Professional Documents
Culture Documents
VOLUME - 1
BEFORE THE ARBITRAL TRIBUNAL COMPRISING OF
BETWEEN
re
\ ',._j
(;
'/
M/S JSC "VO "TECHNOPROMEXPORT", RUSSIA
AND
('
(~)
BEFORE THE ARBITRAL TRIBUNAL COMPRISING
OF
C, NTPC LIMITED
... COUNTER- CLAIMANT /RESPONDENT
STATEMENT OF COUNTER-CLAIM
INDEX OF VOLUME 1
A. Memo of Parties 3
(
(";
!
Statement of Facts supporting the
• 1• 48 -112
(··>..· •
Counter-Claim
(. ;
.
Page I of 150
2. The Points at issue I 113
5. : Vakalatnama 154
i
Index '
!
provided
6. Volumes 3 - 12
(' in each
(·
~- volume
()
c· PLACE: NEW DELHI ~rTa
= ~(• o<"-li'T'l)
Add!. General Manager (ME)
DATE: FEBRUARY 7fH, 2017 l!_,el<i',tf, - <tr<f!NTPC • Barh
COUNTER-CLAIMANT/ RESPONDENT
THROU
®
()
GUST LEGAL
S-553, GREATE KAILASH - II,
NEW DELHI - 110048.
(
•,·
Page 2 of 150
c·.
..'·
/~·-.
ALSO AT:
( 90, POORVI MARG,
(..• VASANT VIHAR,
('
\.
VERSUS
()
NTPC LIMITED
NTPC BHAVAN
SCOPE COMPLEX,
7, INSTITUTION AREA, LODHI ROAD,
() NEW DELHI - 110003.
(}j •.• COUNTER-CLAIMANT /RESPONDENT
C>
('
Page 3 of 150
(
(.
,..
B. LIST OF RELEVANT DATES AND EVENTS
DATES EVENTS
Page 4 of 150
iii) FGUP "VO "Technopromexport"
(which was later renamed as JSC "VO
"Technopromexport" and hereinafter
interchangeably referred to as the
Ci
"Claimant", "Contractor" or "TPE").
()
····--.·,
14 th , 2005 awarded to TPE vide Notifications of Award
(
(hereinafter referred to as "NoA") of date. TPE
C had to undertake the Barh STPP Stage - I
along with its collaborators M/ s Krasny
Kotelschik (hereinafter referred to as "TKZ"),
CJ
M/ s Teploelectroproject (hereinafter referred to
(1
"TEP") and M/ s Zarubezhenergoproject
(;
(hereinafter referred to as "ZEP"), which
(! collaborators had jointly furnished a Deed of
(r·:·:
(: :-·
Joint Undertaking (hereinafter referred to as
"DJU") along with TPE as part of the
documents submitted along with TPE's bid.
(;
The collaborators i.e. TKZ, TEP and ZEP shall
hereinafter be collectively referred to as "DJU
( '·':
,;,/ Associates".
c·~- •.
Page 5 of 150
(',
(>,
\: --
Page 6 of 150
• Six Hundred Eighty Six Million Nine Hundred
Ninety Three Thousand Seven Hundred and
Eighty Four only) amended to INR
772,570,796/-{Rupees Seven Hundred
Seventy Two Million Five Hundred Seventy
Thousand Seven Hundred and Ninety Six
only) vide Amendment No. 3 dated September
J5ti1 , 2007.
Page 7 of 150
only) + INR 2,034,288,297 / (Rupees Two
Billion Thirty Four Million Two Hundred
Eighty Eight Thousand Two Hundred and
Ninety Seven only) vide Amendment No. 4
dated June 18 th , 2009.
(
Page 8 of 150
' '
(" .,
'· . Page9 of 150
such change along with the said letter.
I
/ .
\ .. Page 10 of 150
C offices.
( Page 11 of 150
October Based on the documents provided by TPE to
26 th , 2006 the Russian law firm engaged by NTPC, the
_process of establishing the validity of change
November 1n legal status of TPE and its success10n
-lO th , 2006 could be initiated and ascertained.
(
Page l2 of 150
any matter arising out of or relating to the
recognition of the Company as successor to
FGUP by NTPC from the date it arose till the
()
date hereof and · each party accordingly
C', releases the other from any claims or
( liabilities on account thereof'.
() 20%.
Page 13 of 150
•
{ ,.
February NTPC categorically rejected TPE's demand for
24 th , 2007 inclusion of provisions with regard to time
extension and removal of the existing price
variation ceiling of 20% in the amendment
(
forwarded by NTPC on December 22 nd , 2006.
C·
'·
r
Page 14 of ISO
;
.
(
'. April 4 th , NTPC wrote a letter of date to TPE asking TPE
C.·
April 18 th , TPE conveyed its willingness to sign the
2007 Amendment No. 2 dated December 22 nd ,
2006, after the deletion of clause 3 of the said
,-,
() amendment. The said clause no. 3 is quoted
() hereinabove.
Page 15 of 150
the FGUP 1.e. Federal State Unitary
Enterprise "Foreign Economic Association
"Technopromexport" wherever appeanng 1n
the text of the Contracts was substituted by
the name of the company 1.e. Joint Stock
Company "Foreign Economic Association
"Technopromexport".
(
•.
Page 16 of 150
1·:·
\.
,,,·
:(
November· During a Contract Review Meeting
20 th - 21st, (hereinafter referred to as "CRM") of date, TPE
2007 again requested NTPC to consider time
extension 1n the Contracts schedule and
removal of existing pnce variation ceiling of
20% provided 1n the Contracts. NTPC
reiterated that schedules and terms of the
Contracts shall not be changed and any claim
of TPE with regard to time extension and/ or
(.:
cost. compensation shall be dealt strictly
(
within the framework and terms of the
Contracts.
(_:
(,
'-~·.,
April 22 nd , After several pnor communications and
I.
( Page 17 of 150
!. 9 th , 2008 the situation, TPE failed to adhere to the
(,
terms of the Contracts. Therefore, NTPC was
..
constrained to serve notice on TPE invoking
Adjudication under Clause 6.1 of the GCC in
the event TPE failed to commence Unit # 1
boiler erection by September 23 rd , 2008.
( ,
for appointment of an Adjudicator.
f:.. >.
Page 18 of 150
'
( Further, NTPC was justified in seeking
'
,,,., . documents and information regarding
, .. .
\.
the said transformation and did not act
unreasonably in seeking legal opinion.
);> Both the parties have been responsible
for infringing the time imperatives.
);> It 1s not possible to quantify the
proportion in which the parties have
contributed to the delays.
c~·:
);> An attempt needs to be made to resolve
( the problem by an attitude of give and
take.
i
December Pursuant to the decision of the Adjudicator,
()
2008 - both parties (NPTC and TPE) held multiple
March rounds of discussions in India as well as in
2009 Russia to work out a mutually acceptable
solution. However, all such discussions
remained stalemated.
,·· ....
,., .
('
Page 20 of 150
( .· 2 nd , 2009 the CBI, NTPC sought legal opinion regarding
, . proper course of action in the matter. The
\. :
legal op1n1on, as sought, was received by
('.
\.;./
NTPC from their legal advisors vide letter of
date.
(. '·.
January NTPC vide letter of date stated that TPE
~·· '
9 th , 2010 raised exorbitant claim of increase 1n
Contracts price by 87% in a meeting held on
,.
( Page 21 of 150
;_:_.::_.
\·"·.·
'.,
December 10 th , 2009. The letter further
highlighted the repeated breaches committed
by TPE, inter alia, failure to commence
erection, failure of adherence to the
sequential supply schedule, persistent failure
(: to execute and perform its obligations as
required under the Contracts and discharge
of its (TPE) obligations under the First
Contract selectively by supplying the material
non-sequentially and disregarding the supply
C schedule.
Page 22 of 150
i/
\ _
"•
..
. Corporation, Russian Technologies, Mr.
(··. Alexander A. Lukin, General Director, TPE,
Mr. A Schegolev, Director of representation of
TPE in India from TPE.
C for implementation.
(0)
C Page 23 of 150
("
( ,._·,··.
October The amendment to the Contracts,
29 th , 2010 incorporating agreements reached between
NTPC and TPE as per above discussions, were
,. issued on October 29 th , 2010.
I: '.
Page 24 of 150
.· ..
V .:·
\. ..
>' Unit# 3: October 29th, 2014
c.
Activity Amended Status
Schedule I
() Mobilization of • Was to be Actually
erection achieved by mobilized on
C:' December 14th, February
(
( Page 25 of 150
j sub-contractor 2010 . 10th, 2011~
delay of about '
I
two (2)
months,
l. Only 20,946.2
MT out of the
49,172 MT
{i.e. 42.6%)
was erected
till the date of
termination
i.e. January
14th, 2015,
Page 26 of 150
''
'
i MT (Le.
(.) 38.2%) has
( 45563.4 MT
(i.e: 17.5%)
was erected
till the date of
termination
i.e. January
( 14th, 2015.
@J Completion of Was to be
'
Orders for
!
Page 27 of 150
(hereinafter as on the date
referred to as of termination
"BOls") for all i.e. January
('
"·"' three (3) units 14th, 2015.
(of 660 MW
each)
----····--------
Completion of Was to be Not completed
engineering for completed by till date of
all three (3) January 28 th , termination
, ...
' units (of 660 2012 i.e. January
/'
·\ .'
MW each) 14th ' 2015.
(
\,_ . Page 28 of 150
r
!
14th , 2015. l
r.
\- Synchronisation! Was to be Not completed
and coal firing carried out by till date of
for Unit# 1 June 29 th , 2013 termination
(\ i.e. January
C: 14th, 2015.
Page 29 of 150
(
8th-gth, During the meeting, TPE explained that the
..
,,' .
2013 main reason for delay in executing the
Contracts was financial problems being faced
by TPE. TPE further stated that it would
arrange sufficient funds to execute the
Contracts by the fourth quarter of 2013 and
TPE had accordingly submitted their program
for shipment/ ordering.
Page 30 of 150
\ . ' 450,000,000/- (US Dollar Four Hundred and
/·, Fifty Million only) with support from the
\
Government of Russian Federation.
' ..
'\-'.~:.
November The matter of delays in ordering and supply
2013- of material/ equipment by TPE was regularly
..<.
\ ..
March raised by NTPC vide various letters and
2014 meetings (dated November 1 st , 2013;
November 11th, 2013; November 29, 2013;
December 05 th , 2013; December 16 th , 2013;
C'.
December 17 th , 2013; January 20th, 2014;
(
January 31 st , 2014; February 13th, 2014;.
(
'· February 14 th , 2014; March 14 th , 2014 and
March 28 th , 2014) but to no avail.
! Page 31 of 150
March 3 rd CRM was held between NTPC and TPE at
- 5 th , 2014 Moscow. During the meeting, TPE indicated
that unless TPE received additional financial
support of USD 570,000,000/- {US Dollar
Five Hundred and Seventy Million only) from
the Government of Russian Federation, the
supply of balance material and ordering of
BOis could not be done.
r···.·
(
March TPE, vide its letter of the date, informed NTPC
12 th , 2014 that TPE had the intention to complete its
(
obligations under the Contracts provided it
('.:
(TPE) gets relevant support from the
(~' Government· of Russian Federation in so far
as raising of additional finance for Barh STPP
Stage-I was concerned and the same had
been taken up at the highest government
level with respect · to the existing legislative
r :.:.
Page 32 of 150
1·
r
c. Page 33 of 150
r·
I'' . .
Page 34 of 150
;
(
;
(
.·
Ii
September TKZ, vide letter of date (received on October
30th, 2014 7th, 2014) informed NPTC that it was
interested 1n continuation and successful
completion of the works under Barh STPP
Stage - I and requested for a tripartite
meeting involving NTPC-TPE-TKZ.
Page 35 of 150
C
'.
t
(,
... their scope of work (upto port as per
Contracts between TPE and TKZ) in the
Page 36 of 150
( event TPE releases their outstanding
payment of USD 5,500,000/ (US Dollar
Five Million Five Hundred Thousand
r,,.._··
\, ,.· only) for already supplied material over
. and above the payment required for
supplies of balance material.
• TKZ, further, expressed their inability in
providing any services/ support· in
procurement of other equipments/
components/ systems or any other
involvement for completion of steam
generator Package, without involvement
ofTPE.
Page 37 of 150
(
Page 38 of 150
'<.
its demand for increase in the contract price !
I~--
Two Hundred Forty Eight Million only) by way
\,; .. '
of additional finance.
(;
December' NTPC during its 415 th Board of Directors
23 rd , 2014 meeting held on date decided, in principle, to
terminate the Contracts with TPE.
,_( --..
{ .
... .·.
,:
Thousands Eight Hundred Fifty One and
\ . .-'
Forty Two Cents only) and INR 670,861,773/-
(Rupees Six Hundred Seventy Million Eight
Hundred Sixty One Thousand Seven Hundred
(.• Seventy Three only).
,,
( " ',
c··:.,
'-··· January NTPC, vide letter of date, communicated to
7th, 2015 TPE that:
Page 40 of 150
[ -
(.
\
---,_
( _, July 15 th , TPE, 1n its letter of date, sought mutual
(_
,.-.. Page 41 of 150
September NTPC, vide letter of date, forwarded its
,. 11 th , 2015 convenient dates i.e., September 22 nd , 23 rd
\ .·'
(,··:_
September TPE confirms the dates i.e., September 22 nd ,
c:/~:
16 th , 2015 23 rd and 24 th , 2015 (three dates) for holding
the mutual consultation meetings, as
forwarded by NTPC.
\". '•
I
'· . Page 42 of 150
r -
( Page 43 of 150
May 17 th , NTPC vide letter of date communicated to TPE
2016 about the accident that occurred on May 13th,
\ .
~ .. •
May 20 th , Ld. Adjudicator decided the dispute/ claim of
2016 the Parties vide decision dated May 20 th ,
2016.
( Page 44 of 150
> Termination of Contracts under the
clauses of Contracts as referred to under
Clause 42.2.2(c) of the GCC is valid.
(
Page 45 of I 50
May 25th, TPE expressed its .dissatisfaction with regard
2016 to the decision of the Adjudicator and
t:':"::'.";,
conveyed its intention to commence
\ ·-'
Arbitration for resolution of disputes under
r
(:}
Clause 6.2 of the GCC.
Page 46 of 150
nomination.
c:
c···
r·,
\...
( >.
Page 47 of 150
{ BEFORE THE ARBITRAL TRIBUNAL COMPRISING
OF
I
\ .. JSC "VO "TECHNOPROMEXPORT" .... CLAIMANT
() as under:
l, 1 NTPC having its office at the address
('.
mentioned above in the Memo of Parties is a
(
Page 48 of 150
public sector undertaking incorporated under
the Companies Act, 1956 engaged in the
.
business of generation of electricity and it has
been conferred a Maharatna status by the
Government of India. NTPC 1s being
represented herein through Mr. Kameshwar
Jha, Additional General Manager (Mechanical
Erection), Barh STPP, NTPC Limited.
, -:-~.
\ ..
' 1.2 The Claimant, as represented to NTPC, is, an
( engineering, procurement and construction
company incorporated in Russia.
(.;
1.3 Brief facts, in the background of the present
(,; dispute and submissions of NTPC, are as
(i under:
.
regional power project to meet the
prerequisites of northern region,
(
Page 49 of 150
( western region and home state of Bihar ·
{'' subject to final allocation by
l '
Page 50 ofl 50
!'. ,.·
Page 51 of 150
DJU's duly executed between TPE and
each of the aforementioned
collaborators/ associates referred to as
DJU Associates.
I~'.:_
1.3.5 That Contracts between NTPC and TPE
were trifurcated as under:
Page 52 of 150
f.< CS-9558-102-2-FC-COA-4520 dated
('
March 25 th , 2005 was signed between
\ '
the parties (NTPC and TPE) for
'Supply of Plant & Equipment
including mandatory spares (procured
() from outside India)' on CIF basis at a
contract price of USD 391,121,452/-
(US Dollar Three Hundred Ninety One
Million One Hundred Twenty One
Thousand Four Hundred and Fifty
Two only). The contract pnce was,
(
subsequently, amended to USD
',
388,910,673/-(US Dollar Three
(" Hundred Eighty Eight Million Nine
(i Hundred Ten Thousand Six Hundred
() and Seventy Three only) after deletion
Page 53 of 150
(·
',
I .
' ..
only) after deletion of Ocean Freight
and Marine Insurance {OF&MI) of
matching pieces (TUBE TRANSITION
PIECES) to be welded on turbine and
associated equipment vide
Amendment. No. 6 dated June 18 th ,
2009.
(
CS-9558-102-2-SC-COA-4521 dated
March 25 th , 2005 was signed between
{ .
"·-·'
the parties (NTPC and TPE), for the
'Supply of Plant and Equipment
including mandatory spares (procured
within India)' on ex-works basis at a
contract price of INR 686,993,784/-
(Rupees Six Hundred Eighty Six
Million Nine Hundred Ninety Three
( ..}
"-"· Thousand Seven Hundred and Eighty
@) Four only). The contract price was
amended to INR 772,570,796/-
(Rupees Seven Hundred Seventy Two
{ ·.
\,. __ ..,:
Million Five Hundred Seventy
(. .. Page 54 of 150
( Thousand Seven Hundred and. Ninety
Six only) after inclusion of supply of
auxiliary boiler including all
c· .
( .•. '
Page 55 of ISO
{ Thousand Four Hundred and Sixty
,' "I .
Three only). The aforesaid contract
\, _.·:
(·
(
' .. That the Contracts inter alia included a
Page 56 of 150
(-,
( '
1n Clause 3.1 of their respective NoA.
,.··
' ' The said Clause 3.1 provided that any
'
breach under . any of the three (3)
contracts 1.e. First Contract, Second
Contract or Third Contract shall
(
'· automatically be deemed as a breach of
the other two (2) contracts and shall
give NTPC a right to terminate all the
Contracts and/ or recover damages
thereunder.
i.
Page 57 of 150
(
Page 58 of 150
relevant statute and certificate of
( l
registration. It is submitted that the
documents, so furnished by TPE, could
not clarify NTPC's doubts regarding the
change in legal status of TPE and its
(,.. repercussions on the Contracts and
therefore, NTPC requested for a legal
op1n10n from a Russian law firm
regarding validity of such
transformation and succession to the
Contracts. It is stated that TPE declined
...
:,,~ .
to the proposal for legal opinion stating
that no law firm could get access to all
the internal documents related to
transformation of TPE. It submitted
that it is only after the intervention at
the Government level TPE agreed to
cooperate with the Russian law firm
appointed by NTPC and provided the
requisite documents to such law firm to
enable them to render the legal oi:iinion
sought by NTPC.
Page 59 of 150
uncooperative approach, TPE, vide its
letter dated August 2 nd , 2006, served
upon NTPC the notice to reduce the
'i...:-,;,.:
rate of progress under Clause 41.2 (b)
of the GCC stating that TPE was unable
to perform its contractual obligations.
\ Page 60 of 150
necessary Amendment No. 2 to the
Contracts based on input received from
the Russian law firm. TPE, vide its
letter dated December 26th, 2006,
amongst other grounds refused to
accept the Clause 3 of Amendment No.
02 which read as follows:
. i Page 61 of 150
\. .
attributable to TPE that the execution
of the amendments was delayed.
Page 62 of 150
made to the Contracts at that stage
and again TPE requested to resume
the work without any further delay
and sign the Amendment No. 2. NTPC,
vide its letter dated April 4 th , 2007,
directed TPE to resume work within
fourteen (14) days failing which NTPC
may take action against TPE under
the Contracts including "Completion
of Facilities" by itself or by employing
t· any third party at . the cost and
expense of TPE.
(.
C
1.3.12 That on April 20 th , 2007, TPE signed
the revised Amendment No. 2 issued
by NTPC after deletion of clause 3 and
the parties agreed that the changed
entity 1.e., Joint Stock Company
r"- - "Foreign Economic Association
\
( Economic Association
"Technopromexport" wherever
(
Page 63 of 150
i.
( .
appearing in the text of the Contracts
was substituted by the name of the
company i.e. Joint Stock Company
·"Foreign Economic Association
"Technopromexport".
Page 64 of 150
(
Page 65 of 150
(.'
('i
pre-assembly and storage area. TPE
\:/
Page 66 of 150
i.
1.
()
1.3.15 That the stand of TPE, as mentioned
('c
in the preceding paras, was contrary
I
I .• Page 67 of 150
(..... '·
Page 68 of 150
Adjudicator was pleased to pass a
decision dated November 28th, 2008.
.•
''
Page 69 of 150
(
,-"·
several rounds of discussions during
1{\
December, 2008, till March, 2009, 1n
India and Russia· to work out a
mutually accepted solution. However,
r, all such discussions remained
\ "·
stalemated due to the obstinate
()
approach adopted by TPE. NTPC, vide
"
(; its letter dated January 22°d, 2009,
(':
". categorically mentioned that TPE had
failed to submit its revised proposal of
time extension and/ or cost
compensation for consideration of
NTPC in accordance with the award
(:; dated November 28 th , 2008 passed by
(j(J; the Adjudicator.
(
1.3.19 lt is stated that neither TPE nor NTPC
challenged the decision dated
(
Page 70 of 150
( ..
'
1.3.20 That the stalemate situation between
TPE and NTPC was further
compounded when NTPC received a
communication from the CBI dated
June 30th 2009. The said
'
communication from CBI stated that
TPE had appointed an agent namely
( Page 71 of 150
'' -
Indian agent, the bidder was required
to declare in its bid, the de_tails about
name and address of the local agent,
,::~-.
~9
the services to be rendered by such
agent and the amount of
remuneration for the agent included in
the Bid Price (as defined in the 1TB).
Such information was required to be
furnished in the format of Attachment
8 to the bid form which ,vas mandated
( under Clause 8.3 (h) of Section-II (1TB)
of the bidding documents. TPE in
(
Attachment 8 to the bid form wrote
r.... ·
"NOT . APPLICABLE" across the
(_' Attachment which IS a dear
suppression of fact, as disclosed from
the aforesaid communication received
from CBI and thus also amounts to
misrepresentation. Further, CBI also
conveyed that investigation of the case
had revealed that TPE had paid illegal
commission to the tune of USD
22,334,530.73/- (US Dollar Twenty
Two Million Three Hundred Thirty
()
Four Thousand Five Hundred Thirty
Page 72 of 150
( and Seventy Three Cents only) to the
said agent M/s Ravina & Associates
Page 73 of 150
c-.-
(.:-
'·
>- Price variation shall be calculated
( as per . revised contract schedule
and contract formula and as per
indices provided in the Contracts
since 2005.
(,
(
\
Page 74 of 150
1.
{ ,
' .
1.3.23 That referring to the record of
{ ·.
"' ., abovementioned discussions held on
March 12 th , 2010, the Ministry of
~··, Power, vide letter dated May 28th,
l ..
.; '
Page 75 of 150
1.3.24 Accordingly, issues between NTPC and
( . TPE were discussed during June -
\.
(;
1.3.25 That as per aforesaid amendments to
C> the Contracts, the schedule for the
Completion of Facilities were revised
as under:
(·,
.
'-....: .·
Page 76 of 150
Units Original schedule Revised Schedule
for completion ol for the completion!
the facilities of the facilities
---·
Unit # January, 2009 · October, 2013
c·'·>.
l ..
.. · 1
Unit #I July, 2009 April, 2014
2
I
# January, 2010
i
Unit · October, 2014
C,.
3
I
(. Page 77 of 150
,,-"".
(·
amendments, TPE was again under
contractual obligation to resume
works under the Contracts and meet
the revised schedules. However, TPE
( again lagged behind in achieving the
interim milestones even as per the
reviseq schedules as per mutual
agreement. The following table clearly
f
\.,: shows the delays on the part of TPE
( even as per the revised schedules.
( Page 78 of 150
20,946.2 MT
out of the
'.J
49,172 MT (Le.
42.6%) ·was i
('
Page 79 of 150
I the 45563.4 ~
• {i.e. 17.5%) was I
erected till the
date of
termination i.e.
January 14 th ,
2015.
Page 80 of 150
Boiler light-up & Was to be Not completed
alkali boil out carried out by till date of
(
completion for· January 28th, termination i.e.
Unit# 1 2013 January 14th ,
2015.
I
' Synchronisation Was to be • Not completed
and coal firing carried out by till date of
(." - : .
for Unit# 1 June 29 th , 2013 termination i.e.
(
January 14 th ,
,.
C 2015.
(.
( '
Page 81 of 150
(
( Page 82 of 150
f held between NTPC and TPE on July
..,' '
4 th , 2012, CRM held on August 30th,
'· 2012 and later during an apex level
meeting held on November 23rd & 26th,
2012. It is stated that NTPC, vide its
letter dated December 27 th , 2012,
amongst others, reminded TPE, again,
about various commitments made by
TPE during the meeting on July 4th,
( ..
,',.
Page 83 of 150
C iisted various critical issues including
but not limited to the following:
Page 84 of 150
continued to willfully and intentionally
neglect its contractual obligations
without any justification or cause.
Page 85 of 150
\ October 29th, 2010, which provided
fresh timelines to be adhered to by
TPE for various activities and
milestones to be achieved by TPE.
TPE, once ag8.111, showed . utter
disregard for its contractual
obligations which had been stipulated
based on mutual discussions and
agreement between NTPC and TPE.
c· NTPC, vide letter dated September 4 th ,
C 2013, categorically informed TPE that
Page 86 of 150
(' .
Page 87 of 150
,·
'
I • :
nearly brought the installation work to
'· .
a standstill. In fact, TPE was not even
shipping the equipment/ material
which was ready for shipment and for
which MDCCs had been issued. It is a
matter of undisputed record that
c"'
'·· _:
(, Page 88 of 150
(-·· relation to the shipment of Power
Cycle Piping (388 MT), NMEJ (450
\: .·
pieces), Pressure Parts (2,919 MT), Air
& Gas Ducts (1,516 MT), SG.
(\
'-· .. ' Structures (2,930 MT), Auxiliary Steel
Structure and Tanks (2,143 MT),
Valves from Velan, Germany (77 MT),
Valves from Samkwang (345 MT), APH
(;)
Supporting Structure (1,410 MT),
C Compensators for Flue & Air Gas
(• Ducts (448 MT), RC Feeders (434 MT)
which items were critical for taking up
('.
the erection work at Barh STPP Stage-
( ·,.-'
I site. Even the erection activities at
(°': site were brought to stand still due to
() non-sequential supply of material and
· approximately 45,950 MT of material
was lying idle at site. Further, it is a
matter of undisputed record that TPE
(.
had also not shipped the 3,387 MT of
() material for which letters of credit
Page 89 of 150
(
(
14 th , 2014 written to TPE.
'
Page 90 of 150
( _,
1.3.39 That a CRM was held between NTPC
and TPE between March 3rd - 5th
'
2014, in Moscow, Russia. It is stated
that during the meeting, TPE indicated
( that unless it receives financial
support of USD 570,000,000/- (US
Dollar Five Hundred Seventy Million
only) from the Government of Russian
Federation, the supply of balance
material and ordering of BOis would
,,,,. not be possible. It is pertinent to
()
.. , mention that financial problems faced
( ,'
Page 92 of 150
(- Indian Ambassador to take up the
matter with appropriate authority in
the Government of Russian
Federation.
Page 93 of 150
were being, allegedly, mobilized by
{·
TPE's Russia operations to be
ploughed into the Barh STPP Stage-I.
It is pertinent to mention that TPE did
not provide or share any concrete plan
in relation to the efforts being made to
resolve TPE financial problems.
Page 94 of 150
' .
Page 95 of 150
TEP, for fulfilling their obligations
within fourteen (14) days invoking the
relevant provision of the respective
DJU.
(;
Page 97 of 150
1.3.48 That TPE, in the meanwhile, vide its
letter dated September 26 th , 2014
unilaterally revised (further increased)
its demands for an increase in the
contract price to the tune of USD
(,
248,000,000 /- (US Dollar Two
Hundred and Forty Eight Million only)
by way of additional finance from
NTPC and estimated that Unit # 1
could be completed by November,
2016, Unit# 2 by May, 2017 and Unit
''
# 3 by November, 2017. It is stated
C
that NTPC, vide its letter dated
\ ..
October 8 th , 2014, again rejected TPE's
C proposal demanding an increase in
the contract price by way of additional
finance from NTPC and also rejected
the extension of time as proposed by
TPE.
Page 98 of 150
i..'- .." Technological and Cultural
Cooperation was held in New Delhi on
''
October 30 th -3lst, 2014. During the
said meeting, it was categorically
communicated that if a satisfactory
time table for completion of work is
not agreed between the two sides
(NTPC and TPE) by December 1 st,
2014, NTPC would take appropriates
steps according to the terms of
Contracts. It is stated that the
(
November 11th, 2014, to assess TPE/
Page 99 of 150
TKZ willingness to execute the balance
works as per the· provisions of the
Contracts/DJUs. TKZ expressed its
()
inability to execute the balance works
( ",'
in its entirety. However, TKZ informed
that it was ready to start supply of
balance materials within its scope
(only upto port as per the agreement
between TPE and TKZ) subject to TPE
releasing its outstanding payment of
USD 5,500,000 /- (US Dollar Five
Million Five Hundred Thousand only)
for materials already supplied 1n
addition to the payment required for
supplies of balance materials. TKZ
(··
expressed its inability in providing any
services/ support in procurement of
other equipments/ components/
systems or any other involvement for
completion of steam generator
f···
l:) package, without the involvement of
@ TPE.
('>
;;/
(
14th, 2014, provisionally extended the
.,·"
; . -: without prejudice to NTPC's right to
levy liquidated damages as per Clause
26.2 of the GCC and categorically
(f\
'.'..,
stated that all the other terms and
(i conditions of the Contracts shall
remain unaltered. NTPC specifically
requested TPE for an unconditional
acceptance of the proposal made by
NTPC vide letter dated November 14 th ,
2014.
1·. '
payments to TPE only as per the terms
I: .
'
("
\ of the Contracts. It is re-iterated that
r: the NTPC was not contractually
\•
\. '.
1.3.54 That it became amply clear that in
spite of the mutually discussed and
()
agreed amendments dated October
(. 29 th , 2010, to the originally awarded
C) Contracts under ICB procedure, TPE
was still making contractually
untenable demands · for increase in
contract price by way of additional
finance .. and for unacceptable time
extensions:· It is most respectfully
('
·~.:./
submitted that from the sequences
(
.
. and events as described above, it is
evident that TPE had time and again
(
I·
'· 2014, served a 'notice of default' upon
c, under:
( ,,
20% ceiling
removal)
C;
cj 1.3.59 Between September, 2015 and
December, 2015, various mutual
c·, consultation meetings, as envisaged
1.::-,
\:,,; under Clause 6,1.l of the GCC, were
held for arriving at an amicable
settlement of disputes between NTPC
and TPE. The said process was
terminated by TPE, vide its letter
dated December 23 rd , 2015, which
,-- '
l) sought commencement of adjudication
·~· , '
(·",.
( 1.3.60 It 1s stated that Justice (retd.)
Sadanand Mukherjee was appointed
as Ld. Adjudicator and accordingly the
adjudication proceedings with the
("
,_:.:·
participation of the both the parties
were; held between April, 2016 and
May, 2016.
(-
1.3.61 It is submitted that while parties were
(
awaiting the outcome of the
adjudication proceedings, an accident
( _-_
Page 109 of 150
{
(
Page 110 of 150
...
I~ ..
r··,
,., : '
Counter-Claim. It may further be
noted that facts as presented in the
foregoing paras are based on
oocuments and communications
exchanged between parties which
C:
,..•
~~;
,_
C
()
c.:
(,:
(.
0?
c,
Page l 13 of 150
{
( off)
(· .
minus US Dollar Twenty Seven Million Five
Hundred Ninety Seven Thousand Four
Hundred and Fifty Four only)
s.
Name of!
Vendox
LOA/NO• I
. I I
the A/LOI/P Cost (lliR) Cost (USD) Cost (Euxo)
No. name
Package 0
. :
CS-
• Supply of
M/s 9558-
Air & Gas
l., 1 Lilama 102S-2-
Ducts
Corporal SU-NOA- 17,944,669.
and
ion- 6360 26
Structure
Lisemco dtd.
s
JSC 03.06.20
(i package
15
{
'. ·-
I
•
Page 116 of 150
I Custom:
i I
Clearanc ' i
e and
2
Transpor
tation of P.O. No.
Cargos of M/s 5500020
SG& Eoxco 619-034-
73,362,013.1
aux. Logistics 1028
8
Items for India dtd.
Stage-I Pvt. Ltd 16.05.20
along 15
with its
unloadin
g at Earh
,_'
STPP
(,
i
I i
('_:
& Entry
99 .
Tax, paid
I, 3b. I
-
Entry i
' 25,021,158.4
I
Tax, i
9
anticipat
ed
I 4
i
Erection
P.O. No., i
of Ducts
M/s 5500021
{~- . Supporti
ng
Mukand
570-034- 99,465,875.5
Engineer 1028 - 2
(_ Structure s Ltd.
dtd.
s&
( 26.11.20
Ducts
- --
----
I ' including!
I 15
i
'
NMEJs I
for
Unit# 1
i
i Erection i
of Fuel '
P.O. No. i
5
Oil M/s 5500021
Trestle Abhishe 587-034-
21,319,200.0
Steel k 1028
0
Structure Enterpri LOI dtd.
( ses 03.11.20
s
15
CIF i
i
Supply of
('
6 Balance CS-
a. Work of M/s 9558-
Main Doosan !02R-2-
Plant Power FC-NOA- 68,166,691.
Package Systems 6458 8,275,787.00
00
Part- India dtd.
A(SG& Pvt. Ltd. 30.01.20
Aux.) for 16
(.
· BSTPP
Stage-I
(; 6 Ex-
I Doosan· CS-
I
(,
b. Works(ln
dia)
Power
Systems
9558- ["·:06,90
102R-2-
(··
Supply of India SC-NOA-
~.
----- ~----
Main 30.01.20
Plant 16
Package
Part-
A(SG&
Aux.) for
BSTPP
Stage-!
. lnstal!ati ·
i !
on,
I
i I
Testing M/s
6
and Doosan
c. CS-
Commiss Power
9558-
ioning of Systems 102R-2-
Main India
TC-NOA- 4,385,411, 11
C Pvt. Ltd. 9,494,444
Plant 6460 3
Package dtd.
Part- 30.01.20
A(SG& 16
Aux.) for
BSTPP
Stage-!
9558- I I
Cycle ltd. 102D-2-
1,638,574,44 16,253,260.
Piping FC-NOA- 6,554,556
4.10 25
( Package 6349
for dt.
(
BSTPP 22.05.20
·---·-
•
\,
·---~,-
! ·stage-I 15 I
('"'"•'
\.· I
! Installati I
'
~
M/s CS- I
L) on of
7a. BHEL 9558-
,,_,,..
(,f::-.., Power
ltd. 1020-2-
Cycle
1\ SC-NOA-
1. •• > Piping 478,436,844
6350
Package
dtd.
for
22.05.20
BSTPP
, 15
Stage I
I TPE I
( 8 material Oriental
insuranc Jnsuranc 15.05.20
15,071,983
c after e Co. 15
(/ terminati Ltd.
on
(·
'
PO No
Installati• I Griffin I
9 5500020
on of VIS Power
276
for 2 nos. 175,835.46
Pvt. Ltd.
dtd.
ID fans o
19.06.20
Unit#2
15
Gerb
Surveilla P.O.No.
10 Vibratio
I
nee 5500020
n
during 439-034-
Contr ol
() installati 1028 68,375
Syste ms
on of VIS dtd.
C Pvt. Ltd. 02.07.
20
for 2 no s.
10 fans 0 15
I
I
(
1,
I
i
I
I
. .--1
Umt#2 ~.~---·-·-·,-----~-T----··-
·. . -··---·
I
l. ' i
' I
I '
: Ex-works
CS-
I
i 9558- '
supply of M/s
102T-2-
Coal Mill H.V.
11 FC-NOA-
Rejects Equipme 7,88,90,000
c·, a
Handling nts Pvt.
6518
dtd.
System Ltd.
28.10.20
Package
16
Inland '
(' I ' I
i I
Transpor
( . tation,
lnsuranc
( CS-
e,
9558-
( Installati M/s
102T-2-
on, H.V.
11 SC-NOA-
testing & Equipme 1,42,00,000
b 6519
commissi
c oning of
nts Pvt.
Ltd.
dtd.
28.10.20
Coal Mill
16
,. •.
Rejects
i
Handling
System
Package
16,617;573,9 [ 111,859,06
() Total
85.74/-
14 830 343 I - •
4.51/- '
(: y
(,
(
Page 121 of 150
It may be noted that:
(
\
c,
As per the aforesaid table, total expense incurred
G)
by NTPC in re-awarding the above balance works
of the package 1s INR 16,617,573,986/-
(.:_,;,'·-., (rounded off) + USO 111,859,065/- (rounded
off) + Euro 14,830,343/- (Rupees Sixteen Billion
C; '
are not covered above but which were part of the
Contracts with TPE. These items include supply
and erection of auxiliary boiler, coal flow
measunng system, boiler maintenance work
station (BMW), MPV type combustion system,
steam generator model study, instrument for tube
thickness measurement, software for life
assessment of tube/ pressure parts, coal abrasion
test apparatus, training for Employer's personnel,
C, permanent chemical deaning system, online coal
(; flow measuring system. The costs of such items
( have been estimated based on data available with
c· !2
I
MPV type combustion I
i
Inland
C
Basis I TPE Bid take out price
I C!F USD
transportation
INR
C} (BOD 20041 -
i
i 1135465 89000
I I !
Rate of escalation
I
I:6 ··~
,% 3
~
:
: Number of years for
I escalation uoto Jan 2015 Years i 10 10
I
I USD@INR , 65 ....•
~
I • Escalated price as on date
(} ' :
2015 l 1525970.02 159385.445
~--~---------------------,---
. Total price in INR INR . 99463089.5
'
\._ .'
Page 125 of 150
['
(BOD 2004) -
Rate of escalation '3 6 I
Number of years for
I
escalation upto Jan 2015 , Years ! 10 10
r
(./, • USD@INR 65
!
Escalated price as on date 1·
I
( 5Software for life
assement of
!
( ~ _ __,l_t__u_b_e~/~·p~r_e_s_s_u_r_eJp~:a_rt_s_ _ _t - - - - - + - - - - - - - - 1 - - - - - - - - - 1
i I I
Basis : Cost of Withdrawal by
· bidder in bongaigaon
(
.
}
project {BOD-2007} !NR 33000000 i i
Rate of escalation % 6
Number of years for I
i escalation upto Jan 2015 Years 7 i
Escalated price as on date i
(
Engineering personnel (for
22 man months) USO 34600 i
r · Temporary chemical
I cleaning in place.of
permanent chemical
I
,·. I cleaning
() Basis NTPC estimate for supply
·····-
(-··
Page 127ofl50
/d
r :· ·.•
/. ~
'·-. --····-----
Rate of escalation '% 13 6
, number of years for I :
10 Auxiliary Boiler i
:
I TOTAL 890,521,8 !
i INR 16 I
/; =:
\_,,
(,
€)
( '·,_:;
;,
( ..·
~
Amount paid •
(': LOA value of I
Amount
s. by NTPC
Contracts Currency TPE's contracts balance
(l No. excluding PVC
(a) (c = a-bi
(bi
1st 137,638,168. !
l• USD 388,910,673.00 251,272,504.34
Contract 66
(
I
2nd
I I 629,122,803.,
l
( 2! !NR 772,570,796.00 143,44 7,993.00!
Contract 00
(
:·, I i
'.'.: 3rd
3a. USD 2,818,288.00 I 999,937.80 1,818,350.20
(; Contract
3rd 1, 126,868,06 •
0 3b.
Contract
!NR 2,034,351,463.00 907,483,39s.001
8.00
i
Total balance payable amount = USD
I
139,456,518.86/- + INR!
i
1,755,990,871.00/-
"''~
\~;~ 139,456,519/- (rounded off) + INR
(} 1,755,990,871/· (US Dollar One Hundred
Thirty Nine Million Four Hundred Fifty Six
()
Thousand Five Hundred and Nineteen only
plus Rupees One Billion Seven Hundred Fifty
( -
(,:
3.2 Liquidated Damages
()
NTPC is entitled to the aforesaid claim for
C' liquidated damages as per Clause 26.2 of the
(! GCC read with Clause 8 of the SCC. Clause
26.2 of the GCC stipulates that if Contractor
(
•.
(
(TPE) fails to attain successful Completion of
. the Facilities or any part thereof within the
Time for Completion or any extension
thereof. .. , the Contractor (TPE} shall pay to
the Employer (NTPC) liquidated damages 1n
the amount computed at the rates specified in
the SCC. The corresponding Clause 8 of the
sec provides that liquidated damages for .
delay in successful completion of Facilities
shall be ... subject to maximum of five percent
(5%) of the total contract price for First
C Contract, Second Contract & Third Contract.
r< ,
the total contract price makes the liquidated
I •• ,
(
Page 131 of 150
damages only a miniscule portion of the
actual damages suffered by NTPC. However, if
we were to calculate the liquidated damages
without the aforesaid cap of five percent {5%)
CC·•
( ..
. and as per rates provided in Clause 8 _of the
SCC, a genuine pre-estimate of damages
would be as follows:
(
. •.
·• In any event, in deference to the provisions of
the Contracts, NTPC is compelled to restrict
(, .. '
only)
i
TOTAL
i
USO 19,445,350 + USO 140,914 USO 19,586,264/·
()
lNR38,628,540 + INR 101,714,415 INR 140,342,955/-
()
(·
f. .
'· . 3,3 Claim in respect of Functional
Guarantee/Performance Guarantee Test
(·
may be necessary to meet such guarantees.
:..._1
( Currently unspecified.
(' ·.' ·.
3.4 Claims against damage to material during
removal of TPE's gantry crane from site
after termination of the Contracts
( .
42.2.3 (a) of the GCC to handover the site in
•.
clean and safe condition to NTPC. However,
(
during dismantling of gantry crane being
carried out by TPE's sub-contractor M/ s
C ·_. Sukesh, an accident occurred at site on May
'
13 th , 2016 and resulted 1n damage to
materials of NTPC. This was promptly
(', '1,I _.
( .·
Page I 35 of 150
Computation of the landed cost of material
damaged by gantry crane accident is provided
below.
USO {c)
1 APH 1 30.57 95773.36 6357.95 16542.07 i 117449.94
rotor
block I
2 LPR 3 22.06 147416.39 9786.26 29843.28 I 84754.52
block
!3 LPR 3 11.79 30975.87 2621.86 17820.39 • 45297.18
i JJiJJing '
(.
Total amount, {a + b + c + d) USO
C 356,777.43 and INR 247,501.64
('; Taking 1 USD 67 INR,
(', Total amount in INR = 356,777.43 x 67 +
247,501.64 = 24,151,589.62
EntryTax@8% = INR 1,932,127.17
Total amount= INR 26,083,717/- (rounded
i off) (Rupees Twenty Six Million Eighty Three
(. ·..
-_/
Thousand Seven Hundred and Seventeen
only)
INR 2,528/~
(Rupees Two Thousand Five Hundred and
Twenty Eight only)
(
Total Outstanding payments to be made
by TPE: Total under 3.5.1 + Total under
(: 3.5.2 = INR 559,859/~ (Rupees Five
Hundred Fifty Nine Thousand Eight
(J
Hundred and Fifty Nine only)
('
' '
( :./
,~l NTPC has amply demonstrated and clearly
established wilful misconduct on the part of
TPE in the foregoing paras and hence is
(> /
(
Page 139 of 150
implementation of Barh STPP Stage-I. The
("
aforesaid sums of monies .invested by NTPC
has been in the debt equity ratio of 70:30 as
per the then applicable CERC guidelines. As
of 2014-15, the total project cost for Barh
(.
STPP Stage-I and NTPC's equity investment
is provided in the table herein below:
Non- Generation Loss IStae:e-Il
· S. no. Descriution Amount (in INRl
1 Total Proiect Cost 120 14-151 149,048,159,000
Project Cost {Unit# 1)
including common station I
(
Page 140 of 150
L
'·
,.\ .
.
since the same has not been paid as of now. However, the same shall be
r
payable on realisation of the following calculated amount and· shall also be
;
considered in claim.
(;i
c,
Total claim under the aforesaid head:
c·
2013-2014 2014-2015 : 2015-2016
I
I
(,:;.
( \
\. __ _
20lti-2017 I 2017-2018 2018-2019 I
( ..
., . i
! Delay Delay Delay
Unit in RoE [in INR) in RoE (in INR) m RoE (in INR)
(,;i i davs davs days
····-
:
: 1,905,203,00
I
(, I 365
2,86 I ,725,0 243
0
0 0.00
c, I 00
I
--------
: 2, 146,293,oo I
i
2, 146,293,0 365 60 352,815,000 •
2 365 0
00
:
: 2, 146,293,00 : 1,428,902,00
2,146,293,0 365 243 .
3 365 0 0
(.
I 00
6,197,790,00
•
1,781,718,00
(. I Total .
i 7,154,312,0
0 0
00
(
(.
Rate of return on equity assumed with MAT (Minimum
C Alternate Tax) as per CERC Circular.
n
Interest on
n
Interest on RoE I
I
RoE (in INR) (in INR)
days INR) i davs days
(::} I 153
30,170,00
365 315,652,000 I 365 659,059,000
0 ·····-
:
2 0 0.00 336 118,546,000 365 I 365,870,000
C 3 0 0.00 153 53,981,000
!
365 : 236,739,000
( .·-··: 30,170,00 :
1,261,668,000
Total 488,179,000_L
0
(· '
\ .
Page 142 ofl50
~-.
(
Interest on RoE@l2%
1 I 365
1,002,466,0
00 243
I 0 0.00
I 857,811,000 •
169,467,00
21365 i 623,425,000 365 880,980,000 60 • 0
643,358,00
3 365 I 494,294,ooo 1365 751,850,000. 243 0
Total 2,120,185,0 2,490,641,0 812,826,0
00 00 00
(
.. TOTAL
Amount (in INR)
C Return on Equity
29,224,873,000
IRoEl
( interest on RoE 7203,668,000 I
Grand Total
() i 36,428,541,000
I
(
Page 143 of 150
( ·:..
'- .·
(
INR 30,566,687,240/- (Rupees Thirty
Billion Five Hundred Sixty Six Million Six
Hundred Eighty Seven Thousand Two
Hundred Forty only)
('!
( ~'...-
,
!
Page 145 of 150
({.·.
(.
(_
INR 3;395,590,983.68/- (Rupees Three
('\ Billion Three Hundred Ninety Five Million
'.:.,.,'
A'•
t,) Five Hundred Ninety Thousand Nine
Hundred Eighty Three and Sixty Eight
(?
Paise only)
(:
>" Projected IEDC for Barh STPP Stage - I
between January 2017 till November
2018 (Date of completion of Unit#3) = INR
(
573,000,000/- (Rupees Five Hundred
Seventy Three Million only)
(~.
Total= INR 3,968,590,984/- (rounded-off)
(; (Rupees Three Billion Nine Hundred Sixty
() Eight Million Five Hundred Ninety Thousand
Nine Hundred and Eighty Four only)
()
c:, However, NTPC reserves it's right to the
claim under the aforesaid head as per
actuals.
c: 6,792,368.43
anticipated to be
paid, taken @60%
(J
M/s
C Minimax FOPS, PVC-Erection paid
2 Gmbh Co. Stage-I 11,807,736.34 after L2 revision
(1
PVC-Erection
! anticipated to be
11,793,003.00 paid taken @30%
(~ PVC-applicable, due
9,562,618.00 to L2 revision
() M/s L&T CHP, Stage-I
3 , BG& Insurance
("·,
• .. Charges to be
32,444,384.00 reimbursed
\,
I
i ' !
C,::
3.6.5 Claims against repair of damaged
€} equipment/ missing materials
() That as per the Contracts awarded to
C
(
(.
THROUGH,
()
C' ;
A G'{JST LEGAL
S-553, GREATER KAILASH '- II,
NEW DELHI - 110048.
(-· ··,
.
C '•
(·
c.·.
v.· IN THE MATTER OF:
Versus
/~,· ..
I
\,._,
e
...'
( employment of NTPC Limited, currently posted at Barh-STPP, Patna, Bihar in
the capacity of Additional General Manager and having come down to New
(. our counsel under my instructions and I have also read the contents
r··, thereof. I state the contents of the aforesaid statement of counter claims
\
are true and correct on the basis of records. I state that nothing material
('
3. That the documents filed along with the accompanying statement of
counter claims are either original or. copies of the respective original
(t
documents.
()
(1
() DE~NT
6fi I "'I >ii cl { WIT
c,,
~:.,.,
VERIFICATION: = Kameshwar Jha
lliml'illq; {'fflil, ~ = )
Add!. General Manager (ME)
' 1[-12"\<i\m - sr.,1NTPC - Barh
It is verified on the _lj Ja~lof7i'~!nhary, 2017 at New Delhi that th~ contents
of the aforesaid affidavit are true and correct on the basis of my knowledge and
belief. It is stated that nothing material has been concealed in the aforesaid
affidavit.
. .,
€.,... ;,~,
:·
. .,
( 2f:i I"'I ¾' e; < WIT
" Kameshwar Jha
ill'« llffi'i'l'n ( 'lifi:ri; ""1im )
Add!. General Manager (ME)
1(,iltjml - 'lfi;iNTPC - Barh
(",
' .
' ,
( ',. '
( ..
lFf tt rff rft ffetfflds
{'lffil'ffl1ffl'ifil'3"01,)
\ ..
NTPC Limited
(A Gavemmellt of India Enterprises)
<ITG: / Barh
~,t ffl ! Ref Na. · ~ I Date
D·
l '.
(
..
r,
-4400/llarh/G G M/2017 06.02.2017
(,
(' .
\. .
~<'!'Rm=~. 1::t.rr ,
<llR , 'IT<I, =- 803,1s ~ V'fl1! , 06132-240011112 ,t;,m , 06132-uooio. 240014/240067
Barh Super Thermal Po...,, Proiect, P0>!: Barh. Distrid. Patna. 803215 (Bihar) Phone 06132-240011/12 Fax 06132-240010. 240014(,140067
~ ~ : l"llMllft ~- ~ ~ . l f«l;;.<\!i'l>I dloT, lll<lt iii. 'II ~-l/ R&gd. Off.: ITTPC hwa1 Scq,e~. ,,,.._ l<e.e. lochllool. ,...o.,,.;
BEFORE THE ARBITRAL TRIBUNAL COMPRISING OF
HON'BLE R.C. LAHOTI (Former Chief Justice oflndia),
HON'BLE DR. AR!JIT PASAYAT (Former Judge, Supreme Court of India) &
HON'BLE DEEPAK VERMA (Former Judge, Supreme Court of India)
VERSUS,
KNOW ALL to whom these presents shall come that we, the abovementioned
RESPONDENT/ COUNTER CLAIMANT, hereby appoint,
('
AUGUST LEGAL, S-553, (LGF), GK Part-II, New Delhi -110048 which shall
include the names of the advocates working therewith namely, Mr. Barunesh
Chandra (D/2240/1999), Mr. GK Mishra (D/1151/1998), Ms. Madhumita
Bbattacharjee (012674/1999), Ma. Monika Singh (D/124912016) and Mr. Ayandeb
Mitra (D/1289/2016) hereinafter called the Advocatels to be our Advocate in the above
noted matter and authorize them:-
··.,
( '
J To represent, ac~ appear and plead in the above noted matter before the Hon'ble
Tribunal/Court(s) or in any other Authority/Court in which the same be tried or heard and
(; also in the appellate, courts;
To sign, file, verify and present representations, pleadings, replications, appeals, cross-
objections, or petitions for execu~ion, review, revision, restoration, withdrawal,
compromise and to file replies to petitions, objections or affidavits as may be deemed
necessary or proper for the prosecution of the said case in all its stages;
To file and receive documents;
To take out executions proceedings;
To deposit, wilhdraw and receive monies~ cheques and amounts, refunds of courts fees
,. •,
(, . . etc.j and grant receipts thereof and to do all other acts and chings which may be necessary
to be done for the progress and io the course of the prosecutions o[the said case;
To appoint and instruct any olher legal practitioner authorizing him to exercise the
powers and authorities hereby conferred upon the advocates whenever he/they may think
fit to do so and to sign the power of attorney on my/our behalf;
AND I, the undersigned do hereby agree to ratify and confinn all acts done by the
advocate.or his/their substitutes in the matter as my/our own act/s, as if done by me to all
intents and purposes;
IN WIWESS WHEREOF [ do have unto set my hand to these presents the contents of
(_, . which have been understood by me on this 6'h day of January, 2017.
CLJENT
(;
(12) ~
Kameshwar Jha
°'IBTh~tf<:ii (9ffl Tcm:A)
31tf{
Addl. G~neral M.Jriager (iv':C)
t('Rl,ni\- cn.1NTPC • 82:··,
'
()
{ .-..'·
~~.