Professional Documents
Culture Documents
1: ENGINEERING NOTES
Downloaded from arc.aiaa.org by UNIVERSITY OF MARYLAND on 10/18/14. For personal use only.
David J. Moorhouse¤
Air Force Research Laboratory,
Wright– Patterson Air Force Base, Ohio 45305
Introduction
appropriate for use in design tradeoffs. Actual test data show that Table 1 Detailed de nitions of risk progression
the technology can probably be transitioned to system application,
TRL Risk Risk de nition
but the integration issues are still not well de ned.
9 Zero (0) Successfully demonstrated in UAV ops.
Technology Readiness Level 5 8 Low (1) Concept demonstrated in UAVs
Successfully demonstrated, not in UAVs
This level applies when there has been component and/or bread- 7 Acceptable (2) Problems identi ed and solutions
board validation in a relevant environment. In contrast with TRL 4, known based on UAV development
the testing must be of hardware of appropriate scale and function- Concept demonstrated, but not in UAVs
ally equivalent to ight articles. The hardware may not be ight 6 Medium (3) Current advanced development can probably
weight, representative material, etc., but judgment should be used be accomplished within cost/time schedule;
to assess risk depending on the criticality of those properties to the problems of application to UAVs are identi ed;
application. Also, at this level the relevant test environment is a negligible possibility of failure
high- delity ground demonstration or a simulation with system in- 5 Medium (4) Advanced development can incur cost/time
overruns, but very low possibility of failure
teractions identi ed. There should be analytical models of the tech- for near term (1 year)
nology integrated into the system, including test correlations made 4 Medium (5) Possibility of failure to meet near-term needs;
with good agreement. The products will be models with good esti- negligible possibility of failure for midterm
mates of performance (and cost impacts). The technology is ready (5– 10 years)
for detailed design studies, and uncertainties can be judged to be 3 High (6) Long-term development with estimated
medium. The integration issues have been de ned, and the technol- costs; very low possibility of failure
ogy potential for transition can be considered good, but still high for midterm application
risk for Engineering Management and Development (EMD). 2 High (7) Costs largely unknown; low possibility of failure
for midterm; parallel efforts desirable
1 V. high (8) Concepts indicating high potential payoff,
Technology Readiness Level 6 but technology may not be feasible now;
This level applies when there has been system/subsystem, model, possibility of failure through midterm;
or prototype demonstration in a relevant environment. The tested parallel efforts mandatory
hardware must be of full scale, and the hardware must be actual
ight articles or ight type to be above TRL 5. At this level the rele-
vant test environment is either a high- delity ground demonstration and midterm (5 – 10 year) developments. Table 1 provides detailed
or simulation with components that could y, or a low- delity ight guidance on how the risk would be assessed to augment the appli-
cation of the detailed de nitions of TRL in laying out a required
Journal of Aircraft 2002.39:190-192.
Conclusions
Detailed de nitionshave been suggestedfor technologyreadiness
levels from 1 through 7, the typical range for technology develop-
ment. These de nitions provide guidance on how to progress from
Fig. 2 Heuristic variation of technology cost with TRL.
one level to higher levels. It is suggested that the TRLs can provide
formal exit criteria for tasks or phases in a technology development
program. Risk is discussed as the inverse of the TRL progression.
the prediction of costs without “management reserve” or a factor Last, the cost implications are discussed, but only in a qualitative
to cover “unknown unknowns.” Following the preceding technical manner.
de nitions for each TRL, then there is obviously more uncertainty
on this predicted cost at the lower TRLs. We know absolutely, how-
ever, that there is a 100% probability that costs will be less than Reference
an upper bound and also 0% probability that costs will be less than 1 “Best
Practices—Better Management of Technology Development Can
a lower bound (neither of which will be known, in practice). Only ImproveWeapon System Outcomes,” Rept. GAO/NSIAD-99-162,U.S. Gen-
if the uncertainties are random can we assume that the most likely eral Accounting Of ce, Washington, DC, July 1999.
Journal of Aircraft 2002.39:190-192.
Errata
Strength of Stiffened 2024-T3 Aluminum Panels with Multiple Site Damage