00 140,000.00 92,950.00 100,100.00
L.04 0.143 OH Mandor 125,000.00 135,000.00 17,875.00 19,305.00

B Bahan 500,000.00 520,000.00


1 bh Valve Ø 700 mm 500,000.00 520,000.00 500,000.00 520,000.00

C PERALATAN 80,000.00 91,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00
0.500 hari Mobile crane = < 3 ton 150,000.00 170,000.00 75,000.00 85,000.00
D Jumlah A + B + C 805,145.00 859,015.00
E Overhead & Profit (contoh 10%) 10% 80,514.50 85,901.50
F Harga Satuan Pekerjaan (D+E) 885,659.50 944,916.50

10 A.8.4.3.10 1 bh Pemasangan Valve Ø 800 mm 1,002,479.50 1,073,517.50


A Tenaga 281,345.00 309,925.00
L.01 1.786 OH Pekerja 80,000.00 90,000.00 142,880.00 160,740.00
L.02 0.893 OH Tukang Pipa 130,000.00 140,000.00 116,090.00 125,020.00
L.04 0.179 OH Mandor 125,000.00 135,000.00 22,375.00 24,165.00

B Bahan 550,000.00 575,000.00


1 bh Valve Ø 800 mm 550,000.00 575,000.00 550,000.00 575,000.00

C PERALATAN 80,000.00 91,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00
0.500 hari Mobile crane = < 3 ton 150,000.00 170,000.00 75,000.00 85,000.00
D Jumlah A + B + C 911,345.00 975,925.00
E Overhead & Profit (contoh 10%) 10% 91,134.50 97,592.50
F Harga Satuan Pekerjaan (D+E) 1,002,479.50 1,073,517.50

11 A.8.4.3.11 1 bh Pemasangan Valve Ø 900 mm 1,088,895.50 1,164,707.50


A Tenaga 269,905.00 297,325.00
L.01 1.714 OH Pekerja 80,000.00 90,000.00 137,120.00 154,260.00
L.02 0.857 OH Tukang Pipa 130,000.00 140,000.00 111,410.00 119,980.00
L.04 0.171 OH Mandor 125,000.00 135,000.00 21,375.00 23,085.00
B Bahan 600,000.00 625,000.00
1 bh Valve Ø 900 mm 600,000.00 625,000.00 600,000.00 625,000.00
C PERALATAN 120,000.00 136,500.00
0.750 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 7,500.00 9,000.00
0.750 hari Mobile crane = < 3 ton 150,000.00 170,000.00 112,500.00 127,500.00
D Jumlah A + B + C 989,905.00 1,058,825.00
E Overhead & Profit (contoh 10%) 10% 98,990.50 105,882.50
F Harga Satuan Pekerjaan (D+E) 1,088,895.50 1,164,707.50

12 A.8.4.3.12 1 bh Pemasangan Valve Ø 1.000 mm 1,336,483.50 1,416,937.50


A Tenaga 404,985.00 446,125.00
L.01 2.571 OH Pekerja 80,000.00 90,000.00 205,680.00 231,390.00
L.02 1.286 OH Tukang Pipa 130,000.00 140,000.00 167,180.00 180,040.00
L.04 0.257 OH Mandor 125,000.00 135,000.00 32,125.00 34,695.00

B Bahan 650,000.00 660,000.00


1 bh Valve Ø 1.000 mm 650,000.00 660,000.00 650,000.00 660,000.00

C PERALATAN 160,000.00 182,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00
1.000 hari Mobile crane = < 3 ton 150,000.00 170,000.00 150,000.00 170,000.00
D Jumlah A + B + C 1,214,985.00 1,288,125.00
E Overhead & Profit (contoh 10%) 10% 121,498.50 128,812.50
F Harga Satuan Pekerjaan (D+E) 1,336,483.50 1,416,937.50
13 A.8.4.3.13 1 bh Pemasangan Valve Ø 1.100 mm 1,465,750.00 1,553,750.00
A Tenaga 472,500.00 520,500.00
L.01 3.000 OH Pekerja 80,000.00 90,000.00 240,000.00 270,000.00
L.02 1.500 OH Tukang Pipa 130,000.00 140,000.00 195,000.00 210,000.00
L.04 0.300 OH Mandor 125,000.00 135,000.00 37,500.00 40,500.00

B Bahan 700,000.00 710,000.00


1 bh Valve Ø 1.100 mm 700,000.00 710,000.00 700,000.00 710,000.00

C PERALATAN 160,000.00 182,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00
1.000 hari Mobile crane = < 3 ton 150,000.00 170,000.00 150,000.00 170,000.00
D Jumlah A + B + C 1,332,500.00 1,412,500.00
E Overhead & Profit (contoh 10%) 10% 133,250.00 141,250.00
F Harga Satuan Pekerjaan (D+E) 1,465,750.00 1,553,750.00

14 A.8.4.3.14 1 bh Pemasangan Valve Ø 1.200 mm 1,498,750.00 1,597,750.00


A 472,500.00 520,500.00
L.01 3.000 OH Pekerja 80,000.00 90,000.00 240,000.00 270,000.00
L.02 1.500 OH Tukang Pipa 130,000.00 140,000.00 195,000.00 210,000.00
L.04 0.300 OH Mandor 125,000.00 135,000.00 37,500.00 40,500.00

B Bahan 730,000.00 750,000.00


1 bh Valve Ø 1.200 mm 730,000.00 750,000.00 730,000.00 750,000.00

C PERALATAN 160,000.00 182,000.00


1.000 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,000.00 12,000.00
1.000 hari Mobile crane = < 3 ton 150,000.00 170,000.00 150,000.00 170,000.00
D Jumlah A + B + C 1,362,500.00 1,452,500.00
E Overhead & Profit (contoh 10%) 10% 136,250.00 145,250.00
F Harga Satuan Pekerjaan (D+E) 1,498,750.00 1,597,750.00

15 A.8.4.3.15 1 bh Pemasangan Tee Ø 150 mm 31,927.50 37,159.10


A Tenaga 16,745.00 18,445.00
L.01 0.106 OH Pekerja 80,000.00 90,000.00 8,480.00 9,540.00
L.02 0.053 OH Tukang Pipa 130,000.00 140,000.00 6,890.00 7,420.00
L.04 0.011 OH Mandor 125,000.00 135,000.00 1,375.00 1,485.00

B Bahan 12,000.00 15,000.00


1 bh Tee Ø 150 mm 12,000.00 15,000.00 12,000.00 15,000.00

C PERALATAN 280.00 336.00


0.028 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 280.00 336.00

D Jumlah A + B + C 29,025.00 33,781.00


E Overhead & Profit (contoh 10%) 10% 2,902.50 3,378.10
F Harga Satuan Pekerjaan (D+E) 31,927.50 37,159.10

16 A.8.4.3.16 1 bh Pemasangan Tee Ø 200 mm 54,296.00 63,665.80


A Tenaga 34,070.00 37,530.00
L.01 0.216 OH Pekerja 80,000.00 90,000.00 17,280.00 19,440.00
L.02 0.108 OH Tukang Pipa 130,000.00 140,000.00 14,040.00 15,120.00
L.04 0.022 OH Mandor 125,000.00 135,000.00 2,750.00 2,970.00
B Bahan 15,000.00 20,000.00
1 bh Tee Ø 200 mm 15,000.00 20,000.00 15,000.00 20,000.00

C PERALATAN 290.00 348.00


0.029 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 290.00 348.00
D Jumlah A + B + C 49,360.00 57,878.00
E Overhead & Profit (contoh 10%) 10% 4,936.00 5,787.80
F Harga Satuan Pekerjaan (D+E) 54,296.00 63,665.80
17 A.8.4.3.17 1 bh Pemasangan Tee Ø 250 mm 84,463.50 95,791.30
A Tenaga 51,395.00 56,615.00
L.01 0.326 OH Pekerja 80,000.00 90,000.00 26,080.00 29,340.00
L.02 0.163 OH Tukang Pipa 130,000.00 140,000.00 21,190.00 22,820.00
L.04 0.033 OH Mandor 125,000.00 135,000.00 4,125.00 4,455.00

B Bahan 25,000.00 30,000.00


1 BH Tee Ø 250 mm 25,000.00 30,000.00 25,000.00 30,000.00

C PERALATAN 390.00 468.00


0.039 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 390.00 468.00

D Jumlah A + B + C 76,785.00 87,083.00


E Overhead & Profit (contoh 10%) 10% 7,678.50 8,708.30
F Harga Satuan Pekerjaan (D+E) 84,463.50 95,791.30

18 A.8.4.3.18 1 bh Pemasangan Tee Ø 300 mm 119,592.00 133,870.00


A Tenaga 68,720.00 75,700.00
L.01 0.436 OH Pekerja 80,000.00 90,000.00 34,880.00 39,240.00
L.02 0.218 OH Tukang Pipa 130,000.00 140,000.00 28,340.00 30,520.00
L.04 0.044 OH Mandor 125,000.00 135,000.00 5,500.00 5,940.00

B Bahan 35,000.00 40,000.00


1 bh Tee Ø 300 mm 35,000.00 40,000.00 35,000.00 40,000.00

C PERALATAN 5,000.00 6,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00

D Jumlah A + B + C 108,720.00 121,700.00


E Overhead & Profit (contoh 10%) 10% 10,872.00 12,170.00
F Harga Satuan Pekerjaan (D+E) 119,592.00 133,870.00

19 A.8.4.3.19 1 bh Pemasangan Tee Ø 400 mm 168,707.00 186,857.00


A Tenaga 103,370.00 113,870.00
L.01 0.656 OH Pekerja 80,000.00 90,000.00 52,480.00 59,040.00
L.02 0.328 OH Tukang Pipa 130,000.00 140,000.00 42,640.00 45,920.00
L.04 0.066 OH Mandor 125,000.00 135,000.00 8,250.00 8,910.00

B Bahan 45,000.00 50,000.00


1 bh Tee Ø 400 mm 45,000.00 50,000.00 45,000.00 50,000.00
C PERALATAN 5,000.00 6,000.00
0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00

D Jumlah A + B + C 153,370.00 169,870.00


E Overhead & Profit (contoh 10%) 10% 15,337.00 16,987.00
F Harga Satuan Pekerjaan (D+E) 168,707.00 186,857.00

20 A.8.4.3.20 1 bh Pemasangan Tee Ø 450 mm 209,764.50 229,850.50


A Tenaga 120,695.00 132,955.00
L.01 0.766 OH Pekerja 80,000.00 90,000.00 61,280.00 68,940.00
L.02 0.383 OH Tukang Pipa 130,000.00 140,000.00 49,790.00 53,620.00
L.04 0.077 OH Mandor 125,000.00 135,000.00 9,625.00 10,395.00

B Bahan 65,000.00 70,000.00


1 bh Tee Ø 450 mm 65,000.00 70,000.00 65,000.00 70,000.00

C PERALATAN 5,000.00 6,000.00


0.500 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 5,000.00 6,000.00

D Jumlah A + B + C 190,695.00 208,955.00


E Overhead & Profit (contoh 10%) 10% 19,069.50 20,895.50
F Harga Satuan Pekerjaan (D+E) 209,764.50 229,850.50
21 A.8.4.3.21 1 bh Pemasangan Tee Ø 500 mm 240,922.00 263,164.00
A Tenaga 138,020.00 152,040.00
L.01 0.876 OH Pekerja 80,000.00 90,000.00 70,080.00 78,840.00
L.02 0.438 OH Tukang Pipa 130,000.00 140,000.00 56,940.00 61,320.00
L.04 0.088 OH Mandor 125,000.00 135,000.00 11,000.00 11,880.00

B Bahan 75,000.00 80,000.00


1 bh Tee Ø 500 mm 75,000.00 80,000.00 75,000.00 80,000.00

C PERALATAN 6,000.00 7,200.00


0.600 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 6,000.00 7,200.00

D Jumlah A + B + C 219,020.00 239,240.00


E Overhead & Profit (contoh 10%) 10% 21,902.00 23,924.00
F Harga Satuan Pekerjaan (D+E) 240,922.00 263,164.00

22 A.8.4.3.22 1 bh Pemasangan Tee Ø 600 mm 306,900.00 339,730.60


A Tenaga 172,670.00 190,210.00
L.01 1.096 OH Pekerja 80,000.00 90,000.00 87,680.00 98,640.00
L.02 0.548 OH Tukang Pipa 130,000.00 140,000.00 71,240.00 76,720.00
L.04 0.110 OH Mandor 125,000.00 135,000.00 13,750.00 14,850.00

B Bahan 90,000.00 100,000.00


1 bh Tee Ø 600 mm 90,000.00 100,000.00 90,000.00 100,000.00

C PERALATAN 16,330.00 18,636.00


0.193 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 1,930.00 2,316.00
0.096 hari Mobile crane = < 3 ton 150,000.00 170,000.00 14,400.00 16,320.00
D Jumlah A + B + C 279,000.00 308,846.00
E Overhead & Profit (contoh 10%) 10% 27,900.00 30,884.60
F Harga Satuan Pekerjaan (D+E) 306,900.00 339,730.60

23 A.8.4.3.23 1 bh Pemasangan Tee Ø 700 mm 370,172.00 401,819.00


A Tenaga 207,320.00 228,380.00
L.01 1.316 OH Pekerja 80,000.00 90,000.00 105,280.00 118,440.00
L.02 0.658 OH Tukang Pipa 130,000.00 140,000.00 85,540.00 92,120.00
L.04 0.132 OH Mandor 125,000.00 135,000.00 16,500.00 17,820.00

B Bahan 110,000.00 115,000.00


1 bh Tee Ø 700 mm 110,000.00 115,000.00 110,000.00 115,000.00

C PERALATAN 19,200.00 21,910.00


0.225 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,250.00 2,700.00
0.113 hari Mobile crane = < 3 ton 150,000.00 170,000.00 16,950.00 19,210.00
D Jumlah A + B + C 336,520.00 365,290.00
E Overhead & Profit (contoh 10%) 10% 33,652.00 36,529.00
F Harga Satuan Pekerjaan (D+E) 370,172.00 401,819.00

24 A.8.4.3.24 1 bh Pemasangan Tee Ø 800 mm 422,279.00 463,720.40


A Tenaga 241,970.00 266,550.00
L.01 1.536 OH Pekerja 80,000.00 90,000.00 122,880.00 138,240.00
L.02 0.768 OH Tukang Pipa 130,000.00 140,000.00 99,840.00 107,520.00
L.04 0.154 OH Mandor 125,000.00 135,000.00 19,250.00 20,790.00
B Bahan 120,000.00 130,000.00
1 bh Tee Ø 800 mm 120,000.00 130,000.00 120,000.00 130,000.00
C PERALATAN 21,920.00 25,014.00
0.257 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 2,570.00 3,084.00
0.129 hari Mobile crane = < 3 ton 150,000.00 170,000.00 19,350.00 21,930.00
D Jumlah A + B + C 383,890.00 421,564.00
E Overhead & Profit (contoh 10%) 10% 38,389.00 42,156.40
F Harga Satuan Pekerjaan (D+E) 422,279.00 463,720.40
25 A.8.4.3.25 1 bh Pemasangan Tee Ø 900 mm 488,378.00 534,536.20
A Tenaga 276,620.00 304,720.00
L.01 1.756 OH Pekerja 80,000.00 90,000.00 140,480.00 158,040.00
L.02 0.878 OH Tukang Pipa 130,000.00 140,000.00 114,140.00 122,920.00
L.04 0.176 OH Mandor 125,000.00 135,000.00 22,000.00 23,760.00

B Bahan 140,000.00 150,000.00


1 bh Tee Ø 900 mm 140,000.00 150,000.00 140,000.00 150,000.00

C PERALATAN 27,360.00 31,222.00


0.321 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,210.00 3,852.00
0.161 hari Mobile crane = < 3 ton 150,000.00 170,000.00 24,150.00 27,370.00
D Jumlah A + B + C 443,980.00 485,942.00
E Overhead & Profit (contoh 10%) 10% 44,398.00 48,594.20
F Harga Satuan Pekerjaan (D+E) 488,378.00 534,536.20

26 A.8.4.3.26 1 bh Pemasangan Tee Ø 1.000 mm 552,618.00 603,231.20


A Tenaga 311,270.00 342,890.00
L.01 1.976 OH Pekerja 80,000.00 90,000.00 158,080.00 177,840.00
L.02 0.988 OH Tukang Pipa 130,000.00 140,000.00 128,440.00 138,320.00
L.04 0.198 OH Mandor 125,000.00 135,000.00 24,750.00 26,730.00

B Bahan 160,000.00 170,000.00


1 bh Tee Ø 1.000 mm 160,000.00 170,000.00 160,000.00 170,000.00

C PERALATAN 31,110.00 35,502.00


0.366 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,660.00 4,392.00
0.183 hari Mobile crane = < 3 ton 150,000.00 170,000.00 27,450.00 31,110.00
D Jumlah A + B + C 502,380.00 548,392.00
E Overhead & Profit (contoh 10%) 10% 50,238.00 54,839.20
F Harga Satuan Pekerjaan (D+E) 552,618.00 603,231.20

27 A.8.4.3.27 1 bh Pemasangan Tee Ø 1.100 mm 614,603.00 669,352.20


A Tenaga 345,920.00 381,060.00
L.01 2.196 OH Pekerja 80,000.00 90,000.00 175,680.00 197,640.00
L.02 1.098 OH Tukang Pipa 130,000.00 140,000.00 142,740.00 153,720.00
L.04 0.220 OH Mandor 125,000.00 135,000.00 27,500.00 29,700.00

B Bahan 180,000.00 190,000.00


1 bh Tee Ø 1.100 mm 180,000.00 190,000.00 180,000.00 190,000.00

C PERALATAN 32,810.00 37,442.00


0.386 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 3,860.00 4,632.00
0.193 hari Mobile crane = < 3 ton 150,000.00 170,000.00 28,950.00 32,810.00
D Jumlah A + B + C 558,730.00 608,502.00
E Overhead & Profit (contoh 10%) 10% 55,873.00 60,850.20
F Harga Satuan Pekerjaan (D+E) 614,603.00 669,352.20

28 A.8.4.3.28 1 bh Pemasangan Tee Ø 1.200 mm 680,702.00 740,168.00


A Tenaga 380,570.00 419,230.00
L.01 2.416 OH Pekerja 80,000.00 90,000.00 193,280.00 217,440.00
L.02 1.208 OH Tukang Pipa 130,000.00 140,000.00 157,040.00 169,120.00
L.04 0.242 OH Mandor 125,000.00 135,000.00 30,250.00 32,670.00
B Bahan 200,000.00 210,000.00
1 bh Tee Ø 1.200 mm 200,000.00 210,000.00 200,000.00 210,000.00
C PERALATAN 38,250.00 43,650.00
0.450 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 4,500.00 5,400.00
0.225 hari Mobile crane = < 3 ton 150,000.00 170,000.00 33,750.00 38,250.00
D Jumlah A + B + C 618,820.00 672,880.00
E Overhead & Profit (contoh 10%) 10% 61,882.00 67,288.00
F Harga Satuan Pekerjaan (D+E) 680,702.00 740,168.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN


XIX A.8.4.4
PENYAMBUNGAN PIPA BARU KE PIPA LAMA

1 A.8.4.4.1 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 480,694.50 556,506.50
80 mm
A Tenaga 230,945.00 254,405.00
L.01 1.466 OH Pekerja 80,000.00 90,000.00 117,280.00 131,940.00
L.02 0.733 OH Tukang Pipa 130,000.00 140,000.00 95,290.00 102,620.00
L.04 0.147 OH Mandor 125,000.00 135,000.00 18,375.00 19,845.00

B Bahan 50,000.00 65,000.00


1 bh Pipa Ø 80 mm 50,000.00 65,000.00 50,000.00 65,000.00

C PERALATAN 156,050.00 186,510.00


0.606 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 15,150.00 18,180.00
0.075 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 11,250.00 12,750.00
0.968 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 121,000.00 145,200.00
0.865 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 8,650.00 10,380.00

D Jumlah A + B + C 436,995.00 505,915.00


E Overhead & Profit (contoh 10%) 10% 43,699.50 50,591.50
F Harga Satuan Pekerjaan (D+E) 480,694.50 556,506.50

2 A.8.4.4.2 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 555,527.50 643,276.70
100 mm
A Tenaga 251,065.00 285,635.00
L.01 1.646 OH Pekerja 75,000.00 90,000.00 123,450.00 148,140.00
L.02 0.823 OH Tukang Pipa 130,000.00 140,000.00 106,990.00 115,220.00
L.04 0.165 OH Mandor 125,000.00 135,000.00 20,625.00 22,275.00

B Bahan 70,000.00 80,000.00


1 bh Pipa Ø 100 mm 70,000.00 80,000.00 70,000.00 80,000.00

C PERALATAN 183,960.00 219,162.00


0.650 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 16,250.00 19,500.00
0.159 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 23,850.00 27,030.00
1.078 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 134,750.00 161,700.00
0.911 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 9,110.00 10,932.00

D Jumlah A + B + C 505,025.00 584,797.00


E Overhead & Profit (contoh 10%) 10% 50,502.50 58,479.70
F Harga Satuan Pekerjaan (D+E) 555,527.50 643,276.70

3 A.8.4.4.3 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 795,767.50 906,952.20
150 mm
A Tenaga 319,690.00 363,710.00
L.01 2.096 OH Pekerja 75,000.00 90,000.00 157,200.00 188,640.00
L.02 1.048 OH Tukang Pipa 130,000.00 140,000.00 136,240.00 146,720.00
L.04 0.210 OH Mandor 125,000.00 135,000.00 26,250.00 28,350.00
B Bahan 150,000.00 160,000.00
1 bh Pipa Ø 150 mm 150,000.00 160,000.00 150,000.00 160,000.00
C PERALATAN 253,735.00 300,792.00
0.76 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 19,000.00 22,800.00
0.369 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 55,350.00 62,730.00
1.353 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 169,125.00 202,950.00
1.026 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,260.00 12,312.00
D Jumlah A + B + C 723,425.00 824,502.00
E Overhead & Profit (contoh 10%) 10% 72,342.50 82,450.20
F Harga Satuan Pekerjaan (D+E) 795,767.50 906,952.20
4 A.8.4.4.4 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,003,007.50 1,148,627.70
200 mm
A Tenaga 388,315.00 441,785.00
L.01 2.546 OH Pekerja 75,000.00 90,000.00 190,950.00 229,140.00
L.02 1.273 OH Tukang Pipa 130,000.00 140,000.00 165,490.00 178,220.00
L.04 0.255 OH Mandor 125,000.00 135,000.00 31,875.00 34,425.00
B Bahan 200,000.00 220,000.00
1 bh Pipa Ø 200 mm 200,000.00 220,000.00 200,000.00 220,000.00
C PERALATAN 323,510.00 382,422.00
0.87 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 21,750.00 26,100.00
0.579 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 86,850.00 98,430.00
1.628 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 203,500.00 244,200.00
1.141 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 11,410.00 13,692.00
D Jumlah A + B + C 911,825.00 1,044,207.00
E Overhead & Profit (contoh 10%) 10% 91,182.50 104,420.70
F Harga Satuan Pekerjaan (D+E) 1,003,007.50 1,148,627.70

5 A.8.4.4.5 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,182,747.50 1,346,303.20
250 mm
A Tenaga 456,940.00 519,860.00
L.01 2.996 OH Pekerja 75,000.00 90,000.00 224,700.00 269,640.00
L.02 1.498 OH Tukang Pipa 130,000.00 140,000.00 194,740.00 209,720.00
L.04 0.300 OH Mandor 125,000.00 135,000.00 37,500.00 40,500.00
B Bahan 225,000.00 240,000.00
1 bh Pipa Ø 250 mm 225,000.00 240,000.00 225,000.00 240,000.00
C PERALATAN 393,285.00 464,052.00
0.980 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 24,500.00 29,400.00
0.789 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 118,350.00 134,130.00
1.903 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 237,875.00 285,450.00
1.256 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 12,560.00 15,072.00
D Jumlah A + B + C 1,075,225.00 1,223,912.00
E Overhead & Profit (contoh 10%) 10% 107,522.50 122,391.20
F Harga Satuan Pekerjaan (D+E) 1,182,747.50 1,346,303.20

6 A.8.4.4.6 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,351,487.50 1,532,978.70
300 mm
A Tenaga 525,565.00 597,935.00
L.01 3.446 OH Pekerja 75,000.00 90,000.00 258,450.00 310,140.00
L.02 1.723 OH Tukang Pipa 130,000.00 140,000.00 223,990.00 241,220.00
L.04 0.345 OH Mandor 125,000.00 135,000.00 43,125.00 46,575.00
B Bahan 240,000.00 250,000.00
1 bh Pipa Ø 250 mm 240,000.00 250,000.00 240,000.00 250,000.00
C PERALATAN 463,060.00 545,682.00
1.090 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 27,250.00 32,700.00
0.999 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 149,850.00 169,830.00
2.178 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 272,250.00 326,700.00
1.371 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 13,710.00 16,452.00
D Jumlah A + B + C 1,228,625.00 1,393,617.00
E Overhead & Profit (contoh 10%) 10% 122,862.50 139,361.70
F Harga Satuan Pekerjaan (D+E) 1,351,487.50 1,532,978.70

7 A.8.4.4.7 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,688,967.50 1,917,329.70
400 mm
A Tenaga 662,815.00 754,085.00
L.01 4.346 OH Pekerja 75,000.00 90,000.00 325,950.00 391,140.00
L.02 2.173 OH Tukang Pipa 130,000.00 140,000.00 282,490.00 304,220.00
L.04 0.435 OH Mandor 125,000.00 135,000.00 54,375.00 58,725.00
B Bahan 270,000.00 280,000.00
1 bh Pipa Ø 400 mm 270,000.00 280,000.00 270,000.00 280,000.00
C PERALATAN 602,610.00 708,942.00
1.310 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 32,750.00 39,300.00
1.419 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 212,850.00 241,230.00
2.728 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 341,000.00 409,200.00
1.601 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 16,010.00 19,212.00
D Jumlah A + B + C 1,535,425.00 1,743,027.00
E Overhead & Profit (contoh 10%) 10% 153,542.50 174,302.70
F Harga Satuan Pekerjaan (D+E) 1,688,967.50 1,917,329.70

8 A.8.4.4.8 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,863,207.50 2,115,005.20
450 mm
A Tenaga 731,440.00 832,160.00
L.01 4.796 OH Pekerja 75,000.00 90,000.00 359,700.00 431,640.00
L.02 2.398 OH Tukang Pipa 130,000.00 140,000.00 311,740.00 335,720.00
L.04 0.480 OH Mandor 125,000.00 135,000.00 60,000.00 64,800.00

B Bahan 290,000.00 300,000.00


1 bh Pipa Ø 450 mm 290,000.00 300,000.00 290,000.00 300,000.00

C PERALATAN 672,385.00 790,572.00


1.420 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 35,500.00 42,600.00
1.629 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 244,350.00 276,930.00
3.003 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 375,375.00 450,450.00
1.716 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 17,160.00 20,592.00

D Jumlah A + B + C 1,693,825.00 1,922,732.00


E Overhead & Profit (contoh 10%) 10% 169,382.50 192,273.20
F Harga Satuan Pekerjaan (D+E) 1,863,207.50 2,115,005.20

9 A.8.4.4.9 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,048,447.50 2,323,680.70
500 mm
A Tenaga 800,065.00 910,235.00
L.01 5.246 OH Pekerja 75,000.00 90,000.00 393,450.00 472,140.00
L.02 2.623 OH Tukang Pipa 130,000.00 140,000.00 340,990.00 367,220.00
L.04 0.525 OH Mandor 125,000.00 135,000.00 65,625.00 70,875.00

B Bahan 320,000.00 330,000.00


1 bh Pipa Ø 500 mm 320,000.00 330,000.00 320,000.00 330,000.00

C PERALATAN 742,160.00 872,202.00


1.530 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 38,250.00 45,900.00
1.839 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 275,850.00 312,630.00
3.278 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 409,750.00 491,700.00
1.831 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 18,310.00 21,972.00

D Jumlah A + B + C 1,862,225.00 2,112,437.00


E Overhead & Profit (contoh 10%) 10% 186,222.50 211,243.70
F Harga Satuan Pekerjaan (D+E) 2,048,447.50 2,323,680.70

10 A.8.4.4.10 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,385,927.50 2,708,031.70
600 mm
A Tenaga 937,315.00 1,066,385.00
L.01 6.146 OH Pekerja 75,000.00 90,000.00 460,950.00 553,140.00
L.02 3.073 OH Tukang Pipa 130,000.00 140,000.00 399,490.00 430,220.00
L.04 0.615 OH Mandor 125,000.00 135,000.00 76,875.00 83,025.00
B Bahan 350,000.00 360,000.00
1 bh Pipa Ø 600 mm 350,000.00 360,000.00 350,000.00 360,000.00
C PERALATAN 881,710.00 1,035,462.00
1.750 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 43,750.00 52,500.00
2.259 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 338,850.00 384,030.00
3.828 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 478,500.00 574,200.00
2.061 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 20,610.00 24,732.00
D Jumlah A + B + C 2,169,025.00 2,461,847.00
E Overhead & Profit (contoh 10%) 10% 216,902.50 246,184.70
F Harga Satuan Pekerjaan (D+E) 2,385,927.50 2,708,031.70
11 A.8.4.4.11 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,756,407.50 3,125,382.70
700 mm
A Tenaga 1,074,565.00 1,222,535.00
L.01 7.046 OH Pekerja 75,000.00 90,000.00 528,450.00 634,140.00
L.02 3.523 OH Tukang Pipa 130,000.00 140,000.00 457,990.00 493,220.00
L.04 0.705 OH Mandor 125,000.00 135,000.00 88,125.00 95,175.00
B Bahan 410,000.00 420,000.00
1 bh Pipa Ø 700 mm 410,000.00 420,000.00 410,000.00 420,000.00
C PERALATAN 1,021,260.00 1,198,722.00
1.970 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 49,250.00 59,100.00
2.679 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 401,850.00 455,430.00
4.378 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 547,250.00 656,700.00
2.291 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 22,910.00 27,492.00

D Jumlah A + B + C 2,505,825.00 2,841,257.00


E Overhead & Profit (contoh 10%) 10% 250,582.50 284,125.70
F Harga Satuan Pekerjaan (D+E) 2,756,407.50 3,125,382.70

12 A.8.4.4.11 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 3,082,887.50 3,509,733.70
800 mm
A Tenaga 1,211,815.00 1,378,685.00
L.01 7.946 OH Pekerja 75,000.00 90,000.00 595,950.00 715,140.00
L.02 3.973 OH Tukang Pipa 130,000.00 140,000.00 516,490.00 556,220.00
L.04 0.795 OH Mandor 125,000.00 135,000.00 99,375.00 107,325.00

B Bahan 430,000.00 450,000.00


1 bh Pipa Ø 800 mm 430,000.00 450,000.00 430,000.00 450,000.00

C PERALATAN 1,160,810.00 1,361,982.00


2.190 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 54,750.00 65,700.00
3.099 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 464,850.00 526,830.00
4.928 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 616,000.00 739,200.00
2.521 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 25,210.00 30,252.00

D Jumlah A + B + C 2,802,625.00 3,190,667.00


E Overhead & Profit (contoh 10%) 10% 280,262.50 319,066.70
F Harga Satuan Pekerjaan (D+E) 3,082,887.50 3,509,733.70
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN


XX A.8.4.5
PENGETESAN
1 A.8.4.5.1 1 m' Pengetesan Pipa Ø 50 mm 1,358.83 1,485.44
A Tenaga 740.00 828.00
L.01 0.008 OH Pekerja 80,000.00 90,000.00 640.00 720.00
L.04 0.0008 OH Mandor 125,000.00 135,000.00 100.00 108.00

B Bahan 495.30 522.40


0.002 m³ Air Bersih 150.00 200.00 0.30 0.40
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,235.30 1,350.40
E Overhead & Profit (contoh 10%) 10% 123.53 135.04
F Harga Satuan Pekerjaan (D+E) 1,358.83 1,485.44

2 A.8.4.5.2 1 m' Pengetesan Pipa Ø 75 mm 1,359.16 1,485.88


A Tenaga 740.00 828.00
L.01 0.008 OH Pekerja 80,000.00 90,000.00 640.00 720.00
L.04 0.0008 OH Mandor 125,000.00 135,000.00 100.00 108.00

B Bahan 495.60 522.80


0.004 m³ Air Bersih 150.00 200.00 0.60 0.80
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,235.60 1,350.80
E Overhead & Profit (contoh 10%) 10% 123.56 135.08
F Harga Satuan Pekerjaan (D+E) 1,359.16 1,485.88

3 A.8.4.5.3 1 m' Pengetesan Pipa Ø 100 mm 1,359.82 1,486.76


A Tenaga 740.00 828.00
L.01 0.008 OH Pekerja 80,000.00 90,000.00 640.00 720.00
L.04 0.0008 OH Mandor 125,000.00 135,000.00 100.00 108.00

B Bahan 496.20 523.60


0.008 m³ Air Bersih 150.00 200.00 1.20 1.60
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,236.20 1,351.60
E Overhead & Profit (contoh 10%) 10% 123.62 135.16
F Harga Satuan Pekerjaan (D+E) 1,359.82 1,486.76

4 A.8.4.5.4 1 m' Pengetesan Pipa Ø 150 mm 1,361.47 1,488.96


A Tenaga 740.00 828.00
L.01 0.008 OH Pekerja 80,000.00 90,000.00 640.00 720.00
L.04 0.0008 OH Mandor 125,000.00 135,000.00 100.00 108.00

B Bahan 497.70 525.60


0.0180 m³ Air Bersih 150.00 200.00 2.70 3.60
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,237.70 1,353.60
E Overhead & Profit (contoh 10%) 10% 123.77 135.36
F Harga Satuan Pekerjaan (D+E) 1,361.47 1,488.96
5 A.8.4.5.5 1 m' Pengetesan Pipa Ø 200 mm 1,363.62 1,491.82
A Tenaga 740.00 828.00
L.01 0.008 OH Pekerja 80,000.00 90,000.00 640.00 720.00
L.04 0.0008 OH Mandor 125,000.00 135,000.00 100.00 108.00
B Bahan 499.65 528.20
0.031 m³ Air Bersih 150.00 200.00 4.65 6.20
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,239.65 1,356.20
E Overhead & Profit (contoh 10%) 10% 123.97 135.62
F Harga Satuan Pekerjaan (D+E) 1,363.62 1,491.82

6 A.8.4.5.6 1 m' Pengetesan Pipa Ø 250 mm 1,366.59 1,495.78


A Tenaga 740.00 828.00
L.01 0.008 OH Pekerja 80,000.00 90,000.00 640.00 720.00
L.04 0.0008 OH Mandor 125,000.00 135,000.00 100.00 108.00
B Bahan 502.35 531.80
0.049 m³ Air Bersih 150.00 200.00 7.35 9.80
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,242.35 1,359.80
E Overhead & Profit (contoh 10%) 10% 124.24 135.98
F Harga Satuan Pekerjaan (D+E) 1,366.59 1,495.78

7 A.8.4.5.7 1 m' Pengetesan Pipa Ø 300 mm 1,370.22 1,500.62


A Tenaga 740.00 828.00
L.01 0.008 OH Pekerja 80,000.00 90,000.00 640.00 720.00
L.04 0.0008 OH Mandor 125,000.00 135,000.00 100.00 108.00
B Bahan 505.65 536.20
0.071 m³ Air Bersih 150.00 200.00 10.65 14.20
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,245.65 1,364.20
E Overhead & Profit (contoh 10%) 10% 124.57 136.42
F Harga Satuan Pekerjaan (D+E) 1,370.22 1,500.62

8 A.8.4.5.8 1 m' Pengetesan Pipa Ø 400 mm 1,379.29 1,512.72


A Tenaga 740.00 828.00
L.01 0.008 OH Pekerja 80,000.00 90,000.00 640.00 720.00
L.04 0.0008 OH Mandor 125,000.00 135,000.00 100.00 108.00
B Bahan 513.90 547.20
0.126 m³ Air Bersih 150.00 200.00 18.90 25.20
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,253.90 1,375.20
E Overhead & Profit (contoh 10%) 10% 125.39 137.52
F Harga Satuan Pekerjaan (D+E) 1,379.29 1,512.72

9 A.8.4.5.9 1 m' Pengetesan Pipa Ø 500 mm 1,384.57 1,519.76


A Tenaga 740.00 828.00
L.01 0.008 OH Pekerja 80,000.00 90,000.00 640.00 720.00
L.04 0.0008 OH Mandor 125,000.00 135,000.00 100.00 108.00
B Bahan 518.70 553.60
0.158 m³ Air Bersih 150.00 200.00 23.70 31.60
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
D Jumlah A + B + C 1,258.70 1,381.60
E Overhead & Profit (contoh 10%) 10% 125.87 138.16
F Harga Satuan Pekerjaan (D+E) 1,384.57 1,519.76

10 A.8.4.5.10 1 m' Pengetesan Pipa Ø 600 mm 1,405.20 1,547.26


A Tenaga 740.00 828.00
L.01 0.008 OH Pekerja 80,000.00 90,000.00 640.00 720.00
L.04 0.0008 OH Mandor 125,000.00 135,000.00 100.00 108.00
B Bahan 537.45 578.60
0.283 m³ Air Bersih 150.00 200.00 42.45 56.60
0.060 ltr Bahan Bakar 7,000.00 7,200.00 420.00 432.00
0.002 ltr Oli 37,500.00 45,000.00 75.00 90.00
C PERALATAN - -
- -

D Jumlah A + B + C 1,277.45 1,406.60


E Overhead & Profit (contoh 10%) 10% 127.75 140.66
F Harga Satuan Pekerjaan (D+E) 1,405.20 1,547.26

You might also like